CN109653520A - Prefabrication and assembly construction concrete structure outer bottom tongue and groove protective device and its installation method - Google Patents

Prefabrication and assembly construction concrete structure outer bottom tongue and groove protective device and its installation method Download PDF

Info

Publication number
CN109653520A
CN109653520A CN201910011674.4A CN201910011674A CN109653520A CN 109653520 A CN109653520 A CN 109653520A CN 201910011674 A CN201910011674 A CN 201910011674A CN 109653520 A CN109653520 A CN 109653520A
Authority
CN
China
Prior art keywords
channel steel
protective device
precast facade
prefabrication
tongue
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910011674.4A
Other languages
Chinese (zh)
Inventor
张豪
黄鑫洪
马昆
黄亚璐
单洋洋
张松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LONGXIN CONSTRUCTION GROUP CO Ltd
Original Assignee
LONGXIN CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LONGXIN CONSTRUCTION GROUP CO Ltd filed Critical LONGXIN CONSTRUCTION GROUP CO Ltd
Priority to CN201910011674.4A priority Critical patent/CN109653520A/en
Publication of CN109653520A publication Critical patent/CN109653520A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/26Strutting means for wall parts; Supports or the like, e.g. for holding in position prefabricated walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Finishing Walls (AREA)

Abstract

The present invention provides a kind of prefabrication and assembly construction concrete structure outer bottom tongue and groove protective device and its installation methods, including channel steel, bolt and flitch, precast facade bottom is provided with hole to be provided, the channel steel is mounted in the hole to be provided of precast facade bottom by bolt, and flitch is packed between channel steel and precast facade.Simple structure of the present invention, easy to operate, the construction suitable for prefabricated construction lifting operation personnel.

Description

Prefabrication and assembly construction concrete structure outer bottom tongue and groove protective device and its installation method
Technical field
The present invention relates to prefabricated assembled concrete technical field of structures, outside specifically a kind of prefabrication and assembly construction concrete structure Wall bottom tongue and groove protective device and its installation method.
Background technique
When encountering precast facade height more than transport routes limit for height, component can not can only be adopted using A font by putting the perpendicular fortune of frame With flat fortune scheme, there is the case where turning in component, tongue and groove protection in precast facade bottom is that lifting component was constructed at the construction field (site) The problem of facing is had in journey.Common methods are that precast facade its bottom when turning over is laid with rubber pad or cystosepiment etc. Flexible material, and often there is the problem of tongue and groove destruction in this common methods, and the later period is caused to need to repair, and also can not be complete after repairing All risk insurance demonstrate,proves the piece quality between precast facade.
Summary of the invention
The present invention in order to solve problems in the prior art, provides a kind of prefabrication and assembly construction concrete structure outer bottom tongue and groove Protective device and its installation method, simple structure is easy to operate, suitable for applying for prefabricated construction lifting operation personnel Work.
The present invention includes channel steel, bolt and flitch, and precast facade bottom is provided with hole to be provided, and the channel steel is pacified by bolt In the hole to be provided of precast facade bottom, flitch is packed between channel steel and precast facade.
It is further improved, the reserved hole dia is 20mm, diameter of bolt 16mm.
It is further improved, the channel steel is 12# channel steel.
It is further improved, the flitch specification is 50 × 100mm.
Installation method of the present invention is as follows:
1) prefabricated components drawing is deepened, and 4 20 hole to be provided of φ are arranged in precast facade wall in advance;
2) component produces, according to Deepen Design drawing set aside pre-embedded;
3) before precast facade entrucking transport, 20 hole to be provided of wall φ is passed through using 16 bolt of φ, 12# channel steel is mounted on prefabricated Exterior wall bottom, and 50 × 100mm flitch is clogged between channel steel and precast facade;
4) component is transported to scene, turns in hoisting process, and channel steel is played a supporting role, and tongue and groove is made to be in vacant state always, protects It demonstrate,proves not damaged;
5) it is lifted to leave to precast facade and removes tongue and groove protective device at the 1m of ground under steady state.
The beneficial effects of the invention are that:
1, simple structure, easy to operate, the construction suitable for prefabricated construction lifting operation personnel.
2, departing from the method for traditional tongue and groove bottom place mat rubber pad or cystosepiment, tongue and groove spoilage is reduced.
3, installation and removal are simple, and demolishing process is effective to guarantee tongue and groove quality to precast facade bottom tongue and groove undisturbed.
Detailed description of the invention
Fig. 1 is schematic structural view of the invention.
Specific embodiment
The present invention will be further explained below with reference to the attached drawings.
A kind of specific structure of the present invention is as shown in Figure 1, include 12# channel steel 1,16 bolt 2 of φ, 50 × 100mm flitch 3.Institute The 12# channel steel stated is mounted in 20 hole to be provided of precast facade bottom φ by 16 bolt of φ, is filled out between 12# channel steel and precast facade It is plugged with 50 × 100mm flitch.
Installation method of the present invention is as follows:
1) prefabricated components drawing is deepened, and 4 20 hole to be provided of φ are arranged in precast facade wall in advance;
2) component produces, according to Deepen Design drawing set aside pre-embedded;
3) before precast facade entrucking transport, 20 hole to be provided of wall φ is passed through using 16 bolt of φ, 12# channel steel is mounted on prefabricated Exterior wall bottom, and 50 × 100mm flitch is clogged between channel steel and precast facade;
4) component is transported to scene, turns in hoisting process, and channel steel is played a supporting role, and tongue and groove is made to be in vacant state always, protects It demonstrate,proves not damaged;
5) it is lifted to leave to precast facade and removes tongue and groove protective device at the 1m of ground under steady state.
There are many concrete application approach of the present invention, the above is only a preferred embodiment of the present invention, it is noted that for For those skilled in the art, without departing from the principle of the present invention, it can also make several improvements, this A little improve also should be regarded as protection scope of the present invention.

Claims (5)

1. a kind of prefabrication and assembly construction concrete structure outer bottom tongue and groove protective device, it is characterised in that: including channel steel, bolt and wood Side, precast facade bottom is provided with hole to be provided, and the channel steel is mounted in the hole to be provided of precast facade bottom by bolt, channel steel and Flitch is packed between precast facade.
2. prefabrication and assembly construction concrete structure outer according to claim 1 bottom tongue and groove protective device, it is characterised in that: institute The reserved hole dia stated is 20mm, diameter of bolt 16mm.
3. prefabrication and assembly construction concrete structure outer according to claim 1 bottom tongue and groove protective device, it is characterised in that: institute The channel steel stated is 12# channel steel.
4. prefabrication and assembly construction concrete structure outer according to claim 1 bottom tongue and groove protective device, it is characterised in that: institute The flitch specification stated is 50 × 100mm.
5. a kind of installation method of prefabrication and assembly construction concrete structure outer bottom tongue and groove protective device, it is characterised in that including following Step:
1) prefabricated components drawing is deepened, and 4 20 hole to be provided of φ are arranged in precast facade wall in advance;
2) component produces, according to Deepen Design drawing set aside pre-embedded;
3) before precast facade entrucking transport, 20 hole to be provided of wall φ is passed through using 16 bolt of φ, 12# channel steel is mounted on prefabricated Exterior wall bottom, and 50 × 100mm flitch is clogged between channel steel and precast facade;
4) component is transported to scene, turns in hoisting process, and channel steel is played a supporting role, and tongue and groove is made to be in vacant state always, protects It demonstrate,proves not damaged;
5) it is lifted to leave to precast facade and removes tongue and groove protective device at the 1m of ground under steady state.
CN201910011674.4A 2019-01-07 2019-01-07 Prefabrication and assembly construction concrete structure outer bottom tongue and groove protective device and its installation method Pending CN109653520A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910011674.4A CN109653520A (en) 2019-01-07 2019-01-07 Prefabrication and assembly construction concrete structure outer bottom tongue and groove protective device and its installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910011674.4A CN109653520A (en) 2019-01-07 2019-01-07 Prefabrication and assembly construction concrete structure outer bottom tongue and groove protective device and its installation method

Publications (1)

Publication Number Publication Date
CN109653520A true CN109653520A (en) 2019-04-19

Family

ID=66118886

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910011674.4A Pending CN109653520A (en) 2019-01-07 2019-01-07 Prefabrication and assembly construction concrete structure outer bottom tongue and groove protective device and its installation method

Country Status (1)

Country Link
CN (1) CN109653520A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006056969A1 (en) * 2004-11-24 2006-06-01 Thermotech Research And Development International Limited Prefabricated concrete wall panel and method of manufacture
US20110131899A1 (en) * 2010-04-30 2011-06-09 Stefan Voss Apparatus and method for producing a concrete foundation
CN205617552U (en) * 2016-05-03 2016-10-05 福州大学 Assembled integrated configuration
CN205713166U (en) * 2016-04-19 2016-11-23 山东大学 The support connector of pre-formed members wallboard, pre-formed members wallboard and support system thereof
CN106930537A (en) * 2016-05-19 2017-07-07 福建荣盛钢结构实业有限公司 A kind of steel structure wall hoisting structure
WO2018162802A1 (en) * 2017-03-10 2018-09-13 Businesse Ab Support arrangement and method for installing base and wall units
CN209620645U (en) * 2019-01-07 2019-11-12 龙信建设集团有限公司 Prefabrication and assembly construction concrete structure outer bottom tongue and groove protective device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006056969A1 (en) * 2004-11-24 2006-06-01 Thermotech Research And Development International Limited Prefabricated concrete wall panel and method of manufacture
US20110131899A1 (en) * 2010-04-30 2011-06-09 Stefan Voss Apparatus and method for producing a concrete foundation
CN205713166U (en) * 2016-04-19 2016-11-23 山东大学 The support connector of pre-formed members wallboard, pre-formed members wallboard and support system thereof
CN205617552U (en) * 2016-05-03 2016-10-05 福州大学 Assembled integrated configuration
CN106930537A (en) * 2016-05-19 2017-07-07 福建荣盛钢结构实业有限公司 A kind of steel structure wall hoisting structure
WO2018162802A1 (en) * 2017-03-10 2018-09-13 Businesse Ab Support arrangement and method for installing base and wall units
CN209620645U (en) * 2019-01-07 2019-11-12 龙信建设集团有限公司 Prefabrication and assembly construction concrete structure outer bottom tongue and groove protective device

Similar Documents

Publication Publication Date Title
CN101476331B (en) Closed demolition blasting method for internal concrete reinforcement bracing of basement foundation ditch
CN105926669A (en) Construction method of subway station
CN107190866A (en) A kind of assembled architecture is encorbelmented the construction method of outrigger anchor hoop
CN108130837A (en) A kind of prefabricated road plate and its construction method
CN110670615A (en) Subway green construction adjustment method based on limited space
CN105155553A (en) Green dismantling construction method combining concrete support static crush and splitting method
CN105507170A (en) Reinforced concrete slab culvert reinforcement method
CN204060020U (en) A kind of Reinforced Concrete Reinforcement structure
CN104047422B (en) A kind of cylinder mold fabrication and installation method
CN209620645U (en) Prefabrication and assembly construction concrete structure outer bottom tongue and groove protective device
CN106013774A (en) Slip-form flexible platform device suitable for assigning
CN109653520A (en) Prefabrication and assembly construction concrete structure outer bottom tongue and groove protective device and its installation method
CN105297957A (en) Prefabricated filled wallboard and mounting method thereof
CN109577339A (en) Pattern foundation pit supporting structure waist rail rope saw cutting process
CN205348724U (en) Detachable wire rope rings anchor structure of external scaffolding of encorbelmenting
CN201649654U (en) Discharging platform for high-rise building construction
CN104963344B (en) The deep basal pit underground construction method that concrete supporting removal and structure construction are synchronously carried out
CN202208696U (en) Construction platform used for dry quenching furnace
CN203270595U (en) Independent foundation construction inner formwork device with cup rabbet smaller than 600mm*600mm
CN207176527U (en) Bridge Crack bracing means
CN204626965U (en) For the steel stair template of poured up at a time between architectural stair
CN110067260B (en) Method for treating inclination of station steel pipe column by cover-excavation top-down method
CN101922239B (en) Steel die-concrete underpinning device and construction method thereof
CN106801384A (en) Assembled steel reinforced concrete aliform type culvert opening and construction method
CN102493367A (en) Non-blasting construction method for dismantling pier to land bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination