CN103628602B - Building curtain wall glass fiber reinforced composite plate installation component - Google Patents
Building curtain wall glass fiber reinforced composite plate installation component Download PDFInfo
- Publication number
- CN103628602B CN103628602B CN201310520609.7A CN201310520609A CN103628602B CN 103628602 B CN103628602 B CN 103628602B CN 201310520609 A CN201310520609 A CN 201310520609A CN 103628602 B CN103628602 B CN 103628602B
- Authority
- CN
- China
- Prior art keywords
- glass fiber
- fiber reinforced
- reinforced composite
- composite plate
- curtain wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Load-Bearing And Curtain Walls (AREA)
Abstract
The invention discloses a kind of building curtain wall glass fiber reinforced composite plate installation component and building curtain wall glass fiber reinforced composite method of plate installation, aim to provide and a kind ofly construct building curtain wall glass fiber reinforced composite plate installation component and glass fiber reinforced composite method of plate installation convenient, long service life, applied range, construction costs are low.Installation component comprises bolt group, angle steel and glass fiber reinforced composite plate, also comprises adaptor, steel pad and fixed fitting.Glass fiber reinforced composite method of plate installation comprises unwrapping wire, measures, determines that mounting points position, leveling, boring, pre-embedded steel slab, placement pad and spring pad, composite plate are installed, seam repairing, antirust treatment, base treatment, cleaning ending etc.The present invention is simple to operate, and the click-on design of steel pad and adaptor can make composite plate carry out secondary to move, and reduces the artificial loss of plate timing.Construct convenient, on-the-spot good processability, can carry out sawing according to field condition, dig, follow closely, cut a hole, bore, sticking operation.
Description
Technical field
The present invention relates to the realm of building construction, particularly building curtain wall glass fiber reinforced composite plate installation component and mounting method.
Background technology
Building curtain wall glass fiber reinforced composite plate is a kind of New Building Materials by being formed after glass fiber cement and glass fiber reinforced gypsum optimum combination.It has the fire prevention of glass fiber reinforced cement and glass fiber, waterproof concurrently, mothproof, dry wet expansion factor is little, intensity is high, stable performance, long service life and environmental protection, not containing the advantage such as radioactive element and toxic gas, and modeling ability is strong, splendid external wall decorative material, the ideal substitute of glass fiber cement especially.
The installation of traditional glass fiber cement product decoration material, installation component generally adopts pre-buried diameter to be no more than the round steel of 6mm, building carries out point-to-point being welded to connect after preset expansion bolt, corrosion protection is carried out again by brushing rustproof paint, its position of installing is only limitted to the floor of less than five layers, for high-rise or high-rise building, be definitely non-serviceable.Simultaneously, in building curtain wall work progress, the decoration panel of curtain wall generally adopts overhead welding construction technology, welding distance not easy-regulating, length metering process is loaded down with trivial details, irremovable when sheet material is installed, large-scale hoisting machinery is needed to coordinate or build, construction and installation process requires strictly to constructor, and single plate very easily occurs that plate interval error is excessive after installing, and causes subsequent construction difficulty; According to dry hanging construction technique, also there is decoration panel in work progress and install location difficulty, after single installation, decoration panel is between the upper and lower apart from not easily adjusting, and very easily causes decoration panel gap interval error excessive, affects subsequent construction.Above two kinds of conventional construction schemes all exist and manually expend serious, and waste material production rate is high, and process efficiency is low, to defects such as weather degree of dependence are high.
Summary of the invention
In order to overcome above-mentioned defect, the technical problem to be solved in the present invention is: provide a kind of construct convenient, flexible, long service life, applied range, construction costs are low, to the low building curtain wall glass fiber reinforced composite plate installation component of weather degree of dependence and glass fiber reinforced composite method of plate installation.
The present invention is that to solve the problems of the technologies described above the technical scheme of employing as follows:
A kind of building curtain wall glass fiber reinforced composite plate installation component, comprises bolt group, angle steel and glass fiber reinforced composite plate, also comprises adaptor, steel pad and fixed fitting;
Described fixed fitting is arranged on glass fiber reinforced composite intralamellar part; Described adaptor is fixed on up and down by bolt group on the angle steel in preformed hole, and fixed fitting is stuck in adaptor, and galvanized steel pad is positioned at the bottom of adaptor, fixed fitting, and adaptor and fixed fitting are welded and fixed.
A mounting method for building curtain wall glass fiber reinforced composite plate, it is realized by following steps:
(1) unwrapping wire: first discharge water horizontal line, then messenger wire;
(2) measure: according to the field condition after unwrapping wire, the civil engineering structure of practice of construction is measured;
(3) mounting points position is determined: found out by unwrapping wire and measurement and indicate mounting points position;
(4) leveling;
(5) the position boring of mounting points is being indicated;
(6) be close to horizontal basic unit pre-embedded steel slab, place pad and spring pad;
(7) installation of glass fiber reinforced composite plate: with the bolt that rises through hole reserved on pre-embedded steel slab, be fixed on structural wall.Front balcony place lines and roof eaves line are fixed on structure wall with the bolt that rises up and down.Adaptor is fixed on up and down by bolt group on the angle steel in preformed hole, is stuck in by fixed fitting in adaptor, by the bottom galvanized steel pad adjustment composite plate planeness being positioned at adaptor, fixed fitting, adaptor and fixed fitting is welded and fixed.Wherein the mounting means of the interface of glass fiber reinforced composite plate and glass window is: glass fiber reinforced composite plate and glass window insert outside window frame at inner corner trim 90 degree of places;
(8) seam is repaired: after glass fiber reinforced composite plate installs, carry out filleting to the gap between block and block;
(9) butt welded seam and solder joint place carry out antirust treatment;
(10) base treatment: trimming, brushing rustproof paint;
(11) cleaning ending.
The invention has the beneficial effects as follows:
1, simple to operate, the click-on design of steel pad and adaptor can make composite plate carry out secondary to move, avoid double measurement, reduces operation, reduces the artificial loss of plate timing.
If 2, composite plate occurs comparatively big error after installing, directly can substitute adaptor, reduce percent defective, reduce spillage of material, reduce costs.
3, construct convenient, flexible, on-the-spot good processability, can carry out sawing according to concrete field condition, dig, follow closely, cut a hole, bore, the operation such as stickup, and installation process is simple, rapidly.
4, the seamless close spelling of large area can be carried out, form complete moulding, overcome conventional fiber glass cement products ornament materials and must reserve shrinkage joint and joint shortcoming easy to crack.
Accompanying drawing explanation
Below in conjunction with Figure of description, the utility model is described in further detail:
Fig. 1 is building curtain wall glass fiber reinforced composite plate installation component structural representation;
Fig. 2 is building curtain wall glass fiber reinforced composite plate inner side plane figure.
Detailed description of the invention
As depicted in figs. 1 and 2, a kind of building curtain wall glass fiber reinforced composite plate installation component, comprises bolt group 1, angle steel 2 and glass fiber reinforced composite plate 3, also comprises adaptor 4, steel pad 5 and fixed fitting 6.
It is inner that described fixed fitting 6 is arranged on glass fiber reinforced composite plate 3; Described adaptor 4 is fixed on by bolt group about 1 on the angle steel 2 in preformed hole, and fixed fitting 6 is stuck in adaptor 4, and steel pad 5 is positioned at the bottom of adaptor 4, fixed fitting 6, and adaptor 4 and fixed fitting 6 are welded and fixed.
Described adaptor 4 is process according to measurement size in advance.
Described steel pad 5 is galvanized steel pad.
Described glass fiber reinforced composite plate 3 is according to weight branch adjustment installation component quantity and spacing, and steel pad 5 can adjust thickness and quantity according to actual conditions, and adaptor 4 can be designed to the structure of one up and down according to actual conditions.
The mounting method of glass fiber reinforced composite plate of the present invention, it is realized by following steps:
1, unwrapping wire: the unwrapping wire first carrying out horizontal direction with level gauge or horizontal tube, first discharge water horizontal line, and general iron wire unwrapping wire adopts blue screw to tighten up, and then messenger wire, notes during unwrapping wire, unsuitable unwrapping wire when wind-force is greater than level Four.
2, measure: according to the field condition after unwrapping wire, the civil engineering structure of practice of construction is measured.
3, determine mounting points position: found out by unwrapping wire and measurement and indicate mounting points position, and by messenger wire, it being checked, ensure that verticality is with highly consistent.
4, leveling;
5, indicating the position boring of mounting points with percussive drill, the degree of depth of boring is 9.5mm, and aperture is φ 12mm.
6, pre-buried galvanized steel plain sheet level is close to basic unit, squeezes into structure wall be fixed with expansion bolt, and place pad and spring pad, first-class galvanized bolt also screws;
7, the installation of glass fiber reinforced composite plate: with the bolt that rises through hole reserved on pre-embedded steel slab, be fixed on structural wall.Front balcony place lines and roof eaves line are fixed on structure wall with the bolt that rises up and down.Adaptor 4 is fixed on by bolt group about 1 on the angle steel 2 in preformed hole, is stuck in by fixed fitting 6 in adaptor 4, and with being positioned at adaptor 4, the galvanized steel pad 5 of fixed fitting 6 bottom adjusts composite plate planeness, adaptor 4 and fixed fitting 6 is welded and fixed.Wherein the mounting means of the interface of glass fiber reinforced composite plate and glass window is: glass fiber reinforced composite plate and glass window insert outside window frame at inner corner trim 90 degree of places;
8, seam is repaired: after glass fiber reinforced composite plate installs, and the gap between glass fiber reinforced composite plate and block adopts to be played glue and carry out filleting process;
9, butt welded seam and solder joint place carry out antirust treatment;
10, base treatment: the iron little nail hammer of the slag of all commissures is struck totally, afterwards with small brushes to the commissure brushing rustproof paint cleaned out, brush second time again after 10-12 to be dried hour.
11, cleaning ending.
Should be understood that, above-mentioned detailed description of the invention of the present invention only for exemplary illustration or explain principle of the present invention, and is not construed as limiting the invention.Therefore, any amendment made when without departing from the spirit and scope of the present invention, equivalent replacement, improvement etc., all should be included within protection scope of the present invention.In addition, claims of the present invention be intended to contain fall into claims scope and border or this scope and border equivalents in whole change and modification.
Claims (9)
1. a building curtain wall glass fiber reinforced composite plate installation component, comprise bolt group (1), angle steel (2) and glass fiber reinforced composite plate (3), it is characterized in that: also comprise adaptor (4), steel pad (5) and fixed fitting (6);
It is inner that described fixed fitting (6) is arranged on glass fiber reinforced composite plate (3);
Described adaptor (4) is fixed on the angle steel (2) in preformed hole up and down by bolt group (1);
Described fixed fitting (6) is stuck in adaptor (4), steel pad (5) is positioned at the bottom of adaptor (4), fixed fitting (6), and adaptor (4) and fixed fitting (6) are welded and fixed;
Described building curtain wall glass fiber reinforced composite method of plate installation, comprises the following steps:
(1) unwrapping wire: first discharge water horizontal line, then messenger wire;
(2) measure: according to the field condition after unwrapping wire, the civil engineering structure of practice of construction is measured;
(3) mounting points position is determined: found out by unwrapping wire and measurement and indicate mounting points position;
(4) leveling;
(5) the position boring of mounting points is being indicated;
(6) be close to horizontal basic unit pre-embedded steel slab, place pad and spring pad;
(7) installation of glass fiber reinforced composite plate: with the bolt that rises through hole reserved on pre-embedded steel slab, be fixed on structural wall; Front balcony place lines and roof eaves line are fixed on structure wall with the bolt that rises up and down; Adaptor (4) is fixed on the angle steel (2) in preformed hole up and down by bolt group (1), fixed fitting (6) is stuck in adaptor (4), by galvanized steel pad (5) the adjustment composite plate planeness being positioned at adaptor (4), fixed fitting (6) bottom, adaptor (4) and fixed fitting (6) are welded and fixed; Wherein the mounting means of the interface of glass fiber reinforced composite plate and glass window is: glass fiber reinforced composite plate and glass window insert outside window frame at inner corner trim 90 degree of places;
(8) seam is repaired: after glass fiber reinforced composite plate installs, carry out filleting to the gap between block and block;
(9) butt welded seam and solder joint place carry out antirust treatment;
(10) base treatment: trimming, brushing rustproof paint;
(11) cleaning ending.
2. building curtain wall glass fiber reinforced composite plate installation component according to claim 1, is characterized in that: described adaptor (4) is process according to measurement size in advance.
3. building curtain wall glass fiber reinforced composite plate installation component according to claim 1, is characterized in that: described steel pad (5) is galvanized steel pad.
4. building curtain wall glass fiber reinforced composite plate installation component according to claim 1, is characterized in that: in described step (5), and the degree of depth of boring is 9.5mm, and aperture is φ 12mm.
5. building curtain wall glass fiber reinforced composite plate installation component according to claim 1, is characterized in that: described pre-embedded steel slab is galvanized steel plain sheet, squeezes into structure wall be fixed with expansion bolt.
6. building curtain wall glass fiber reinforced composite plate installation component according to claim 1, is characterized in that: the bolt that rises in described step (7) is that nylon rises bolt.
7. building curtain wall glass fiber reinforced composite plate installation component according to claim 1, is characterized in that: the connection of described glass fiber reinforced composite plate and glass window is that glue-line flexibly connects.
8. building curtain wall glass fiber reinforced composite plate installation component according to claim 1, is characterized in that: in described step (8), the mode of filleting process is for play glue process.
9. building curtain wall glass fiber reinforced composite plate installation component according to claim 1, it is characterized in that: the base cleaning in described step (10) strikes totally by the iron little nail hammer of the slag of all commissures, afterwards with small brushes to the commissure brushing rustproof paint cleaned out, brush second time again after 10-12 to be dried hour.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310520609.7A CN103628602B (en) | 2013-10-29 | 2013-10-29 | Building curtain wall glass fiber reinforced composite plate installation component |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310520609.7A CN103628602B (en) | 2013-10-29 | 2013-10-29 | Building curtain wall glass fiber reinforced composite plate installation component |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103628602A CN103628602A (en) | 2014-03-12 |
CN103628602B true CN103628602B (en) | 2016-04-06 |
Family
ID=50210025
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310520609.7A Active CN103628602B (en) | 2013-10-29 | 2013-10-29 | Building curtain wall glass fiber reinforced composite plate installation component |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103628602B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103953197B (en) * | 2014-05-13 | 2016-08-24 | 深圳市宝鹰建设集团股份有限公司 | Glass curtain wall construction method |
CN104358374A (en) * | 2014-11-04 | 2015-02-18 | 中建三局东方装饰设计工程有限公司 | Wall-face dry-hanging system of large metal aluminum sheet |
CN108942085B (en) * | 2017-05-17 | 2020-09-04 | 中科智远信息科技有限公司 | Radar fixing frame hole forming process |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0625618A2 (en) * | 1993-05-18 | 1994-11-23 | STO VEROTEC GmbH | Lining Panel |
CN2828180Y (en) * | 2005-07-13 | 2006-10-18 | 赵华 | Support structure for glass of full glass curtain |
CN201339263Y (en) * | 2008-12-02 | 2009-11-04 | 吴国良 | Installation structure of pottery clay plate curtain wall |
CN201635313U (en) * | 2010-01-20 | 2010-11-17 | 马义和 | Back-bolt type dry-hanging device of glass fibre enhanced cement board |
CN102535796A (en) * | 2011-12-23 | 2012-07-04 | 苏州金螳螂建筑装饰股份有限公司 | Glass block cladding mounting structure |
CN202347795U (en) * | 2011-11-04 | 2012-07-25 | 中建三局东方装饰设计工程有限公司 | Back-bolt connection structure of wall surface and arc composite stones |
CN202644791U (en) * | 2012-05-18 | 2013-01-02 | 上海国际航运服务中心开发有限公司 | Mounting structure of argil curtain wall for super highrise building |
-
2013
- 2013-10-29 CN CN201310520609.7A patent/CN103628602B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0625618A2 (en) * | 1993-05-18 | 1994-11-23 | STO VEROTEC GmbH | Lining Panel |
CN2828180Y (en) * | 2005-07-13 | 2006-10-18 | 赵华 | Support structure for glass of full glass curtain |
CN201339263Y (en) * | 2008-12-02 | 2009-11-04 | 吴国良 | Installation structure of pottery clay plate curtain wall |
CN201635313U (en) * | 2010-01-20 | 2010-11-17 | 马义和 | Back-bolt type dry-hanging device of glass fibre enhanced cement board |
CN202347795U (en) * | 2011-11-04 | 2012-07-25 | 中建三局东方装饰设计工程有限公司 | Back-bolt connection structure of wall surface and arc composite stones |
CN102535796A (en) * | 2011-12-23 | 2012-07-04 | 苏州金螳螂建筑装饰股份有限公司 | Glass block cladding mounting structure |
CN202644791U (en) * | 2012-05-18 | 2013-01-02 | 上海国际航运服务中心开发有限公司 | Mounting structure of argil curtain wall for super highrise building |
Also Published As
Publication number | Publication date |
---|---|
CN103628602A (en) | 2014-03-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104018598B (en) | A kind of external wall structure and construction installation method | |
CN104533046B (en) | Dry-hanging and wet-adhering combined mounting method of cement-based artificial flat stone | |
CN107338967A (en) | A kind of new technology and new material of aging blocks outdoor tile facing renewal and reform | |
CN103628602B (en) | Building curtain wall glass fiber reinforced composite plate installation component | |
CN102505762A (en) | Sand aerated concrete heat-insulation block outer wall outer heat-insulation system and construction method thereof | |
CN104746772A (en) | Ash concrete hollow partition board anti-cracking construction method | |
CN102003077A (en) | Stone curtain wall construction method | |
CN106013691A (en) | GRC partition dry-hanging glassy brick structure and construction method thereof | |
CN110985986A (en) | Light extraction system of light guide well and construction method thereof | |
CN103993689A (en) | Curtain wall glass installation method and glass bracket used for same | |
CN113006353A (en) | Construction method of prefabricated hanging plate curtain wall | |
CN108071238B (en) | Environment-friendly exterior wall tile reinforcing process | |
CN103774817B (en) | Obform body decorative stone metope method of attaching | |
CN104818822A (en) | Indoor large-layout wall brick wire bonding construction process | |
CN111364767B (en) | Construction method of short-slot dry-hanging argil plate | |
CN206512866U (en) | Concealed installation Fire Hose backing apparatus | |
CN202809898U (en) | Mortise joint type light partition wall | |
CN110259144A (en) | A kind of novel energy-saving environment-friendly ash concrete lightweight wall plate construction method | |
CN106939699B (en) | Construction method for galvanized steel sheet waterproof layer on inner side of open type ceramic plate curtain wall | |
CN202899526U (en) | Wall body decoration structure for old house renovation | |
CN102839803A (en) | Construction method for installing decorating and modeling concrete slab | |
CN207228439U (en) | A kind of viscous anchor combination ceramic thin plate decoration wall | |
CN205976290U (en) | Compound incubation intergral template anchor is held in palm and is hung structure | |
CN109707128A (en) | A kind of hollow light partition wall compact-panel dry hanging construction method | |
CN211011184U (en) | Light extraction system of light guide well |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: 100097 Golden Resources Hotel, Haidian District, Beijing, Beijing, Haidian District, Beijing, Beijing Patentee after: Built in East Decoration Co. Ltd. Address before: 100097 Golden Resources Hotel, Haidian District, Beijing, Beijing, Haidian District, Beijing, Beijing Patentee before: Dongfang Decoration Design Engineering Co., Ltd. of China Construction Third Engineering Bureau |