CN116220027A - BIM auxiliary reinforced pile and non-reinforced pile engaged pile construction method - Google Patents

BIM auxiliary reinforced pile and non-reinforced pile engaged pile construction method Download PDF

Info

Publication number
CN116220027A
CN116220027A CN202310218393.2A CN202310218393A CN116220027A CN 116220027 A CN116220027 A CN 116220027A CN 202310218393 A CN202310218393 A CN 202310218393A CN 116220027 A CN116220027 A CN 116220027A
Authority
CN
China
Prior art keywords
pile
piles
reinforced
construction
center
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310218393.2A
Other languages
Chinese (zh)
Inventor
李兰菊
潘吉应
周炳秋
刘燕
代云峰
安勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Construction Group Construction Engineering Co ltd 7
Original Assignee
Guizhou Construction Group Construction Engineering Co ltd 7
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Construction Group Construction Engineering Co ltd 7 filed Critical Guizhou Construction Group Construction Engineering Co ltd 7
Priority to CN202310218393.2A priority Critical patent/CN116220027A/en
Publication of CN116220027A publication Critical patent/CN116220027A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/06Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers for observation while placing
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses a construction method of a BIM auxiliary reinforced pile and a reinforced pile-free occluding pile, wherein a rotary drilling machine is adopted for forming holes on a drilled occluding pile, a hard cutting process is adopted for carrying out hole jumping construction on an I-order pile and a II-order pile, wherein the I-order pile is a reinforced pile, the II-order pile is a reinforced pile, the I-order pile and the II-order pile are arranged at intervals, during construction, the I-order pile is firstly constructed, the II-order pile is then constructed, after the concrete of the I-order pile is finally set, the II-order pile is constructed, during construction of the II-order pile, part of concrete of the adjacent I-order pile is cut off by utilizing the rotary drilling machine, so that the I-order pile and the II-order pile which are sequentially constructed are mutually occluded and stressed together to form a seamless continuous pile wall. According to the scheme of the invention, the technology is advanced, the speed is increased, the efficiency is improved, the cost can be reduced, the construction period is shortened, the seepage-proofing and water-stopping effects can be improved, the rigidity is high, the safety is high, and the environmental protection benefit is obvious.

Description

BIM辅助有筋桩与无筋桩咬合桩施工方法BIM-assisted construction method of reinforced and unreinforced interlocking piles

技术领域Technical Field

本发明涉及建筑施工技术领域,尤其涉及一种BIM辅助有筋桩与无筋桩咬合桩施工方法。The present invention relates to the technical field of building construction, and in particular to a BIM-assisted reinforced pile and unreinforced pile interlocking pile construction method.

背景技术Background Art

因城市市区内建设工程多存在施工场地狭窄、毗邻建筑林立,因此,紧邻周边建筑的深基坑支护,应考虑周边各种地下埋设管线、水文、气候、地下水位丰富、建筑物基础等因素。Because most construction projects in urban areas have narrow construction sites and are adjacent to numerous buildings, the deep foundation pit support adjacent to surrounding buildings should take into account factors such as various surrounding underground pipelines, hydrology, climate, groundwater levels, and building foundations.

现有的咬合桩支护方式多为SMW工法桩,受挡墙底部抛石的影响拌桩无法施工至岩层,且H型钢无法插入至设计标高,基坑围护结构无法满足止水和受力问题。The existing interlocking pile support methods are mostly SMW method piles. Due to the influence of riprap at the bottom of the retaining wall, the mixed piles cannot be constructed to the rock layer, and the H-shaped steel cannot be inserted to the designed elevation. The foundation pit retaining structure cannot meet the water-stopping and stress problems.

而且,现有围护结构需增加辅助截水帷幕等防水措,大大增加了项目成本,增加了工期。而且施工过程泥浆多,施工现场脏乱,施工时存在噪声、有振动,对地层及周边环境影响大。Moreover, the existing enclosure structure needs to be equipped with auxiliary water-blocking curtains and other waterproof measures, which greatly increases the project cost and construction period. In addition, there is a lot of mud during the construction process, the construction site is dirty and messy, there is noise and vibration during construction, and it has a great impact on the stratum and surrounding environment.

发明内容Summary of the invention

本发明的目的在于解决背景技术中的至少一个技术问题,提供一种BIM辅助有筋桩与无筋桩咬合桩施工方法。The purpose of the present invention is to solve at least one technical problem in the background technology and to provide a BIM-assisted reinforced pile and unreinforced pile interlocking pile construction method.

为实现上述目的,本发明提供一种BIM辅助有筋桩与无筋桩咬合桩施工方法,钻孔咬合桩采用旋转钻机成孔,采用硬切割工艺,分I序桩和II序桩跳孔施工,其中I序桩为无筋桩,II序桩为有筋桩,I序桩和II序桩间隔布置,在施工时,先施工I序桩,后施工II序桩,在I序桩混凝土终凝后II序桩开始施工,II序桩施工时,利用旋挖钻机切割掉相邻I序桩的部分混凝土,使先后施工的I序桩与II序桩之间相互咬合,共同受力形成无缝的连续桩墙。To achieve the above object, the present invention provides a BIM-assisted reinforced pile and unreinforced pile interlocking pile construction method, wherein the bored interlocking piles are bored by a rotary drilling rig, and a hard cutting process is adopted, and the I-sequence piles and the II-sequence piles are constructed by skipping holes, wherein the I-sequence piles are unreinforced piles, and the II-sequence piles are reinforced piles, and the I-sequence piles and the II-sequence piles are arranged at intervals. During construction, the I-sequence piles are constructed first, and then the II-sequence piles are constructed. After the concrete of the I-sequence piles is finally set, the II-sequence piles are started to be constructed. During the construction of the II-sequence piles, a rotary drilling rig is used to cut off part of the concrete of the adjacent I-sequence piles, so that the I-sequence piles and the II-sequence piles constructed successively interlock with each other and bear force together to form a seamless continuous pile wall.

根据本发明的一个方面,所述I序桩和所述II序桩单桩施工包括:According to one aspect of the present invention, the construction of the single piles of the sequence I piles and the sequence II piles includes:

施工准备、BIM策划模拟、桩位放样、导墙施工、护筒埋设、钻机就位、旋挖钻进、成孔验收、导管安装、灌注混凝土成桩和成桩验收。Construction preparation, BIM planning and simulation, pile position marking, guide wall construction, casing burial, drilling rig positioning, rotary drilling, hole completion acceptance, conduit installation, concrete pouring and pile completion acceptance.

根据本发明的一个方面,所述BIM策划模拟为在BIM模型中结合场地布置对加工场、放置材料位置、垂直运输机械位置进行确定,按照当前道路状况与永久性道路重新调整临时设施,规划施工现场运输道路。According to one aspect of the present invention, the BIM planning simulation is to determine the processing site, material placement location, and vertical transportation machinery location in combination with the site layout in the BIM model, readjust temporary facilities according to current road conditions and permanent roads, and plan construction site transportation roads.

根据本发明的一个方面,所述桩位放样为采用全站仪测放桩位,桩位中心插钢筋,四周各打一根控制桩来控制桩位中心,然后复核桩位中心,复核后开钻,下护筒,再复测护筒,校正护筒,再测标高,完成桩位放样。According to one aspect of the present invention, the pile position is laid out by using a total station to measure and lay out the pile position, reinforcing bars are inserted in the center of the pile position, a control pile is driven around each side to control the center of the pile position, and then the center of the pile position is verified. After verification, drilling is started, casing is lowered, the casing is remeasured, the casing is calibrated, and the elevation is measured again to complete the pile position layout.

根据本发明的一个方面,所述桩位中心误差控制在5mm以内。According to one aspect of the present invention, the pile position center error is controlled within 5 mm.

根据本发明的一个方面,所述导墙施工为在桩顶按照排桩桩位设置钢筋混凝土导墙,所述钢筋混凝土导墙的厚度为500mm,宽度为1500mm。According to one aspect of the present invention, the guide wall is constructed by setting a reinforced concrete guide wall at the top of the pile according to the pile position, and the reinforced concrete guide wall has a thickness of 500 mm and a width of 1500 mm.

根据本发明的一个方面,所述护筒埋设为根据桩位点设置护筒,护筒的内径大于钻头直径200mm,护筒中心和桩位中心偏差≤50mm,倾斜度的偏差≤0.5%,护筒与坑壁之间采用粘土填实。According to one aspect of the present invention, the casing is buried according to the pile position, the inner diameter of the casing is 200mm larger than the drill bit diameter, the deviation between the casing center and the pile position center is ≤50mm, the deviation of the inclination is ≤0.5%, and clay is used to fill the space between the casing and the pit wall.

根据本发明的一个方面,所述护筒埋设完成后,将桩位中心通过四个控制护桩引回校正,使护筒中心与桩位中心重合,并在护筒上用红油漆标识护桩方向线。According to one aspect of the present invention, after the casing is buried, the pile center is led back for correction through four control piles so that the casing center coincides with the pile center, and the pile direction line is marked on the casing with red paint.

根据本发明的一个方面,所述钻机就位为转盘中心对准桩位中心的偏差小于20mm,并用水平尺校对转盘水平,并使天车中心、转盘中心与桩位中心成一垂直线,偏差小于20mm。According to one aspect of the present invention, the drilling rig is positioned so that the deviation between the center of the turntable and the center of the pile is less than 20 mm, and the level of the turntable is calibrated with a spirit level, and the center of the overhead crane, the center of the turntable and the center of the pile are in a vertical line with a deviation less than 20 mm.

根据本发明的一个方面,所述导管采用壁厚≥6mm的钢板卷制焊成,其直径为300mm;导管的中间节长2m,最下节长4m,导管使用前预拼,配备0.5m、1m、1.5m、2m非标准节。According to one aspect of the present invention, the conduit is rolled and welded from steel plates with a wall thickness of ≥6 mm, and has a diameter of 300 mm; the middle section of the conduit is 2 m long, and the lowest section is 4 m long. The conduit is pre-assembled before use and is equipped with non-standard sections of 0.5 m, 1 m, 1.5 m, and 2 m.

根据本发明的方案,本发明的BIM辅助有筋桩与无筋桩咬合桩施工方法具有以下有益效果:According to the solution of the present invention, the BIM-assisted reinforced pile and unreinforced pile interlocking pile construction method of the present invention has the following beneficial effects:

技术先进、提速增效:针对场地狭窄、施工机具种类多、数量多,利用BIM技术的模拟性,提前合理布局,动态模拟成孔顺序、可优化资源配置机具使用率最大化、现场用地最优化,材料运输畅通化便于咬合桩施工。Advanced technology, speed-up and efficiency improvement: In view of the narrow site and the large number and variety of construction machinery and equipment, the simulation of BIM technology is utilized to make reasonable layout in advance, dynamically simulate the drilling sequence, optimize resource allocation to maximize the utilization rate of machinery and equipment, optimize on-site land use, and facilitate material transportation for the construction of interlocking piles.

降低成本,缩短工期:本工法的咬合桩,即有筋桩与无筋桩互相咬合使桩与桩之间形成一道连续无缝的“桩墙”。由于是素荤咬合,有筋桩间距较其他排桩大、钢筋用量相对少,与其他围护结构形式相比,无需增加辅助截水帷幕等防水措,施大大减少项目成本,缩短工期。Reduce costs and shorten construction period: The interlocking piles of this construction method, that is, the reinforced piles and the unreinforced piles interlock with each other to form a continuous and seamless "pile wall" between the piles. Due to the interlocking, the spacing between the reinforced piles is larger than that of other pile rows, and the amount of steel bars used is relatively small. Compared with other forms of enclosure structures, there is no need to add auxiliary water-cutting curtains and other waterproofing measures, which greatly reduces project costs and shortens construction period.

提升防渗止水效果:特别在地下水丰富地层采用咬合桩排桩围护结构具有良好的防渗效果,无需另外增加辅助截水帷幕等防水措施,在挡土支护的同时,又可以有效地起到止水的作用。Improve the anti-seepage and water-stopping effect: Especially in the strata with abundant groundwater, the use of interlocking piles and pile retaining structures has a good anti-seepage effect. There is no need to add additional waterproofing measures such as auxiliary water-cutting curtains. While retaining soil and supporting it, it can also effectively stop water.

刚度大、安全度高:有筋桩与无筋桩互相咬合,有筋桩间采用无筋桩“填充”而无需设置截水帷幕,且具有较大的整体刚度,有利于施工安全。High rigidity and safety: the reinforced piles and unreinforced piles are interlocked, and unreinforced piles are used to "fill" between the reinforced piles without the need to set up water-cutting curtains. They also have greater overall rigidity, which is beneficial to construction safety.

环保效益明显:施工过程中,泥浆少,施工现场清洁,施工无噪声、无振动,对地层及周边环境影响小,改善了施工环境,实现文明施工。The environmental benefits are obvious: during the construction process, there is less mud, the construction site is clean, there is no noise or vibration during construction, and the impact on the stratum and surrounding environment is small, which improves the construction environment and realizes civilized construction.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

图1示意性表示根据本发明的一种实施方式的BIM辅助有筋桩与无筋桩咬合桩施工方法的施工顺序图;FIG1 schematically shows a construction sequence diagram of a BIM-assisted reinforced pile and unreinforced pile interlocking pile construction method according to an embodiment of the present invention;

图2示意性表示根据本发明的一种实施方式的单桩施工的流程图。FIG. 2 schematically shows a flow chart of a single pile construction according to an embodiment of the present invention.

具体实施方式DETAILED DESCRIPTION

现在将参照示例性实施例来论述本发明的内容。应当理解,论述的实施例仅是为了使得本领域普通技术人员能够更好地理解且因此实现本发明的内容,而不是暗示对本发明的范围的任何限制。The content of the present invention will now be discussed with reference to exemplary embodiments. It should be understood that the embodiments discussed are only to enable those skilled in the art to better understand and thus implement the content of the present invention, rather than implying any limitation on the scope of the present invention.

如本文中所使用的,术语“包括”及其变体要被解读为意味着“包括但不限于”的开放式术语。术语“基于”要被解读为“至少部分地基于”。术语“一个实施例”和“一种实施例”要被解读为“至少一个实施例”。As used herein, the term “including” and variations thereof are to be interpreted as open-ended terms meaning “including, but not limited to.” The term “based on” is to be interpreted as “based, at least in part, on.” The terms “one embodiment” and “an embodiment” are to be interpreted as “at least one embodiment.”

本发明适用于建(构)筑物密集区素填土、地下水丰富、易产生流砂不良条件地质的深基坑围护结构。利用BIM技术模拟特性,对总平面布置实时进行动态调整、可优化资源配置机具使用率最大化、现场用地最优化,材料运输畅通,在节约资源的同时保证了现场施工有序进行,实现现场平面布置合理、高效。The present invention is applicable to deep foundation pit retaining structures in areas with densely populated buildings (structures), abundant groundwater, and unfavorable geological conditions prone to quicksand. By utilizing the simulation characteristics of BIM technology, the overall layout can be dynamically adjusted in real time, resource allocation can be optimized to maximize the utilization rate of machinery and tools, optimize the site land use, and ensure smooth material transportation. While saving resources, it ensures that the on-site construction is carried out in an orderly manner, and realizes a reasonable and efficient on-site layout.

本发明的钻孔咬合桩采用旋转钻机成孔,采用硬切割工艺,分两序(I、II)跳孔施工,I序桩为无筋桩,II序桩为有筋桩,无筋桩(I序)和有筋桩(II序)间隔布置,先施工I序桩,后施工II序桩,跳挖的间距大于设计要求(设计为4m)。I序桩混凝土终凝后II序桩才能施工,II序桩施工时,利用旋挖钻机切割掉相邻I序桩的部分混凝土,使先后施工的桩与桩之间相互咬合,共同受力形成无缝的连续“桩墙”。The drilled interlocking pile of the present invention adopts a rotary drilling machine to form holes, adopts a hard cutting process, and is divided into two sequences (I, II) for skip hole construction. The I sequence pile is a non-reinforced pile, and the II sequence pile is a reinforced pile. The non-reinforced pile (I sequence) and the reinforced pile (II sequence) are arranged at intervals, and the I sequence pile is constructed first, and then the II sequence pile is constructed, and the spacing of the skipping excavation is greater than the design requirement (designed to be 4m). The II sequence pile can only be constructed after the I sequence pile concrete is finally set. When the II sequence pile is constructed, a rotary drilling machine is used to cut off part of the concrete of the adjacent I sequence piles, so that the piles constructed successively and successively are interlocked with each other, and jointly stressed to form a seamless continuous "pile wall".

在本发明中,总的施工原则是先施工I桩,后施工II桩,施工工艺及顺下与合计要求相一致,间隔3个孔跳挖施工,其施工顺序如图1所示。In the present invention, the general construction principle is to construct pile I first and then pile II. The construction technology and sequence are consistent with the total requirements, and the construction is carried out by skipping and digging at intervals of 3 holes. The construction sequence is shown in FIG1 .

图2示意性表示根据本发明的一种实施方式的单桩施工的流程图。如图2所示,在本实施方式中,I序桩和所述II序桩单桩施工包括:Fig. 2 schematically shows a flow chart of a single pile construction according to an embodiment of the present invention. As shown in Fig. 2, in this embodiment, the construction of the single piles of sequence I and sequence II piles includes:

施工准备、BIM策划模拟、桩位放样、导墙施工、护筒埋设、钻机就位、旋挖钻进、成孔验收、导管安装、灌注混凝土成桩和成桩验收。Construction preparation, BIM planning and simulation, pile position marking, guide wall construction, casing burial, drilling rig positioning, rotary drilling, hole completion acceptance, conduit installation, concrete pouring and pile completion acceptance.

在本实施方式中,BIM策划模拟为在BIM模型中结合场地布置对加工场、放置材料位置、垂直运输机械位置进行确定,按照当前道路状况与永久性道路重新调整临时设施,规划施工现场运输道路。In this embodiment, BIM planning simulation is to determine the processing site, material placement location, and vertical transportation machinery location in combination with the site layout in the BIM model, readjust temporary facilities according to current road conditions and permanent roads, and plan construction site transportation roads.

在本实施方式中,桩位放样为在工程开工后,组织专业测量人员进行测量放线定位,用全站仪测放桩位,桩位中心插一钢筋,四周各打一根控制桩来控制桩位中心,再请监理单位复核,复核之后开钻,下护筒,再复测,校正护筒,再测标高后,进入下道工序。桩位中心误差须控制在5mm以内。进一步确定是否有障碍物,必须待甲方或监理验收合格后方可进行成孔施工。In this embodiment, the stakeout is to organize professional surveyors to measure and lay out the lines after the project starts, use a total station to measure and lay out the pile position, insert a steel bar in the center of the pile position, and drive a control pile around to control the center of the pile position. Then ask the supervision unit to review it. After the review, start drilling, put down the casing, re-measure, calibrate the casing, and measure the elevation before entering the next process. The error of the pile center must be controlled within 5mm. To further determine whether there are obstacles, the hole construction can only be carried out after the acceptance by Party A or the supervisor.

在本实施方式中,为提高钻孔咬合桩孔口的定位精度,提高就位效率,保证底部有足够的咬合量,在桩顶按照排桩桩位设置钢筋混凝土导墙,根据规范要求导墙厚度500mm,导墙宽度1500mm,导墙预留定位孔模板直径比套管直径扩大30mm。In this embodiment, in order to improve the positioning accuracy of the bored pile hole, improve the positioning efficiency, and ensure sufficient engagement at the bottom, a reinforced concrete guide wall is set at the top of the pile according to the pile position. According to the specifications, the guide wall thickness is 500mm, the guide wall width is 1500mm, and the diameter of the guide wall reserved positioning hole template is 30mm larger than the casing diameter.

在本实施方式中,根据桩位点设置护筒,护筒的内径应大于钻头直径200mm,护筒位置应埋设正确稳定,护筒中心和桩位中心偏差不得大于50mm,倾斜度的偏差不大于0.5%,护筒与坑壁之间应用粘土填实。护筒埋设后再将桩位中心通过四个控制护桩引回校正,使护筒中心与桩位中心重合,并在护筒上用红油漆标识护桩方向线。In this embodiment, the casing is set according to the pile position. The inner diameter of the casing should be 200mm larger than the drill bit diameter. The casing position should be buried correctly and stably. The deviation between the center of the casing and the center of the pile position should not be greater than 50mm. The deviation of the inclination should not be greater than 0.5%. Clay should be filled between the casing and the pit wall. After the casing is buried, the center of the pile position is led back and corrected through four control piles so that the center of the casing coincides with the center of the pile position, and the pile direction line is marked on the casing with red paint.

在本实施方式中,护筒的埋设深度为6~8m。In this embodiment, the buried depth of the casing is 6 to 8 m.

在本实施方式中,护筒既保护孔壁,又是钻孔的导向,则钢护筒平面位置与垂直度应准确,钢护筒周围和护筒底脚应紧密,不透水。为防止跑浆和防止地表水渗入孔内影响泥浆比重,护筒周围要填实,用粘土封口,即在钢护筒周围对称地、均匀地回填最佳含水量的粘土,要分层夯实,达到最佳密实度,以保证其垂直度和防止泥浆流失及位移、掉落。In this embodiment, the casing not only protects the hole wall, but also serves as a guide for drilling. Therefore, the plane position and verticality of the steel casing should be accurate, and the surrounding area and the bottom of the casing should be tight and impermeable. In order to prevent slurry from running out and prevent surface water from seeping into the hole to affect the specific gravity of the mud, the area around the casing should be filled and sealed with clay, that is, clay with the best water content should be backfilled symmetrically and evenly around the steel casing, and it should be compacted in layers to achieve the best density to ensure its verticality and prevent mud from running out, displacement, and falling.

采用机械开挖埋设护筒,先由旋挖钻头将孔位处护筒埋设深度范围内的土挖除,再利用旋挖钻将护筒吊装到位后直接压入土中。Mechanical excavation is used to bury the casing. First, the soil within the casing burial depth range at the hole location is excavated by a rotary drill bit, and then the casing is lifted into place by the rotary drill and directly pressed into the soil.

在本实施方式中,钻机就位时,转盘中心对准桩位中心标志的偏差应小于20mm,并用水平尺校对转盘水平,并做到天车中心、转盘中心与桩位中心成一垂直线,偏差小于20mm。钻机就位过程中避开测量桩位,避免对桩位的破坏,并专人进行监护。钻机的安装就位必须对中、水平、稳固,保证钻塔中心、转盘中心与桩位中心“三点一线”。In this embodiment, when the drilling rig is in place, the deviation of the turntable center aligning with the pile position center mark should be less than 20mm, and the turntable level should be calibrated with a level ruler, and the center of the overhead crane, the center of the turntable and the center of the pile position should be in a vertical line with a deviation of less than 20mm. During the process of the drilling rig being in place, avoid measuring the pile position to avoid damage to the pile position, and a dedicated person should be on guard. The installation of the drilling rig must be centered, horizontal, and stable to ensure that the center of the drilling tower, the center of the turntable and the center of the pile position are "three points in one line".

在本实施方式中,旋挖钻进施工中应根据地层情况合理选择钻进参数,一般开孔宜轻压慢转,正常钻进时钻进速度控制在5m--8m/h以内,临近终孔前或易坍地段放慢钻速至0.5m/h,以便及时排出钻屑,减少孔内沉渣,使易坍塌土层泥浆充分护壁,在不同土质交界处应放慢钻进速度。为防止相邻桩串孔或影响邻桩的成桩质量,相邻桩的成孔施工以满足不少于36小时为宜,因此,对不满足要求的桩跳桩(间隔3桩)施工。In this embodiment, the drilling parameters should be reasonably selected according to the formation conditions during the rotary drilling construction. Generally, the hole should be opened with light pressure and slow rotation. The drilling speed is controlled within 5m-8m/h during normal drilling. The drilling speed is slowed down to 0.5m/h before the end of the hole or in the easily collapsed section, so as to discharge the drill cuttings in time, reduce the sediment in the hole, and make the mud of the easily collapsed soil layer fully protect the wall. The drilling speed should be slowed down at the junction of different soil types. In order to prevent the adjacent piles from being drilled in series or affecting the pile quality of the adjacent piles, the hole construction of the adjacent piles should meet no less than 36 hours. Therefore, the piles that do not meet the requirements are skipped (3 piles apart) for construction.

在钻孔过程中应注意监视钻进进尺速度,密切注意孔内水位与出土量,尤其是提钻和出土的时候。若因故停钻更应保持孔内具有规定的水位和泥浆密度与粘度,避免出现塌孔现象。钻进过程中时刻观察孔洞垂直度及有无塌孔、缩径等现象,出现问题,及时处理。待问题处理后继续钻进。During the drilling process, attention should be paid to monitoring the drilling footage speed, paying close attention to the water level and the amount of excavation in the hole, especially when lifting the drill and excavating. If drilling is stopped for some reason, the water level, mud density and viscosity in the hole should be maintained to avoid hole collapse. During the drilling process, always observe the verticality of the hole and whether there is hole collapse, shrinkage and other phenomena. If there is a problem, deal with it in time. Continue drilling after the problem is solved.

在本实施方式中,钻孔达到设计标高后,对孔位、孔径、孔深和倾斜度进行检查(即成孔验收),成孔质量检查可采用先进的测壁仪或孔规进行检查,孔规采用钢筋制作,孔规直径不少于桩孔钢筋笼的设计直径加100mm,孔规长度为4d(d为桩孔直径),若出现缩径现象应进行反复扫孔,符合要求后进入下道工序。In this embodiment, after the drilling reaches the designed elevation, the hole position, hole diameter, hole depth and inclination are checked (i.e., hole acceptance). The hole quality inspection can be carried out using an advanced wall measuring instrument or hole gauge. The hole gauge is made of steel bars, and the hole gauge diameter is not less than the design diameter of the pile hole steel cage plus 100 mm. The hole gauge length is 4d (d is the pile hole diameter). If the diameter shrinkage phenomenon occurs, the hole should be scanned repeatedly, and the next process will be entered after meeting the requirements.

在本实施方式中,还需进行沉渣厚度检测,把沉渣检测器放入钻孔,记录检测圆板上测绳的长度;再用钢丝测绳把检孔钢筋放入钻孔、记录检孔钢筋加测绳的长度;两长度之间的差就是沉渣厚度。In this embodiment, it is also necessary to perform sediment thickness detection. The sediment detector is placed in the drill hole, and the length of the measuring rope on the detection circular plate is recorded; then the inspection hole steel bar is placed in the drill hole using a wire measuring rope, and the length of the inspection hole steel bar plus the measuring rope is recorded; the difference between the two lengths is the sediment thickness.

进一步地,在本实施方式中,I序桩和所述II序桩单桩施工还包括清孔,在本实施方式中,清孔是钻孔灌注桩施工中的一道重要工序,清孔质量的好坏直接影响水下混凝土灌注施工、桩身质量与桩基承载力的大小。钻孔灌注桩钻孔深度达到设计要求深度后,立即进行清孔,清孔后孔内沉渣厚度不大于200mm,在第1次清孔后将钢筋笼、导管放下,进行第2次清孔,并以第2次清孔为主。Furthermore, in this embodiment, the construction of the single pile of the sequence I pile and the sequence II pile also includes hole cleaning. In this embodiment, hole cleaning is an important process in the construction of bored piles. The quality of hole cleaning directly affects the underwater concrete pouring construction, the quality of the pile body and the bearing capacity of the pile foundation. After the drilling depth of the bored pile reaches the design required depth, the hole is cleaned immediately. After the hole is cleaned, the thickness of the sediment in the hole is not more than 200mm. After the first hole cleaning, the steel cage and the guide tube are lowered, and the second hole cleaning is performed, and the second hole cleaning is mainly performed.

为了保证清孔质量,本发明采用两次正循环清孔。在保证泥浆性能的同时,必须在终孔后清孔一次和灌注前清孔一次。采用优质泥浆清孔,进口泥浆比重不大于1.15,出口泥浆比重小于1.20,增大泥浆粘度,提高其悬浮能力,确保清孔彻底。第一次清孔是钻孔终孔时利用泥浆通过钻具进行的。一次清孔时间视不同的施工情况而定,一般控制在40-50分钟左右。In order to ensure the quality of hole cleaning, the present invention adopts two positive circulation hole cleaning. While ensuring the performance of the mud, the hole must be cleaned once after the hole is completed and once before the injection. Use high-quality mud to clean the hole, the inlet mud specific gravity is not more than 1.15, and the outlet mud specific gravity is less than 1.20, increase the mud viscosity, improve its suspension ability, and ensure thorough hole cleaning. The first hole cleaning is carried out by using mud through the drilling tool when the hole is completed. The time for one hole cleaning depends on different construction conditions and is generally controlled at about 40-50 minutes.

第二次清孔是钢筋笼在孔内安装完毕,利用导管进行的。根据桩孔体积计算,拟定第二次清孔时间为30-50分钟左右。二次清孔验收标准:孔底沉渣厚度小于100mm,泥浆比重小于1.20。二次清孔结束后应在30分钟内灌注混凝土。The second hole cleaning is carried out after the steel cage is installed in the hole, using a conduit. According to the calculation of the pile hole volume, the second hole cleaning time is planned to be about 30-50 minutes. The acceptance criteria for the second hole cleaning are: the thickness of the sediment at the bottom of the hole is less than 100mm, and the mud specific gravity is less than 1.20. Concrete should be poured within 30 minutes after the second hole cleaning.

进一步地,如图2所示,在本实施方式中,在进行导管安装前,还包括钢筋笼制作和钢筋笼安装,其中,钢筋笼采用现场加工制作,纵向每隔2m设置三角形内撑加劲箍筋,防止吊运时扭转、弯曲。沿钢筋笼周长安设4个成品垫块,用以保证灌注桩的钢筋保护层厚度。纵向受力钢筋采用机械连接,接头宜相互错开,位于同一连接区段内纵向受拉钢筋接头面积百分率不大于50%。相邻两接头中心间距应大于35d(d为受力钢筋较大直径)且不小于500mm,间距需满足设计及相关规范的要求。钢筋笼底部主筋可稍向内弯曲以利导向。Furthermore, as shown in FIG. 2 , in this embodiment, before the conduit is installed, it also includes the production and installation of a steel cage, wherein the steel cage is manufactured on-site, and triangular inner support stiffening stirrups are arranged every 2 m in the longitudinal direction to prevent twisting and bending during lifting. Four finished pads are installed along the circumference of the steel cage to ensure the thickness of the steel protection layer of the cast-in-place pile. The longitudinal force-bearing steel bars are mechanically connected, and the joints should be staggered with each other. The percentage of the area of the longitudinal tension steel bar joints in the same connection section is not more than 50%. The center distance between two adjacent joints should be greater than 35d (d is the larger diameter of the force-bearing steel bar) and not less than 500mm, and the distance must meet the requirements of the design and relevant specifications. The main reinforcement at the bottom of the steel cage can be slightly bent inward to facilitate guidance.

安装钢筋笼前,检查桩孔成孔质量,验收合格后,用25t吊车吊装下放钢筋笼。下放时由人工辅助对准孔位,使钢筋笼轴线与桩轴线吻合,保持垂直、轻放,严禁高提猛放和强制压入,避免碰撞孔壁及钢护筒。当钢筋笼下放到设计标高后,在孔口固定,防止钢筋笼在灌注混凝土时上浮及偏位,锚索位置提前埋放φ150钢套管,避免锚索孔施工时破坏主筋,下放钢筋笼时定好钻孔位置。在灌注桩施工时,为了保证声测管的标高、倾斜度,声测管两端采用成品堵头封堵,防止管内落入混凝土。Before installing the steel cage, check the quality of the pile hole. After acceptance, use a 25t crane to hoist and lower the steel cage. When lowering, use manual assistance to align the hole position so that the axis of the steel cage coincides with the axis of the pile. Keep it vertical and gently lower it. It is strictly forbidden to lift it up and force it in to avoid collision with the hole wall and steel casing. When the steel cage is lowered to the designed elevation, it is fixed at the hole mouth to prevent the steel cage from floating up and deviating when pouring concrete. The φ150 steel casing is buried in the anchor position in advance to avoid damaging the main reinforcement during the construction of the anchor hole. The drilling position is determined when the steel cage is lowered. During the construction of cast-in-place piles, in order to ensure the elevation and inclination of the sonic detection pipe, the two ends of the sonic detection pipe are sealed with finished plugs to prevent concrete from falling into the pipe.

钢筋笼安装吊放到位后复测钢筋笼外露长度是否满足冠梁的锚固长度。在钢护筒两侧放置垫台固定钢筋笼,不得以钢护筒作为钢筋笼的支撑。After the steel cage is installed and hoisted into place, re-measure the exposed length of the steel cage to see if it meets the anchorage length of the crown beam. Place pads on both sides of the steel casing to fix the steel cage, and the steel casing shall not be used as a support for the steel cage.

在本实施方式中,在有筋桩内埋设3根声测管。声测管均匀分布,基本等分桩的周长,声测管底部封闭且应在灌注桩的底部以上100mm,顶部应高出桩顶面500mm。同一根桩的声测管外露高度宜相同,混凝土浇筑时注意保持管内清洁。In this embodiment, three acoustic detection tubes are buried in the reinforced pile. The acoustic detection tubes are evenly distributed, basically dividing the circumference of the pile equally. The bottom of the acoustic detection tube is closed and should be 100mm above the bottom of the cast-in-place pile, and the top should be 500mm higher than the top surface of the pile. The exposed height of the acoustic detection tubes of the same pile should be the same, and care should be taken to keep the inside of the tube clean during concrete pouring.

在本实施方式中,导管安装时,导管采用壁厚不小于6mm的钢板卷制焊成直径300mm;导管的分节长度按工艺要求确定,中间节长2m,最下节长4m,导管使用前,须计算确定管节后预拼,配备0.5m、1m、1.5m、2m非标准节。导管制作要坚固、内壁光滑、顺直、无局部凹凸,对于旧导管在试压前应通过称重的方式判定导管壁厚是否满足使用要求。最上端采用0.3-2m的几节短管调节导管的长度,使管底距孔底300-500mm,并位于钻孔中央。导管采用法兰盘连接、活接头螺母连接以及快速插接连接;用橡胶“O”型密封圈或厚度为4-5mm的橡胶垫圈密封,严防漏水、漏气。In this embodiment, when the conduit is installed, the conduit is rolled and welded with a steel plate with a wall thickness of not less than 6mm into a diameter of 300mm; the length of the conduit sections is determined according to the process requirements, the middle section is 2m long, and the lowest section is 4m long. Before the conduit is used, the pipe sections must be calculated and determined before pre-assembly, and non-standard sections of 0.5m, 1m, 1.5m, and 2m are provided. The conduit should be made strong, with a smooth and straight inner wall and no local bumps. For old conduits, the wall thickness of the conduit should be determined by weighing before pressure testing to determine whether it meets the use requirements. Several short tubes of 0.3-2m are used at the top to adjust the length of the conduit so that the bottom of the tube is 300-500mm away from the bottom of the hole and is located in the center of the drill hole. The conduit is connected by flange, union nut and quick plug-in; it is sealed with a rubber "O" type sealing ring or a rubber gasket with a thickness of 4-5mm to prevent water leakage and air leakage.

导管在使用前,除应对其规格、质量和拼接构造进行认真地检查外,应进行试拼和试压,试压导管的长度应满足最长桩灌注需要,导管按自下而上的顺序编号和节段长度,且严格保持导管的组合顺序,每组导管不能混用。导管组拼后轴线差,不宜超过钻孔深的0.5%且不大于10cm。试压压力为孔底静水压力的1.5倍,检查合格后方可使用。Before using the conduit, in addition to carefully checking its specifications, quality and splicing structure, it should be tested for assembly and pressure testing. The length of the pressure test conduit should meet the needs of the longest pile casting. The conduits are numbered and segmented in order from bottom to top, and the combination order of the conduits is strictly maintained. Each group of conduits cannot be mixed. The axis difference after the conduit is assembled should not exceed 0.5% of the borehole depth and not exceed 10cm. The test pressure is 1.5 times the hydrostatic pressure at the bottom of the hole, and it can only be used after passing the inspection.

导管长度应按孔深和工作平台高度决定。漏斗底至钻孔上口段,宜使用非标准节导管。The length of the conduit should be determined according to the hole depth and the height of the working platform. Non-standard section conduits should be used from the bottom of the funnel to the upper opening of the borehole.

导管下放应竖直、轻放、以免碰撞钢筋笼。下放时要记录下放的节数,下放到孔底后,理论长度与实际长度进行比较,是否吻合。The conduit should be lowered vertically and gently to avoid collision with the steel cage. The number of sections lowered should be recorded when lowering. After lowering to the bottom of the hole, the theoretical length should be compared with the actual length to see if they match.

在本实施方式中,灌注混凝土成桩为在钢筋笼安装完后,再次检查孔底沉渣厚度是否符合设计要求,检查验收合格后,立即灌注水下混凝土,并保持连续进行,尽量缩短灌注时间。采用导管灌注水下混凝土,采用汽车吊机提升,灌注时混凝土通过臂架泵卸入料斗内灌注。导管直径300mm,在使用前及灌注4~6根桩后,要检查导管及其接头的密封性。In this embodiment, the concrete pile pouring is to check again whether the thickness of the sediment at the bottom of the hole meets the design requirements after the steel cage is installed. After the inspection and acceptance, the underwater concrete is poured immediately and continuously to shorten the pouring time as much as possible. The underwater concrete is poured by a conduit and lifted by a car crane. During the pouring, the concrete is unloaded into the hopper through a boom pump for pouring. The diameter of the conduit is 300mm. Before use and after pouring 4 to 6 piles, the sealing of the conduit and its joints should be checked.

导管下口底离孔底200~500mm,第一盘混凝土量必须满足导管埋入混凝土内深度不小于1m的要求,第一盘料应不小于2m3,并严密监视导管出料孔与混凝土面的相对位置,整个灌注过程中,导管埋入混凝土面始终保持在2m-6m之间,混凝土灌注必须连续,防止断桩,安放导管时做好每节导管长度及位置的记录,去除导管要根据测设的混凝土面高度及导管安放记录确定。The bottom of the lower end of the conduit is 200-500mm away from the bottom of the hole. The amount of the first batch of concrete must meet the requirement that the depth of the conduit buried in the concrete is not less than 1m. The first batch of material should be no less than 2m3 , and the relative position of the conduit outlet and the concrete surface should be closely monitored. During the entire pouring process, the conduit buried in the concrete surface is always maintained between 2m and 6m. Concrete pouring must be continuous to prevent broken piles. When placing the conduit, keep a record of the length and position of each section of the conduit. The removal of the conduit should be determined based on the measured concrete surface height and the conduit placement record.

水下混凝土性能:入孔时混凝土的坍落度控制在20±2cm,每立方混凝土中水泥用量不少于360kg;粗骨料最大粒径不大于40mm;混凝土含砂率控制在40%~45%。Performance of underwater concrete: The slump of concrete when entering the hole is controlled at 20±2cm, the cement consumption in each cubic meter of concrete is not less than 360kg; the maximum particle size of coarse aggregate is not more than 40mm; the sand content of concrete is controlled at 40%~45%.

水下灌注混凝土应超灌0.5m以上,待冠梁施工前,应凿除桩头。凿桩前须测定标高,以控制准确地凿到设计标高。凿除桩头混凝土必须采用人工凿除,不得采用爆破或其它影响桩身质量的方法进行。凿除桩头留下的部分不能有残余松散层和薄弱混凝土层,嵌入冠梁内的桩头及锚固钢筋长度要符合设计要求。Underwater concrete pouring should be over-cast by more than 0.5m. Before the crown beam is constructed, the pile head should be chiseled out. The elevation must be measured before chiseling the pile to control the accurate chiseling to the designed elevation. The pile head concrete must be chiseled out manually, and blasting or other methods that affect the quality of the pile body must not be used. The part left after the pile head is chiseled out must not have residual loose layers and weak concrete layers. The length of the pile head and anchor steel bars embedded in the crown beam must meet the design requirements.

在本实施方式中,混凝土灌注桩质量检验标准,详见下表1:In this embodiment, the quality inspection standard of cast-in-place concrete piles is shown in Table 1 below:

Figure BDA0004115855780000091
Figure BDA0004115855780000091

Figure BDA0004115855780000101
Figure BDA0004115855780000101

表1Table 1

进一步地,在本实施方式中,还包括:凿除桩头和冠梁施工;在本实施方式中,水下灌注混凝土应超灌0.5m以上,待冠梁施工前,应凿除桩头。凿桩前须测定标高,以控制准确地凿到设计标高。凿除桩头混凝土必须采用人工凿除,不得采用爆破或其它影响桩身质量的方法进行。凿除桩头留下的部分不能有残余松散层和薄弱混凝土层,嵌入冠梁内的桩头及锚固钢筋长度要符合设计要求。Furthermore, in this embodiment, it also includes: chiseling away the pile head and construction of the crown beam; in this embodiment, the underwater concrete pouring should be over-poured by more than 0.5m, and the pile head should be chiseled away before the construction of the crown beam. The elevation must be measured before chiseling the pile to control the accurate chiseling to the designed elevation. The chiseling away of the pile head concrete must be done manually, and blasting or other methods that affect the quality of the pile body must not be used. The part left after the pile head is chiseled away must not have any residual loose layer or weak concrete layer, and the length of the pile head and anchor steel bar embedded in the crown beam must meet the design requirements.

根据冠梁尺寸,为避损伤抗滑桩,采用人工开挖;工作面宽度为每侧30cm,由于表层土方为素填土,放坡系数根据规范安全要求选择为1:0.5。According to the size of the crown beam, manual excavation is adopted to avoid damaging the anti-slip piles; the width of the working surface is 30cm on each side. Since the surface soil is plain fill, the slope coefficient is selected as 1:0.5 according to the safety requirements of the specifications.

冠梁根据咬合桩施工进度分段进行施工,冠梁尺寸为1.5m*1.0m,钢筋为16φ18受力钢筋和φ14@200的箍筋构成。每15~20m设置一道伸缩沉降缝,伸缩缝宽度为2cm,采用沥青麻絮充填,充填深度不小于20cm。为加快基坑施工进度,在咬合桩施工完成一段后进行冠梁施工,采取现场钢筋绑扎、关模及砼浇注。The crown beam is constructed in sections according to the progress of the interlocking pile construction. The size of the crown beam is 1.5m*1.0m, and the steel bars are composed of 16φ18 stress steel bars and φ14@200 stirrups. An expansion and settlement joint is set every 15-20m. The expansion joint width is 2cm and is filled with asphalt hemp. The filling depth is not less than 20cm. In order to speed up the progress of the foundation pit construction, the crown beam construction is carried out after the interlocking pile construction is completed for one section, and on-site steel bar binding, mold closing and concrete pouring are adopted.

根据本发明的上述方案,本发明的BIM辅助有筋桩与无筋桩咬合桩施工方法具有以下有益效果:According to the above solution of the present invention, the BIM-assisted reinforced pile and unreinforced pile interlocking pile construction method of the present invention has the following beneficial effects:

技术先进、提速增效:针对场地狭窄、施工机具种类多、数量多,利用BIM技术的模拟性,提前合理布局,动态模拟成孔顺序、可优化资源配置机具使用率最大化、现场用地最优化,材料运输畅通化便于咬合桩施工。Advanced technology, speed-up and efficiency improvement: In view of the narrow site and the large number and variety of construction machinery and equipment, the simulation of BIM technology is utilized to make reasonable layout in advance, dynamically simulate the drilling sequence, optimize resource allocation to maximize the utilization rate of machinery and equipment, optimize on-site land use, and facilitate material transportation for the construction of interlocking piles.

降低成本,缩短工期:本工法的咬合桩,即有筋桩与无筋桩互相咬合使桩与桩之间形成一道连续无缝的“桩墙”。由于是素荤咬合,有筋桩间距较其他排桩大、钢筋用量相对少,与其他围护结构形式相比,无需增加辅助截水帷幕等防水措施,施大大减少项目成本,缩短工期。Reduce costs and shorten construction period: The interlocking piles of this construction method, that is, the reinforced piles and the unreinforced piles interlock with each other to form a continuous and seamless "pile wall" between the piles. Due to the interlocking, the spacing between the reinforced piles is larger than that of other pile rows, and the amount of steel bars used is relatively small. Compared with other forms of enclosure structures, there is no need to add auxiliary water-cutting curtains and other waterproofing measures, which greatly reduces project costs and shortens construction period.

提升防渗止水效果:特别在地下水丰富地层采用咬合桩排桩围护结构具有良好的防渗效果,无需另外增加辅助截水帷幕等防水措施,在挡土支护的同时,又可以有效地起到止水的作用。Improve the anti-seepage and water-stopping effect: Especially in the strata with abundant groundwater, the use of interlocking piles and pile retaining structures has a good anti-seepage effect. There is no need to add additional waterproofing measures such as auxiliary water-cutting curtains. While retaining soil and supporting it, it can also effectively stop water.

刚度大、安全度高:有筋桩与无筋桩互相咬合,有筋桩间采用无筋桩“填充”而无需设置截水帷幕,且具有较大的整体刚度,有利于施工安全。High rigidity and safety: the reinforced piles and unreinforced piles are interlocked, and unreinforced piles are used to "fill" between the reinforced piles without the need to set up water-cutting curtains. They also have greater overall rigidity, which is beneficial to construction safety.

环保效益明显:施工过程中,泥浆少,施工现场清洁,施工无噪声、无振动,对地层及周边环境影响小,改善了施工环境,实现文明施工。The environmental benefits are obvious: during the construction process, there is less mud, the construction site is clean, there is no noise or vibration during construction, and the impact on the stratum and surrounding environment is small, which improves the construction environment and realizes civilized construction.

最后说明的是,以上优选实施例仅用以说明本发明的技术方案而非限制,尽管通过上述优选实施例已经对本发明进行了详细的描述,但本领域技术人员应当理解,可以在形式上和细节上对其作出各种各样的改变,而不偏离本发明权利要求书所限定的范围。Finally, it should be noted that the above preferred embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail through the above preferred embodiments, those skilled in the art should understand that various changes can be made in form and details without departing from the scope defined by the claims of the present invention.

Claims (10)

1.BIM辅助有筋桩与无筋桩咬合桩施工方法,其特征在于,钻孔咬合桩采用旋转钻机成孔,采用硬切割工艺,分I序桩和II序桩跳孔施工,其中I序桩为无筋桩,II序桩为有筋桩,I序桩和II序桩间隔布置,在施工时,先施工I序桩,后施工II序桩,在I序桩混凝土终凝后II序桩开始施工,II序桩施工时,利用旋挖钻机切割掉相邻I序桩的部分混凝土,使先后施工的I序桩与II序桩之间相互咬合,共同受力形成无缝的连续桩墙。1. The BIM-assisted construction method of interlocking piles with reinforced piles and non-reinforced piles is characterized in that the drilled interlocking piles are drilled with a rotary drilling rig and hard cutting technology is used, and the construction method is divided into sequence I piles and sequence II piles, where sequence I The piles are unreinforced piles, and the II piles are reinforced piles. The I piles and II piles are arranged at intervals. During construction, the I piles are constructed first, and then the II piles are constructed. The pile starts to be constructed, and during the construction of the sequence II pile, the rotary drilling rig is used to cut off part of the concrete of the adjacent sequence I pile, so that the sequence I pile and the sequence II pile constructed successively interlock with each other, and jointly form a seamless continuous pile wall. 2.根据权利要求1所述的BIM辅助有筋桩与无筋桩咬合桩施工方法,其特征在于,所述I序桩和所述II序桩单桩施工包括:2. BIM-assisted reinforced pile and unreinforced pile occlusal pile construction method according to claim 1, is characterized in that, described I sequence pile and described II sequence pile single pile construction comprise: 施工准备、BIM策划模拟、桩位放样、导墙施工、护筒埋设、钻机就位、旋挖钻进、成孔验收、导管安装、灌注混凝土成桩和成桩验收。Construction preparation, BIM planning simulation, stake out, guide wall construction, casing burial, drilling rig in place, rotary drilling, hole acceptance, conduit installation, poured concrete pile formation and pile acceptance. 3.根据权利要求2所述的BIM辅助有筋桩与无筋桩咬合桩施工方法,其特征在于,所述BIM策划模拟为在BIM模型中结合场地布置对加工场、放置材料位置、垂直运输机械位置进行确定,按照当前道路状况与永久性道路重新调整临时设施,规划施工现场运输道路。3. The BIM-assisted construction method of reinforced pile and unreinforced pile occlusal pile according to claim 2, characterized in that, the BIM planning simulation is combined with site layout in the BIM model to process field, place material position, vertical transportation Determine the location of the machinery, readjust the temporary facilities according to the current road conditions and permanent roads, and plan the transportation roads on the construction site. 4.根据权利要求2所述的BIM辅助有筋桩与无筋桩咬合桩施工方法,其特征在于,所述桩位放样为采用全站仪测放桩位,桩位中心插钢筋,四周各打一根控制桩来控制桩位中心,然后复核桩位中心,复核后开钻,下护筒,再复测护筒,校正护筒,再测标高,完成桩位放样。4. BIM-assisted construction method of reinforced pile and non-reinforced pile occlusal pile according to claim 2, characterized in that, the pile position setting out is to adopt total station instrument to measure and place the pile position, and the center of the pile position inserts steel bars, and the four sides Drive a control pile to control the center of the pile position, then check the center of the pile position, drill after the review, lower the casing, retest the casing, correct the casing, measure the elevation again, and complete the stake out. 5.根据权利要求4所述的BIM辅助有筋桩与无筋桩咬合桩施工方法,其特征在于,所述桩位中心误差控制在5mm以内。5. The BIM-assisted construction method for interlocking piles with reinforced piles and unreinforced piles according to claim 4, characterized in that the center error of the pile position is controlled within 5 mm. 6.根据权利要求2所述的BIM辅助有筋桩与无筋桩咬合桩施工方法,其特征在于,所述导墙施工为在桩顶按照排桩桩位设置钢筋混凝土导墙,所述钢筋混凝土导墙的厚度为500mm,宽度为1500mm。6. BIM-assisted construction method of reinforced pile and unreinforced pile occlusal pile according to claim 2, characterized in that, the construction of the guide wall is to set a reinforced concrete guide wall at the top of the pile according to the row of piles, and the steel bar The thickness of the concrete guide wall is 500mm and the width is 1500mm. 7.根据权利要求2所述的BIM辅助有筋桩与无筋桩咬合桩施工方法,其特征在于,所述护筒埋设为根据桩位点设置护筒,护筒的内径大于钻头直径200mm,护筒中心和桩位中心偏差≤50mm,倾斜度的偏差≤0.5%,护筒与坑壁之间采用粘土填实。7. BIM-aided construction method of reinforced pile and non-reinforced pile occlusal pile according to claim 2, characterized in that, said casing is buried as a casing according to the pile site, and the inner diameter of casing is greater than the diameter of the drill bit by 200mm, The deviation between the center of the casing and the center of the pile position is ≤50mm, the deviation of the inclination is ≤0.5%, and the gap between the casing and the pit wall is filled with clay. 8.根据权利要求7所述的BIM辅助有筋桩与无筋桩咬合桩施工方法,其特征在于,所述护筒埋设完成后,将桩位中心通过四个控制护桩引回校正,使护筒中心与桩位中心重合,并在护筒上用红油漆标识护桩方向线。8. The BIM-assisted construction method for occlusal piles with reinforced piles and unreinforced piles according to claim 7, characterized in that, after the casing is buried, the center of the pile position is led back to be corrected through four control piles, so that The center of the casing coincides with the center of the pile position, and the direction line of the pile protection is marked with red paint on the casing. 9.根据权利要求2所述的BIM辅助有筋桩与无筋桩咬合桩施工方法,其特征在于,所述钻机就位为转盘中心对准桩位中心的偏差小于20mm,并用水平尺校对转盘水平,并使天车中心、转盘中心与桩位中心成一垂直线,偏差小于20mm。9. The BIM-assisted construction method for occlusal piles with reinforced piles and non-reinforced piles according to claim 2, characterized in that, when the drilling rig is in place, the deviation between the center of the turntable and the center of the pile position is less than 20 mm, and the turntable is checked with a level ruler Horizontal, and make the center of the crown block, the center of the turntable and the center of the pile position form a vertical line, and the deviation is less than 20mm. 10.根据权利要求2-9中任一项所述的BIM辅助有筋桩与无筋桩咬合桩施工方法,其特征在于,所述导管采用壁厚≥6mm的钢板卷制焊成,其直径为300mm;导管的中间节长2m,最下节长4m,导管使用前预拼,配备0.5m、1m、1.5m、2m非标准节。10. The BIM-assisted construction method for occlusal piles with reinforced piles and unreinforced piles according to any one of claims 2-9, wherein the conduit is rolled and welded with a steel plate with a wall thickness ≥ 6mm, and its diameter The length of the middle section of the catheter is 2m, and the length of the bottom section is 4m. The catheter is pre-assembled before use, and it is equipped with non-standard sections of 0.5m, 1m, 1.5m, and 2m.
CN202310218393.2A 2023-03-08 2023-03-08 BIM auxiliary reinforced pile and non-reinforced pile engaged pile construction method Pending CN116220027A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310218393.2A CN116220027A (en) 2023-03-08 2023-03-08 BIM auxiliary reinforced pile and non-reinforced pile engaged pile construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310218393.2A CN116220027A (en) 2023-03-08 2023-03-08 BIM auxiliary reinforced pile and non-reinforced pile engaged pile construction method

Publications (1)

Publication Number Publication Date
CN116220027A true CN116220027A (en) 2023-06-06

Family

ID=86590794

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310218393.2A Pending CN116220027A (en) 2023-03-08 2023-03-08 BIM auxiliary reinforced pile and non-reinforced pile engaged pile construction method

Country Status (1)

Country Link
CN (1) CN116220027A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116561873A (en) * 2023-06-21 2023-08-08 湖南省交通规划勘察设计院有限公司 Pile foundation parameter visualization method and system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103276723A (en) * 2013-04-27 2013-09-04 瑞华建设集团有限公司 Construction method of concrete bored secant pile
CN103388333A (en) * 2013-07-25 2013-11-13 中铁十六局集团有限公司 Construction process for carrying out construction on interlocking pile by adopting rotary drilling rig and mud protection wall method
CN104808610A (en) * 2015-02-13 2015-07-29 上海同筑信息科技有限公司 Machinery control system and machinery control method based on a BIM (building information model)
CN108625369A (en) * 2018-06-22 2018-10-09 中铁二局第工程有限公司 The hard patterning method construction method of interlocking pile in karst area
CN108755660A (en) * 2018-08-22 2018-11-06 中国建筑第四工程局有限公司 One kind entering 30 meters of construction method of underground continuous wall of rock close to subway
AU2020103672A4 (en) * 2020-11-25 2021-02-04 Beijing Building Materials Engineering Co. Ltd Construction method of rotary drilling hole-forming and jet mixing cement-soil occlusion curtain piles
CN113653039A (en) * 2021-08-31 2021-11-16 中国五冶集团有限公司 Occlusive pile construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103276723A (en) * 2013-04-27 2013-09-04 瑞华建设集团有限公司 Construction method of concrete bored secant pile
CN103388333A (en) * 2013-07-25 2013-11-13 中铁十六局集团有限公司 Construction process for carrying out construction on interlocking pile by adopting rotary drilling rig and mud protection wall method
CN104808610A (en) * 2015-02-13 2015-07-29 上海同筑信息科技有限公司 Machinery control system and machinery control method based on a BIM (building information model)
CN108625369A (en) * 2018-06-22 2018-10-09 中铁二局第工程有限公司 The hard patterning method construction method of interlocking pile in karst area
CN108755660A (en) * 2018-08-22 2018-11-06 中国建筑第四工程局有限公司 One kind entering 30 meters of construction method of underground continuous wall of rock close to subway
AU2020103672A4 (en) * 2020-11-25 2021-02-04 Beijing Building Materials Engineering Co. Ltd Construction method of rotary drilling hole-forming and jet mixing cement-soil occlusion curtain piles
CN113653039A (en) * 2021-08-31 2021-11-16 中国五冶集团有限公司 Occlusive pile construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116561873A (en) * 2023-06-21 2023-08-08 湖南省交通规划勘察设计院有限公司 Pile foundation parameter visualization method and system
CN116561873B (en) * 2023-06-21 2024-05-31 湖南省交通规划勘察设计院有限公司 Pile foundation parameter visualization method and system

Similar Documents

Publication Publication Date Title
CN109629455B (en) Construction method for reconstructing bridge of highway
CN108842819B (en) Urban rail transit cable line tunnel construction method
CN100473790C (en) Tower crane foundation for construction and manufacturing method thereof
CN110106868B (en) Karst geology large-diameter pile foundation pore-forming process method
CN104532813A (en) Overwater building construction platform and erecting method and use method thereof
CN114411761B (en) Advanced pre-supporting system and method for subway tunnel to be built in new building construction
CN116289969A (en) Anti-leakage construction method of occlusal piles for deep foundation pit enclosure structure based on sonar detection technology
CN110805029A (en) Subway underground-excavated station drilling and grouting fender post construction method
CN117626947A (en) Construction method of bored piles with rotary drill
CN110145232B (en) Construction method for rotary drilling hole without slurry supplement
CN116220027A (en) BIM auxiliary reinforced pile and non-reinforced pile engaged pile construction method
CN115217098A (en) A cast-in-place pile construction technology
CN118704502A (en) A method for dewatering a deep foundation pit pipe well in a quicksand layer adjacent to an existing building
CN113981958A (en) Method for plugging karst cave of mechanical pore-forming cast-in-place pile
CN118774155A (en) Construction method of dewatering deep foundation pit in pressurized water
CN117449904A (en) Construction method for reinforcing and breaking barrier-like pile in underground tunnel construction
CN114319432B (en) Construction process of semi-underground subway station and semi-underground subway station
CN113685190B (en) Reinforcing system for shield to penetrate shallow soft clay and construction method
CN112095377B (en) Off-pit construction road structure next to subway deep foundation pit and construction method thereof
CN114622572A (en) Large-scale round foundation pit triaxial mixing pile supporting structure and construction method thereof
CN111042049A (en) Rainwater pipe construction process
CN216788421U (en) Reinforcement construction system of tunnel business turn over hole portal
CN219692444U (en) Pipeline protection structure crossing foundation pit
CN116398701B (en) Improved large-diameter main water pipe traversing foundation pit protection structure and construction method thereof
CN114319372B (en) Construction method of anchorage supporting structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination