CN109772768A - A kind of operating method of photovoltaic solar panel maintenance facility - Google Patents
A kind of operating method of photovoltaic solar panel maintenance facility Download PDFInfo
- Publication number
- CN109772768A CN109772768A CN201910101945.5A CN201910101945A CN109772768A CN 109772768 A CN109772768 A CN 109772768A CN 201910101945 A CN201910101945 A CN 201910101945A CN 109772768 A CN109772768 A CN 109772768A
- Authority
- CN
- China
- Prior art keywords
- solar panel
- photovoltaic solar
- cabinet
- bolt
- maintenance facility
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/50—Photovoltaic [PV] energy
Abstract
A kind of operating method of photovoltaic solar panel maintenance facility, a kind of photovoltaic solar panel maintenance facility includes cabinet, mounting plate, driving motor, fixing bearing, battery, rubber slab, clean hatch, fixing sucking disk, transmission shaft, cleaning assemblies, linking arm, vertical plate, second sliding block and shifting roller, the top side of the cabinet is equipped with vertical plate by bolt, the side of the vertical plate is provided with linking arm, cleaning assemblies is provided on the outside of the linking arm, the cleaning assemblies includes equipment box, dust catcher, connect hose, partition is installed, cylinder, piston rod, push plate, sweep-up pipe, dust removal port, connecting rod, cleaning brush and the first sliding block, the inside of the equipment box is equipped with installation partition by bolt, the top of the installation partition is equipped with cylinder by bolt, the photovoltaic solar panel maintenance facility, knot Structure is simple, cleaning dedusting can be carried out to photovoltaic solar panel, cleaning effect is good, can effectively improve the service life of photovoltaic solar panel.
Description
Technical field
The present invention relates to photovoltaic solar panel technical field, specially a kind of operation of photovoltaic solar panel maintenance facility
Method.
Background technique
Photovoltaic solar panel is that solar radiant energy is passed through photoelectric effect or photochemical effect is straight by absorbing sunlight
It connects or indirect conversion is at the device of electric energy, the main material of most of solar panel is " silicon ";Photovoltaic solar panel makes
It during, is usually an exposure in air, to be easy the surface accumulation dust so that photovoltaic solar panel, makes for a long time
Used time seriously affects the generating effect and service life of photovoltaic solar panel, traditional maintenance if dust not cleaned
Method is usually manually cleaned, and cleaning effect is poor, therefore, designs a kind of operation of photovoltaic solar panel maintenance facility
Method is necessary.
Summary of the invention
The purpose of the present invention is to provide a kind of operating methods of photovoltaic solar panel maintenance facility, to solve above-mentioned back
The problem of being proposed in scape technology.
The purpose of the present invention can be achieved through the following technical solutions:
A kind of operating method of photovoltaic solar panel maintenance facility, a kind of photovoltaic solar panel maintenance facility
Including cabinet, mounting plate, driving motor, fixing bearing, battery, rubber slab, clean hatch, fixing sucking disk, transmission shaft, cleaning group
The top side of part, linking arm, vertical plate, the second sliding block and shifting roller, the cabinet is equipped with vertical plate by bolt, described vertical
The side of plate is provided with linking arm, and cleaning assemblies is provided on the outside of the linking arm, and the cleaning assemblies includes equipment box, inhales
Dirt device, connection hose, installation partition, cylinder, piston rod, push plate, sweep-up pipe, dust removal port, connecting rod, cleaning brush and first are sliding
The inside of block, the equipment box is equipped with installation partition by bolt, and the top of the installation partition is equipped with gas by bolt
Cylinder is equipped with dust catcher at the top of the cylinder, and the bottom of the equipment box is provided with push plate, and the bottom side of the push plate is solid
Dingan County is equipped with sweep-up pipe, and the bottom of sweep-up pipe is equipped with dust removal port, and the bottom other side of the push plate is fixedly installed with connection
Bar, and the bottom of connecting rod is fixedly installed with cleaning brush, the inside of the cabinet is equipped with mounting plate by bolt, described
The inside bottom of cabinet is provided with rubber slab, and battery is fixedly installed at the top of rubber slab, and the top of the cabinet is another
Side is provided with clean hatch, and the top surrounding of clean hatch is separately installed with fixing sucking disk, and the bottom surrounding of the cabinet is led to respectively
It crosses bolt and shifting roller is installed;
A kind of operating method of the photovoltaic solar panel maintenance facility, specific steps are as follows:
In use, cabinet is moved to suitable position by shifting roller, photovoltaic solar panel is placed on clean hatch
Top, photovoltaic solar panel is fixed by four fixing sucking disks, the battery at the top of rubber slab be the equipment power supply, pass through
Second sliding slot is moved on the second sliding block of vertical plate side, so that linking arm is moved to suitable height, then passes through the
One sliding slot is mobile in the outside of the first sliding block, so that equipment box is moved to suitable distance, the driving motor at the top of mounting plate
Work drives transmission shaft rotation, under the action of fixing bearing, so that clean hatch and photovoltaic solar panel are rotated, passes through
Cleaning assemblies cleans photovoltaic solar panel, installs the cylinder operation at the top of partition, and piston rod is pushed to move down, and then pushes
Push plate moves down, and until the cleaning brush of connecting rod bottom is contacted with photovoltaic solar panel, cleans to photovoltaic solar panel, together
When, the clean dust of cleaning brush is sucked the inside of dust catcher by dust catcher work by dust removal port and sweep-up pipe through connection hose,
As clean hatch constantly rotates and the position of mobile connection arm and equipment box, so as to by the different portions of photovoltaic solar panel
It is cleaned position.
As a further solution of the present invention: the top side of the vertical plate is provided with the second sliding block, the linking arm
Side offers second sliding slot, and the second sliding block is slidably connected with second sliding slot.
As a further solution of the present invention: the side of the equipment box is provided with the first sliding block, and the one of the linking arm
Side offers first sliding groove, and the first sliding block is slidably connected with first sliding groove.
As a further solution of the present invention: the bottom of the cylinder is fitted with piston rod, and piston rod is passed through and set
Standby case is connect by bolt with push plate.
As a further solution of the present invention: the bottom air entry of the dust catcher is fixedly installed with connection hose, and even
Hose is connect to connect across equipment box and push plate with sweep-up pipe.
As a further solution of the present invention: the top side of the mounting plate is equipped with driving motor by bolt, and
The top of driving motor is equipped with transmission shaft by shaft coupling, and the top side of the cabinet is equipped with fixing bearing, and is driven
Axis passes through fixing bearing and is fixedly connected with clean hatch.
Beneficial effects of the present invention: the maintenance facility, structure is simple, easy to operate, in use, passing through driving motor work
Make, drives transmission shaft rotation, under the action of fixing bearing, so that clean hatch and photovoltaic solar panel are rotated, pass through gas
Cylinder pushes piston rod to move down, and then push plate is pushed to move down, right until the cleaning brush of connecting rod bottom is contacted with photovoltaic solar panel
Photovoltaic solar panel is cleaned, meanwhile, the clean dust of cleaning brush is entered the inside of dust catcher, with clear by dust catcher work
The position of clean continuous rotation and mobile connection arm and equipment box, so as to carry out the different parts of photovoltaic solar panel
Cleaning, cleaning effect is good, avoids the surface that dust is deposited in photovoltaic solar panel for a long time, can effectively improve photovoltaic solar
The service life of energy plate.
Detailed description of the invention
In order to facilitate the understanding of those skilled in the art, the present invention will be further described below with reference to the drawings.
Fig. 1 is overall structure of the present invention;
Fig. 2 is the schematic diagram of internal structure of cabinet of the present invention;
Fig. 3 is the structural schematic diagram of cleaning assemblies of the present invention;
Fig. 4 is the cross-sectional view of cleaning assemblies of the present invention;
In figure: 1, cabinet;2, mounting plate;3, driving motor;4, fixing bearing;5, battery;6, rubber slab;7, it cleans
Platform;8, fixing sucking disk;9, transmission shaft;10, cleaning assemblies;11, equipment box;12, dust catcher;13, hose is connected;14, installation every
Plate;15, cylinder;16, piston rod;17, push plate;18, sweep-up pipe;19, dust removal port;20, connecting rod;21, cleaning brush;22, first
Sliding block;23, linking arm;24, vertical plate;25, the second sliding block;26, shifting roller.
Specific embodiment
Technical solution of the present invention is clearly and completely described below in conjunction with embodiment, it is clear that described reality
Applying example is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, this field is general
Logical technical staff all other embodiment obtained without creative efforts belongs to what the present invention protected
Range.
As shown in Figs 1-4, a kind of operating method of photovoltaic solar panel maintenance facility, a kind of photovoltaic solar
Plate maintenance facility includes cabinet 1, mounting plate 2, driving motor 3, fixing bearing 4, battery 5, rubber slab 6, clean hatch 7, consolidates
Determine sucker 8, transmission shaft 9, cleaning assemblies 10, linking arm 23, vertical plate 24, the second sliding block 25 and shifting roller 26, the top of cabinet 1
Side is equipped with vertical plate 24 by bolt, and the side of vertical plate 24 is provided with linking arm 23, and the top side of vertical plate 24 is provided with
Two sliding blocks 25, the side of linking arm 23 offers second sliding slot, and the second sliding block 25 is slidably connected with second sliding slot, convenient for connection
Arm 23 is moved forward and backward by second sliding slot in the outside of the second sliding block 25;The outside of linking arm 23 is provided with cleaning assemblies
10, cleaning assemblies 10 includes equipment box 11, dust catcher 12, connection hose 13, installation partition 14, cylinder 15, piston rod 16, push plate
17, sweep-up pipe 18, dust removal port 19, connecting rod 20, cleaning brush 21 and the first sliding block 22, it is sliding that the side of equipment box 11 is provided with first
Block 22, the side of linking arm 23 offers first sliding groove, and the first sliding block 22 is slidably connected with first sliding groove, is convenient for equipment box 11
Moved left and right by first sliding groove in the outside of the first sliding block 22, the inside of equipment box 11 by bolt be equipped with installation every
The top of plate 14, installation partition 14 is equipped with cylinder 15 by bolt, and the top of cylinder 15 is equipped with dust catcher 12, equipment box 11
Bottom be provided with push plate 17, the bottom of cylinder 15 is fitted with piston rod 16, and piston rod 16 passes through equipment box 11 and passes through
Bolt is connect with push plate 17, and convenient for pushing push plate 17 to carry out lifting moving by piston rod 16, the bottom side of push plate 17 is fixed
Sweep-up pipe 18 is installed, and the bottom of sweep-up pipe 18 is equipped with dust removal port 19, the bottom air entry of dust catcher 12 is fixedly installed with
Hose 13 is connected, and connects hose 13 and is connect across equipment box 11 and push plate 17 with sweep-up pipe 18, is convenient for cleaning, push plate 17
The bottom other side be fixedly installed with connecting rod 20, and the bottom of connecting rod 20 is fixedly installed with cleaning brush 21, the inside of cabinet 1
Mounting plate 2 is installed by bolt, the inside bottom of cabinet 1 is provided with rubber slab 6, and the top of rubber slab 6 is fixedly installed with
Battery 5, the top other side of cabinet 1 is provided with clean hatch 7, and the top surrounding of clean hatch 7 is separately installed with fixing sucking disk
8, the top side of mounting plate 2 is equipped with driving motor 3 by bolt, and the top of driving motor 3 is equipped with by shaft coupling
Transmission shaft 9, the top side of cabinet 1 is equipped with fixing bearing 4, and transmission shaft 9 passes through fixing bearing 4 and the fixed company of clean hatch 7
It connects, convenient for driving clean hatch 7 to be rotated by transmission shaft 9;The bottom surrounding of cabinet 1 passes through bolt respectively and is equipped with mobile rolling
Wheel 26.
In use, cabinet 1 is moved to suitable position by shifting roller 26, photovoltaic solar panel is placed on cleaning
Photovoltaic solar panel is fixed by four fixing sucking disks 8 in the top of platform 7, and the battery 5 at 6 top of rubber slab is equipment confession
Electricity is moved by second sliding slot on the second sliding block 25 of 24 side of vertical plate, so that linking arm 23 is moved to suitably
Highly, then it is mobile in the outside of the first sliding block 22 by first sliding groove, so that equipment box 11 is moved to suitable distance, install
The driving motor 3 at 2 top of plate works, and drives transmission shaft 9 to rotate, under the action of fixing bearing 4, so that clean hatch 7 and photovoltaic
Solar panels are rotated, and are cleaned by cleaning assemblies 10 to photovoltaic solar panel, the cylinder 15 at 14 top of installation partition
Work pushes piston rod 16 to move down, and then push plate 17 is pushed to move down, until the cleaning brush 21 and photovoltaic solar of 20 bottom of connecting rod
Energy plate contact, cleans photovoltaic solar panel, meanwhile, dust catcher 12 works, by the clean dust of cleaning brush 21 by removing
Dirt mouth 19 and sweep-up pipe 18 suck the inside of dust catcher 12 through connection hose 13, as the constantly rotation and movement of clean hatch 7 connects
The position of arm 23 and equipment box 11 is connect, so as to clean the different parts of photovoltaic solar panel.
Present invention disclosed above preferred embodiment is only intended to help to illustrate the present invention.There is no detailed for preferred embodiment
All details are described, are not limited the invention to the specific embodiments described.Obviously, according to the content of this specification,
It can make many modifications and variations.These embodiments are chosen and specifically described to this specification, is in order to better explain the present invention
Principle and practical application, so that skilled artisan be enable to better understand and utilize the present invention.The present invention is only
It is limited by claims and its full scope and equivalent.
Claims (6)
1. a kind of operating method of photovoltaic solar panel maintenance facility, a kind of photovoltaic solar panel with maintenance facility its
It is characterized in that, including cabinet (1), mounting plate (2), driving motor (3), fixing bearing (4), battery (5), rubber slab (6), clear
Clean (7), fixing sucking disk (8), transmission shaft (9), cleaning assemblies (10), linking arm (23), vertical plate (24), the second sliding block (25) and
The top side of shifting roller (26), the cabinet (1) is equipped with vertical plate (24) by bolt, and the side of the vertical plate (24) is set
It is equipped with linking arm (23), is provided with cleaning assemblies (10) on the outside of the linking arm (23), the cleaning assemblies (10) includes setting
Standby case (11), dust catcher (12), installation partition (14), cylinder (15), piston rod (16), push plate (17), are inhaled at connection hose (13)
Dirt pipe (18), dust removal port (19), connecting rod (20), cleaning brush (21) and the first sliding block (22), the inside of the equipment box (11)
Installation partition (14) is installed by bolt, the top of installation partition (14) is equipped with cylinder (15) by bolt, described
It is equipped at the top of cylinder (15) dust catcher (12), the bottom of the equipment box (11) is provided with push plate (17), the push plate
(17) bottom side is fixedly installed with sweep-up pipe (18), and the bottom of sweep-up pipe (18) is equipped with dust removal port (19), described to push away
The bottom other side of plate (17) is fixedly installed with connecting rod (20), and the bottom of connecting rod (20) is fixedly installed with cleaning brush
(21), the inside of the cabinet (1) is equipped with mounting plate (2) by bolt, and the inside bottom of the cabinet (1) is provided with
Rubber slab (6), and battery (5) are fixedly installed at the top of rubber slab (6), the top other side of the cabinet (1) is provided with
Clean hatch (7), and the top surrounding of clean hatch (7) is separately installed with fixing sucking disk (8), the bottom surrounding point of the cabinet (1)
Shifting roller (26) are not equipped with by bolt;
A kind of operating method of the photovoltaic solar panel maintenance facility, specific steps are as follows:
In use, cabinet (1) is moved to suitable position by shifting roller (26), photovoltaic solar panel is placed on cleaning
Photovoltaic solar panel is fixed by four fixing sucking disks (8) in the top of platform (7), and the battery (5) at the top of rubber slab (6) is
Equipment power supply, is moved by second sliding slot on second sliding block (25) of vertical plate (24) side, thus by linking arm
(23) it is moved to suitable height, then mobile in the outside of the first sliding block (22) by first sliding groove, thus by equipment box (11)
It is moved to suitable distance, driving motor (3) work at the top of mounting plate (2) drives transmission shaft (9) rotation, in fixing bearing
(4) under the action of, so that clean hatch (7) and photovoltaic solar panel are rotated, by cleaning assemblies (10) to photovoltaic solar
Plate is cleaned, and cylinder (15) work at the top of installation partition (14) pushes piston rod (16) to move down, and then push push plate (17)
It moves down, until the cleaning brush (21) of connecting rod (20) bottom is contacted with photovoltaic solar panel, photovoltaic solar panel is cleaned,
Meanwhile dust catcher (12) works, cleaning brush (21) clean dust is soft through connecting by dust removal port (19) and sweep-up pipe (18)
The inside for managing (13) sucking dust catcher (12), with clean hatch (7) constantly rotation and mobile connection arm (23) and equipment box
(11) position, so as to clean the different parts of photovoltaic solar panel.
2. a kind of operating method of photovoltaic solar panel maintenance facility according to claim 1, which is characterized in that described
The top side of vertical plate (24) is provided with the second sliding block (25), and the side of the linking arm (23) offers second sliding slot, and
Two sliding blocks (25) are slidably connected with second sliding slot.
3. a kind of operating method of photovoltaic solar panel maintenance facility according to claim 1, which is characterized in that described
The side of equipment box (11) is provided with the first sliding block (22), and the side of the linking arm (23) offers first sliding groove, and first
Sliding block (22) is slidably connected with first sliding groove.
4. a kind of operating method of photovoltaic solar panel maintenance facility according to claim 1, which is characterized in that described
The bottom of cylinder (15) is fitted with piston rod (16), and piston rod (16) passes through equipment box (11) and passes through bolt and push plate
(17) it connects.
5. a kind of operating method of photovoltaic solar panel maintenance facility according to claim 1, which is characterized in that described
The bottom air entry of dust catcher (12) is fixedly installed with connection hose (13), and connects hose (13) and pass through equipment box (11) and push away
Plate (17) is connect with sweep-up pipe (18).
6. a kind of operating method of photovoltaic solar panel maintenance facility according to claim 1, which is characterized in that described
The top side of mounting plate (2) is equipped with driving motor (3) by bolt, and the top of driving motor (3) is pacified by shaft coupling
Equipped with transmission shaft (9), the top side of the cabinet (1) is equipped with fixing bearing (4), and transmission shaft (9) passes through fixing bearing
(4) it is fixedly connected with clean hatch (7).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910101945.5A CN109772768A (en) | 2019-02-01 | 2019-02-01 | A kind of operating method of photovoltaic solar panel maintenance facility |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910101945.5A CN109772768A (en) | 2019-02-01 | 2019-02-01 | A kind of operating method of photovoltaic solar panel maintenance facility |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109772768A true CN109772768A (en) | 2019-05-21 |
Family
ID=66504218
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910101945.5A Pending CN109772768A (en) | 2019-02-01 | 2019-02-01 | A kind of operating method of photovoltaic solar panel maintenance facility |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109772768A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113992143A (en) * | 2021-11-04 | 2022-01-28 | 西安热工研究院有限公司 | Solar photovoltaic power generation cleaning and dust removing system |
CN114450100A (en) * | 2021-12-24 | 2022-05-06 | 无锡市东舟船舶设备股份有限公司 | Synchronous dust removal equipment for processing door plate for large ship |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202683549U (en) * | 2012-05-30 | 2013-01-23 | 北京桑纳斯太阳能电池有限公司 | Small-sized intelligent anhydrous cleaner used in solar PV power station |
EP2551610A1 (en) * | 2011-07-27 | 2013-01-30 | Alberto Piccoli | Photovoltaic and solar panels cleaning machine |
CN205308841U (en) * | 2015-12-02 | 2016-06-15 | 连云港神舟新能源有限公司 | Photovoltaic module self -cleaning system |
CN205851439U (en) * | 2016-08-04 | 2017-01-04 | 魏显文 | Mobile photovoltaic module cleaning device |
CN206550038U (en) * | 2017-02-14 | 2017-10-13 | 马鞍山佳夫尼电气科技有限公司 | A kind of cleaning device for photovoltaic module |
CN207188264U (en) * | 2017-07-20 | 2018-04-06 | 中国大唐集团科学技术研究院有限公司 | Photovoltaic module cleaning structure |
CN108405383A (en) * | 2018-01-24 | 2018-08-17 | 青海大学 | A kind of solar panel rail cleaning device |
CN108580357A (en) * | 2018-06-27 | 2018-09-28 | 广州市加简派电子科技有限公司 | A kind of photovoltaic generation solar panels cleaning device |
-
2019
- 2019-02-01 CN CN201910101945.5A patent/CN109772768A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2551610A1 (en) * | 2011-07-27 | 2013-01-30 | Alberto Piccoli | Photovoltaic and solar panels cleaning machine |
CN202683549U (en) * | 2012-05-30 | 2013-01-23 | 北京桑纳斯太阳能电池有限公司 | Small-sized intelligent anhydrous cleaner used in solar PV power station |
CN205308841U (en) * | 2015-12-02 | 2016-06-15 | 连云港神舟新能源有限公司 | Photovoltaic module self -cleaning system |
CN205851439U (en) * | 2016-08-04 | 2017-01-04 | 魏显文 | Mobile photovoltaic module cleaning device |
CN206550038U (en) * | 2017-02-14 | 2017-10-13 | 马鞍山佳夫尼电气科技有限公司 | A kind of cleaning device for photovoltaic module |
CN207188264U (en) * | 2017-07-20 | 2018-04-06 | 中国大唐集团科学技术研究院有限公司 | Photovoltaic module cleaning structure |
CN108405383A (en) * | 2018-01-24 | 2018-08-17 | 青海大学 | A kind of solar panel rail cleaning device |
CN108580357A (en) * | 2018-06-27 | 2018-09-28 | 广州市加简派电子科技有限公司 | A kind of photovoltaic generation solar panels cleaning device |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113992143A (en) * | 2021-11-04 | 2022-01-28 | 西安热工研究院有限公司 | Solar photovoltaic power generation cleaning and dust removing system |
CN114450100A (en) * | 2021-12-24 | 2022-05-06 | 无锡市东舟船舶设备股份有限公司 | Synchronous dust removal equipment for processing door plate for large ship |
CN114450100B (en) * | 2021-12-24 | 2023-12-05 | 无锡市东舟船舶设备股份有限公司 | Synchronous dust removal equipment for processing door plate for large ship |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20210140682A1 (en) | Dust removal device for solar panel | |
CN206997145U (en) | A kind of cleaning plant for timber spray painting processing early stage | |
CN109772768A (en) | A kind of operating method of photovoltaic solar panel maintenance facility | |
CN112039420B (en) | Hydraulic drive and photovoltaic cleaning device with dust removal function | |
CN105672179A (en) | Road sweeper | |
CN219287455U (en) | Solar cell panel sprays cleaning device | |
CN105537215A (en) | Robot cleaner | |
CN210341768U (en) | Civil engineering operation cleans dust collector | |
CN202621483U (en) | Solar silicon wafer automatic dust-removal device | |
CN201728195U (en) | Automatic dust removing device of solar panel | |
CN116422621B (en) | Power distribution part cleaning device | |
CN109013563A (en) | A kind of main frame dust cleaner | |
CN209577500U (en) | A kind of photovoltaic solar panel maintenance facility | |
CN114472280B (en) | Surface cleaning system for photovoltaic panel and cleaning method thereof | |
CN215508197U (en) | Oil smoke pipeline cleaning robot | |
CN213883031U (en) | French window dust collector | |
CN209597794U (en) | Clearing apparatus suitable for carrying out electric power maintenance cable duct | |
CN108478096B (en) | Intelligent hoisting equipment for building glass curtain wall | |
CN209252721U (en) | A kind of multifunctional cleaning vehicle | |
CN206676787U (en) | A kind of removing dust and clearing ash device | |
CN112386155A (en) | High altitude glass curtain wall cleaning robot | |
CN215305431U (en) | Rail type high-altitude cleaning robot | |
CN220629284U (en) | Novel photovoltaic power generation device | |
CN220827752U (en) | Track trolley type high-pressure water gun cleaning device of stacker-reclaimer | |
CN215997983U (en) | New forms of energy dust removal cleaner |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |