CN109800509A - A kind of building method of the curved wall based on BIM - Google Patents
A kind of building method of the curved wall based on BIM Download PDFInfo
- Publication number
- CN109800509A CN109800509A CN201910060564.7A CN201910060564A CN109800509A CN 109800509 A CN109800509 A CN 109800509A CN 201910060564 A CN201910060564 A CN 201910060564A CN 109800509 A CN109800509 A CN 109800509A
- Authority
- CN
- China
- Prior art keywords
- curved wall
- information
- built
- constructing operation
- staff
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 44
- 238000010276 construction Methods 0.000 claims description 22
- 230000003542 behavioural effect Effects 0.000 claims description 17
- 230000000694 effects Effects 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 3
- 238000009435 building construction Methods 0.000 description 2
- 238000004088 simulation Methods 0.000 description 2
- 235000013399 edible fruits Nutrition 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 230000002123 temporal effect Effects 0.000 description 1
Abstract
The invention discloses a kind of building methods of curved wall based on BIM, are related to building field, and the masonry for solving curved wall only waits and can find to build the problem in building courses, its key points of the technical solution are that: obtain curved wall information;Drawing and actual ratio A are chosen according to curved wall information, and draws the two-dimentional drawing of curved wall according to drawing and actual ratio A;The threedimensional model BIM of curved wall is established according to the two-dimentional drawing of drafting;Based on BIM, threedimensional model dynamic analog is built to the dynamic process of curved wall, and simulates the constructing operation information and constructing operation points for attention information for being loaded with standard in the dynamic process for building curved wall;Staff is according to the masonry for opening curved wall based on the information in BIM, a kind of building method of curved wall based on BIM of the invention, the dynamic process of curved wall is built by threedimensional model dynamic analog, is found the problem during dynamic analog builds curved wall convenient for staff to correct.
Description
Technical field
The present invention relates to building field, in particular to the building method of a kind of curved wall based on BIM.
Background technique
Building Information Model is the new tool of architecture, engineering science and civil engineering.Building Information Model (Building
Information Modeling, abbreviation BIM), it is defined as by constituting completely with insufficient information to support life cycle management,
And it can be by building or architectural engineering information model that computer applied algorithm is directly explained.In short, i.e. digital technology support
Life cycle management to architectural environment.Existing building construction is assisted using BIM technology, is that the one of construction becomes greatly
Gesture.
The masonry of existing curved wall is built according to CAD two dimension drawing, and the best side of construction cannot be obtained
Case, and can find to build the problem in only equal building courses, this is time-consuming and laborious for building construction, influences work
Cheng Jindu.
Summary of the invention
The object of the present invention is to provide a kind of building methods of curved wall based on BIM, pass through threedimensional model dynamic analog
The proposed dynamic process for making curved wall is found the problem convenient for staff during dynamic analog builds curved wall to repair
Just.
Above-mentioned technical purpose of the invention has the technical scheme that
A kind of building method of the curved wall based on BIM, comprising:
(1), the curved wall information for needing to build is obtained;
(2), the curved wall information built as needed chooses drawing and actual ratio A, and draws according to drawing and actual ratio A
The two-dimentional drawing for the curved wall that system needs to build;
(3), the threedimensional model BIM for needing the curved wall built is established according to the two-dimentional drawing of drafting;
(4), it is based on BIM, threedimensional model dynamic analog is built to the dynamic process of curved wall, and simulate and build curved wall
The constructing operation information and constructing operation points for attention information of standard are loaded in dynamic process;
(5), staff is according to the masonry for opening curved wall based on the information in BIM.
By using above-mentioned technical proposal, the curved wall for needing to build is drawn according to suitable drawing and actual ratio A
Two-dimentional drawing, establish the threedimensional model BIM of curved wall again according to two-dimentional drawing, and threedimensional model dynamic analog builds arc
The dynamic process of shape wall is found the problem during dynamic analog builds curved wall convenient for staff to correct;
Simulate the constructing operation information and constructing operation points for attention information for building the dynamic process Plays of curved wall
Load, plays and instructs staff's constructing operation effect, reduces unreasonable operation of staff during constructing operation, with
Ensure built curved wall quality.
The present invention is further arranged to: the curved wall information that the needs in (1) are built includes the arc for needing to build
The geographical location information for the curved wall that the dimension information and needs of shape wall are built.
By using above-mentioned technical proposal, the acquisition of the dimension information for the curved wall that need to be built builds arc convenient for responsible
The quantity and completion date of responsible person's reasonable arrangement high level operational personnel of wall, intermediate staff, primary staff;
The acquisition of the geographical location information for the curved wall that need to be built, convenient for being responsible for building the responsible person of curved wall according to the geography position
Set the good required masonry tool of reasonable arrangement.
The present invention is further arranged to: the constructing operation Step Information in (4) includes: a, curved wall payoff operation
Information;B, construction builds operation information.
By using above-mentioned technical proposal, constructing operation Step Information includes: a, curved wall payoff operation information;B, it applies
Work builds operation information, is good at the behaviour in each constructing operation step of responsible person's reasonable arrangement convenient for being responsible for building curved wall
Make the staff of step, improves working efficiency and quality.
The present invention is further arranged to: curved wall unwrapping wire is operated using string away from method.
By using above-mentioned technical proposal, curved wall line-putting method uses string away from method, to ensure the too long of curved wall of string
The construction effect of body.
The present invention is further arranged to: further include:
(6), the constructing operation information that staff builds in this curved wall is obtained;
From the corresponding relationship between pre-set, standard constructing operation information and monitoring center behavioural information, search with
The corresponding monitoring center behavioural information of constructing operation information that this described curved wall is built;The monitoring center behavioural information
The constructing operation information that this curved wall is built is compared with the constructing operation information of standard: when this curved wall is built
The constructing operation information built is consistent with the constructing operation information of standard, gives staff and supports information, when this curved wall
The constructing operation information of masonry and the constructing operation information of standard do not give staff then unanimously and oppose information.
By using above-mentioned technical proposal, staff is given in the constructing operation information that this curved wall is built and is marked
Quasi- constructing operation information compares, when the constructing operation information of constructing operation information and standard that this curved wall is built
It is consistent then give staff support information, when this curved wall build constructing operation information and standard constructing operation believe
Breath does not give staff then unanimously and opposes information, convenient for staff according to support information, opposition information to understand itself
Constructing operation ability.
The present invention is further arranged to: (6) further include:
Record storage is carried out to monitoring center behavioural information.
By using above-mentioned technical proposal, monitoring center behavioural information carries out record storage, at any time may be used convenient for staff
It transfers and checks.
The present invention is further arranged to: (6) further include:
This curved wall build after the completion of according to monitoring center behavioural information to automatically generate to participate in this curved wall
The merit rating information of the staff of masonry.
By using above-mentioned technical proposal, monitoring center behavioural information is automatically generated to participation this curved wall masonry
The merit rating information of staff, so that staff or the responsible responsible person for building curved wall are directly viewable work people
The merit rating information of member, more convenient, intelligence.
The present invention is further arranged to: the constructing operation information that this curved wall of the staff is built includes work
The construction operation time information that this curved wall of personnel is built;The constructing operation information of the standard is the constructing operation of standard
Temporal information;
When the construction operation time information that this staff's curved wall is built is consistent with the construction operation time information of standard
Then give staff support information, when this curved wall build constructing operation information and standard constructing operation information not
It is consistent then give staff oppose information.
By using above-mentioned technical proposal, the construction operation time information built to this curved wall of staff is given
The construction operation time information of standard compares, and then the construction operation time built to this curved wall is monitored,
It avoids the problem that slack, delay engineering occurs in staff, improves the working efficiency of staff.
In conclusion the invention has the following advantages:
1, the threedimensional model BIM of curved wall is established according to two-dimentional drawing, and threedimensional model dynamic analog builds curved wall
Dynamic process is found the problem during dynamic analog builds curved wall convenient for staff to correct;
2, the constructing operation information and constructing operation points for attention information of the dynamic process Plays of curved wall are built in simulation
Load, play and instruct staff's constructing operation effect, reduce unreasonable operation of staff during constructing operation,
To ensure built curved wall quality.
Detailed description of the invention
Fig. 1 is the flow chart of the building method of the curved wall based on BIM.
Specific embodiment
Below in conjunction with attached drawing 1, invention is further described in detail.
The embodiment of the present invention provides a kind of building method of curved wall based on BIM, comprising:
(1), the curved wall information for needing to build is obtained;
(2), the curved wall information built as needed chooses drawing and actual ratio A, and draws according to drawing and actual ratio A
The two-dimentional drawing for the curved wall that system needs to build;
(3), the threedimensional model BIM for needing the curved wall built is established according to the two-dimentional drawing of drafting;
(4), it is based on BIM, threedimensional model dynamic analog is built to the dynamic process of curved wall, and simulate and build curved wall
The constructing operation information and constructing operation points for attention information of standard are loaded in dynamic process;
(5), staff is according to the masonry for opening curved wall based on the information in BIM.
The two-dimentional drawing for needing the curved wall built is drawn according to suitable drawing and actual ratio A, again according to two
Dimension drawing establishes the threedimensional model BIM of curved wall, and threedimensional model dynamic analog builds the dynamic process of curved wall, is convenient for
Staff is found the problem during dynamic analog builds curved wall to correct;The dynamic process of curved wall is built in simulation
The load of the constructing operation information and constructing operation points for attention information of Plays is played and staff's constructing operation is instructed to imitate
Fruit reduces unreasonable operation of staff during constructing operation, to ensure built curved wall quality.
(1) the curved wall information that the needs in are built includes the dimension information and needs for needing the curved wall built
The geographical location information of the curved wall of masonry;Namely the arc for needing the size of the curved wall built and needs to build
The geographical location of wall.
The acquisition of the size for the curved wall that need to be built is convenient for the responsible responsible person's reasonable arrangement for building curved wall
The quantity and completion date of high level operational personnel, intermediate staff, primary staff;The ground for the curved wall that need to be built
The acquisition of position is managed, convenient for being responsible for building the responsible person of curved wall according to the good required masonry of the geographical location reasonable arrangement
Tool.
(4) the constructing operation Step Information in includes: a, curved wall payoff operation information;B, construction builds operation letter
Breath.Wherein, curved wall unwrapping wire is operated using string away from method.String away from method arc fragmenting at several segments, it is then that these are small
The endpoint line of section.
The building method of curved wall based on BIM further include:
(6), the constructing operation information that staff builds in this curved wall is obtained;
From the corresponding relationship between pre-set, standard constructing operation information and monitoring center behavioural information, search with
The corresponding monitoring center behavioural information of constructing operation information that this curved wall is built;Monitoring center behavioural information is by this arc
The constructing operation information of shape building wall is compared with the constructing operation information of standard: when the construction that this curved wall is built
Operation information is consistent with the constructing operation information of standard, gives staff and supports information, when what this curved wall was built applies
The constructing operation information of work operation information and standard does not give staff then unanimously and opposes information.
Staff is carried out in the constructing operation information that the constructing operation information that this curved wall is built gives standard
Comparison, when this curved wall build constructing operation information it is consistent with the constructing operation information of standard, give staff's branch
Information is held, when the constructing operation information of constructing operation information and standard that this curved wall is built does not give work people then unanimously
Member opposes information, understands the constructing operation ability of itself according to information, opposition information is supported convenient for staff.
The building method of curved wall based on BIM further include: record storage is carried out to monitoring center behavioural information, is convenient for
Staff can transfer check at any time.And further include: according to monitoring center behavioural information after the completion of this curved wall is built
To automatically generating to the merit rating information for participating in the staff that this curved wall is built, so that staff or responsible
The responsible person for building curved wall is directly viewable the merit rating information of staff, more convenient, intelligence.
For avoid the problem that staff occur it is slack, delay engineering, in an alternative embodiment of the invention, staff this
The constructing operation information that curved wall is built includes the construction operation time information that this curved wall of staff is built, namely
The construction operation time that this curved wall of staff is built;The constructing operation information of standard is the construction operation time of standard
Information;When the construction operation time information that this staff's curved wall is built is consistent with the construction operation time information of standard
Then give staff support information, when this curved wall build constructing operation information and standard constructing operation information not
It is consistent then give staff oppose information;To improve the working efficiency of staff.
The technical solution of the application substantially the part that contributes to existing technology or the technical solution in other words
Completely or partially it can be embodied in the form of software products, which is stored in a storage medium,
Including some instructions use so that a computer equipment (can be personal computer, server or the network equipment etc.) or
The all or part of the steps of processor (processor) the execution each embodiment method of the application.
Above embodiments are only described in detail to the technical solution to the application, but the explanation of above embodiments is only
It is to be used to help understand method and its core concept of the invention, should not be construed as limiting the invention.The art
In the technical scope disclosed by the present invention, any changes or substitutions that can be easily thought of by technical staff, should all cover in guarantor of the invention
Within the scope of shield.
Claims (8)
1. a kind of building method of the curved wall based on BIM characterized by comprising
(1), the curved wall information for needing to build is obtained;
(2), the curved wall information built as needed chooses drawing and actual ratio A, and draws according to drawing and actual ratio A
The two-dimentional drawing for the curved wall that system needs to build;
(3), the threedimensional model BIM for needing the curved wall built is established according to the two-dimentional drawing of drafting;
(4), it is based on BIM, threedimensional model dynamic analog is built to the dynamic process of curved wall, and simulate and build curved wall
The constructing operation information and constructing operation points for attention information of standard are loaded in dynamic process;
(5), staff is according to the masonry for opening curved wall based on the information in BIM.
2. the building method of a kind of curved wall based on BIM according to claim 1, it is characterized in that: in (1)
The curved wall information for needing to build includes the curved wall for needing the dimension information of the curved wall built and needs to build
Geographical location information.
3. the building method of a kind of curved wall based on BIM according to claim 1, it is characterized in that: in (4)
Constructing operation Step Information includes: a, curved wall payoff operation information;B, construction builds operation information.
4. the building method of a kind of curved wall based on BIM according to claim 3, it is characterized in that: curved wall is put
Line is operated using string away from method.
5. a kind of building method of curved wall based on BIM according to claim 1, it is characterized in that: further include:
(6), the constructing operation information that staff builds in this curved wall is obtained;
From the corresponding relationship between pre-set, standard constructing operation information and monitoring center behavioural information, search with
The corresponding monitoring center behavioural information of constructing operation information that this described curved wall is built;The monitoring center behavioural information
The constructing operation information that this curved wall is built is compared with the constructing operation information of standard: when this curved wall is built
The constructing operation information built is consistent with the constructing operation information of standard, gives staff and supports information, when this curved wall
The constructing operation information of masonry and the constructing operation information of standard do not give staff then unanimously and oppose information.
6. the building method of a kind of curved wall based on BIM according to claim 5, it is characterized in that: (6) are also wrapped
It includes:
Record storage is carried out to monitoring center behavioural information.
7. the building method of a kind of curved wall based on BIM according to claim 5, it is characterized in that: (6) are also wrapped
It includes:
This curved wall to participation is automatically generated according to monitoring center behavioural information after the completion of this curved wall is built to build
The merit rating information of the staff built.
8. the building method of a kind of curved wall based on BIM according to claim 5, it is characterized in that: the work people
The constructing operation information that this curved wall of member is built includes the construction operation time letter that this curved wall of staff is built
Breath;The constructing operation information of the standard is the construction operation time information of standard;
When the construction operation time information that this staff's curved wall is built is consistent with the construction operation time information of standard
Then give staff support information, when this curved wall build constructing operation information and standard constructing operation information not
It is consistent then give staff oppose information.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910060564.7A CN109800509A (en) | 2019-01-22 | 2019-01-22 | A kind of building method of the curved wall based on BIM |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910060564.7A CN109800509A (en) | 2019-01-22 | 2019-01-22 | A kind of building method of the curved wall based on BIM |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109800509A true CN109800509A (en) | 2019-05-24 |
Family
ID=66560143
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910060564.7A Pending CN109800509A (en) | 2019-01-22 | 2019-01-22 | A kind of building method of the curved wall based on BIM |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109800509A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112700548A (en) * | 2021-01-08 | 2021-04-23 | 中国南方电网有限责任公司超高压输电公司广州局 | Fusion method of BIM (building information modeling) model and video information in visual transformer substation |
CN112814146A (en) * | 2020-12-31 | 2021-05-18 | 湖北创威建筑装饰工程有限公司 | BIM technology-based wall green construction method |
CN117172426A (en) * | 2023-11-01 | 2023-12-05 | 浙江东南设计集团有限公司 | Low-carbonization construction method, system and storage medium for urban and rural buildings |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107451358A (en) * | 2017-07-28 | 2017-12-08 | 成都智建新业建筑设计咨询有限公司 | A kind of building method of the curved wall based on BIM |
-
2019
- 2019-01-22 CN CN201910060564.7A patent/CN109800509A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107451358A (en) * | 2017-07-28 | 2017-12-08 | 成都智建新业建筑设计咨询有限公司 | A kind of building method of the curved wall based on BIM |
Non-Patent Citations (6)
Title |
---|
全国建设职业教育系列教材: "《建筑结构施工实际操作》", 中国建筑工业出版社, pages: 27 * |
姚建南等: "BIM技术在建筑工程施工中的应用", 《江西建材》 * |
姚建南等: "BIM技术在建筑工程施工中的应用", 《江西建材》, no. 18, 30 September 2017 (2017-09-30), pages 69 * |
陆彪: "BIM对建筑工程施工技术的影响分析", 《建筑施工》 * |
陆彪: "BIM对建筑工程施工技术的影响分析", 《建筑施工》, no. 02, 25 February 2017 (2017-02-25), pages 107 - 109 * |
陈杨光: "BIM技术在建筑施工安全管理中的应用研究", 《山西建筑》, no. 34, 1 December 2017 (2017-12-01), pages 252 - 253 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112814146A (en) * | 2020-12-31 | 2021-05-18 | 湖北创威建筑装饰工程有限公司 | BIM technology-based wall green construction method |
CN112700548A (en) * | 2021-01-08 | 2021-04-23 | 中国南方电网有限责任公司超高压输电公司广州局 | Fusion method of BIM (building information modeling) model and video information in visual transformer substation |
CN117172426A (en) * | 2023-11-01 | 2023-12-05 | 浙江东南设计集团有限公司 | Low-carbonization construction method, system and storage medium for urban and rural buildings |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109800509A (en) | A kind of building method of the curved wall based on BIM | |
CN102360535A (en) | Three-dimensional visual simulation training system and method | |
CN106960410A (en) | Underground pipe gallery approaches to IM based on BIM and GIS technology | |
CN103280137B (en) | 220KV power transformer 3D modelling system | |
CN108022039A (en) | A kind of Substation Training Simulator based on augmented reality | |
CN103065513A (en) | Three-dimensional virtual training system of transformer equipment | |
CN101520951A (en) | Training system for ultra-high voltage transmission system overvoltage and insulation coordination technology | |
CN112884290A (en) | BIM-based field construction management method | |
CN108153932A (en) | The modeling of Table top type three-dimensional Maintenance Model | |
CN107679332B (en) | Transmission tower BIM model construction method based on Tekla platform | |
CN106789332B (en) | Computer room visualized management operation platform and method | |
Stanilov | Bridging the gap between urban morphology and urban modelling K. Stanilov | |
CN111428310A (en) | Underground pipe gallery model construction method based on BIM and GIS | |
CN107515966A (en) | A kind of radar simulator system layering construction method based on DDS | |
JP2010183703A (en) | Large region power system simulator and simulation method | |
CN110675072A (en) | BIM-based transformer substation construction process control method | |
CN104050342B (en) | Transformer substation soft wire assembling simulating optimization design system | |
CN103268386A (en) | 110kVGL312 sulfur hexafluoride breaker three-dimensional model system | |
CN103839476A (en) | Three-dimensional simulation system for production supervision of assembly of transformer | |
CN116341064A (en) | Modeling system and method of intelligent substation cloud system based on 3DMax modeling | |
CN111968015B (en) | Interactive training method for power transmission and transformation project construction process | |
CN110502838A (en) | Spare parts management strategy optimization model based on emulation | |
CN202650332U (en) | Virtual simulation training system of distributed transformer substation based on province, prefecture and county level networks | |
Gao et al. | The Research and Development of Integrated Operation-Maintenance Simulation Training System [J] | |
CN103268719A (en) | Three-dimensional model system of 220 KVGL314 sulphur hexafluoride circuit breaker |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190524 |