JP2655322B2 - Construction method of revetment structure - Google Patents

Construction method of revetment structure

Info

Publication number
JP2655322B2
JP2655322B2 JP6559396A JP6559396A JP2655322B2 JP 2655322 B2 JP2655322 B2 JP 2655322B2 JP 6559396 A JP6559396 A JP 6559396A JP 6559396 A JP6559396 A JP 6559396A JP 2655322 B2 JP2655322 B2 JP 2655322B2
Authority
JP
Japan
Prior art keywords
joint hole
water
floating
pile
chamber
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP6559396A
Other languages
Japanese (ja)
Other versions
JPH08311841A (en
Inventor
忠典 大友
賢一 本橋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP6559396A priority Critical patent/JP2655322B2/en
Publication of JPH08311841A publication Critical patent/JPH08311841A/en
Application granted granted Critical
Publication of JP2655322B2 publication Critical patent/JP2655322B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Revetment (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、水理構造物として
人工島等の護岸構造物の施工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a revetment structure such as an artificial island as a hydraulic structure.

【0002】[0002]

【従来の技術】人工島などは、護岸によって埋立て領域
を囲い、その内側を土砂で埋立てて造成する。このよう
な護岸建設の方法としては、従来、コンクリートブロッ
クやケーソンを用いる方法と鋼矢板、鋼板セルなどの締
切をつくる方法とに大別される。
2. Description of the Related Art Artificial islands and the like are constructed by enclosing a landfill area with a seawall and burying the inside with earth and sand. Conventionally, such revetment construction methods are broadly classified into a method using a concrete block or caisson and a method of creating a deadline such as a steel sheet pile or a steel sheet cell.

【0003】特に、海底地盤が軟弱土層である場合に
は、前記コンクリートブロックやケーソンを用いる方法
では、設置基礎を形成するのに深層混合、砂置換、砂
杭、捨石マウンドなどの一つないしは複数の方法で、軟
弱地盤を改良している。
[0003] In particular, when the seabed ground is a soft soil layer, in the method using the concrete block or caisson, one or more of deep mixing, sand replacement, sand piles, and rubble mounds are used to form an installation foundation. Has improved soft ground in several ways.

【0004】[0004]

【発明が解決しようとする課題】前記従来の護岸建設工
法のうち、基礎形成に軟弱地盤の改良を伴うものでは、
別途工事としてこれを行わなければならないことも多
く、多大の工期と費用を要する。
Among the above-mentioned conventional revetment construction methods, those in which improvement of soft ground is required for foundation formation,
This often has to be done as a separate construction, which requires a lot of construction time and cost.

【0005】また、鋼矢板等の金属部材を使用する締切
り工法では、スプラッシュゾーンなど腐食環境の厳しい
部位で、鋼材の腐食が激しく、コンクリートを被覆する
などの防蝕工を施しても長期的には充分でない。
[0005] In the shut-off method using a metal member such as a steel sheet pile, the corrosion of the steel material is severe in a severely corrosive environment such as a splash zone. Not enough.

【0006】さらに、地盤改良工事を不要とする水中埋
設構造物の施工法として、特開昭63-40024号公報が挙げ
られる。これは、周側壁を二重壁で形成したケーソンを
曳航して設置し、該二重壁をガイドとして杭を支持地盤
まで打設した後、二重壁にコンクリートを打設して杭と
ケーソンとを剛結するものである。
Further, Japanese Patent Application Laid-Open No. 63-40024 discloses a method of constructing an underwater buried structure that does not require ground improvement work. This is done by towing a caisson whose peripheral side wall is formed by a double wall, setting the pile to the supporting ground using the double wall as a guide, and then driving concrete to the double wall to form a pile and caisson. It is a rigid connection between

【0007】しかし、特開昭63-40024号では、ケーソン
の杭を打ち込む位置に予め開口部を形成しておき、曳航
の際にはケーソン内に海水が入らないように前記開口部
を鉄板等の薄板で閉塞しており、しかも浮力を高めるた
めにケーソンの外側壁にフロートを取付けているので、
使用する部材点数が多くなって取扱いが複雑であった。
一方、ケーソンを海底に接地する際にはこのフロートを
取り外して浮力を弱めなければならず、接地後には杭を
打設する前に前記薄板を撤去しなければならないので、
それだけ工程が多くなり工期も遅れてしまっていた。
However, in Japanese Patent Application Laid-Open No. 63-40024, an opening is formed in advance at a position where a caisson pile is driven, and the opening is formed with an iron plate or the like so that seawater does not enter the caisson during towing. Because it is closed with a thin plate and a float is attached to the outer wall of the caisson to increase buoyancy,
The number of members used increased and handling was complicated.
On the other hand, when grounding the caisson on the seabed, this float must be removed to reduce buoyancy, and after grounding, the thin plate must be removed before driving the pile,
The number of processes increased and the construction period was delayed.

【0008】本発明は前記従来例の不都合を解消し、簡
単かつ安価で施工ですむとともに工期の短縮も図ること
ができ、しかも完成した護岸構造物は海水による腐食に
対して耐久性の高いものが得られる護岸構造物の施工法
を提供することにある。
The present invention eliminates the disadvantages of the prior art described above, is simple and inexpensive, requires less work and can shorten the construction period, and the completed revetment structure has high durability against corrosion by seawater. An object of the present invention is to provide a method for constructing the obtained revetment structure.

【0009】[0009]

【課題を解決するための手段】本発明は前記目的を達成
するため、多数の浮室を有し、かつ側部に位置する前記
浮室以外の室の底板に接合孔を形成したコンクリート構
造物を、前記接合孔を有する室に海面と同じ水嵩となる
ように海水を浸水させ、かつ前記浮室に適宜量の水を収
容して浮上姿勢のバランスをとった状態で水中に浮か
べ、かつ所定の設置場所まで曳航し、この所定場所で浮
室内への注水を加減して前記コンクリート構造物を海底
に沈め、次に接合孔に杭打ちし、最後に接合孔と杭間の
隙間に水中不分離性混和剤を混入した水中不分離性コン
クリートを打設して固定することを要旨とするものであ
る。
SUMMARY OF THE INVENTION In order to achieve the above object, the present invention provides a concrete structure having a large number of floating chambers and a joint hole formed in a bottom plate of a chamber other than the floating chamber located on the side. Seawater into the chamber having the joint hole so as to have the same water volume as the sea surface, and float in water in a state where the floating posture is balanced by storing an appropriate amount of water in the floating chamber, and The concrete structure is submerged in the sea floor by adjusting the water injection into the floating room at this predetermined location, and then piled into the joint hole. The gist of the invention is to cast and fix underwater non-separable concrete mixed with a separable admixture.

【0010】本発明によれば、地上で予め製作したコン
クリート構造物を用いることで工程の簡略化や工期の短
縮を図ることができる。また、コンクリート構造物の曳
航は、接合孔を有する室に海面と同じ水嵩となるように
海水を浸水させ、かつその他の浮室に適宜量の水を収容
しているので、浮上姿勢のバランスをうまくとった状態
で行うことができる。さらに、このコンクリート構造物
を所定位置に沈めた後に杭を打設するので、杭の打設位
置の合わせが比較的容易となる。
According to the present invention, the use of a concrete structure manufactured in advance on the ground makes it possible to simplify the process and shorten the construction period. In addition, when towing a concrete structure, seawater is flooded in the room with the joint hole so that it has the same water volume as the sea surface, and an appropriate amount of water is stored in other floating rooms. It can be done in a good condition. Furthermore, since the pile is driven after the concrete structure is submerged at a predetermined position, it is relatively easy to adjust the driving position of the pile.

【0011】また、杭を打設する接合孔を有する室内に
は海水が浸水しているが、この室内の海水を取り除くこ
となく、接合孔と杭間の隙間には水中不分離性混和剤を
混入した水中不分離性コンクリートを打設するので、簡
単かつ迅速に工程を進めることができる。さらに、得ら
れる護岸構造物としてはスプラッシュゾーンはコンクリ
ート構造物であり、海水による腐蝕に充分耐えうるもの
となる。
[0011] Seawater is flooded in a room having a joint hole for placing a pile, but without removing the seawater in the room, a water-immiscible admixture is filled in a gap between the joint hole and the pile. Since the mixed underwater non-separable concrete is cast, the process can be performed easily and quickly. Further, as the obtained revetment structure, the splash zone is a concrete structure, which can sufficiently withstand corrosion by seawater.

【0012】[0012]

【発明の実施の形態】以下、図面に基づいて本発明の実
施の形態を詳細に説明する。図1〜図3は本発明の護岸
構造物の施工法の第1実施形態を示す各工程の縦断側面
図である。
Embodiments of the present invention will be described below in detail with reference to the drawings. 1 to 3 are longitudinal side views of respective steps showing a first embodiment of a method for constructing a seawall structure of the present invention.

【0013】先ず、地上では図4〜図6に示すような多
数の浮室4を有し、かつ側部に位置する前記浮室4以外
の室の底板6に接合孔5を形成した護岸構造物となるコ
ンクリート構造物としてのケーソンを製作する。なお、
前記接合孔5は、後述する杭1の径より大きいもので、
図7,図8に示すように周囲に補強鉄筋7を配設する。
First, a seawall structure having a large number of floating chambers 4 on the ground as shown in FIGS. 4 to 6, and having a joint hole 5 formed in a bottom plate 6 of a chamber other than the floating chamber 4 located on the side. Make caisson as a concrete structure. In addition,
The joining hole 5 is larger than the diameter of the pile 1 described below,
As shown in FIGS. 7 and 8, a reinforcing reinforcing bar 7 is provided around the periphery.

【0014】このケーソンは、前記接合孔5を有する室
に海面と同じ水嵩となるように海水を浸水させ、かつ前
記浮室4に適宜量の水を収容して浮上姿勢のバランスを
とった状態で水中に浮かべ、かつ船3で所定の設置場所
まで曳航する。
In this caisson, seawater is immersed in the chamber having the joint hole 5 so as to have the same water volume as the sea surface, and an appropriate amount of water is stored in the floating chamber 4 to balance the floating posture. Floats underwater and tow the ship 3 to a predetermined location.

【0015】所定場所では浮室4内への注水を加減して
前記ケーソンを海底に沈める。なお、浮室4内への注水
の加減は、底板6に過大な過重が作用せず、かつその後
の潮位の変化や後述の水中打設コンクリートの影響でケ
ーソンが動かないようなバランスのよい状態にするのに
必要である。
At a predetermined place, the caisson is submerged on the sea floor by adjusting the amount of water injected into the floating chamber 4. It should be noted that the injection of water into the floating chamber 4 is performed in a well-balanced state in which no excessive load acts on the bottom plate 6 and the caisson does not move due to the subsequent change in tide level or the influence of the submerged concrete described below. It is necessary to

【0016】次いで、前記接合孔4に杭1を作業船2等
を用いて打設する。打設時にはこの杭1は水面上に上端
が突出するが、その後、杭頭部1aを海底に突出するよ
うな所定高さで切断する。
Next, the pile 1 is cast into the joint hole 4 using the work boat 2 or the like. At the time of casting, the pile 1 projects above the water surface, but thereafter, the pile head 1a is cut at a predetermined height so as to project to the sea floor.

【0017】この杭頭部1aは、図9に示すように、適
宜深さを掘下げ、前記接合孔5の周囲の底板6上に型枠
を設置し、掘下げた杭頭部1a内部、杭1と接合孔5と
の隙間および型枠内に、コンクリートに粘稠性を与え、
水中での材料の分離を防ぐ水中不分離性混和剤(あるい
は分離低減剤)を混入した水中不分離性コンクリートで
ある水中打設コンクリート9を打設して、杭1と接合孔
5をしっかりと固定する。このようにしてから、ケーソ
ンで囲われた内側を埋立てて、埋立て地10を造成する。
As shown in FIG. 9, the pile head 1a is dug down to an appropriate depth, a formwork is installed on the bottom plate 6 around the joint hole 5, and the inside of the pile head 1a, the pile 1 The concrete is made viscous in the gap between the and the joining hole 5 and in the formwork,
Underwater cast concrete 9, which is a water-inseparable concrete mixed with a water-inseparable admixture (or a separation-reducing agent) that prevents the separation of materials in water, is cast, and the pile 1 and the joint hole 5 are firmly connected. Fix it. After this, the inside surrounded by the caisson is buried to form the landfill 10.

【0018】図14は本発明の第2実施例を示すもので、
コンクリート構造物としてケーソンの代わりにL型ブロ
ックを用いた場合である。該L型ブロックの詳細は図10
〜図13に示すが、浮室4を有しかつ底板6に接合孔5を
形成した点は前記ケーソンと同様であり、工程も同様で
ある。
FIG. 14 shows a second embodiment of the present invention.
This is a case where an L-shaped block is used as a concrete structure instead of a caisson. The details of the L-shaped block are shown in FIG.
13 to FIG. 13, the point that the floating chamber 4 is provided and the joining hole 5 is formed in the bottom plate 6 is the same as that of the caisson, and the process is also the same.

【0019】[0019]

【発明の効果】以上述べたように本発明の護岸構造物の
施工法は、海底地盤が軟弱であっても従来工法でケーソ
ン等のコンクリート構造物を支えるための地盤改良工事
を不要とし、しかも水中工事を極力少なくして大幅な工
期の短縮、工費の削減を期することができる。また、コ
ンクリート構造物の浮上姿勢のバランスをうまくとった
状態で曳航することができる。さらに、このコンクリー
ト構造物を所定位置に沈めた後に杭を打設するので、杭
の打設位置の合わせが比較的容易となる。
As described above, the construction method of the revetment structure of the present invention eliminates the need for ground improvement work for supporting a concrete structure such as a caisson by the conventional method, even if the seabed ground is soft, and Underwater work can be reduced as much as possible to greatly shorten the construction period and reduce construction costs. Further, the towing can be performed in a state where the floating posture of the concrete structure is well balanced. Furthermore, since the pile is driven after the concrete structure is submerged at a predetermined position, it is relatively easy to adjust the driving position of the pile.

【0020】また、杭を打設する接合孔を有する室内に
は海水が浸水しているが、この室内の海水を取り除くこ
となく、接合孔と杭間の隙間には水中不分離性混和剤を
混入した水中不分離性コンクリートを打設するので、簡
単かつ迅速に工程を進めることができる。さらに、得ら
れる護岸構造物としてはスプラッシュゾーンはコンクリ
ート構造物であり、海水による腐蝕に充分耐えうるもの
である。
Seawater is flooded in a room having a joint hole for placing a pile, but without removing the seawater in the room, a gap between the joint hole and the pile is filled with a water-immiscible admixture. Since the mixed underwater non-separable concrete is cast, the process can be performed easily and quickly. Further, as the obtained revetment structure, the splash zone is a concrete structure, which can sufficiently withstand corrosion by seawater.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の護岸構造物の施工法の第1実施形態を
示す第1工程の縦断側面図である。
FIG. 1 is a vertical sectional side view of a first step showing a first embodiment of a method for constructing a seawall structure of the present invention.

【図2】本発明の護岸構造物の施工法の第1実施形態を
示す第2工程の縦断側面図である。
FIG. 2 is a vertical sectional side view of a second step showing the first embodiment of the method for installing a seawall structure of the present invention.

【図3】本発明の護岸構造物の施工法の第1実施形態を
示す第3工程の縦断側面図である。
FIG. 3 is a vertical sectional side view of a third step showing the first embodiment of the method for constructing a seawall structure of the present invention.

【図4】本発明の護岸構造物の施工法の第1実施形態で
使用するケーソンの平面図である。
FIG. 4 is a plan view of a caisson used in the first embodiment of the method of constructing a seawall structure of the present invention.

【図5】図4のA−A線断面図である。FIG. 5 is a sectional view taken along line AA of FIG. 4;

【図6】図4のB−B線断面図である。FIG. 6 is a sectional view taken along line BB of FIG. 4;

【図7】本発明の護岸構造物の施工法で使用するケーソ
ンの接合孔部分の縦断側面図である。
FIG. 7 is a vertical sectional side view of a joint hole of a caisson used in the method of constructing a seawall structure of the present invention.

【図8】本発明の護岸構造物の施工法で使用するケーソ
ンの接合孔部分の横断平面図である。
FIG. 8 is a cross-sectional plan view of a joint hole of a caisson used in the method of constructing a seawall structure of the present invention.

【図9】本発明の護岸構造物の施工法の杭とコンクリー
ト構造物の接合状態を示す縦断側面図である。
FIG. 9 is a longitudinal sectional side view showing a joint state between a pile and a concrete structure in the method for constructing a seawall structure of the present invention.

【図10】本発明の護岸構造物の施工法の第2実施形態
で使用するケーソンの平面図である。
FIG. 10 is a plan view of a caisson used in a second embodiment of the method for constructing a seawall structure of the present invention.

【図11】図10のA−A線断面図である。FIG. 11 is a sectional view taken along line AA of FIG. 10;

【図12】図10のB−B線断面図である。FIG. 12 is a sectional view taken along line BB of FIG. 10;

【図13】図10のC−C線断面図である。FIG. 13 is a sectional view taken along line CC of FIG. 10;

【図14】本発明の護岸構造物の施工法の第2実施形態
を示す縦断側面図である。
FIG. 14 is a vertical sectional side view showing a second embodiment of the method for constructing a seawall structure of the present invention.

【符号の説明】[Explanation of symbols]

1…杭 1a…杭頭部 2…作業船 3…船 4…浮室 5…接合孔 6…底板 7…補強鉄筋 9…水中打設コンクリート 10…埋立て地 DESCRIPTION OF SYMBOLS 1 ... Pile 1a ... Pile head 2 ... Work boat 3 ... Ship 4 ... Floating room 5 ... Joint hole 6 ... Bottom plate 7 ... Reinforcing steel 9 ... Underwater concrete 10 ... Landfill

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 多数の浮室を有し、かつ側部に位置する
前記浮室以外の室の底板に接合孔を形成したコンクリー
ト構造物を、前記接合孔を有する室に海面と同じ水嵩と
なるように海水を浸水させ、かつ前記浮室に適宜量の水
を収容して浮上姿勢のバランスをとった状態で水中に浮
かべ、かつ所定の設置場所まで曳航し、この所定場所で
浮室内への注水を加減して前記コンクリート構造物を海
底に沈め、次に接合孔に杭打ちし、最後に接合孔と杭間
の隙間に水中不分離性混和剤を混入した水中不分離性コ
ンクリートを打設して固定することを特徴とする護岸構
造物の施工法。
1. A concrete structure having a large number of floating chambers and having a joint hole formed in a bottom plate of a chamber other than the floating chamber located on the side, and having the same water volume as the sea surface in the chamber having the joint hole. So that the seawater is flooded, and the floating chamber contains an appropriate amount of water, floats in the water in a state where the floating posture is balanced, and is towed to a predetermined installation location, and into the floating chamber at the predetermined location The concrete structure is submerged into the sea floor by adjusting the water injection, and then piled into the joint hole, and finally, the underwater non-separable concrete mixed with the water-immiscible admixture is poured into the gap between the joint hole and the pile. Construction method of revetment structure characterized by installing and fixing.
JP6559396A 1996-03-22 1996-03-22 Construction method of revetment structure Expired - Fee Related JP2655322B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6559396A JP2655322B2 (en) 1996-03-22 1996-03-22 Construction method of revetment structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6559396A JP2655322B2 (en) 1996-03-22 1996-03-22 Construction method of revetment structure

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP1205021A Division JP2556380B2 (en) 1989-08-07 1989-08-07 Construction method of revetment structure

Publications (2)

Publication Number Publication Date
JPH08311841A JPH08311841A (en) 1996-11-26
JP2655322B2 true JP2655322B2 (en) 1997-09-17

Family

ID=13291477

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6559396A Expired - Fee Related JP2655322B2 (en) 1996-03-22 1996-03-22 Construction method of revetment structure

Country Status (1)

Country Link
JP (1) JP2655322B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013177276A (en) * 2012-02-28 2013-09-09 Ohbayashi Corp In-water inseparable concrete

Also Published As

Publication number Publication date
JPH08311841A (en) 1996-11-26

Similar Documents

Publication Publication Date Title
JP2655322B2 (en) Construction method of revetment structure
JPS58143023A (en) Caisson for pile supporting type breakwater
JP2000290936A (en) Method and caisson for constructing bridge pier footing
JP4018288B2 (en) Artificial ground made of box that can pass water and its construction method
JP3463604B2 (en) Dolphin construction method
JP2815492B2 (en) How to build an underwater foundation
JP2556380B2 (en) Construction method of revetment structure
JP3378982B2 (en) Basic structure of underwater tunnel
JP2002047665A (en) Installation method for jacket structure
JPH0323689B2 (en)
JPS6226371B2 (en)
JPH0588326B2 (en)
JPS58160420A (en) Levee body using king post
JPS6220326B2 (en)
JP2745097B2 (en) Construction method of low temperature liquefied gas underground tank
JPS622081B2 (en)
JPS631411B2 (en)
JPH06257163A (en) Droughty pontoon for constructing shallow foundation
JPS58150629A (en) Construction of caisson levee
KR20040105541A (en) A box for construction on the sea and method for construction working construction on the sea
JPH02252807A (en) Execution process of transmission type breakwater for deep depth
JPH05280058A (en) Caisson structure
JPH08113935A (en) Artificial island
JPH0448128B2 (en)
JPH07216915A (en) Construction method of underground type storage tank and bottom mounting float

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees