CN109736332A - The empty van placement method and empty van filling structure for preventing sinkage dock pit siltation from shoaling - Google Patents
The empty van placement method and empty van filling structure for preventing sinkage dock pit siltation from shoaling Download PDFInfo
- Publication number
- CN109736332A CN109736332A CN201910010932.7A CN201910010932A CN109736332A CN 109736332 A CN109736332 A CN 109736332A CN 201910010932 A CN201910010932 A CN 201910010932A CN 109736332 A CN109736332 A CN 109736332A
- Authority
- CN
- China
- Prior art keywords
- empty van
- sinkage
- group
- dock pit
- zone
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Barrages (AREA)
Abstract
The invention discloses a kind of empty van placement method for preventing sinkage dock pit siltation from shoaling and empty van filling structures, the deep water case group mutually fitted with profundal zone to be filled out and phytal zone respectively and phytal zone case group are connected by the empty van body assembly of predetermined quantity, and counterweight is placed in corresponding empty van chamber, so that deep water case group and shallow water case group can sink down into it is inconsistent with profundal zone and phytal zone bottom wall respectively, to which entire sinkage dock pit be filled and the part exposure of empty van group, it can stop during sinkage dock pit is idle or silt is greatly decreased to fall into sinkage dock pit, and then prevent sinkage dock pit siltation from shoaling;When needing using sinkage dock pit, the indoor counterweight of empty van body cavity is taken out, so that cabinet is floated and cabinet is moved away from sinkage dock pit, floating dock can be allowed to sink down into required depth, to carry out shipbuilding, maintenance and service work;Dredging operation need not be carried out to sinkage dock pit, to save corresponding dredging cost and time, reduce the pollution of dredging bring, the operation cost of sinkage dock pit is greatly reduced.
Description
Technical field
The present invention relates to the technologies such as port engineering, marine engineering, inspection and repair of ship maintenance engineering, salvaging and Transportation Engineering
Field, in particular to a kind of empty van placement method for preventing sinkage dock pit siltation from shoaling and empty van filling structure.
Background technique
Sinkage dock pit refers to since the depth of water is inadequate in rivers,lakes and seas, is formed by dell by digging deep riverbed or sea bed, the depth
Hole for allow floating dock (floating dock, abbreviation floating dock, be it is a kind of be mainly used for repairing, the engineering ship of shipbuilding, it may also be used for it is heavy to salvage
Ship transports the navigation channel etc. that deepwater ship passes through shallow water) necessary depth can be sunk to, to carry out shipbuilding, maintenance and maintenance
Work, then leaves unused useless within remaining time.
Fig. 1 is a kind of sectional schematic diagram of typical sinkage dock pit, on its length and width direction, including is located at intermediate and bottom
The flat profundal zone 101 of wall and positioned at edge and bottom wall is in inclined-plane or the shallow water transition region 102 of cambered surface;Profundal zone 101 is
The key operation area of sinkage dock pit 100.From profundal zone to natural stream channel or sea bed, using segmentation gentle slope form, gradually transition, thus
Shallow water transition region is formed, to reduce silt slump or siltation.Sinkage dock pit can also be using vertical shaft type or the patterns such as U-shaped.
In sinkage dock pit profundal zone or phytal zone lay-up period, since sinkage dock pit is very deep, near mud, soil or sand, can exist
It is moved under water flow, sea area ocean current or wave or the isokinetic effect of storm tide to the profundal zone of sinkage dock pit in river, and no longer
Phytal zone is returned to, the siltation for ultimately causing sinkage dock pit shoals.
Even if the partial region of shallow water transition region is also at blank state, and the area is easy to form during sinkage dock pit work
Siltation shoals, and directly affects the depth of water of profundal zone.
In general, silt is mainly derived from two aspects in sinkage dock pit, it is on the one hand silt around sinkage dock pit
Or the soil body slides to sinkage dock pit profundal zone direction under hydrodynamic force or own wt effect and causes to deposit;It on the other hand is sea
After the silt of water float floats with water flow to above sinkage dock pit, sink to causing to deposit because hydrodynamic force weakens.
Sinkage dock pit is generally in the majority in sea area to build, since the energy that sea area wave and storm tide are carried under one's arms is very powerful, energy
The quantity of sand and mud of drive is very big, so especially when encountering typhoon, it is easy to cause sinkage dock pit to deposit, be known as in profession rapid
It becomes silted up.
Very big to its function and function influence after sinkage dock pit siltation shoals, therefore floating dock can not can sink to specified
Depth, and then the manufacture, maintenance and service work of ship can not be carried out.For this purpose, need to clear up the sinkage dock pit to shoal.But it is heavy
Wu Keng is generally very deep, and silt is difficult to be cleaned, and corresponding dredging engineering cost is very high, expend the time and there are environment dirts
Dye problem.
There is typhoon for several times in coastal area every year, brings the risk that shoals of greatly depositing to sinkage dock pit, prevents from depositing in nothing
In the case where measure, the annual dredging of sinkage dock pit or maintainability silt cleaning up cost are high, increase to the sinkage dock pit owner very big
Operation and management cost.
In brief, conventional sinkage dock pit dredging uses dredging method, exist such as increase water pollution, construction cost it is high,
The deficiencies of dredging markets disposition is difficult and storage is difficult place.
Summary of the invention
The main object of the present invention is to propose a kind of to prevent the sinkage dock pit empty van placement method that shoals of siltation and empty van filling
Structure, it is intended to prevent sinkage dock pit siltation from shoaling.
To achieve the above object, the present invention proposes a kind of empty van placement method for preventing sinkage dock pit siltation from shoaling, including such as
Lower step:
S1, region above the profundal zone that the water surface is located at sinkage dock pit be laid with first layer by the cabinet assembly connection of predetermined quantity and
At empty van group, the hollow formation chamber of box house, the tank wall of cabinet opens up the through-hole of connecting chamber, can after chamber water-filling
It bubbles through the water column, the vertical projection area or range and the bottom wall area or range of profundal zone of first layer empty van group are mutually fitted;
S2, the empty van group that the second layer is formed by connecting by the cabinet assembly of predetermined quantity, first layer are laid in first layer empty van group
Empty van group is under the gravity of second layer empty van group, and can sink predetermined depth;
S3, it is mutually fitted by the total height of the empty van group above step S2 repetitive operation to profundal zone and the depth of profundal zone, Huo Zhekong
Case group total height is slightly larger than the depth of sinkage dock pit, forms deep water case group, and via through holes place counterweight so that deep water to the chamber of cabinet
Case group is sunk down into be contradicted with profundal zone bottom wall, completes the filling operation of the deep water case group of profundal zone;Fill rear box group height with
Sinkage dock pit height is mutually fitted, or slightly larger than the height;
S4, the phytal zone of profundal zone surrounding is divided at least one shallow water area to be filled out on the length and width direction of sinkage dock pit
Domain is operated in the top in the shallow water region to be filled out that the water surface is located most closely to profundal zone referring to the mode of step S1 to S3, and completing should
The shallow water case group in shallow water region to be filled out fills operation;
S5, on the length and width direction of sinkage dock pit, using profundal zone as reference, by being operated by step S4 closely to remote sequence,
The shallow water case group for completing all shallow waters in phytal zone region to be filled out fills operation, is finally completed the empty van for preventing sinkage dock pit siltation from shoaling
Group filling operation;Filling rear box group height is mutually fitted with sinkage dock pit depth, or is slightly larger than the depth.
The present invention also proposes a kind of empty van filling structure for preventing sinkage dock pit siltation from shoaling, including for filling profundal zone
Deep water case group and positioned at profundal zone surrounding and for filling the shallow water case group of phytal zone.The deep water case group and shallow water case group are wrapped
At least one layer of empty van group is included, every layer of empty van group is formed by connecting by the cabinet assembly of respective numbers, the hollow shape of box house
At chamber, the tank wall of cabinet opens up the through-hole of connecting chamber, at least partly counterweight is placed in the chamber of cabinet, so that deep water case
Group and shallow water case group can sink down into inconsistent with the bottom wall of profundal zone and phytal zone respectively.
The present invention also propose it is another prevent sinkage dock pit from depositing the empty van placement method to shoal, include the following steps: A,
The top that the water surface is located at the idle region in profundal zone or phytal zone of sinkage dock pit is laid with first layer and is connected by the cabinet assembly of predetermined quantity
Empty van group made of connecing, the hollow formation chamber of box house, the tank wall of cabinet open up the through-hole for leading to chamber, chamber water-filling
After can bubble through the water column, the leave unused area in region of the vertical projection area of first layer empty van group and profundal zone or phytal zone is mutually fitted;
B, the empty van group that the second layer is formed by connecting by the cabinet assembly of predetermined quantity is laid in first layer empty van group, first layer is empty
Case group is under the gravity of second layer empty van group, and can sink predetermined depth;
C, by the total height of the empty van group of the idle overlying regions of step B repetitive operation to profundal zone or phytal zone and profundal zone or shallowly
The depth in the idle region in pool is mutually fitted or depth of the empty van group total height slightly larger than the idle region in profundal zone or phytal zone, shape
At deep water case group or shallow water case group, via through holes place counterweight so that deep water case group or shallow water case group are sink to and depth to the chamber of cabinet
Pool or phytal zone the region bottom wall that leaves unused contradict, and complete profundal zone or phytal zone is left unused the deep water case group or shallow water case group in region
Filling operation is finally completed the empty van filling operation for preventing the idle region siltation in profundal zone or phytal zone from shoaling.
Technical solution of the present invention by the empty van body assembly of predetermined quantity connect into respectively with profundal zone and phytal zone bottom boundaries
Mutually suitable deep water case group and phytal zone case group, and counterweight is placed in the chamber of corresponding empty van, so that deep water case group and shallow water
Case group can sink down into it is inconsistent with the bottom wall of profundal zone and phytal zone respectively, so that entire sinkage dock pit be filled and empty van group part
Thus exposure can stop or silt is greatly reduced fall into sinkage dock pit (especially to fall during sinkage dock pit is completely or partially idle
Enter profundal zone), and then prevent sinkage dock pit siltation from shoaling.When needing using sinkage dock pit, the indoor counterweight of cabinet chamber is first taken out, so that
Cabinet floats automatically and cabinet group is moved away from sinkage dock pit working space, and floating dock can be allowed to sink down into required depth, to carry out ship
Oceangoing ship manufacture, maintenance and service work, and highly difficult dredging need not be carried out to sinkage dock pit and operated, thus save corresponding dredging at
Sheet and dredging time, the operation and management cost of the sinkage dock pit owner can be greatly reduced, can also reduce bring water of desilting and dredging
Body pollution and environmental degradation.The cabinet for being moved away from sinkage dock pit can then be stored to specified position, with when sinkage dock pit next time is idle, then
Secondary filling sinkage dock pit.Therefore the present invention has the characteristics that convenient construction, low cost, environmental protection and energy saving and can be recycled.
Detailed description of the invention
Fig. 1 is the sectional schematic diagram of sinkage dock pit;
Fig. 2 is the stereoscopic schematic diagram of single cabinet;
Splicing relation schematic diagram of the Fig. 3 between horizontally adjacent and neighbouring cabinet;
Fig. 4 is that the stereoscopic schematic diagram after cabinet group is filled within the scope of sinkage dock pit partial-length;
Fig. 5 to 9 is the schematic diagram of sinkage dock pit profundal zone cabinet group stowing operation;
Figure 10 is that the schematic diagram after the filling operation of deep water case group is completed in sinkage dock pit profundal zone;
Figure 11 to 14 is the schematic diagram of sinkage dock pit phytal zone cabinet group stowing operation;
Figure 15 is the schematic diagram completed after entire sinkage dock pit cabinet filling.
Specific embodiment
Below in conjunction with attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that institute
The embodiment of description is only a part of the embodiments of the present invention, instead of all the embodiments.Based on the implementation in the present invention
Example, every other embodiment obtained by those of ordinary skill in the art without making creative efforts belong to
The scope of protection of the invention.
It is to be appreciated that if related in the embodiment of the present invention directionality instruction (such as up, down, left, right, before and after, top,
Bottom, inside and outside, vertical, transverse direction, longitudinal direction, counterclockwise, clockwise, circumferentially, radially, axially ...), then directionality instruction is only used
In explaining in relative positional relationship, the motion conditions etc. under a certain particular pose (as shown in the picture) between each component, if should
When particular pose changes, then directionality instruction also correspondingly changes correspondingly.
It, should " first " or " the in addition, if relating to the description of " first " or " second " etc. in the embodiment of the present invention
Two " etc. description is used for description purposes only, and is not understood to indicate or imply its relative importance or is implicitly indicated meaning
The quantity of the technical characteristic shown." first " is defined as a result, the feature of " second " can explicitly or implicitly include at least one
A this feature.It in addition, the technical solution between each embodiment can be combined with each other, but must be with ordinary skill
Based on personnel can be realized, this technical side will be understood that when the combination of technical solution appearance is conflicting or cannot achieve
The combination of case is not present, also not the present invention claims protection scope within.
The present invention proposes a kind of empty van placement method for preventing sinkage dock pit siltation from shoaling.
In the embodiment of the present invention, as shown in Fig. 1 to 15, the empty van placement method for preventing sinkage dock pit siltation from shoaling, including
Following steps:
S1, be located at sinkage dock pit 100 profundal zone 101 above water-surface areas be laid with first layer (from bottom to top successively sequence) by
The empty van group that 1 assembly of cabinet of predetermined quantity is formed by connecting, 1 inner hollow of cabinet form chamber (not shown), cabinet 1
Tank wall opens up the through-hole (not shown) of connecting chamber, and chamber water-filling is bubbled through the water column, the vertical projection area of first layer empty van group with
The bottom wall area of profundal zone 101 mutually fits (see Fig. 1 to 5).
Specifically, the density of 1 material of cabinet is close with water phase, preferably slightly smaller than water density (such as density be 0.5g/cm3~
0.9g/cm3), can bubble through the water column after guaranteeing 1 water-filling of cabinet (not place to chamber counterweight), cabinet 1 can be used plastics or its
His lightweight and there is the material (such as wood) of sufficient intensity to be made.
In step sl, the region above the profundal zone 101 that the water surface is located at sinkage dock pit 100 is laid with first layer by predetermined number
It, will be horizontally adjacent including the cooperation by plug tenon 11 and slot 12 in the operation for the empty van group that 1 assembly of cabinet of amount is formed by connecting
Cabinet 1 carry out assembled process.
S2, the empty van group that the second layer is formed by connecting by 1 assembly of cabinet of predetermined quantity is laid in first layer empty van group, the
One layer of empty van group is under the gravity of second layer empty van group, sinking predetermined depth, and second layer empty van group then partially stretches out water
Face (see figure 6);
In embodiments of the present invention, the second layer is laid in first layer empty van group to be formed by connecting by 1 assembly of cabinet of predetermined quantity
Empty van group step S2 in, further include the process that neighbouring cabinet 1 is carried out to assembled connection, to prevent the sky of upper and lower level
Dislocation movement occurs for case group (such as first layer empty van group and second layer empty van group).
Specifically, being by the process of the neighbouring assembled connection of cabinet 1 will be upper by the cooperation of plug tenon 11 and slot 12
Under adjacent cabinet 1 splice.
S3, by step S2 repetitive operation to the top of profundal zone 101 empty van group total height and the depth phase of profundal zone 101
Suitable or empty van group total height is slightly larger than the depth of sinkage dock pit, forms deep water case group 10, and via through holes are matched to the placement of the chamber of cabinet 1
Weight is so that deep water case group 10 is sunk down into and the conflict of 101 bottom wall of profundal zone, the filling operation of the deep water case group 10 of completion profundal zone 101
(see Fig. 7 to 10) can stop or silt is greatly reduced to fall into profundal zone 101 when 100 profundal zone 101 of sinkage dock pit is left unused.
Counterweight can be metal (such as iron) or the weight of the similar density of sandstone.
It should be noted that 100 depth of sinkage dock pit refers to 101 bottom wall of profundal zone to sinkage dock pit top surface (or mud face)
Vertical distance.In step s3, (in other words accumulate) how many layers of empty van group should be laid with, be according to the depth of sinkage dock pit 100 and
Depending on the height of single layer empty van group.
S4, on the length and width direction of sinkage dock pit 100 by the phytal zone 102 of 101 surrounding of profundal zone be divided into
A few shallow water region to be filled out, the shallow water region to be filled out that the water surface is located most closely to profundal zone 101 top referring to step S1 extremely
The mode of S3 operates, and completes the filling operation of shallow water case group 20 (see Figure 11) in shallow water region to be filled out.
It should be noted that shallow water case group 20 equally include multiple-level stack empty van group, empty van group by predetermined quantity case
1 assembly of body is formed by connecting, and specific assembly connection type is placed referring to deep water case group 10, and in the chamber of at least partly cabinet 1
Counterweight contradicts so that shallow water case group 20 is sunk with the bottom wall in corresponding shallow water region to be filled out, can be not busy in 100 phytal zone of sinkage dock pit 102
When setting, stop or silt be greatly reduced to fall into shallow water region to be filled out.
S5, on the length and width direction of sinkage dock pit 100, be reference with profundal zone 101, by closely to remote sequence, pressing
Step S4 operation, the shallow water case group 20 for completing 102 all shallow waters region to be filled out of phytal zone fill operation, and being finally completed prevents entirely
The empty van filling operation that the siltation of sinkage dock pit 100 shoals (see Figure 12 to 15).By the filling of entire sinkage dock pit 100 and empty van group part goes out
Dew can stop or be greatly reduced silt to fall into sinkage dock pit 100(and especially fall into profundal zone in the idle period of sinkage dock pit 100
101), and then prevent the siltation of sinkage dock pit 100 from shoaling.And when needing using sinkage dock pit 100, the chamber for gradually taking out cabinet 1 is indoor
Counterweight so that cabinet 1 automatically float and cabinet 1 is moved away from sinkage dock pit 100, floating dock can be allowed to sink down into required depth, with into
Row shipbuilding, maintenance and service work;It need not carry out highly difficult dredging to sinkage dock pit 100 to operate, to save corresponding
The operation and management cost of sinkage dock pit 100 is greatly reduced in dredging cost and time, also can be reduced desilt and dredge bring pollution and
Environmental disruption.The cabinet 1 for being moved away from sinkage dock pit 100 can then be stored to specified position, with when sinkage dock pit 100 next time is idle, then
Secondary filling sinkage dock pit 100.Method proposed by the invention has convenient construction, low cost, environmental protection and energy saving and can be recycled
The features such as.
It is to be appreciated that the phytal zone 102 of 101 surrounding of profundal zone be respectively divided into how many a shallow water regions to be filled out can basis
Depending on actual conditions (such as by the inclination conditions of 102 bottom wall of phytal zone), it can such as be respectively divided into one, two, three, four
A, five even more shallow waters regions to be filled out, are as shown in figs. 11 and 15 the situation for being respectively divided into four, shallow water area to be filled out
The width in domain may be the same or different, and as shown be different situations.
The present invention also proposes a kind of empty van filling structure for preventing sinkage dock pit siltation from shoaling, including for filling profundal zone
The shallow water of 101 deep water case group 10 and each shallow water region to be filled out positioned at 101 surrounding of profundal zone and for filling phytal zone 102
Case group 20, the deep water case group 10 and shallow water case group 20 include at least one layer of (including one layer and multilayer) empty van group, every layer of sky
Case group is formed by connecting by 1 assembly of cabinet of respective numbers, and 1 inner hollow of cabinet forms chamber, and the tank wall of cabinet 1 opens up
The through-hole (not shown) of connecting chamber, is at least partly placed with counterweight in the chamber of cabinet 1, so that deep water case group 10 and shallow water case
Group 20 sinks down into inconsistent with the bottom wall in each shallow water of profundal zone 101 and phytal zone 102 region to be filled out respectively.
In embodiments of the present invention, as shown in Fig. 1 to 15, the density of 1 material of cabinet is close with water phase, preferably slightly smaller than water
Density (such as density is 0.5g/cm3~0.9g/cm3), water can be floated on after guaranteeing 1 water-filling of cabinet (not place to chamber counterweight)
Face, cabinet 1 can be used plastics or other lightweights and have the material (such as wood) of sufficient intensity to be made.
In embodiments of the present invention, the shape of cabinet 1 is preferred with hexahedron, and top surface is horizontal, side vertical or with heavy depressed place
The side wall in hole is mutually fitted, and bottom surface is mutually fitted with the top surface of cabinet 1 or the bottom wall of sinkage dock pit being in contact, for example, with 101 bottom of profundal zone
The bottom surface of the inconsistent cabinet 1 of wall be plane, with shallow water region to be filled out the bottom surface of inconsistent cabinet 1 be inclined-plane or cambered surface,
The bottom surface of remaining cabinet 1 is plane.Certainly, the shape of cabinet 1 may be that other are easy the other shapes that accumulation is laid with.
Implement in embodiment in the present invention, in the empty van group of same layer, two horizontally adjacent cabinets 1 pass through 11 He of plug tenon
The cooperation of slot 12 can carry out assembled connection, in order to prevent empty van group (such as the first layer empty van group and second layer empty van of upper and lower level
Group) misplace movement, and neighbouring cabinet 1 can also be spliced by the cooperation of slot 12 and plug tenon 11.Certainly, horizontally adjacent
Cabinet 1 and neighbouring cabinet 1 between can also pass through buckle structure and complete assembled and connection.
Can choose ground, the through-hole can be provided on any tank wall of cabinet 1, for example, it can be provided with top case wall, side case
On wall or under casing wall, for the ease of placing counterweight to chamber, preferably it is provided on side box wall or top case wall.
In embodiments of the present invention, counterweight can be metal (such as iron) or sandstone isodensity be water 2 times or more weight
Object.The also mountable removable cover for opening and closing through-hole of cabinet 1 of counterweight is placed in chamber, which can be hinged
Either clamping is perhaps connected to cabinet 1 when needing to chamber water-filling or placing counterweight by being threadedly engaged, and cover board is beaten
It opens, after the completion, cover board is closed, can prevent sundries from entering chamber.
It should be noted that when sinkage dock pit part waters is occupied, the unappropriated waters in sinkage dock pit profundal zone, or
The empty van placement method that unappropriated phytal zone and its part waters can also prevent sinkage dock pit siltation from shoaling using the present invention
And empty van filling structure is filled, and equally can also prevent sinkage dock pit siltation from shoaling.Specifically, this prevents sinkage dock pit siltation from becoming
Shallow empty van placement method, includes the following steps:
A, the top for being located at each idle region in profundal zone or phytal zone of sinkage dock pit in the water surface is laid with first layer by predetermined quantity
The empty van group that is formed by connecting of cabinet assembly, the hollow formation chamber of box house, the tank wall of cabinet, which opens up, leads to chamber
Through-hole can bubble through the water column after chamber water-filling, and the vertical projection area of first layer empty van group and profundal zone or phytal zone are each idle
The area in region is mutually fitted;
B, the empty van group that the second layer is formed by connecting by the cabinet assembly of predetermined quantity is laid in first layer empty van group, first layer is empty
Case group is under the gravity of second layer empty van group, and can sink predetermined depth;
C, the total height by the empty van group of each idle overlying regions of step B repetitive operation to profundal zone or phytal zone and profundal zone
Or the depth in the idle region in phytal zone is mutually fitted or empty van group total height is slightly larger than each idle region in profundal zone or phytal zone
Depth, forms deep water case group or shallow water case group, and via through holes place counterweight so that deep water case group or shallow water case group to the chamber of cabinet
It is sink to and is contradicted with each idle region bottom wall in profundal zone or phytal zone, complete the deep water case group in the idle region in profundal zone or phytal zone
Or the filling operation of shallow water case group, it is finally completed the empty van stower for preventing the idle region siltation in profundal zone or phytal zone from shoaling
Make.It can refer to above-described embodiment as the connecting method between the structure, material and cabinet of cabinet.
The above description is only a preferred embodiment of the present invention, is not intended to limit the scope of the invention, all at this
Under the inventive concept of invention, using equivalent structure transformation made by description of the invention and accompanying drawing content, or directly/use indirectly
It is included in other related technical areas in scope of patent protection of the invention.
Claims (11)
1. the empty van placement method for preventing sinkage dock pit siltation from shoaling, which comprises the steps of:
S1, region above the profundal zone that the water surface is located at sinkage dock pit be laid with first layer by the cabinet assembly connection of predetermined quantity and
At empty van group, the hollow formation chamber of box house, the tank wall of cabinet opens up the through-hole for leading to chamber, can after chamber water-filling
It bubbles through the water column, the vertical projection area of first layer empty van group is mutually fitted with the bottom wall area of profundal zone;
S2, the empty van group that the second layer is formed by connecting by the cabinet assembly of predetermined quantity, first layer are laid in first layer empty van group
Empty van group is under the gravity of second layer empty van group, and can sink predetermined depth;
S3, it is mutually fitted by the total height of the empty van group above step S2 repetitive operation to profundal zone and the sinkage dock pit depth of profundal zone,
Or empty van group total height be slightly larger than sinkage dock pit depth, formed deep water case group, via through holes to the chamber of cabinet place counterweight with
It sinks down into deep water case group to contradict with profundal zone bottom wall, completes the filling operation of the deep water case group of profundal zone;
S4, it the phytal zone of profundal zone surrounding is divided at least one shallow water on the length and width direction of sinkage dock pit waits filling out
Region is operated in the top in the shallow water region to be filled out that the water surface is located most closely to profundal zone referring to the mode of step S1 to S3, is completed
The shallow water case group in shallow water region to be filled out fills operation;
S5, on the length and width direction of sinkage dock pit, using profundal zone as reference, by being operated by step S4 closely to remote sequence,
The shallow water case group for completing all shallow waters in phytal zone region to be filled out fills operation, and being finally completed prevents the siltation of entire sinkage dock pit from shoaling
Empty van filling operation.
2. the empty van placement method for preventing sinkage dock pit siltation from shoaling as described in claim 1, it is characterised in that: tank material
The density of water body where density is slightly less than sinkage dock pit.
3. the empty van placement method for preventing sinkage dock pit siltation from shoaling as claimed in claim 2, it is characterised in that: cabinet is using modeling
Material or it is wooden at.
4. the empty van placement method for preventing sinkage dock pit siltation from shoaling as described in claim 1, it is characterised in that: in step S1
In, the region above the profundal zone that the water surface is located at sinkage dock pit is laid with what first layer was formed by connecting by the cabinet assembly of predetermined quantity
In the operation of empty van group, horizontally adjacent cabinet is carried out to the process of assembled connection including the cooperation by plug tenon and slot.
5. the empty van placement method for preventing sinkage dock pit siltation from shoaling as described in claim 1, is laid in first layer empty van group
In the step S2 for the empty van group that the second layer is formed by connecting by the cabinet assembly of predetermined quantity, further include by neighbouring cabinet into
The process of the assembled connection of row.
6. the empty van placement method for preventing sinkage dock pit siltation from shoaling as claimed in claim 5, it is characterised in that: will be neighbouring
Cabinet splicing is completed by the cooperation of plug tenon and slot.
7. the empty van placement method for preventing sinkage dock pit siltation from shoaling as described in claim 1, it is characterised in that: counterweight is metal
Or sandstone.
8. the empty van placement method for preventing sinkage dock pit siltation from shoaling as described in claim 1, it is characterised in that: the shape of cabinet
For hexahedron, top surface is horizontal, side vertical perhaps mutually fitted with the side wall of sinkage dock pit bottom surface and the top surface of cabinet being in contact or
The bottom wall of sinkage dock pit is mutually fitted.
9. the empty van placement method for preventing sinkage dock pit siltation from shoaling as claimed in any of claims 1 to 8 in one of claims, feature exist
In: in step S4, the phytal zone of profundal zone surrounding is divided into multiple shallow waters on the length and width direction of sinkage dock pit and is waited for
Fill out region, each shallow water region to be filled out it is of same size or different.
10. the empty van filling structure for preventing sinkage dock pit siltation from shoaling, it is characterised in that: including the deep water case for filling profundal zone
Group and positioned at profundal zone surrounding and for fill phytal zone each shallow water region to be filled out shallow water case group, the deep water case group and
Shallow water case group includes at least one layer of empty van group, and every layer of empty van group is formed by connecting by the cabinet assembly of respective numbers, the case
Body inner hollow forms chamber, and the tank wall of cabinet opens up the through-hole for leading to chamber, is at least partly placed with and matches in the chamber of cabinet
Weight, so that deep water case group and shallow water case group can sink down into the bottom wall with each shallow water of profundal zone and phytal zone region to be filled out respectively
It is inconsistent.
11. the empty van placement method for preventing sinkage dock pit siltation from shoaling, which comprises the steps of:
A, the top for being located at each idle region in profundal zone or phytal zone of sinkage dock pit in the water surface is laid with first layer by predetermined quantity
The empty van group that is formed by connecting of cabinet assembly, the hollow formation chamber of box house, the tank wall of cabinet, which opens up, leads to chamber
Through-hole can bubble through the water column after chamber water-filling, and the vertical projection area of first layer empty van group and profundal zone or phytal zone are each idle
The area in region is mutually fitted;
B, the empty van group that the second layer is formed by connecting by the cabinet assembly of predetermined quantity is laid in first layer empty van group, first layer is empty
Case group is under the gravity of second layer empty van group, and can sink predetermined depth;
C, the total height by the empty van group of each idle overlying regions of step B repetitive operation to profundal zone or phytal zone and profundal zone
Or the leave unused depth in region of phytal zone is mutually fitted or empty van group total height is left unused the depth in region slightly larger than profundal zone or phytal zone
Degree, forms deep water case group or shallow water case group, and via through holes place counterweight so that under deep water case group or shallow water case group to the chamber of cabinet
It is sink to and is contradicted with each idle region bottom wall in profundal zone or phytal zone, complete the deep water in profundal zone or each idle region in phytal zone
The filling of case group or shallow water case group operates, and is finally completed the empty van filling for preventing the idle region siltation in profundal zone or phytal zone from shoaling
Work.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910010932.7A CN109736332B (en) | 2019-01-07 | 2019-01-07 | The empty van placement method and empty van filling structure for preventing sinkage dock pit siltation from shoaling |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910010932.7A CN109736332B (en) | 2019-01-07 | 2019-01-07 | The empty van placement method and empty van filling structure for preventing sinkage dock pit siltation from shoaling |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109736332A true CN109736332A (en) | 2019-05-10 |
CN109736332B CN109736332B (en) | 2019-11-05 |
Family
ID=66363463
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910010932.7A Active CN109736332B (en) | 2019-01-07 | 2019-01-07 | The empty van placement method and empty van filling structure for preventing sinkage dock pit siltation from shoaling |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109736332B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113486288A (en) * | 2021-06-30 | 2021-10-08 | 中国科学院生态环境研究中心 | Method for determining ecological dredging depth of sediment |
CN113550339A (en) * | 2021-07-20 | 2021-10-26 | 上海建工一建集团有限公司 | Deep foundation pit water leakage rescue cofferdam and construction method thereof |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20020008314A (en) * | 2000-07-21 | 2002-01-30 | 이원영 | Method for construction of hydraulic concrete structure |
CN104878779A (en) * | 2015-05-28 | 2015-09-02 | 中交一航局第二工程有限公司 | Covering-type silt prevention cover plate, silt prevention system and construction method of immersed tunnel gravel foundation bed |
-
2019
- 2019-01-07 CN CN201910010932.7A patent/CN109736332B/en active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20020008314A (en) * | 2000-07-21 | 2002-01-30 | 이원영 | Method for construction of hydraulic concrete structure |
CN104878779A (en) * | 2015-05-28 | 2015-09-02 | 中交一航局第二工程有限公司 | Covering-type silt prevention cover plate, silt prevention system and construction method of immersed tunnel gravel foundation bed |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113486288A (en) * | 2021-06-30 | 2021-10-08 | 中国科学院生态环境研究中心 | Method for determining ecological dredging depth of sediment |
CN113486288B (en) * | 2021-06-30 | 2024-02-02 | 中国科学院生态环境研究中心 | Method for determining ecological dredging depth of sediment |
CN113550339A (en) * | 2021-07-20 | 2021-10-26 | 上海建工一建集团有限公司 | Deep foundation pit water leakage rescue cofferdam and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN109736332B (en) | 2019-11-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109736332B (en) | The empty van placement method and empty van filling structure for preventing sinkage dock pit siltation from shoaling | |
US3464212A (en) | Method of building concrete structures in water bottoms | |
JP3576974B2 (en) | Wave-dissipating blocks for coastal structures | |
KR102039782B1 (en) | FD Type Direct Bottoming Caisson for Tidal Current Power Generator | |
CN209568458U (en) | The empty van filling structure for preventing sinkage dock pit siltation from shoaling | |
KR102389280B1 (en) | Method of constructing concrete block structure | |
CN114182764A (en) | Foundation anti-scouring device and construction method | |
KR20090121864A (en) | Shore protection revetments of hydrophilic with capacity of wave dissipating | |
CN211849251U (en) | Floating box type breakwater structure | |
KR101256043B1 (en) | Caisson with tank collecting rainwater | |
CN209760272U (en) | Prevent long-pending device of silt | |
CN114223595A (en) | Movable bottom-sitting type ocean platform net cage structure and construction method thereof | |
CN109723033B (en) | Fish reef prefabricated member dam and manufacturing method thereof | |
JP4776694B2 (en) | Harbor structure and method for constructing such a structure | |
CN217580242U (en) | Bridge steel-concrete combined cofferdam structure | |
CN109736258A (en) | The method of sediment prevention siltation | |
CN109537522A (en) | The application method of utricule structure, anti-siltation device and anti-siltation device | |
CN110195420B (en) | Lane guardrail structure for tidal area | |
KR20140140911A (en) | Water-reserving structure for using underground water | |
JPH08311850A (en) | Removing device for sea floating matter | |
US4662780A (en) | Method for docking of a floating structure | |
JP5656143B2 (en) | Construction method of sea area control structure | |
CN109653230B (en) | Anti-fouling device and anti-fouling method | |
JP2655322B2 (en) | Construction method of revetment structure | |
CN209243880U (en) | A kind of submerged drain structure for water in coastal thermal power plant |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |