CN109764189A - The pre-buried functor of spigot-and-socket waterproof PVC and once mounting forming method - Google Patents

The pre-buried functor of spigot-and-socket waterproof PVC and once mounting forming method Download PDF

Info

Publication number
CN109764189A
CN109764189A CN201811630804.4A CN201811630804A CN109764189A CN 109764189 A CN109764189 A CN 109764189A CN 201811630804 A CN201811630804 A CN 201811630804A CN 109764189 A CN109764189 A CN 109764189A
Authority
CN
China
Prior art keywords
spigot
functor
buried
socket
pvc
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811630804.4A
Other languages
Chinese (zh)
Inventor
朱哲锋
石穗嘉
吴本奕
范秀佳
陈琳
黄舒雨
吴开专
甘志标
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGDONG NO 1 CONSTRUCTION ENGINEERING Co Ltd
Original Assignee
GUANGDONG NO 1 CONSTRUCTION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG NO 1 CONSTRUCTION ENGINEERING Co Ltd filed Critical GUANGDONG NO 1 CONSTRUCTION ENGINEERING Co Ltd
Priority to CN201811630804.4A priority Critical patent/CN109764189A/en
Publication of CN109764189A publication Critical patent/CN109764189A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a kind of pre-buried functor of spigot-and-socket waterproof PVC and once mounting forming method, the pre-buried functor of spigot-and-socket waterproof PVC, including main body, main body is tubular, and body top is upper socket joint nozzle, and upper socket joint nozzle outer wall is provided with water-proof wing-ring;It is angle ring-shaped step in the middle part of main body;Lower body part is lower interpolation bellmouth, and lower interpolation bellmouth inner wall, which is provided with to insert, holds slot;Bottom part body is equipped with mounting seat;The pre-buried functor once mounting forming method step of spigot-and-socket waterproof PVC includes: to draw fixation → concreting in the pre-buried functor positioning drawing → template of spigot-and-socket sealing PVC;The pre-buried functor of spigot-and-socket sealing PVC and floorslab concrete system formed by integrally casting, connection is firm closely knit, and barrier properties are good, effectively prevents hanging hidden leakage defect caused by mould is in the milk because secondary.

Description

The pre-buried functor of spigot-and-socket waterproof PVC and once mounting forming method
Technical field
The present invention relates to a kind of pre-buried functor of spigot-and-socket waterproof PVC and once mounting forming methods.
Background technique
Traditional architectural drainage system installation, reserving hole (or service sleeve), concrete usually at pipeline through-flooring Poling is installed again after molding, formwork or hang mould carry out it is secondary pour closure hole, then do water-proofing treatment.This conventional construction side Formula was both time-consuming and laborious, and secondary plugging quality, the perception at hole are difficult to ensure that there is also infiltration leakage hidden troubles.
Summary of the invention
To solve the above problems, the present invention provides a kind of pre-buried functor once mounting forming method of spigot-and-socket waterproof PVC.
To achieve the above object, the technical solution adopted by the present invention is that: a kind of pre-buried functor of spigot-and-socket waterproof PVC, packet Main body is included, main body is tubular, and body top is upper socket joint nozzle, and upper socket joint nozzle outer wall is provided with water-proof wing-ring;In the middle part of main body For angle ring-shaped step;Lower body part is lower interpolation bellmouth, and lower interpolation bellmouth inner wall, which is provided with to insert, holds slot;Bottom part body is equipped with peace Fill pedestal.
Further, the water-proof wing-ring is the conduit for being looped around socket joint nozzle outer wall.
Further, the mounting seat is equipped with several flanges, and flange is equipped with fixation hole.
Further, the pre-buried functor passes through fixation hole by screw and is fixed in template.
The pre-buried functor once mounting forming method of spigot-and-socket waterproof PVC, step include:
(1) it draws the pre-buried functor of spigot-and-socket sealing PVC and positions drawing, according to the drainage that design drawing designs, understand Building, the specific bulk of structure construction drawing carry out through-flooring antiseepage built-in fitting positioning figure and draw, and the drafting of positioning figure should refer to The pre-buried functor model of the choice of diameter spigot-and-socket sealing PVC in fixture drain road, the pre-buried function of spigot-and-socket sealing PVC Part location dimension must consider structural beams and build the alternate position spike of brick wall body line and the finishing surface thickness that brick wall body is reserved;
(2) fixed in template, drawing is positioned referring to the pre-buried functor of spigot-and-socket sealing PVC, utilizes infrared ray perpendicular positioning Instrument is reverse-located from the mounted pre-buried functor of spigot-and-socket sealing PVC of bottom, to the built-in fitting verticality of each floor It measures, deviation controls within 1mm, then selects in working lining pre- with the spigot-and-socket sealing PVC of drawing dimension It is fixed on building template using screw or iron nail to bury functor, each pre-buried functor fixed point of spigot-and-socket sealing PVC is not Less than 3 points, when fixed such as building template has part usually, the three-ply board (hardboard) of book not to can be used in spigot-and-socket sealing PVC The contact surface of pre-buried functor and building template is fixed again after being leveled up, after the pre-buried functor of spigot-and-socket sealing PVC is fixed not Obtain crooked, loosening, deformation;Slow setting soil enters built-in fitting when to avoid pouring, and seals both ends open using sealing tape;
(3) concreting cannot encounter pre-buried functor when slow setting soil pours, pre-buried functor position cannot be made to shift Or inclination, nurse should be tracked when pouring, and should be repaired in time if any being damaged;After civil engineering demoulding before Pipe installing, it should will consolidate The part that the screw or iron nail for determining built-in fitting appear concrete slab is cut off, and makees antirust treatment with antirust paint;
(4) standpipe is installed, and operating platform is set up in place cleaning before installing as needed;Simultaneously by pipe fitting sealing two ends adhesive tape It tears off, and it is the pre-buried functor internal cleaning of spigot-and-socket sealing PVC is clean, when installation, upper one layer of hole is first protruded into supervisor upper end In mouthful, until being vertically forcibly inserted into lower layer's telescopic joint to label, generally reserved harmomegathus amount is 20-30mm;Then levelling, centering, And measure whether top plate meets the requirements away from the distance at three port centers, after errorless, close through-flooring hole;
(5) branch pipe is installed, place cleaning before installing, and sets up operating platform as needed, when installation bonds, spigot-and-socket sealing PVC It must be cleaned out in the pipe of pre-buried functor, remove the dirt and moisture of bonding site, branch pipe level is tentatively sling, is smeared Adhesive, is forced into antiseepage built-in fitting, adjusts the gradient according to length of pipe section, suitable rear fixed -piping supporting member, interim to seal Close each reserved nozzle;
(6) closed-water test, drainage pipeline install, and are placed under layer standpipe telescopic joint with inflating rubber air bag along standpipe, Temporary plugging is done in inflation, and the height poured water to upper layer sanitary apparatus connection tube top carries out pipeline closed-water test, full water 15min water After the decline of face, then observation 5min is filled, liquid level does not decline, and pipeline and interface ne-leakage are qualification.
The beneficial effects of the present invention are: Quality advance: the pre-buried functor of spigot-and-socket sealing PVC and floorslab concrete system Formed by integrally casting, connection is firm closely knit, and barrier properties are good, effectively prevents hanging hidden leakage defect caused by mould is in the milk because secondary;Due to pre- Pipe laying connector positioning accuracy is high, consolidates after pouring, also avoiding the secondary mould grouting operation that hangs may cause pipeline location, the gradient Offset;Beautiful appearance, no back-grouting pollution;It saves material: using this construction technology, eliminate and stay plug-hole hole process, save About reserving hole casing and secondary hang the materials such as mould, template, iron wire, the pea gravel concreten that grouting uses;Save the construction period And construction cost.
Detailed description of the invention
Fig. 1 is the pre-buried functor structural schematic diagram of spigot-and-socket waterproof PVC.
Fig. 2 is the pre-buried functor partial sectional view of spigot-and-socket waterproof PVC.
Fig. 3 is the pre-buried functor once mounting forming method steps flow chart block diagram of spigot-and-socket waterproof PVC.
Specific embodiment
The present invention is about a kind of pre-buried functor once mounting forming method of spigot-and-socket waterproof PVC.
As shown in Figs. 1-2, the pre-buried functor of a kind of spigot-and-socket waterproof PVC, including main body, main body are tubular, body top For upper socket joint nozzle 1, upper 1 outer wall of socket joint nozzle is provided with water-proof wing-ring 2;It is angle ring-shaped step 3 in the middle part of main body;Lower body part For lower interpolation bellmouth 4, lower interpolation bellmouth inner wall, which is provided with to insert, holds slot 41;Bottom part body is equipped with mounting seat 5.
Water-proof wing-ring 2 is the conduit for being looped around 1 outer wall of socket joint nozzle.
Mounting seat 5 is equipped with several flanges 51, and flange is equipped with fixation hole 511.
Pre-buried functor passes through fixation hole 511 by screw 512 and is fixed in template.
As shown in figure 3, the pre-buried functor once mounting forming method of spigot-and-socket waterproof PVC, step include:
(1) it draws the pre-buried functor of spigot-and-socket sealing PVC and positions drawing, according to the drainage that design drawing designs, understand Building, the specific bulk of structure construction drawing carry out through-flooring antiseepage built-in fitting positioning figure and draw, and the drafting of positioning figure should refer to The pre-buried functor model of the choice of diameter spigot-and-socket sealing PVC in fixture drain road, the pre-buried function of spigot-and-socket sealing PVC Part location dimension must consider structural beams and build the alternate position spike of brick wall body line and the finishing surface thickness that brick wall body is reserved;
(2) construction technology is told somebody what one's real intentions are, and is carried out teams and groups according to construction technology process and is told somebody what one's real intentions are, is familiar with Pipe installing operating method and specification is wanted It asks, specifies the control of built-in fitting allowable error and require, the standard size of toilet positioning is carried out to construction teams and groups and mounting technique is handed over Bottom carries out three-dimensional installation effect simulation using BIM technology, further rendering space size Deepen Design figure, to construction teams and groups into One step is told somebody what one's real intentions are;
(3) fixed in template, drawing is positioned referring to the pre-buried functor of spigot-and-socket sealing PVC, utilizes infrared ray perpendicular positioning Instrument is reverse-located from the mounted pre-buried functor of spigot-and-socket sealing PVC of bottom, to the built-in fitting verticality of each floor It measures, deviation controls within 1mm, then selects in working lining pre- with the spigot-and-socket sealing PVC of drawing dimension It is fixed on building template using screw or iron nail to bury functor, each pre-buried functor fixed point of spigot-and-socket sealing PVC is not Less than 3 points, when fixed such as building template has part usually, the three-ply board (hardboard) of book not to can be used in spigot-and-socket sealing PVC The contact surface of pre-buried functor and building template is fixed again after being leveled up, after the pre-buried functor of spigot-and-socket sealing PVC is fixed not Obtain crooked, loosening, deformation;Slow setting soil enters built-in fitting when to avoid pouring, and seals both ends open using sealing tape;
(4) nurse is tracked when concreting, should be repaired in time if any being damaged;After civil engineering demoulding before Pipe installing, answer The part that the screw of fixed built-in fitting or iron nail appear concrete slab is cut off, and makees antirust treatment with antirust paint;
(5) pipe prefabrication is processed, and according to drawing requirement and is combined actual conditions, by reserved opening measuring scale of position cun, is drawn processing Sketch.Line size is measured according to sketch, carries out disconnected pipe, disconnected piping tool preferably selects the equipments such as rack saw, cutter and pipe cutter, fracture Answer smooth and perpendicular to pipe longitudinal axis, section part must not have any deformation, and spigot can be rasped to 15 ° of -30 ° of slopes with medium size flat file Mouthful.Groove thickness is preferably the 1/3-1/2 of tube wall, and length is typically no less than 3mm, should remove detritus completely, glue after the completion of groove Reply bell and spigot is first inserted into test before knot, must not be entirely insertable, generally 3/4 depth of bellmouth.After examination plugs together lattice, cotton is used Moisture, the dust wiped clean that bell and spigot is needed to bonded part, need to be removed if any greasy dirt with acetone, smear binder with hairbrush, Socket is smeared after first smearing bellmouth, is firmly inserted perpendicularly into immediately, insertion slightly rotates socket when bonding, with the distribution of sharp binder Uniformly, it can be firmly bonded within about 30 seconds to 60 seconds, immediately by the binder wiped clean of spilling after cementing, whens more mouthfuls of adhesions is answered Pay attention to reserved opening direction;
(6) pipe supports are installed, and support member material is plastics and metal, but should be able to play bearing pipeline, metal branch Bearing member will do antirust treatment, and the inner wall of supporting member is answered smooth, when using metal carrier, install additional between pipeline and metal carrier Rubber gasket transition;
(7) standpipe is installed, and operating platform is set up in place cleaning before installing as needed;Simultaneously by pipe fitting sealing two ends adhesive tape It tears off, and it is the pre-buried functor internal cleaning of spigot-and-socket sealing PVC is clean, when installation, upper one layer of hole is first protruded into supervisor upper end In mouthful, until being vertically forcibly inserted into lower layer's telescopic joint to label, generally reserved harmomegathus amount is 20-30mm;Then levelling, centering, And measure whether top plate meets the requirements away from the distance at three port centers, after errorless, close through-flooring hole;
(8) branch pipe is installed, place cleaning before installing, and sets up operating platform as needed, when installation bonds, spigot-and-socket sealing PVC It must be cleaned out in the pipe of pre-buried functor, remove the dirt and moisture of bonding site, branch pipe level is tentatively sling, is smeared Adhesive, is forced into antiseepage built-in fitting, adjusts the gradient according to length of pipe section, suitable rear fixed -piping supporting member, interim to seal Close each reserved nozzle;
(9) closed-water test, drainage pipeline install, and are placed under layer standpipe telescopic joint with inflating rubber air bag along standpipe, Temporary plugging is done in inflation, and the height poured water to upper layer sanitary apparatus connection tube top carries out pipeline closed-water test, full water 15min water After the decline of face, then observation 5min is filled, liquid level does not decline, and pipeline and interface ne-leakage are qualification.
Embodiment of above be only preferred embodiments of the present invention will be described, not to the scope of the present invention into Row limits, and without departing from the spirit of the design of the present invention, this field ordinary engineering and technical personnel is to technical side of the invention The various changes and improvements that case is made, should fall within the scope of protection determined by the claims of the present invention.

Claims (5)

1. a kind of pre-buried functor of spigot-and-socket waterproof PVC, including main body, main body are tubular, it is characterised in that: body top is upper Socket joint nozzle (1), upper socket joint nozzle (1) outer wall are provided with water-proof wing-ring (2);It is in the middle part of main body angle ring-shaped step (3);Main body Lower part is lower interpolation bellmouth (4), and lower interpolation bellmouth inner wall, which is provided with to insert, holds slot (41);Bottom part body is equipped with mounting seat (5).
2. the pre-buried functor of spigot-and-socket waterproof PVC according to claim 1, it is characterised in that: the water-proof wing-ring (2) is It is looped around the conduit of socket joint nozzle (1) outer wall.
3. the pre-buried functor of spigot-and-socket waterproof PVC according to claim 1, it is characterised in that: on the mounting seat (5) Equipped with several flanges (51), flange is equipped with fixation hole (511).
4. the pre-buried functor of spigot-and-socket waterproof PVC according to claim 1, it is characterised in that: the mounting seat (5) is logical Screw (512) are crossed to be fixed in template across fixation hole (511).
5. the pre-buried functor once mounting forming method of spigot-and-socket waterproof PVC, it is characterised in that step includes:
(1), it draws the pre-buried functor of spigot-and-socket sealing PVC and positions drawing, according to the drainage that design drawing designs, Solution building, the specific bulk of structure construction drawing carry out through-flooring antiseepage built-in fitting positioning figure and draw, and the drafting of positioning figure should be joined According to the pre-buried functor model of the choice of diameter spigot-and-socket sealing PVC in fixture drain road, the pre-buried function of spigot-and-socket sealing PVC Energy part location dimension must consider structural beams and build the alternate position spike of brick wall body line and the finishing surface thickness that brick wall body is reserved;
(2), fixed in template, drawing is positioned referring to the pre-buried functor of spigot-and-socket sealing PVC, utilizes infrared ray perpendicular positioning Instrument is reverse-located from the mounted pre-buried functor of spigot-and-socket sealing PVC of bottom, to the built-in fitting verticality of each floor It measures, deviation controls within 1mm, then selects in working lining pre- with the spigot-and-socket sealing PVC of drawing dimension It is fixed on building template using screw or iron nail to bury functor, each pre-buried functor fixed point of spigot-and-socket sealing PVC is not Less than 3 points, when fixed such as building template has part not usually, using the three-ply board (hardboard) of book in spigot-and-socket sealing PVC The contact surface of pre-buried functor and building template is fixed again after being leveled up, after the pre-buried functor of spigot-and-socket sealing PVC is fixed not Obtain crooked, loosening, deformation;Slow setting soil enters built-in fitting when to avoid pouring, and seals both ends open using sealing tape;
(3), concreting cannot encounter the pre-buried functor of spigot-and-socket sealing PVC, spigot-and-socket cannot be made to stop when slow setting soil pours The pre-buried functor position water PVC shifts or tilts, and should be repaired in time if any being damaged.
CN201811630804.4A 2018-12-29 2018-12-29 The pre-buried functor of spigot-and-socket waterproof PVC and once mounting forming method Pending CN109764189A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811630804.4A CN109764189A (en) 2018-12-29 2018-12-29 The pre-buried functor of spigot-and-socket waterproof PVC and once mounting forming method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811630804.4A CN109764189A (en) 2018-12-29 2018-12-29 The pre-buried functor of spigot-and-socket waterproof PVC and once mounting forming method

Publications (1)

Publication Number Publication Date
CN109764189A true CN109764189A (en) 2019-05-17

Family

ID=66452521

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811630804.4A Pending CN109764189A (en) 2018-12-29 2018-12-29 The pre-buried functor of spigot-and-socket waterproof PVC and once mounting forming method

Country Status (1)

Country Link
CN (1) CN109764189A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110512708A (en) * 2019-09-30 2019-11-29 谢伦杰 A kind of assembled architecture embedded pipeline part
CN113136927A (en) * 2021-04-30 2021-07-20 中国建筑第二工程局有限公司 Construction method of modular toilet
CN115045521A (en) * 2022-07-29 2022-09-13 中建八局第一建设有限公司 Electric embedded box rust-proof nail-free mounting and plugging integrated device and mounting method
CN115262964A (en) * 2022-07-14 2022-11-01 中国十七冶集团有限公司 One-time embedded water stop joint for drainage of constructional engineering and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102095033A (en) * 2010-12-15 2011-06-15 成都市第四建筑工程公司 One-time embedded water-stop section for construction engineering drainage and construction method thereof
CN104846978A (en) * 2015-05-26 2015-08-19 江苏南通二建集团有限公司 Cast-in-situ house drainage system quasi-industrialized construction method
CN204875972U (en) * 2015-08-21 2015-12-16 中建二局第一建筑工程有限公司 Pre -buried seat of drain pipe between kitchen guarding
CN108443590A (en) * 2018-04-08 2018-08-24 中建二局第二建筑工程有限公司 Side-type direct-burried part and its construction method
CN207796289U (en) * 2017-12-05 2018-08-31 重庆双为科技有限公司 A kind of pre-buried type water-seal piecing devices
CN210034649U (en) * 2018-12-29 2020-02-07 广东省第一建筑工程有限公司 Socket-type waterproof PVC embedded functional part

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102095033A (en) * 2010-12-15 2011-06-15 成都市第四建筑工程公司 One-time embedded water-stop section for construction engineering drainage and construction method thereof
CN104846978A (en) * 2015-05-26 2015-08-19 江苏南通二建集团有限公司 Cast-in-situ house drainage system quasi-industrialized construction method
CN204875972U (en) * 2015-08-21 2015-12-16 中建二局第一建筑工程有限公司 Pre -buried seat of drain pipe between kitchen guarding
CN207796289U (en) * 2017-12-05 2018-08-31 重庆双为科技有限公司 A kind of pre-buried type water-seal piecing devices
CN108443590A (en) * 2018-04-08 2018-08-24 中建二局第二建筑工程有限公司 Side-type direct-burried part and its construction method
CN210034649U (en) * 2018-12-29 2020-02-07 广东省第一建筑工程有限公司 Socket-type waterproof PVC embedded functional part

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110512708A (en) * 2019-09-30 2019-11-29 谢伦杰 A kind of assembled architecture embedded pipeline part
CN113136927A (en) * 2021-04-30 2021-07-20 中国建筑第二工程局有限公司 Construction method of modular toilet
CN115262964A (en) * 2022-07-14 2022-11-01 中国十七冶集团有限公司 One-time embedded water stop joint for drainage of constructional engineering and construction method thereof
CN115045521A (en) * 2022-07-29 2022-09-13 中建八局第一建设有限公司 Electric embedded box rust-proof nail-free mounting and plugging integrated device and mounting method
CN115045521B (en) * 2022-07-29 2023-07-25 中建八局第一建设有限公司 Anti-rust nail-free installation and plugging integrated device and installation method for electric embedded box

Similar Documents

Publication Publication Date Title
CN109764189A (en) The pre-buried functor of spigot-and-socket waterproof PVC and once mounting forming method
CN106088364B (en) A kind of basement antiseep connection structure and its construction method
CN102937027A (en) Construction method of edge top arch and bottom arch of concrete pouring tunnel
CN107489167A (en) A kind of underground pipe gallery socket joint deformation joint structure and its construction method
CN210482605U (en) Building structure movement joint mounting structure
CN106640154A (en) Treatment method and structure for water seepage of tunnel lining circular construction joint crack
CN109736847A (en) Primary concreting concrete inverted arch and its construction method
CN101418641A (en) Obligate pore construction method for construction floor
CN109356201A (en) A kind of the interface waterproof construction and interface method for waterproofing of new-old concrete
CN110206074A (en) A kind of underground waterproof engineering construction technology
CN210034649U (en) Socket-type waterproof PVC embedded functional part
CN102877538A (en) Construction method for fixing HDPE (high-density polypropylene) pipe by embedding iron wires
CN209162909U (en) A kind of interface waterproof construction of new-old concrete
CN207959289U (en) Structure is repaired in a kind of leak for basement post-pouring zone position
CN206429253U (en) Seep water treatment structures in tunnel-liner circular construction joint crack
CN103835421B (en) Leakage-proof floor and anti-seepage construction method
CN205875426U (en) Novel basement antiseep connection structure
CN113338993B (en) Connecting channel reinforcing ring beam structure and construction method thereof
CN102213006B (en) UPVC (Unplasticized Polyvinyl Chloride) sleeve direct burying method
CN113137081A (en) Deformation joint acrylate grouting plugging construction method
CN113802418A (en) Construction method of ballastless track
CN206943599U (en) Floor drainage pipeline service sleeve
CN209568553U (en) Flexible water sealing system
CN101225910A (en) Building pipe built-in joint
CN218326599U (en) Anti-seepage pipe fitting of pre-buried pipeline

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination