CN109707128A - A kind of hollow light partition wall compact-panel dry hanging construction method - Google Patents

A kind of hollow light partition wall compact-panel dry hanging construction method Download PDF

Info

Publication number
CN109707128A
CN109707128A CN201811453007.3A CN201811453007A CN109707128A CN 109707128 A CN109707128 A CN 109707128A CN 201811453007 A CN201811453007 A CN 201811453007A CN 109707128 A CN109707128 A CN 109707128A
Authority
CN
China
Prior art keywords
embedded part
partition wall
line
construction method
hollow light
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811453007.3A
Other languages
Chinese (zh)
Other versions
CN109707128B (en
Inventor
李钻水
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Yongzhuxin Science And Technology Development Co Ltd
Original Assignee
Fujian Yongzhuxin Science And Technology Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Yongzhuxin Science And Technology Development Co Ltd filed Critical Fujian Yongzhuxin Science And Technology Development Co Ltd
Priority to CN201811453007.3A priority Critical patent/CN109707128B/en
Publication of CN109707128A publication Critical patent/CN109707128A/en
Application granted granted Critical
Publication of CN109707128B publication Critical patent/CN109707128B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a kind of hollow light partition wall compact-panel dry hanging construction methods, including step 1, clear up metope;Step 2, snap the line positioning;Step 3 installs keel;Step 4, mounting suspension member;Step 5, mounting plate material;Step 6, subsequent arrangement, remove the dust of wall basal plane, greasy dirt and laitance, and it dries, vertical line is beaten at four big angles of building and door-window opening side theodolite, then according to door and window, floor levels baseline hands over circle to look for control point, according to design piecemeal drawing, on ground, the piecemeal line of the bottom plate position line and wall board is popped up on metope respectively, this method, pass through main joist and secondary joist, the expanding cement filled in the connection of second embedded part and pendant and mounting groove can greatly enhance degree of firmly installing, and convenient for operation, save material, improve construction efficiency, reduce the duration, and substantially increase the intensity that compact-panel is impacted, energy conservation and environmental protection, stress is avoided to concentrate.

Description

A kind of hollow light partition wall compact-panel dry hanging construction method
Technical field
The present invention relates to partition wall technical field of construction, specially a kind of hollow light partition wall compact-panel dry hanging construction side Method.
Background technique
It is cladding to refer to that ornament materials is securely suspended on to one kind that facing is formed on structural body using metal hanger to be mounted and apply The abbreviation of work method, compact-panel is to be impregnated with melamine resin by decoration coloured paper, in addition multilayer black or the impregnation of brown brown paper Novolac resin layer poststack, then suppressed with steel plate via the environment of high temperature (150 DEG C) high pressure (1430psi), thickness is from 1.6mm It can all be made to 25mm.It is a kind of high-pressure decorating plate of core structure, and the coloured paper layer on surface can not only meet a variety of pattern choosings It selects, the decoration demand of " bright face, pearl flannelette, Microstar face, water chestnut check, check design, snow meteor " can also be provided, it is existing to resist again Special plate dried hanging hang structure degree of firmly installing is not high enough, and installation place, once damaging, monolithic stability degree will be affected, while inconvenient In operation, stability is not good enough.
Summary of the invention
The purpose of the present invention is to provide a kind of hollow light partition wall compact-panel dry hanging construction methods, to solve above-mentioned back The problem of being proposed in scape technology.
In order to solve the above technical problem, the present invention provides following technical solutions: a kind of hollow light partition wall compact-panel Dry hanging construction method, including step 1 clear up metope;Step 2, snap the line positioning;Step 3 installs keel;Step 4, installation Pendant;Step 5, mounting plate material;Step 6, subsequent arrangement;
In said step 1, the dust, greasy dirt and laitance of wall basal plane are removed, and is dried;
In the step 2, snap the line positioning the following steps are included:
Vertical line is beaten at four big angles of building and door-window opening side theodolite, is then handed over according to door and window, floor levels baseline Circle looks for control point;
2) according to design piecemeal drawing, the bottom plate position line and wall board snap the line: are popped up respectively on ground, metope Piecemeal line;
3) the vertically and horizontally keel position line is popped up according to the piecemeal line of plate and plate installation site on wall;
In the step 3, installation keel the following steps are included:
1) using the way of post-install, the first embedded part and the second embedded part embedded part: are installed;
2) it welds: main joist is welded on the first embedded part, press piecemeal line position welding secondary joist after qualification on inspection;
3) remove the gred: level height and weld seam beat welding slag completely after meeting design requirement on inspection;
4) anti-corrosion: first uniformly applying in commissure and brush one times zinc rich primer, it is dry after brushing antirust paint again, avoid leakage from brushing;
In the step 4, mounting suspension member the following steps are included:
1) through hole connects one end of pendant and the installation of the second embedded part;
2) full expanding cement will be filled in mounting groove, to its drying;
3) nut is mounted on the pendant other end, and contacts and tightens with wall;
In the step 5, mounting plate material the following steps are included:
1) side of plate is bolted and mounting blocks is installed;
2) mounting blocks are fixedly connected with one end of pendant;
3) check whether that installation is vertical;
It is using rag and detergent that plate surface is clean after being installed in the step 6, it is dried in filleting Only, intersection should seal.
According to the above technical scheme, the first embedded part and the second embedded part use thick galvanized steel plain sheet embedded part in the step 3, and It is installed and is fixed by expansion bolt, second embedded part is located between two secondary joists, and symmetrical.
According to the above technical scheme, main joist is vertically-mounted in the step 3, and secondary joist is horizontally mounted, and answers before welding It is punched in advance according to board dimension, pendant position, the shape in hole is ellipse.
According to the above technical scheme, antirust paint is at least brushed 2 times in the step 3.
According to the above technical scheme, pendant is connected through a screw thread with the second embedded part in the step 4.
According to the above technical scheme, mounting groove end face need to be smooth in the step 4, polishes smooth after dry.
According to the above technical scheme, full cloud stone glue is smeared in the junction of plate and mounting blocks in the step 5.
According to the above technical scheme, it is looked for vertically in the step 5 by plaster ground, horizontal ruler is levelling whole, and square chi looks for yin-yang Angle is upright, and vernier caliper checks plate stitch, is modified after discovery plate installation is undesirable.
According to the above technical scheme, use black weather-resistant glue by intersection gap sealing in the step 5.
Compared with prior art, the beneficial effects obtained by the present invention are as follows being: hollow light partition wall compact-panel is cladding applies for this Work method, can be with by the expanding cement filled in main joist and secondary joist, the connection of the second embedded part and pendant and mounting groove Degree of firmly installing is greatly enhanced, and convenient for operation, saves material, improves construction efficiency, reduce the duration, and substantially increase anti-times The intensity that special plate is impacted, energy conservation and environmental protection avoid stress from concentrating.
Detailed description of the invention
Attached drawing is used to provide further understanding of the present invention, and constitutes part of specification, with reality of the invention It applies example to be used to explain the present invention together, not be construed as limiting the invention.In the accompanying drawings:
Fig. 1 is overall structure diagram of the invention;
Fig. 2 is overall flow schematic diagram of the invention;
In figure: 1, plate;2, main joist;3, mounting blocks;4, hole;5, pendant;6, wall;7, the first embedded part;8, the second embedded part;9, Mounting groove;10, expanding cement;11, secondary joist.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
The present invention provides a kind of technical solution referring to FIG. 1-2: a kind of hollow light partition wall compact-panel dry hanging construction side Method, including step 1 clear up metope;Step 2, snap the line positioning;Step 3 installs keel;Step 4, mounting suspension member 5;Step Five, mounting plate material 1;Step 6, subsequent arrangement;
In step 1, dust, greasy dirt and the laitance of 6 basal plane of wall are removed, and is dried;
In step 2, snap the line positioning the following steps are included:
Vertical line is beaten at four big angles of building and door-window opening side theodolite, is then handed over according to door and window, floor levels baseline Circle looks for control point;
2) according to design piecemeal drawing, 1 position line of bottom plate and wall board 1 snap the line: are popped up respectively on ground, metope Piecemeal line;
3) the vertically and horizontally keel position line is popped up according to the piecemeal line of plate 1 and 1 installation site of plate on wall 6;
In step 3, installation keel the following steps are included:
1) using the way of post-install, the first embedded part 7 and the second embedded part 8 embedded part: are installed;
2) it welds: main joist 2 is welded on the first embedded part 7, press piecemeal line position welding secondary joist 11 after qualification on inspection;
3) remove the gred: level height and weld seam beat welding slag completely after meeting design requirement on inspection;
4) anti-corrosion: first uniformly applying in commissure and brush one times zinc rich primer, it is dry after brushing antirust paint again, avoid leakage from brushing;
In step 4, mounting suspension member 5 the following steps are included:
1) through hole 4 connects one end of pendant 5 and the installation of the second embedded part 8;
2) full expanding cement 10 will be filled in mounting groove 9, to its drying;
3) nut is mounted on 5 other end of pendant, and contacts and tightens with wall 6;
In step 5, mounting plate material 1 the following steps are included:
1) side of plate 1 is bolted and mounting blocks 3 is installed;
2) mounting blocks 3 are fixedly connected with one end of pendant 5;
3) check whether that installation is vertical;
It is using rag and detergent that 1 surface cleaning of plate is clean after being installed in step 6, it is wiped clean in filleting, Intersection should seal.
According to the above technical scheme, the first embedded part 7 and the second embedded part 8 use thick galvanized steel plain sheet embedded part in step 3, and lead to It crosses expansion bolt installation to fix, the second embedded part 8 is located between two secondary joists 11, and symmetrical.
According to the above technical scheme, main joist 2 is vertically-mounted in step 3, and secondary joist 11 is horizontally mounted, and answers before welding Punching 4 is carried out in advance according to 1 size of plate, 5 position of pendant, and the shape in hole 4 is ellipse, in order to the left and right adjustment of pendant 5.
According to the above technical scheme, antirust paint is at least brushed 2 times in step 3.
According to the above technical scheme, pendant 5 is connected through a screw thread with the second embedded part 8 in step 4, ensure that the steady of connection It is qualitative.
According to the above technical scheme, 9 end face of mounting groove need to be smooth in step 4, polishes smooth after dry.
According to the above technical scheme, full cloud stone glue is smeared in the junction of plate 1 and mounting blocks 3 in step 5.
According to the above technical scheme, it is looked for vertically in step 5 by plaster ground, horizontal ruler is levelling whole, and square chi looks for yin-yang angle side Just, vernier caliper check plate stitch, discovery plate 1 install it is undesirable after be modified.
According to the above technical scheme, use black weather-resistant glue by intersection gap sealing in step 5.
Based on above-mentioned, it is an advantage of the current invention that it is of the invention, first the dust, greasy dirt and laitance of 6 basal plane of wall are removed, And dry, vertical line then is beaten at four big angles of building and door-window opening side theodolite, further according to door and window, floor levels base Line hands over circle to look for control point, according still further to design piecemeal drawing, pops up 1 position line of bottom plate and wall respectively on ground, metope The piecemeal line of panel material 1 pops up the vertically and horizontally keel position line according to 1 installation site of plate, is fixed by expansion bolt installation After the first embedded part 7 and the second embedded part 8 of thick galvanized steel plain sheet material, main joist 2 is welded on the first embedded part 7 vertically, on inspection Piecemeal line position level welding secondary joist 11 is pressed after qualification, level height and weld seam strike welding slag after meeting design requirement on inspection It beats completely, and is first uniformly applied in commissure and brush one times zinc rich primer, brush at least 2 times antirust paints again after dry, avoid leaking and brush, lead to Via hole 4 connects one end of pendant 5 and the installation of the second embedded part 8, full expanding cement 10 will be filled in mounting groove 9, after its drying, Nut is mounted on 5 other end of pendant, and contacts and tightens with wall 6, is fixedly connected, is leaned on one end of pendant 5 by mounting blocks 3 Ruler plate is looked for vertically, and horizontal ruler is levelling whole, and square chi looks for yin-yang angle upright, and vernier caliper checks plate stitch, and the discovery installation of plate 1 is not met It is modified after it is required that, it is using rag and detergent that 1 surface cleaning of plate is clean after being installed, it is wiped clean in filleting, Intersection should use black weather-resistant glue by gap sealing;Pass through the connection of main joist 2 and secondary joist 11, the second embedded part 8 and pendant 5 And the expanding cement 10 filled in mounting groove 9 can greatly enhance degree of firmly installing, and convenient for operation, save material, improve Construction efficiency reduces the duration, and substantially increases the intensity that compact-panel is impacted, and energy conservation and environmental protection avoids stress from concentrating.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment Intrinsic element.
Finally, it should be noted that the foregoing is only a preferred embodiment of the present invention, it is not intended to restrict the invention, Although the present invention is described in detail referring to the foregoing embodiments, for those skilled in the art, still may be used To modify the technical solutions described in the foregoing embodiments or equivalent replacement of some of the technical features. All within the spirits and principles of the present invention, any modification, equivalent replacement, improvement and so on should be included in of the invention Within protection scope.

Claims (9)

1. a kind of hollow light partition wall compact-panel dry hanging construction method, including step 1 clear up metope;Step 2, snap the line are fixed Position;Step 3 installs keel;Step 4, mounting suspension member;Step 5, mounting plate material;Step 6, subsequent arrangement;Its feature exists In:
In said step 1, the dust, greasy dirt and laitance of wall basal plane are removed, and is dried;
In the step 2, snap the line positioning the following steps are included:
Vertical line is beaten at four big angles of building and door-window opening side theodolite, is then handed over according to door and window, floor levels baseline Circle looks for control point;
2) according to design piecemeal drawing, the bottom plate position line and wall board snap the line: are popped up respectively on ground, metope Piecemeal line;
3) the vertically and horizontally keel position line is popped up according to the piecemeal line of plate and plate installation site on wall;
In the step 3, installation keel the following steps are included:
1) using the way of post-install, the first embedded part and the second embedded part embedded part: are installed;
2) it welds: main joist is welded on the first embedded part, press piecemeal line position welding secondary joist after qualification on inspection;
3) remove the gred: level height and weld seam beat welding slag completely after meeting design requirement on inspection;
4) anti-corrosion: first uniformly applying in commissure and brush one times zinc rich primer, it is dry after brushing antirust paint again, avoid leakage from brushing;
In the step 4, mounting suspension member the following steps are included:
1) through hole connects one end of pendant and the installation of the second embedded part;
2) full expanding cement will be filled in mounting groove, to its drying;
3) nut is mounted on the pendant other end, and contacts and tightens with wall;
In the step 5, mounting plate material the following steps are included:
1) side of plate is bolted and mounting blocks is installed;
2) mounting blocks are fixedly connected with one end of pendant;
3) check whether that installation is vertical;
It is using rag and detergent that plate surface is clean after being installed in the step 6, it is dried in filleting Only, intersection should seal.
2. a kind of hollow light partition wall compact-panel dry hanging construction method according to claim 1, it is characterised in that: described The first embedded part and the second embedded part are using thick galvanized steel plain sheet embedded part in step 3, and are installed and fixed by expansion bolt, and described second Embedded part is located between two secondary joists, and symmetrical.
3. a kind of hollow light partition wall compact-panel dry hanging construction method according to claim 1, it is characterised in that: described Main joist is vertically-mounted in step 3, and secondary joist is horizontally mounted, and should be carried out in advance according to board dimension, pendant position before welding Punching, the shape in hole are ellipse.
4. a kind of hollow light partition wall compact-panel dry hanging construction method according to claim 1, it is characterised in that: described Antirust paint is at least brushed 2 times in step 3.
5. a kind of hollow light partition wall compact-panel dry hanging construction method according to claim 1, it is characterised in that: described Pendant is connected through a screw thread with the second embedded part in step 4.
6. a kind of hollow light partition wall compact-panel dry hanging construction method according to claim 1, it is characterised in that: described Mounting groove end face needs smooth in step 4, polishes smooth after dry.
7. a kind of hollow light partition wall compact-panel dry hanging construction method according to claim 1, it is characterised in that: described Full cloud stone glue is smeared in the junction of plate and mounting blocks in step 5.
8. a kind of hollow light partition wall compact-panel dry hanging construction method according to claim 1, it is characterised in that: described It is looked for vertically in step 5 by plaster ground, horizontal ruler is levelling whole, and square chi looks for yin-yang angle upright, and vernier caliper checks plate stitch, discovery It is modified after plate installation is undesirable.
9. a kind of hollow light partition wall compact-panel dry hanging construction method according to claim 1, it is characterised in that: described Use black weather-resistant glue by intersection gap sealing in step 5.
CN201811453007.3A 2018-11-30 2018-11-30 Dry hanging construction method for hollow light partition wall anti-doubling plate Active CN109707128B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811453007.3A CN109707128B (en) 2018-11-30 2018-11-30 Dry hanging construction method for hollow light partition wall anti-doubling plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811453007.3A CN109707128B (en) 2018-11-30 2018-11-30 Dry hanging construction method for hollow light partition wall anti-doubling plate

Publications (2)

Publication Number Publication Date
CN109707128A true CN109707128A (en) 2019-05-03
CN109707128B CN109707128B (en) 2020-12-22

Family

ID=66255411

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811453007.3A Active CN109707128B (en) 2018-11-30 2018-11-30 Dry hanging construction method for hollow light partition wall anti-doubling plate

Country Status (1)

Country Link
CN (1) CN109707128B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111075051A (en) * 2019-12-19 2020-04-28 青岛海尔洗衣机有限公司 Wall mounting method for household electrical appliance and wall-mounted household electrical appliance
CN112210963A (en) * 2019-07-10 2021-01-12 青岛海尔洗衣机有限公司 Wall-mounted washing equipment and mounting method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102003056A (en) * 2010-11-15 2011-04-06 易科美德(天津)环保建材有限公司 Wall connecting part of insertion type integrated insulation board and application method thereof
CN103806577A (en) * 2012-11-06 2014-05-21 南通四建装饰工程有限公司 Installation method for super-large-area unit type slabstone curtain wall
CN104652740A (en) * 2015-01-13 2015-05-27 杭锦旗亿利朗新材料科技有限公司 Installation method for thermal insulation and decoration integrated facade panels
CN105756221A (en) * 2016-04-07 2016-07-13 文登蓝岛建筑工程有限公司 Anchoring part applied to hollow wall
CN106013691A (en) * 2016-05-25 2016-10-12 青岛海川建设集团有限公司 GRC partition dry-hanging glassy brick structure and construction method thereof
RU171923U1 (en) * 2017-03-31 2017-06-21 Владимир Александрович Борисов Thermopanel front high-strength
CN107143104A (en) * 2017-06-06 2017-09-08 浙江舜江建设集团有限公司 A kind of construction technology of steel structure heat-insulating decorative integrated plate exterior wall

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102003056A (en) * 2010-11-15 2011-04-06 易科美德(天津)环保建材有限公司 Wall connecting part of insertion type integrated insulation board and application method thereof
CN103806577A (en) * 2012-11-06 2014-05-21 南通四建装饰工程有限公司 Installation method for super-large-area unit type slabstone curtain wall
CN104652740A (en) * 2015-01-13 2015-05-27 杭锦旗亿利朗新材料科技有限公司 Installation method for thermal insulation and decoration integrated facade panels
CN105756221A (en) * 2016-04-07 2016-07-13 文登蓝岛建筑工程有限公司 Anchoring part applied to hollow wall
CN106013691A (en) * 2016-05-25 2016-10-12 青岛海川建设集团有限公司 GRC partition dry-hanging glassy brick structure and construction method thereof
RU171923U1 (en) * 2017-03-31 2017-06-21 Владимир Александрович Борисов Thermopanel front high-strength
CN107143104A (en) * 2017-06-06 2017-09-08 浙江舜江建设集团有限公司 A kind of construction technology of steel structure heat-insulating decorative integrated plate exterior wall

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
钟生平等: "外墙抗倍特板施工技术", 《施工技术》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112210963A (en) * 2019-07-10 2021-01-12 青岛海尔洗衣机有限公司 Wall-mounted washing equipment and mounting method thereof
CN111075051A (en) * 2019-12-19 2020-04-28 青岛海尔洗衣机有限公司 Wall mounting method for household electrical appliance and wall-mounted household electrical appliance

Also Published As

Publication number Publication date
CN109707128B (en) 2020-12-22

Similar Documents

Publication Publication Date Title
CN102051923B (en) Fireproofing retardant cement calcium silicate board insulating wall body and construction method thereof
EP3070227B1 (en) Foam glass integrated plate effective in water and fire proofing, thermal insulation and decoration
CN109707128A (en) A kind of hollow light partition wall compact-panel dry hanging construction method
CN211691012U (en) Indoor suspended ceiling and side wall edge-closing connecting node structure
CN108952053A (en) Shingle nail installation assembly and its installation method
CN201433537Y (en) Expansion compensation device
CN103628602B (en) Building curtain wall glass fiber reinforced composite plate installation component
CN202731191U (en) Polystyrene board building special decoration component
CN111594783B (en) Mounting structure and mounting method of top surface hidden type light-transmitting lamp box
CN213868637U (en) Glass guardrail node structure
CN210507918U (en) Light steel villa EPS lath structure
CN211286169U (en) Short cantilever type dry-hanging ceramic plate curtain wall bottom edge folding node
CN208088673U (en) Roofing slate installing mechanism
CN206495452U (en) A kind of environment-friendly type wall brick structure
CN213572493U (en) Aerated concrete block wall with anti-cracking structure
CN219753657U (en) Suspended ceiling connecting component of steel structure house
CN204590381U (en) A kind of detachable environment-friendly type grid ceiling
CN207988307U (en) Facing is in the plaster tablet suspended ceiling structure of metal effect
CN204510689U (en) A kind of novel environment friendly assembling link plate system
CN214144335U (en) Indoor floor tip lamp area node structure
CN205577131U (en) Movement joint structure device is decorated to building outer wall
CN215442871U (en) Inorganic stone-like external wall panel
CN220620517U (en) External wall insulation structure
CN219604743U (en) Aluminum veneer connecting structure for indoor wall surface
CN218148936U (en) Wall body built-in fitting waterproof construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant