CN109882158A CN201910214225.XA CN201910214225A CN109882158A CN 109882158 A CN109882158 A CN 109882158A CN 201910214225 A CN201910214225 A CN 201910214225A CN 109882158 A CN109882158 A CN 109882158A
Authority
CN
China
Prior art keywords
water level
water
hole
data
hydraulic pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910214225.XA
Other languages
Chinese (zh)
Other versions
CN109882158B (en
Inventor
董书宁
王经明
刘其声
王皓
黄浩
赵亚飞
田延哲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
North China Institute of Science and Technology
Xian Research Institute Co Ltd of CCTEG
Original Assignee
North China Institute of Science and Technology
Xian Research Institute Co Ltd of CCTEG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by North China Institute of Science and Technology, Xian Research Institute Co Ltd of CCTEG filed Critical North China Institute of Science and Technology
Priority to CN201910214225.XA priority Critical patent/CN109882158B/en
Publication of CN109882158A publication Critical patent/CN109882158A/en
Application granted granted Critical
Publication of CN109882158B publication Critical patent/CN109882158B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The present invention provides a kind of drill-hole pumping water level test method and drilling water level test device, and this method includes the initial water level obtained in drilling hole;It opens water pump and carries out single-well pumping test, obtain water level and restore observation data;Restore observation data according to water level, fitting water level restores observation curve;Restore observation curve according to water level, obtains hole wall water level;The depth displacement between initial water level and hole wall water level is calculated, drilling water level drawdown value is obtained.Realize that fitting water level restores observation curve, the corresponding water level of coordinate points that the water level restores observation curve maximum curvature is determined as hole wall water level, reduce the error of water level, to obtain accurate drawdown, it is calculated for the water in exploration process and evaluation provides accurate parameter, avoid damage caused by due to hydrogeological parameter mistake.

Description

Drill-hole pumping water level test method and drilling water level test device
Technical field
The present invention relates to drilling technique fields, survey in particular to drill-hole pumping water level test method and drilling water level Trial assembly is set.
Background technique
Currently, the test of drill-hole pumping precipitation is indispensable work, mine pit water discharge in the exploration process of mineral resources Amount calculate and groundwater resources amount calculating by be geological prospecting routine work, wherein drilling water level drawdown value, be calculate Essential parameter in pit inflow of water and groundwater resources amount.
Currently, drilling water level drawdown value mainly passes through the minimum of the initial water level and water level in borehole measured in drilling hole Point, and using the minimum point of the water level in borehole of measurement as hopper centre's water level, then by calculating initial water level and hopper centre The difference of the elevation of water level obtains drilling water level drawdown value.
Since the definition of drawdown value is the difference of initial water level and hopper centre's water level at structures of drawing water, wherein Hopper centre's water level is the minimum point of hole wall water level, and hopper centre's water level in the minimum point and definition of the water level in borehole measured Between there are very big difference, by the minimum point of water level in borehole directly as hopper centre's water level, lead to the Drilling Water potential drop calculated Deep value error is very big, and the error by the hydrogeological parameter of drilling water level drawdown value acquisition is very big, and according to the Drilling Water The water yield of other hydrogeological parameter calculations of the deep value of potential drop and its reverse is far smaller than the practical water yield of pit shaft or pit, from And pit shaft or pit is be easy to cause to be flooded and dead disaster.
Summary of the invention
In view of this, the embodiment of the present invention is designed to provide a kind of drill-hole pumping water level test method and drilling water level Test device realizes that fitting water level restores observation curve, and the coordinate points which is restored observation curve maximum curvature are corresponding Water level is determined as hopper centre's water level, reduces the error of hopper centre's water level of definition, so as to obtain accurate water level Drawdown, the water yield for pit calculates and evaluation provides accurate parameter, avoids and causes because of hydrogeological parameter mistake Damage.
In a first aspect, the embodiment of the invention provides a kind of drill-hole pumping water level test methods, which comprises
Obtain the initial water level in drilling hole;
It opens water pump and carries out single-well pumping test, obtain water level and restore observation data;
Restore observation data according to the water level, fitting water level restores observation curve;
Restore observation curve according to the water level, obtains hole wall water level;
The depth displacement between the initial water level and the hole wall water level is calculated, drilling water level drawdown value is obtained.
With reference to first aspect, the embodiment of the invention provides the first possible implementation of above-mentioned first aspect, In, the unlatching water pump carries out single-well pumping test, obtains water level and restores observation data, comprising:
It opens water pump and carries out test of drawing water;
It after the pumping operation for carrying out preset time period, switches off the pump, after being stopped pumping by hydraulic pressure sensor acquisition Restore water pressure data in hole;
It will restore water pressure data in the hole and be converted into water level recovery observation data.
With reference to first aspect, the embodiment of the invention provides second of possible implementation of above-mentioned first aspect, In, described to restore observation data according to the water level, fitting water level restores observation curve, comprising:
Restore observation data according to the water level and draws water level recovery curve;
Water level, which is fitted, according to the water level recovery curve restores observation curve.
With reference to first aspect, the embodiment of the invention provides the third possible implementation of above-mentioned first aspect, In, it is described that position observation curve is restored according to the water, obtain hole wall water level, comprising:
Water level recovery curve observational equation is established according to the water-level observation curve;
According to the water level recovery curve observational equation, it is corresponding to calculate each coordinate points on the water level recovery observation curve Curvature;
The coordinate points of maximum curvature are determined from the corresponding curvature of each coordinate points;
The corresponding water level of the coordinate points of the determination is determined as hole wall water level.
The possible embodiment of with reference to first aspect the first, the embodiment of the invention provides the of above-mentioned first aspect Four kinds of possible implementations, wherein it is described after the pumping operation for carrying out preset time period, it switches off the pump, passes through the water Pressure sensor, which obtains in the hole after stopping pumping, restores water pressure data, comprising:
After the pumping operation for carrying out preset time period, switches off the pump, continued in acquisition pores by the hydraulic pressure sensor Water pressure data;
Real-time monitoring is carried out to water pressure data in the hole of lasting acquisition, when water pressure data is full in the hole for monitoring to continuously acquire When sufficient pre-determined stability condition, stop water pressure data in acquisition pores;
It will be determined as stopping from switching off the pump to water pressure data in the hole for stopping obtaining during water pressure data in acquisition pores Restore water pressure data in hole after only drawing water.
Second aspect, the embodiment of the invention provides a kind of drilling water level test device, described device includes hydraulic pressure sensing Device, secondary meter, data processor and data cable;
The diving end of the data cable connects the hydraulic pressure sensor, the ground surface end connection described two of the data cable Secondary instrument;
The hydraulic pressure sensor, for acquiring water pressure data in initial water level and hole, and will be in the initial water level and hole Water pressure data is transferred to the secondary meter by the data cable;
The secondary meter sends monitoring order to the hydraulic pressure sensor by the data cable;Receive, storage and Show water pressure data in the initial water level and hole of the hydraulic pressure sensor transmission;
Water pressure data in the hole is converted into water level and restores observation data by the data processor;According to the water level Restore observation data and draws water level recovery curve;Water level, which is fitted, according to the water level recovery curve restores observation curve;According to institute It states water level and restores observation curve acquisition hole wall water level;The depth displacement between initial water level and the hole wall water level is calculated, is bored Hole drawdown value.
In conjunction with second aspect, the embodiment of the invention provides the first possible implementation of above-mentioned second aspect, In, described device further includes water pump and metallic rod;
The suction hose of the water pump is bundled with the metallic rod;
The data cable is fixed in the metallic rod, and the hydraulic pressure sensor is fixedly mounted on the latent of the metallic rod Water end (W.E.).
In conjunction with second aspect, the embodiment of the invention provides second of possible implementation of above-mentioned second aspect, In, the secondary meter includes receiving element, memory element, control element, signal key and display screen;
The receiving element is connect with the memory element, the display screen and the hydraulic pressure sensor respectively, receives institute Water pressure data in the hole of hydraulic pressure sensor transmission is stated, and transmits in the hole water pressure data to the memory element and described Display screen;The memory element, for storing water pressure data in the hole;The display screen, for showing hydraulic pressure in the hole Data;
The control element respectively with the memory element, the display screen, the signal key and the hydraulic pressure sensor Connection receives the trigger signal of the signal key transmission, and sends monitoring order according to the trigger signal and pass to the hydraulic pressure Sensor, or according to the trigger signal, from transferring water pressure data in the hole in the memory element, and by the hole Nei Shui Pressure data are transferred to the display screen.
In conjunction with second of possible embodiment of second aspect, the embodiment of the invention provides the of above-mentioned second aspect Three kinds of possible implementations, wherein the signal key includes clock and watch check and correction key, storage key, display key, sample frequency setting Key, water level conversion key and data export key.
In conjunction with second of possible embodiment of second aspect, the embodiment of the invention provides the of above-mentioned second aspect Four kinds of possible implementations, wherein the secondary meter further includes USB interface and network interface;
The USB interface restores data for exporting initial water level and drilling water level in borehole in the drilling hole acquired;
The network interface, for connecting the secondary meter and the data processor by wireline cable.
In method and device provided in an embodiment of the present invention, which includes obtaining drilling hole Interior initial water level;It opens water pump and carries out single-well pumping test, obtain water level and restore observation data;Restore observation number according to water level According to fitting water level restores observation curve;Restore observation curve according to water level, obtains hole wall water level;Calculate initial water level and hole wall Depth displacement between water level obtains drilling water level drawdown value;The drilling water level test device includes hydraulic pressure sensor, secondary instrument Table, data processor and data cable;The diving end of data cable connects hydraulic pressure sensor, the ground surface end connection two of data cable Secondary instrument;Hydraulic pressure sensor leads to for acquiring water pressure data in initial water level and hole, and by water pressure data in initial water level and hole It crosses data cable and is transferred to secondary meter;Secondary meter sends monitoring order to hydraulic pressure sensor by data cable;Receive, Water pressure data in the initial water level and hole of storage and display hydraulic pressure sensor transmission;Data processor turns water pressure data in hole It changes water level into and restores observation data;Restore observation data according to water level and draws water level recovery curve;It is quasi- according to water level recovery curve Heshui bit recovery observation curve;Restore observation curve according to water level and obtains hole wall water level;Calculate initial water level and hole wall water level it Between depth displacement, obtain drilling water level drawdown value.It realizes fitting water level and restores observation curve, which is restored into observation curve The corresponding water level of the coordinate points of maximum curvature is determined as hole wall water level, reduces the error with hopper centre's water level of definition, from And available accurate drawdown, the water yield for pit calculates and evaluation provides accurate parameter, avoids because of water Literary geologic parameter mistake and caused by damage.
To enable the above objects, features and advantages of the present invention to be clearer and more comprehensible, preferred embodiment is cited below particularly, and cooperate Appended attached drawing, is described in detail below.
Detailed description of the invention
In order to illustrate the technical solution of the embodiments of the present invention more clearly, below will be to needed in the embodiment attached Figure is briefly described, it should be understood that the following drawings illustrates only certain embodiments of the present invention, therefore is not construed as pair The restriction of range for those of ordinary skill in the art without creative efforts, can also be according to this A little attached drawings obtain other relevant attached drawings.
Figure 1A shows the flow chart of drill-hole pumping water level test method provided by the embodiment of the present invention 1;
Figure 1B shows and obtains the flow chart that water level restores observation data provided by the embodiment of the present invention 1;
Fig. 1 C shows the flow chart that hole wall water level is obtained provided by the embodiment of the present invention 1;
Fig. 1 D shows water level recovery curve provided by the embodiment of the present invention 1 and water level restores observation curve;
Fig. 2A shows a kind of structural schematic diagram of drilling water level test device provided by the embodiment of the present invention 2;
Fig. 2 B shows the structure chart of drilling water level test device provided by the embodiment of the present invention 2.
Specific embodiment
Below in conjunction with attached drawing in the embodiment of the present invention, technical solution in the embodiment of the present invention carries out clear, complete Ground description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Usually exist The component of the embodiment of the present invention described and illustrated in attached drawing can be arranged and be designed with a variety of different configurations herein.Cause This, is not intended to limit claimed invention to the detailed description of the embodiment of the present invention provided in the accompanying drawings below Range, but it is merely representative of selected embodiment of the invention.Based on the embodiment of the present invention, those skilled in the art are not doing Every other embodiment obtained under the premise of creative work out, shall fall within the protection scope of the present invention.
In view of in the prior art, due between hopper centre's water level in the minimum point and definition of the water level in borehole of measurement There are very big differences, by the minimum point of water level in borehole directly as hopper centre's water level, lead to the drilling water level drawdown value calculated Error is very big, and the error by the hydrogeological parameter of drilling water level drawdown value acquisition is very big, and according to the Drilling Water potential drop The water yield that deep value calculates is far smaller than the practical water yield of pit shaft and pit, to be easy to cause pit shaft or mine in exploration process Hole is flooded and dead disaster.Based on this, the present invention provides a kind of drill-hole pumping water level test method and drilling water level test dresses It sets, realizes that fitting water level restores observation curve, the corresponding water level of coordinate points which is restored observation curve maximum curvature is true It is set to hopper centre's water level, reduces the error with hopper centre's water level of definition, so as to obtain accurate drawdown, To provide accurate parameter to the calculating of pit inflow of water water and evaluation in exploration process, avoid because of hydrogeological parameter mistake It is damaged caused by accidentally.It is described below by embodiment.
Embodiment 1
Referring to Figure 1A, the embodiment of the invention provides a kind of drill-hole pumping water level test methods.This method includes following S101-S105 step.
Step S101: the initial water level in drilling hole is obtained.
Step S102: opening water pump and carry out single-well pumping test, obtains water level and restores observation data.
Step S103: it according to water-level observation data, is fitted water level and restores observation curve.
Step S104: observation curve is restored according to water level, obtains hole wall water level.
Step S105: the depth displacement between initial water level and hole wall water level is calculated, drilling water level drawdown value is obtained.
In embodiments of the present invention, it before carrying out single-well pumping test to drilling, needs first to obtain first in drilling hole Beginning water level.Wherein, the initial water level in drilling hole is obtained, is first to acquire the hydraulic pressure number for boring water level in borehole by hydraulic pressure sensor According to the water pressure data of acquisition is transferred to secondary meter by hydraulic pressure sensor, then passes through secondary meter or other water level route markers Water pressure data is converted into corresponding water level value, using the water level value as the initial water level in drilling hole.
In above-mentioned S102 step, single hole pumping is being carried out according to professional standards such as exploration specification and single-well pumping testing standards During water test, water-level observation data are obtained, can specifically be obtained by following S1021-S1023 step, as shown in Figure 1B.
Step S1021: it opens water pump and carries out test of drawing water.
When water pump is drawn water, above-mentioned hydraulic pressure sensor acquires water pressure data of drawing water in hole in real time, and passes through data line The secondary meter that water pressure data of drawing water in hole is transferred on ground by cable, secondary meter display and store the hydraulic pressure number that draws water in hole According to.
Step S1022: after the pumping operation for carrying out preset time period, switching off the pump, and is stopped by hydraulic pressure sensor acquisition Restore water pressure data in hole after only drawing water.
In above-mentioned steps S1022, is obtained in the hole after stopping pumping by hydraulic pressure sensor and restore water pressure data, specifically It can be obtained by following S10221-S10223 step.
Step S10221: it after the pumping operation for carrying out preset time period, switches off the pump, is persistently obtained by hydraulic pressure sensor Take water pressure data in hole.
Above-mentioned preset time period, to the high rate observation of drilling water level than shortest time for being required in single-well pumping testing standard It grows, can be 1 hour, after the pumping operation for carrying out preset time, then can reduce sample frequency.
After switching off the pump, secondary meter sends monitoring order to hydraulic pressure sensor, and hydraulic pressure sensor receives monitoring life After order, start to acquire water pressure data in hole according to the sample frequency that monitoring order includes.Wherein, the sample frequency not less than 5 times/ Second.
Step S10222: real-time monitoring is carried out to water pressure data in the hole of lasting acquisition, when the hole for monitoring to continuously acquire When interior water pressure data meets pre-determined stability condition, stop water pressure data in acquisition pores.
When hydraulic pressure sensor orders water pressure data in acquisition hole according to monitoring, secondary meter can receive hydraulic pressure biography Water pressure data in the hole of sensor transmission, and water pressure data in the hole received is counted, when water pressure data in the hole of statistics In most latter two water pressure data difference be less than or equal to preset value when, then illustrate that water pressure data meets pre-determined stability condition in hole, At this point, secondary meter, which is sent, stops monitoring order to hydraulic pressure sensor, hydraulic pressure sensor stops water pressure data in acquisition hole;Work as system The difference of last continuous two water pressure datas is greater than preset value in water pressure data in the hole of meter, then illustrates that water pressure data is unsatisfactory in hole Pre-determined stability condition, at this point, hydraulic pressure sensor continues to acquire water pressure data in hole, secondary meter is calculated in real time in most latter two hole The difference of water pressure data, until the difference of water pressure data is less than preset value in most latter two hole, secondary meter, which is sent, stops monitoring life It enables to hydraulic pressure sensor, hydraulic pressure sensor stops water pressure data in acquisition hole.
Step S10223: will be from switching off the pump to hydraulic pressure number in the hole for stopping obtaining during water pressure data in acquisition pores According to being determined as restoring water pressure data in the hole after stopping pumping.
After getting recovery water pressure data in hole by S1022 step, it is extensive water level can be obtained by following S1023 step Data are observed again.
Step S1023: water pressure data will be restored in hole and be converted into water level recovery observation data.
After getting water level recovery observation data by S102 step, the above S103 step can be passed through and obtain water level recovery Observation curve.
In above-mentioned steps S103, observation data are restored according to water level, fitting water level restores observation curve, can be by following Process is completed.
Observation data are restored according to water level first and draw water level recovery curve;Then water level is fitted according to water level recovery curve Restore observation curve.
Since the water level got restores data very big there are some errors in observation data, lead to the water of above-mentioned drafting Bit recovery curve is unsmooth, also needs to establish corresponding water level recovery curve equation according to the water level recovery curve at this time, pass through The water level recovery curve equation of the foundation is optimized, so as to be drawn out smoothly according to the water level recovery curve equation after optimization Water level recovery curve, and by the smooth water level recovery curve be determined as water level restore observation curve.
In embodiments of the present invention, the water level recovery curve of drafting, and the water level that fitting obtains restore observation curve, show Meaning property is as schemed as shown in 1D.In Fig. 1 D, the corresponding equation of water level recovery curve is h1=V (t), and it is corresponding that water level restores observation curve Equation be h2=V (t), wherein V is hydraulic pressure, and t is recovery time.
In above-mentioned steps S104, observation curve is restored according to water level, hole wall water level is obtained, following S1041- can be passed through S1044 step obtains, as shown in Figure 1 C.
Step S1041: observation curve is restored according to water level and establishes water level recovery curve observational equation.
Step S1042: according to water level recovery curve observational equation, it is corresponding that each coordinate points on water level recovery observation curve are calculated Curvature.
Step S1043: the coordinate points of maximum curvature are determined from the corresponding curvature of each coordinate points.
Step S1044: the determining corresponding water level of coordinate points is determined as hole wall water level.
In embodiments of the present invention, according to water-level observation curve, hole wall water level is obtained, can also be observed by ocular estimate Water level restores the coordinate points of maximum curvature on observation curve, and the determining corresponding water level of coordinate points is determined as hole wall water level.
After obtaining hole wall water level by the above S104, the above S105 step drilling water level drawdown value can be passed through.
In embodiments of the present invention, restore observation curve by establishing water level, most by curvature on water level recovery observation curve The corresponding water level of big coordinate points, is determined as hole wall water level, in this way, the mistake of the hopper centre of the hole wall water level determined and definition Poor very little, thus it is very high according to the drilling water level drawdown value accuracy that hopper centre's water level calculates, pass through the Drilling Water potential drop Deep value calculates the error very little of hydrogeological parameter, in exploration process, is gushed according to the pit that the drilling water level drawdown value calculates Water or inflow of water are more reasonable, it is possible to reduce pit shaft or pit occur and flooded and the probability of dead disaster.
In drill-hole pumping water level test method provided in an embodiment of the present invention, this method includes initial in acquisition drilling hole Water level;It opens water pump and carries out single-well pumping test, obtain water level and restore observation data;Restore observation data, fitting according to water level Water level restores observation curve;Restore observation curve according to water level, obtains hole wall water level;It calculates between initial water level and hole wall water level Depth displacement, obtain drilling water level drawdown value.Fitting water-level observation curve is realized, the water-level observation curvature of curve is maximum The corresponding water level of coordinate points is determined as hole wall water level, the error with hopper centre's water level of definition is reduced, so as to obtain Accurate drawdown calculates for the water in exploration process and evaluation provides accurate parameter, avoids because of hydrogeology Parameter error and caused by damage.
Embodiment 2
A or 2B referring to fig. 2, the embodiment of the invention provides a kind of drilling water level test device, which includes that hydraulic pressure passes Sensor 1, secondary meter 2, data processor 3 and data cable 4;
The diving end of data cable 4 connects hydraulic pressure sensor 1, and the ground surface end of data cable 4 connects secondary meter 2;
Hydraulic pressure sensor 1, for acquiring water pressure data in initial water level and hole, and by water pressure data in initial water level and hole Secondary meter 2 is transferred to by data cable 4;
Secondary meter 2 sends monitoring order to hydraulic pressure sensor 1 by data cable 4;Receive, store and show hydraulic pressure Water pressure data in the initial water level of the transmission of sensor 1 and hole;
Water pressure data in hole is converted into water level and restores observation data by data processor 3;Restore observation data according to water level Draw water level recovery curve;Water level, which is fitted, according to water level recovery curve restores observation curve;Restore observation curve according to water level to obtain Take hole wall water level;The depth displacement between initial water level and hole wall water level is calculated, drilling water level drawdown value is obtained.
In embodiments of the present invention, above-mentioned data cable 4 is waterproof, anticorrosion, jamproof type low-voltage cable.The data line The ground surface end of cable 4 is exposed at end above the ground, and the diving end of the data cable 4 is the end being exposed in drilling.
When acquiring water pressure data in the corresponding water pressure data of initial water level and hole, above-mentioned hydraulic pressure sensor 1 needs to place At the drilling following pre-determined distance of water level in borehole.Hydraulic pressure sensor 1 starts to adopt according to the monitoring order that above-mentioned secondary meter 2 is sent Collect water pressure data in hole, wherein the monitoring order includes acquisition time and frequency acquisition etc..
Above-mentioned secondary meter 2 is storage display equipment, according to the control command of user or user's test journey set in advance Sequence sends monitoring order to hydraulic pressure sensor 1 or stops monitoring order.
Above-mentioned data processor 3 can be computer, mobile phone or the equipment for carrying out water pressure data processing.The data processor 3 can be set in the remote control center far from exploration scene, and user can export the initial of storage from above-mentioned secondary meter 2 Water pressure data in the corresponding water pressure data of water level and hole, and water pressure data in the corresponding water pressure data of the initial water level and hole is led to Network transmission is crossed to above-mentioned data processor 3;The data processor 3 can also be arranged in exploration scene, by the communications cable with Secondary meter 2 connects, and secondary meter 2 is by the communications cable, by the corresponding hydraulic pressure of initial water level of storage or real-time acquisition Water pressure data is transferred to the data processor 3 in data and hole.
B referring to fig. 2, the device further include water pump 5 and metallic rod 6;
The suction hose of water pump 5 is bundled with metallic rod 6.
Data cable 4 is fixed in metallic rod 6, and hydraulic pressure sensor 1 is fixedly mounted on the diving end of metallic rod 6.
In embodiments of the present invention, above-mentioned water pump 5 can be centrifugal water pump 5.Hydraulic pressure sensor 1 and above-mentioned water pump 5 The distance of the water inlet of suction hose is not less than 10m.Above-mentioned data cable 4 is fixed in metallic rod 6, can be tried to avoid single-well pumping During testing, data cable 4 is inhaled into the suction hose of water pump 5.
In embodiments of the present invention, above-mentioned secondary meter 2 include receiving element, memory element, control element, signal key and Display screen;
Receiving element is connect with memory element, display screen and hydraulic pressure sensor 1 respectively, receives what hydraulic pressure sensor 1 transmitted Water pressure data in hole, and in transmission hole water pressure data to memory element and display screen;Memory element, for hydraulic pressure number in storage hole According to;Display screen, for water pressure data in show hole;
Control element is connect with memory element, display screen, signal key and hydraulic pressure sensor 1 respectively, receives signal key transmission Trigger signal, and monitoring order is sent to hydraulic pressure sensor 1, or according to trigger signal, from storage member according to trigger signal Water pressure data in hole is transferred in part, and water pressure data in hole is transferred to display screen.
Above-mentioned signal key includes clock and watch check and correction key, storage key, display key, sample frequency set key, water level conversion key sum number According to export key.
Above-mentioned clock and watch proofread key, and for proofreading the time of above-mentioned hydraulic pressure sensor 1, user is pressed this key, and secondary meter 2 can To send the instruction of clock and watch check and correction to hydraulic pressure sensor 1 so that hydraulic pressure sensor 1 by the watch time of itself adjust to it is secondary 2 current time of the instrument consistent time.It is proofreaded by clock and watch, it can be ensured that the data and hydraulic pressure sensor 1 that secondary meter 2 stores The data of acquisition are synchronous, improve the accuracy of data.
Above-mentioned storage key, for storing the data of the transmission of hydraulic pressure sensor 1, user is pressed this key, and secondary meter 2 starts to protect The data that water pressure sensor 1 transmits, press this key again, and since hydraulic pressure sensor 1 will be pressing this key to pressing this again Data between key carry out segmentation preservation, and restart the preservation of another segment data.In embodiments of the present invention, secondary meter 2 can also carry out preservation data according to the timing node in program by pre-set program.
Above-mentioned display key, the water pressure data that hydraulic pressure sensor 1 can be acquired real-time display in the form of water level, can also show Show a certain section of the corresponding water level of water pressure data that secondary meter 2 stores.
Above-mentioned sample frequency set key, can according to the demand of bailing test, the customized setting sample frequency of user, when with Family sets after sample frequency and presses this key, which is sent to hydraulic pressure sensor 1, hydraulic pressure sensing by secondary meter 2 Device 1 carries out water pressure data acquisition according to the sample frequency.In embodiments of the present invention, secondary meter 2 can also be by setting in advance The program set carries out water pressure data acquisition according to the frequency set in program.
Above-mentioned water level conversion key, for hydraulic pressure value to be scaled corresponding water level value.In embodiments of the present invention, work as user After pressing this key, the water pressure data that hydraulic pressure sensor 1 transmits can be converted into waterlevel data and shown by secondary meter 2, be used Family can according to need setting or save the data of hydraulic pressure form or the data of water level form.
Above-mentioned data export key, for exporting the water pressure data or waterlevel data of the storage of secondary meter 2.
In embodiments of the present invention, above-mentioned secondary meter 2 further includes the test such as power switch key, test starting/stop key Equipment often uses key.
Above-mentioned secondary meter 2 further includes USB interface and network interface;
USB interface restores data for exporting initial water level and drilling water level in borehole in the drilling hole acquired;
Network interface, for connecting secondary meter 2 and data processor 3 by wireline cable.
In embodiments of the present invention, above-mentioned network interface can be divided into wired network interface and radio network interface, above-mentioned Secondary meter 2 can connect the local area network or internet near upper by the network interface, will be deposited by local area network or internet The water pressure data or waterlevel data of storage are transferred to above-mentioned data processor 3.
In drilling water level test device provided in an embodiment of the present invention, the device include hydraulic pressure sensor, secondary meter, Data processor and data cable;The diving end of data cable connects hydraulic pressure sensor, and the ground surface end connection of data cable is secondary Instrument;Hydraulic pressure sensor passes through for acquiring water pressure data in initial water level and hole, and by water pressure data in initial water level and hole Data cable is transferred to secondary meter;Secondary meter sends monitoring order to hydraulic pressure sensor by data cable;It receives, deposit Water pressure data in the initial water level and hole of storage and display hydraulic pressure sensor transmission;Data processor converts water pressure data in hole Restore observation data at water level;Restore observation data according to water level and draws water level recovery curve;It is fitted according to water level recovery curve Water level restores observation curve;Restore observation curve according to water level and obtains hole wall water level;It calculates between initial water level and hole wall water level Depth displacement, obtain drilling water level drawdown value.It realizes fitting water level and restores observation curve, it is bent which is restored observation curve The corresponding water level of the maximum coordinate points of rate is determined as hole wall water level, reduces the error with hopper centre's water level of definition, thus Available accurate drawdown, in exploration process water calculate and evaluation provide accurate parameter, avoid because Hydrogeological parameter mistake and caused by damage.
The above description is merely a specific embodiment, but scope of protection of the present invention is not limited thereto, any Those familiar with the art in the technical scope disclosed by the present invention, can easily think of the change or the replacement, and should all contain Lid is within protection scope of the present invention.Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.

Claims (10)

1. drill-hole pumping water level test method, which is characterized in that the described method includes:
Obtain the initial water level in drilling hole;
It opens water pump and carries out single-well pumping test, obtain water level and restore observation data;
Restore observation data according to the water level, fitting water level restores observation curve;
Restore observation curve according to the water level, obtains hole wall water level;
The depth displacement between the initial water level and the hole wall water level is calculated, drilling water level drawdown value is obtained.
2. drill-hole pumping water level test method according to claim 1, which is characterized in that the unlatching water pump carries out single hole Bailing test obtains water level and restores observation data, comprising:
It opens water pump and carries out test of drawing water;
It after the pumping operation for carrying out preset time period, switches off the pump, is obtained by hydraulic pressure sensor in the hole after stopping pumping Restore water pressure data;
It will restore water pressure data in the hole and be converted into water level recovery observation data.
3. drill-hole pumping water level test method according to claim 1, which is characterized in that described to be restored according to the water level Data are observed, fitting water level restores observation curve, comprising:
Restore observation data according to the water level and draws water level recovery curve;
Water level, which is fitted, according to the water level recovery curve restores observation curve.
4. drill-hole pumping water level test method according to claim 1, which is characterized in that described to be restored according to the water level Observation curve obtains hole wall water level, comprising:
Restore observation curve according to the water level and establishes water level recovery curve observational equation;
According to the water level recovery curve observational equation, calculates the water level and restore the corresponding song of each coordinate points on observation curve Rate;
The coordinate points of maximum curvature are determined from the corresponding curvature of each coordinate points;
The corresponding water level of the coordinate points of the determination is determined as hole wall water level.
5. drill-hole pumping water level test method according to claim 2, which is characterized in that described to carry out preset time period Pumping operation after, switch off the pump, by the hydraulic pressure sensor obtain stop pumping after hole in restore water pressure data, wrap It includes:
After the pumping operation for carrying out preset time period, switches off the pump, hydraulic pressure in acquisition pores is continued by the hydraulic pressure sensor Data;
Real-time monitoring is carried out to water pressure data in the hole of lasting acquisition, when water pressure data meets in advance in the hole for monitoring to continuously acquire If when stable condition, stopping water pressure data in acquisition pores;
It will be determined as stopping taking out to water pressure data in the hole for stopping obtaining during water pressure data in acquisition pores from switching off the pump Restore water pressure data in hole after water.
6. drilling water level test device, which is characterized in that described device includes hydraulic pressure sensor, secondary meter, data processor And data cable;
The diving end of the data cable connects the hydraulic pressure sensor, and the ground surface end of the data cable connects the secondary instrument Table;
The hydraulic pressure sensor, for acquiring water pressure data in initial water level and hole, and by hydraulic pressure in the initial water level and hole Data are transferred to the secondary meter by the data cable;
The secondary meter sends monitoring order to the hydraulic pressure sensor by the data cable;It receives, store and shows Water pressure data in the initial water level of the hydraulic pressure sensor transmission and hole;
Water pressure data in the hole is converted into water level and restores observation data by the data processor;Restored according to the water level It observes data and draws water level recovery curve;Water level, which is fitted, according to the water level recovery curve restores observation curve;According to the water Bit recovery observation curve obtains hole wall water level;The depth displacement between initial water level and the hole wall water level is calculated, Drilling Water is obtained Potential drop is worth deeply.
7. drilling water level test device according to claim 6, which is characterized in that described device further includes water pump and metal Bar;
The suction hose of the water pump is bundled with the metallic rod;
The data cable is fixed in the metallic rod, and the hydraulic pressure sensor is fixedly mounted on the diving of the metallic rod End.
8. drilling water level test device according to claim 6, which is characterized in that the secondary meter includes receiving member Part, memory element, control element, signal key and display screen;
The receiving element is connect with the memory element, the display screen and the hydraulic pressure sensor respectively, receives the water Water pressure data in the hole of pressure sensor transmission, and water pressure data is transmitted in the hole to the memory element and the display Screen;The memory element, for storing water pressure data in the hole;The display screen, for showing water pressure data in the hole;
The control element is connect with the memory element, the display screen, the signal key and the hydraulic pressure sensor respectively, The trigger signal of the signal key transmission is received, and monitoring is sent according to the trigger signal and is ordered to the hydraulic pressure sensor, Or according to the trigger signal, from transferring water pressure data in the hole in the memory element, and by hydraulic pressure number in the hole According to being transferred to the display screen.
9. drilling water level test device according to claim 8, which is characterized in that the signal key includes clock and watch check and correction Key, storage key, display key, sample frequency set key, water level conversion key and data export key.
10. drilling water level test device according to claim 8, which is characterized in that the secondary meter further includes that USB connects Mouth and network interface;
The USB interface restores data for exporting initial water level and drilling water level in borehole in the drilling hole acquired;
The network interface, for connecting the secondary meter and the data processor by wireline cable.
CN201910214225.XA 2019-03-20 2019-03-20 Drilling water pumping level testing method and drilling water level testing device Active CN109882158B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910214225.XA CN109882158B (en) 2019-03-20 2019-03-20 Drilling water pumping level testing method and drilling water level testing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910214225.XA CN109882158B (en) 2019-03-20 2019-03-20 Drilling water pumping level testing method and drilling water level testing device

Publications (2)

Publication Number Publication Date
CN109882158A true CN109882158A (en) 2019-06-14
CN109882158B CN109882158B (en) 2023-03-14

Family

ID=66933321

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910214225.XA Active CN109882158B (en) 2019-03-20 2019-03-20 Drilling water pumping level testing method and drilling water level testing device

Country Status (1)

Country Link
CN (1) CN109882158B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110284876A (en) * 2019-06-25 2019-09-27 徐清清 A kind of method and apparatus carrying out multiple water-bearing layer bailing tests in single gun drilling
CN111946333A (en) * 2020-07-02 2020-11-17 临沂矿业集团菏泽煤电有限公司 Simple test and solution method for aquifer hydrogeological parameters under curtain grouting condition
CN113532579A (en) * 2021-05-25 2021-10-22 天地科技股份有限公司 Aquifer water level monitoring method and device, electronic equipment and storage medium

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103162762A (en) * 2011-12-19 2013-06-19 西安广融电气有限公司 Control loop for water level monitor
CN104297129A (en) * 2014-10-29 2015-01-21 中国电建集团成都勘测设计研究院有限公司 Hydrogeologic testing method based on water injection free vibration method
CN104597224A (en) * 2015-01-27 2015-05-06 河南理工大学 Three-drop distance non-steady flow dewatering test method for probing mine hydrogeology
CN104612663A (en) * 2013-11-05 2015-05-13 核工业二一六大队 Vehicle-mounted borehole water level meter
CN105386430A (en) * 2015-10-16 2016-03-09 上海交通大学 Method for confirming water head of two sides of waterproof curtain under waterproof curtain effect
CN106485018A (en) * 2016-10-21 2017-03-08 安徽理工大学 One kind asks for infiltration coefficient method for coal mine roof plate outflow test
CN107941675A (en) * 2017-12-01 2018-04-20 黄河勘测规划设计有限公司 Drill slug test test method
CN109184663A (en) * 2018-10-11 2019-01-11 中煤科工集团西安研究院有限公司 A method of drilling specific capacity is obtained using outflow test

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103162762A (en) * 2011-12-19 2013-06-19 西安广融电气有限公司 Control loop for water level monitor
CN104612663A (en) * 2013-11-05 2015-05-13 核工业二一六大队 Vehicle-mounted borehole water level meter
CN104297129A (en) * 2014-10-29 2015-01-21 中国电建集团成都勘测设计研究院有限公司 Hydrogeologic testing method based on water injection free vibration method
CN104597224A (en) * 2015-01-27 2015-05-06 河南理工大学 Three-drop distance non-steady flow dewatering test method for probing mine hydrogeology
CN105386430A (en) * 2015-10-16 2016-03-09 上海交通大学 Method for confirming water head of two sides of waterproof curtain under waterproof curtain effect
CN106485018A (en) * 2016-10-21 2017-03-08 安徽理工大学 One kind asks for infiltration coefficient method for coal mine roof plate outflow test
CN107941675A (en) * 2017-12-01 2018-04-20 黄河勘测规划设计有限公司 Drill slug test test method
CN109184663A (en) * 2018-10-11 2019-01-11 中煤科工集团西安研究院有限公司 A method of drilling specific capacity is obtained using outflow test

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
原国红等: "水文地质参数自动监测处理系统的研制与应用", 《岩石力学与工程学报》 *
张海: "单孔抽水试验中水文地质的参数计算", 《住宅与房地产》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110284876A (en) * 2019-06-25 2019-09-27 徐清清 A kind of method and apparatus carrying out multiple water-bearing layer bailing tests in single gun drilling
CN111946333A (en) * 2020-07-02 2020-11-17 临沂矿业集团菏泽煤电有限公司 Simple test and solution method for aquifer hydrogeological parameters under curtain grouting condition
CN111946333B (en) * 2020-07-02 2021-05-18 临沂矿业集团菏泽煤电有限公司 Simple test and solution method for aquifer hydrogeological parameters under curtain grouting condition
CN113532579A (en) * 2021-05-25 2021-10-22 天地科技股份有限公司 Aquifer water level monitoring method and device, electronic equipment and storage medium
CN113532579B (en) * 2021-05-25 2024-02-20 天地科技股份有限公司 Water level monitoring method and device for aquifer, electronic equipment and storage medium

Also Published As

Publication number Publication date
CN109882158B (en) 2023-03-14

Similar Documents

Publication Publication Date Title
CN109882158A (en) Drill-hole pumping water level test method and drilling water level test device
CN101813478B (en) Ground sedimentation monitoring system
US11603755B2 (en) Downhole rock debris extraction system and control method for downhole rock debris extraction system
CN112253083B (en) Automatic positioning device and method for drilling
CN105091840A (en) Guide-wheel-free inclinometer for measuring deep displacement of landslide and installation method thereof
CN202688979U (en) Integral monitoring system of foundation pit under construction
CN110284876A (en) A kind of method and apparatus carrying out multiple water-bearing layer bailing tests in single gun drilling
CN102263690B (en) Method for uploading data in measurement-while-drilling system
CN109183861A (en) A kind of foundation pit intelligent monitoring method and monitoring system based on mems sensor
CN105041298A (en) Device and method for wirelessly positioning depths of strings in real time during coiled tubing operation
CN207991517U (en) A kind of automated watch-keeping facility of settlement of foundation
CN110924457A (en) Foundation pit deformation monitoring method and system based on measuring robot
CN103498660B (en) The moisture long-distance metering device of individual well and individual well moisture content data transmission method
CN205138544U (en) Intelligence is measured and is managed integration system based on internet
CN1982648A (en) Data collecting system at bottom of unbalancing borehole
CN211043430U (en) Underground water flow direction and flow velocity monitoring device
CN207833303U (en) Construction speed monitors system, server and terminal device
CN106351649A (en) Magnetoinductive wave intelligent drill pipe measuring system
CN107355214B (en) Oil-submersible linear motor reciprocating pump closed-loop control system
CN214066037U (en) Scalable tubular earth's surface subsides automatic monitoring device
CN112096370B (en) Self-learning method of intermittent system
CN108768501A (en) A kind of oil field Data transfer system and method based on Beidou satellite communication
CN112240198B (en) Method and device for measuring drilling depth by water level
CN107941675A (en) Drill slug test test method
CN111006742B (en) Underground mine main draw shaft material level real-time monitoring system and method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant