CN102877538A - Construction method for fixing HDPE (high-density polypropylene) pipe by embedding iron wires - Google Patents

Construction method for fixing HDPE (high-density polypropylene) pipe by embedding iron wires Download PDF

Info

Publication number
CN102877538A
CN102877538A CN2012104023287A CN201210402328A CN102877538A CN 102877538 A CN102877538 A CN 102877538A CN 2012104023287 A CN2012104023287 A CN 2012104023287A CN 201210402328 A CN201210402328 A CN 201210402328A CN 102877538 A CN102877538 A CN 102877538A
Authority
CN
China
Prior art keywords
pipe
concrete
iron wires
hdpe
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012104023287A
Other languages
Chinese (zh)
Inventor
韩玉德
李长泽
丁寿亮
杨亚峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinan Urban Construction Group Co Ltd
Original Assignee
Jinan Urban Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinan Urban Construction Group Co Ltd filed Critical Jinan Urban Construction Group Co Ltd
Priority to CN2012104023287A priority Critical patent/CN102877538A/en
Publication of CN102877538A publication Critical patent/CN102877538A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention provides a construction method for fixing an HDPE (high-density polypropylene) pipe by embedding iron wires. Machine bricks are embedded and the iron wires with sufficient lengths are bound during concrete flat foundation construction before concrete is wrapped on the municipal drain pipe, and the HDPE pipe is firmly bound by the embedded iron wires after being laid. The construction method sequentially includes particular steps of laying out for measurement; excavating a groove; embedding the machine bricks, binding the iron wires, and pouring to form a concrete flat foundation; laying the pipe; checking tightness; binding the HDPE pipe by the iron wires; and wrapping the pipe by the concrete. The iron wires are embedded when the flat foundation of the flexible municipal drain pipe is poured, and the pipe is fixed by the embedded iron wires after being arranged in place, so that the construction precision is guaranteed, the flexible pipe is prevented from moving when the concrete is poured, and rework caused by movement of the pipe is stopped. The construction method has the advantages of high safety, firmness, reliability, convenience and speediness in construction and high economical efficiency. Besides, the mounting quality of the pipe is effectively guaranteed, and the method guarantees that the pipe is mounted and is wrapped by the concrete at one step.

Description

Pre-buried iron wire is HDPE pipe construction method fixedly
Technical field
The present invention relates to a kind of urban construction project job practices, specifically the fixing HDPE pipe construction method of the pre-buried iron wire of a kind of municipal drainage pipeline flexible pipe.
Background technology
According to the engineering of building up in the past, HDPE pipeline coagulation mount pipe by traditional construction technology, the pipeline rising phenomenon very easily occurs during pouring concrete, need to do over again, and causes simultaneously the waste of people, material, machine, has increased construction cost.Along with the development of my incorporated business, the technology of construction, method, level all at waxing development year by year, are improved job practices consciously, have formed " pre-buried iron wire is HDPE pipe construction method fixedly ".This method is simple, successful.The pipeline rising phenomenon very easily occurs when using the method mainly to solve the cast of HDPE pipeline coagulation mount pipe concrete, greatly reduced the significant wastage of finishing process in the work progress and people, material, machine.
Summary of the invention
The invention provides fixedly HDPE pipe construction method of a kind of high safety, the front pre-buried iron wire of municipal drainage pipeline flexible pipe pouring concrete solid and reliable, convenient and quick construction economy.
The present invention is achieved through the following technical solutions:
A kind of pre-buried iron wire is HDPE pipe construction method fixedly; it is characterized in that: the iron wire of pre-buried machine brick and the good sufficient length of colligation when the municipal drainage pipeline concrete is assured the flat base construction of front, concrete; after the HDPE pipeline laying is good; it is fastening with pre-buried good iron wire the HDPE pipe to be carried out colligation; the HDPE pipe is not subjected to displacement when guaranteeing that concrete is assured, and the Specific construction step is as follows: measure setting-out → channel excavation → embeded machine brick tie wire, the flat base of concrete cast → pipeline laying → seal check → iron wire colligation HDPE pipe → concrete is assured.
Spacing between the described iron wire is 1m.
The invention has the beneficial effects as follows: the present invention is pre-buried iron wire when municipal flexible water drainage pipe plane base cast, pipeline is in place to utilize pre-buried iron wire to be fixed afterwards, guarantee construction precision, prevent that flexible duct from producing displacement in concrete placement, the problem of pipeline come-up and in-plane displancement is stopped the phenomenon of doing over again that produces because of the tubing displacement in the time of can effectively avoiding assuring pouring concrete.Job practices of the present invention is workable, easy and simple to handle, technical difficulty is little, and pipeline process installation quality is controlled easily, has improved efficiency of construction; Pipeline once mounting qualification rate is high, has reduced the phenomenon of doing over again that pipeline is installed, thereby has saved the expenditure of plant equipment and labour cost; This construction technology compared with prior art has high safety, solid and reliable, convenient and quick construction, both economical characteristics, has effectively guaranteed the pipeline installation quality, has guaranteed that pipeline is installed to assure once with concrete to survive.Adopt the construction of this method method, the bright dew time shorten of groove has reduced the dust discharging, reduces traffic and ambient influnence, is conducive to civilized construction; Along with the extensive use of HDPE pipeline, the present invention will better be implemented, and obtain preferably social benefit.Job practices of the present invention should be used in the flexible water drainage pipe works of city.
Description of drawings
The present invention is further illustrated below in conjunction with accompanying drawing.
Fig. 1 is flat base cast and pre-buried machine brick tie wire schematic diagram;
Fig. 2 is that pipeline is installed and colligation fastening structure schematic diagram;
Among the figure, the flat base of 1-concrete, the pre-buried machine brick of 2-, 3-iron wire, 4-HDPE pipe.
The specific embodiment
With reference to Figure of description method of the present invention is done following detailed explanation.As shown in drawings; the iron wire 3 of pre-buried machine brick 2 and the good sufficient length of colligation during the flat base construction of concrete; spacing between the iron wire 3 is 1m; HDPE manages after 4 roads lay; it is fastening to carry out colligation with the 3 couples of HDPE of pre-buried good iron wire pipe 4, guarantees that the displacement of any direction does not occur for HDPE pipe 4 when concrete is assured.
The Specific construction step is as follows: measure setting-out → channel excavation → embeded machine brick 2 tie wires 3, the flat base of concrete cast → pipeline laying → seal check → iron wire 3 colligation HDPE pipe 4 → concrete is assured.
Its technical indicator: the allowable variation of the 66th page of pipe laying of " code for construction and acceptance of water supply and sewerage pipeline engineering " GB50268-2008, horizontal axis 15mm, pipe end elevation ± 10mm.
One, measures setting-out
Should the school before going into operation survey plan-position and the elevations such as the built pipeline that is connected with this engineering, structure.Elder generation's measuring channel system centre line and manhole position during measurement arrange the construction control stake and spread out the lime line so that excavation sets up level gauge and carries out tracking measurement when mechanical equivalent of light excavation is constructed in pipeline turning, bifurcation.
Two, channel excavation
1) before the channel excavation, should investigate according to the construction needs situation of site contour, landforms, building, various pipeline and other facilities that the grasp pipeline is along the line and engineering geology, hydrogeologic data, drainage condition, and establishment drainaging scheme.The water that the construction drainage system discharges should be delivered to beyond the radius of influence scope of drawing water, and must not affect traffic and destroy road, farmland, riverbank and other structure.
2) the channel excavation process is in time controlled cutting depth, prevents from backbreaking; Should in time recover groove center line and control elevation behind the channel excavation, employing arranges gradient plate and carries out elevation, center line control, checks at any time whether gradient plate setting position and elevation be accurate, guarantees groove center line, the gradient and ancillary structure correct position.
3) width of groove should be convenient to pipe laying, installation, and backfilling operation and underground water discharge.The minimum widith of groove should be calculated as follows definite:
b≥D1+2S
B in the formula: the minimum widith of groove (mm);
D1: pipe external diameter (mm);
S: tube wall is to the distance (mm) of trench wall, and according to the form below is determined.
4) steepest gradient of groove side slope should be determined according to the groove soil property, and trench wall should arrange and support or backplate in case of necessity, and the establishment emergency preplan.Soil excavation adopts mechanical equivalent of light excavation, and bottom land is reserved 20cm by the artificial clear end, and digging process is forbidden to backbreak, in case the disturbance ground.
5) on top, weak soil groove slope static load or dynamic load should not be set; In the time of need to arranging, the bearing capacity of reply soil and the stability of side slope check.
6) dig when deeply larger when groove, should determine by reasonable mechanical performance the degree of depth of stage excavation.
Three, embeded machine brick tie wire, the flat base cast of concrete
1) template: should in time install flat basic mode plate after check of foundation subsoil is qualified, Ping Jibianmo can adopt 10# channel-section steel or 100 * 100mm lumps of wood template, and template is fixed with drill rod or the lumps of wood behind.
2) flat base concrete: build the machine brick that flat base concrete should be imbedded the good iron wire of colligation simultaneously, adopt vibration board will put down basic vibration compacting, according to the absolute altitude control line, carry out surperficial darby levelling, wood is smeared rubbing and pressure and is made real, and can carry out the next procedure construction after concrete strength reaches 1.2MPa.
Four, pipeline laying
1) material specification such as tubing, rubber ring should meet designing requirement, has work certificate and the properties of product manual of quality inspection department, and should indicate product specification and date of manufacture.
2) the sealing joint rubber ring adopts neoprene to make, and shore hardness is 45~55MPa, is provided together by specification by pipe production producer.
3) tubing requires outward appearance consistent, and inner wall smooth is smooth, and pipe shaft must not have the crack, and the mouth of pipe must not have the defectives such as breakage, breach, distortion.
4) tube end face should be smooth, and is vertical with the tube hub axis, and obvious crooked the appearance axially must not be arranged, and the size of tubing socket external diameter, bellmouth internal diameter and circularity must meet the regulation of product standard.
5) tubing compressive resistance and rigidity should meet design requirement.
6) pipe joint should meet designing requirement with rubber ring performance, size.The rubber ring outward appearance should be smooth smooth, and pore, crack, volume wrinkle, breakage, pipe and seam phenomenon must not be arranged.
7) pipeline is installed and can be adopted artificial installation, can enter groove by manually lifting pipe when groove depth is little, and also available nonmetal rope elephant trunk enters groove, is placed on reposefully successively on the sand cushion pipe position.Forbid to catch on the two ends mouth of pipe or tubing is thrown in the groove from trough rim rolling with metallic cable.
8) interface is installed, and the interface direction should be consistent with flowing water face direction, installed successively to height point by low spot.
9) the rubber ring interface should be observed following regulation:
(1) before the connection, should check first whether rubber ring is supporting intact, confirm the cushion rubber riding position.
(2) during the interface operation, should now the interfaces face be cleaned out with cotton yarn, the foreign material such as earth must not be arranged.
When (3) using Hough spare to connect, first the disjunctor sealing rubber ring one end outside is dug, put a tube connector port, turn down the edge in the outside, the cushion rubber of digging is packed into help groove; Dig afterwards the cushion rubber other end, another root tube connector is aligned be close to, put down cushion rubber, pack into the rib groove, again that Hough spare is good and sound, evenly pull tight bolt, must not lack dress.
Five, iron wire colligation HDPE pipe
It is fastening to carry out colligation with 3 pairs of HDPE pipes 4 of pre-buried iron wire after the pipeline installation, and come-up and in-plane displancement occur HDPE pipe 4 when preventing from assuring pouring concrete, affect workmanship.
Six, seal check
The pipeline colligation is complete through after the assay was approved, should carry out the seal check.Can adopt the check of closed-water test method.The closed-water test head should satisfy following requirement:
When 1) the upstream design head was no more than pipe top inwall, test head added 2m as the code test head with upstream tube top inwall;
When 2) the upstream design head surpassed pipe top inwall, test head added 2m in the upstream design head;
3) when the test head that calculates less than 10m, but when having surpassed upstream manhole well head, test head is as the criterion with upstream manhole well head height, but must not be less than 0.5m.
4) the test section soak time of filling behind the water should be less than 24h.
5) during the pipeline closed check, visual inspection must not have drainage, and the water percolating capacity of pipeline 24h should satisfy following formula result of calculation:
Q≤0.0046d
In the formula: Q: the permission water percolating capacity (m3/24hkm) of every 1km duct length 24h
D: internal diameter of the pipeline (mm)
Seven, concrete is assured
Template: template can adopt combined steel formwork or plywood form on-site consolidation, formwork edge joint must be tightly spillage not, mould planted agent cleaning.The brushing of template interleaving agent is even.
1) wooden form
(1) make: wooden form should select quality solid, be out of shape little, without the timber of rotten, distortion, crackle.Template medial surface, end face will be scraped, the piece close and firm, and the corner is smooth intact.
(2) install: wooden form is propped up plan-position and the elevation of vertical formwork erection by the unwrapping wire position, should meet designing requirement, and Ying Zhili is firm, joint is closely smooth-going, wrong stubble and the phenomenon such as be uneven before and after must not having.Both sides are with iron short wooden stake stickfast and near template, and inboard iron short wooden stake should be higher than template (about l00mm), spacing 0.8m-1.0m, outside iron short wooden stake push up should with template with high or low l0mm.Bend place iron short wooden stake should be encrypted, and spacing is 0.4m-0.8m.Template Zhi Haohou, inboard evenly brushing interleaving agent.
2) steel form
(1) makes: should adopt channel-section steel or section steel manufacture, if its thickness should satisfy intensity, rigidity requirement when adopting steel plate to make.
(2) install: it is identical that steel form and wooden form prop up cube method.
Eight, assure concrete
Before the concrete making, smooth, the built-in fitting of reply shuttering supporting, basic unit, wetting situation etc. check comprehensively.Assure concrete and should fill out puddling in fact, concrete adopts the internal vibration rod to vibrate, during concreting, answer both sides to carry out simultaneously according to the absolute altitude control line, carry out surperficial darby levelling, wood is smeared rubbing and pressure and is made real, and health will in time cover and sprinkle water after the cast-in-situ concrete form removal, especially summer temperature is high, prevents that dry and cracked phenomenon from appearring in concrete surface.After reaching 1.2MPa, concrete strength can carry out the next procedure construction.

Claims (2)

1. the fixing HDPE pipe construction method of a pre-buried iron wire; it is characterized in that: before the municipal drainage pipeline concrete is assured; the iron wire (3) of pre-buried machine brick (2) and the good sufficient length of colligation during the flat base construction of concrete; after HDPE pipe (4) road lays; it is fastening with pre-buried good iron wire (3) HDPE pipe (4) to be carried out colligation; HDPE pipe (4) is not subjected to displacement when guaranteeing that concrete is assured, and the Specific construction step is as follows: measure setting-out → channel excavation → embeded machine brick (2) tie wire (3); the flat base of concrete cast → pipeline laying → seal check → iron wire (3) colligation HDPE pipe (4) → concrete is assured.
2. the fixing HDPE pipe construction method of pre-buried iron wire according to claim 1, it is characterized in that: the spacing between the described iron wire (3) is 1m.
CN2012104023287A 2012-10-22 2012-10-22 Construction method for fixing HDPE (high-density polypropylene) pipe by embedding iron wires Pending CN102877538A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012104023287A CN102877538A (en) 2012-10-22 2012-10-22 Construction method for fixing HDPE (high-density polypropylene) pipe by embedding iron wires

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012104023287A CN102877538A (en) 2012-10-22 2012-10-22 Construction method for fixing HDPE (high-density polypropylene) pipe by embedding iron wires

Publications (1)

Publication Number Publication Date
CN102877538A true CN102877538A (en) 2013-01-16

Family

ID=47479038

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012104023287A Pending CN102877538A (en) 2012-10-22 2012-10-22 Construction method for fixing HDPE (high-density polypropylene) pipe by embedding iron wires

Country Status (1)

Country Link
CN (1) CN102877538A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105239660A (en) * 2015-11-09 2016-01-13 中建八局第四建设有限公司 Diversion trench and diversion trench construction method
CN106838461A (en) * 2017-03-08 2017-06-13 济南黄河路桥建设集团有限公司 A kind of cities and towns flexible duct rapid constructing method
CN107630500A (en) * 2017-09-27 2018-01-26 广东景源建设工程有限公司 A kind of water supply and drainage construction method
CN108978838A (en) * 2018-08-10 2018-12-11 湖南省建筑设计院有限公司 Concrete expires packet drainage pipeline tubine construction method
CN112227514A (en) * 2020-07-15 2021-01-15 杭州市市政工程集团有限公司 Construction method of sewage allocation main pipe network
CN113566019A (en) * 2021-06-29 2021-10-29 中国二十冶集团有限公司 Construction method for laying drainage pipe network without excavating upper part of ground reservoir

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2719521A1 (en) * 1976-05-04 1977-11-24 Meag Ab CONCRETE BASE FOR PIPES, PIPELINES, CABLES, ETC.
JPH04119280A (en) * 1990-09-07 1992-04-20 Nkk Corp Ring support for piping
JPH04119280U (en) * 1991-04-01 1992-10-26 昭次 毎田 modified car
CN101775826A (en) * 2010-01-26 2010-07-14 济南金鼎信息技术有限公司 Construction method for laying water pipes

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2719521A1 (en) * 1976-05-04 1977-11-24 Meag Ab CONCRETE BASE FOR PIPES, PIPELINES, CABLES, ETC.
JPH04119280A (en) * 1990-09-07 1992-04-20 Nkk Corp Ring support for piping
JPH04119280U (en) * 1991-04-01 1992-10-26 昭次 毎田 modified car
CN101775826A (en) * 2010-01-26 2010-07-14 济南金鼎信息技术有限公司 Construction method for laying water pipes

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105239660A (en) * 2015-11-09 2016-01-13 中建八局第四建设有限公司 Diversion trench and diversion trench construction method
CN106838461A (en) * 2017-03-08 2017-06-13 济南黄河路桥建设集团有限公司 A kind of cities and towns flexible duct rapid constructing method
CN107630500A (en) * 2017-09-27 2018-01-26 广东景源建设工程有限公司 A kind of water supply and drainage construction method
CN108978838A (en) * 2018-08-10 2018-12-11 湖南省建筑设计院有限公司 Concrete expires packet drainage pipeline tubine construction method
CN112227514A (en) * 2020-07-15 2021-01-15 杭州市市政工程集团有限公司 Construction method of sewage allocation main pipe network
CN113566019A (en) * 2021-06-29 2021-10-29 中国二十冶集团有限公司 Construction method for laying drainage pipe network without excavating upper part of ground reservoir

Similar Documents

Publication Publication Date Title
CN110306616B (en) Construction method of sewage pipeline
CN107938692B (en) Drainage and recharging construction method and structure
CN103758084B (en) A kind of ecological riverway interlocking type building block and construct the construction that protects bank
CN106978843A (en) Municipal drainage pipeline construction technology
CN103774616B (en) From the Ecological Retaining Wall construction method that embedded block is built by laying bricks or stones
CN102877538A (en) Construction method for fixing HDPE (high-density polypropylene) pipe by embedding iron wires
CN107587557A (en) Outdoor water engineering construction method
CN102392549B (en) Construction working method for seamless prestressed-concrete self-waterproof clean water reservoir
CN101565964A (en) Construction method for mounting outdoor embedded high-density polyethylene double-wall corrugated drain pipe
CN103669374A (en) Combined supporting construction method of steel sheet pile used in silt soil slope
CN107761911A (en) A kind of construction method for the blowdown pipe network for improving installation quality
CN101597888B (en) Construction method of municipal drainage culvert sinking trough
CN107630500A (en) A kind of water supply and drainage construction method
CN110952586A (en) Construction process for bearing platform below expressway
CN101638898B (en) Suspension type construction method of top pipe shaft
CN113774917A (en) Safe construction method for earth and rockfill excavation and side slope supporting engineering
CN110645411B (en) Pipeline laying method
CN110761316B (en) Prefabricated foundation ring beam prefabricating method and storage tank construction method applying prefabricated foundation ring beam prefabricating method
CN108411933A (en) Soft soil foundation concrete reinforced pipe construction method and its foundation structure
CN111456085A (en) Cast-in-place concrete construction method for pipe gallery segment
CN110924435A (en) Transverse pipeline fixing device under transverse structure and construction method thereof
CN116220027A (en) BIM auxiliary reinforced pile and non-reinforced pile engaged pile construction method
CN110512594A (en) The simple and easy method of churning driven opportunity cavity pore-forming
CN115262730A (en) Construction method of rain sewage pipeline
CN211873077U (en) High and large gravity type concrete retaining wall structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130116