CN109629580A - A kind of side slope surface seepage prevention design method - Google Patents

A kind of side slope surface seepage prevention design method Download PDF

Info

Publication number
CN109629580A
CN109629580A CN201811471042.8A CN201811471042A CN109629580A CN 109629580 A CN109629580 A CN 109629580A CN 201811471042 A CN201811471042 A CN 201811471042A CN 109629580 A CN109629580 A CN 109629580A
Authority
CN
China
Prior art keywords
geomembrane
side slope
slope surface
geotextiles
gutter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811471042.8A
Other languages
Chinese (zh)
Inventor
牛向东
侯克鹏
芦涌峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Asia Mining Technology Co Ltd
Kunming University of Science and Technology
Original Assignee
Yunnan Asia Mining Technology Co Ltd
Kunming University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Asia Mining Technology Co Ltd, Kunming University of Science and Technology filed Critical Yunnan Asia Mining Technology Co Ltd
Priority to CN201811471042.8A priority Critical patent/CN109629580A/en
Publication of CN109629580A publication Critical patent/CN109629580A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/202Securing of slopes or inclines with flexible securing means
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/005Soil-conditioning by mixing with fibrous materials, filaments, open mesh or the like

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention discloses a kind of side slope surface seepage prevention design methods, including smooth side slope surface, it excavates in gutter, it is laid with geotextiles and geomembrane, geomembrane is fixed, the present invention utilizes the barrier characteristics of geomembrane, Anti-seeping technology is carried out using geomembrane as antiseepage substrate side slope slope surface, achieve the purpose that water (rainfall) is prevented to penetrate into side slope, the present invention has construction is simple, it is laid with high-efficient, it is at low cost, safe operation, the advantages that good seepage-proof property, the present invention almost can block water (rainfall) to penetrate into the slopes of side slope completely, influence side slope slopes by water (rainfall), greatly improve the stability of side slope slopes.

Description

A kind of side slope surface seepage prevention design method
Technical field
The invention belongs to slope project fields, specifically, being related to a kind of side slope surface seepage prevention design method.
Background technique
Field is utilized in underground engineering, can often encounter the top plate of the underground engineerings such as stope/tunnel/chamber even water conservancy and hydropower Control problem, one of them is exactly the thickness for needing to accurately determine roof strata, is the disposition and roof control of subsequent top plate Foundation is provided.
The measurement research of coal seam thickness, the physics in coal seam are concentrated mainly on about the research of roof strata thickness measurement at present Chemical property is totally different from the rock stratum of other lithology rock mass, it is impossible to be used in the measurement of other underground engineering top plate thicknesses.In addition, In underground engineering support work, it is sometimes desirable to the loosening belt range of Underground engineering roof strata country rock, it is deep as anchoring Degree or the scientific basis of other support engineering measures.Such as it in the underground water-seal oil depot digging process of East China, needs to detect The Relaxation Zone range size of cavern's roof strata country rock, provides technical basis for method for protecting support.
It is special due to ore body immediate roof bauxite and clay rock especially in the aluminous mine recovery process of underground Property, it solves and control stope ore body immediate roof soft rock rock stratum is the shared technical problem of aluminous mine exploitation.For stope top Plate security control and management provide foundation, are exactly at present to seek a kind of ore body one of the problem of aluminous mine most urgent urgent need to resolve The ways and means of immediate roof thickness quick detection.
In view of this present invention is specifically proposed.
Summary of the invention
The technical problem to be solved in the present invention is that overcoming the deficiencies of the prior art and provide a kind of side slope surface seepage prevention design Method, in order to solve the above technical problems, the present invention is using the basic conception of technical solution:
A kind of side slope surface seepage prevention design method, includes the following steps:
Step 1, smooth side slope surface makes slope surface biggish uneven face do not occur, while avoiding having point in slope surface The bare rock at angle occurs, and excavation and anchorage ditch simultaneously;
Step 2, backfill is carried out at the bottom of slope of each platform, accomplishes inclined-plane, and carry out hand compaction, to increase side slope Stability;
Step 3, gutter excavation is carried out in next adjacent platforms;
Step 4, it is first laid with one layer of geotextiles on side slope surface, prevents geomembrane from being scratched by the rock in slope surface, plays Protective effect to geomembrane, adjacent two width geotextiles are connected by binding hole using Binding material;
Step 5, it then in the geotextiles laid is laid with geomembrane, geotextiles and geomembrane top will pass through anchoring groove And be compacted with backfill, and to reserve certain length, and the lower part of geotextiles and geomembrane will be taped against always next phase Until the gutter position of adjacent platform;
It step 6, is the convenience of constructing operation, the junction between adjacent two width geomembrane is geotechnological using the connection of one fixed width Film is flexibly connected;
Step 7, the geomembrane in slope surface is fixed, prevents the geomembrane in slope surface from slipping off along slope surface, keeps away simultaneously The geomembrane exempted from slope surface is wiped off by strong wind;
Step 8, in the gutter excavated, geotextiles are first laid with, re-lay geomembrane, and to the geotechnique in gutter Cloth and geomembrane are fixed.
Further, in the step 1, side slope surface either opencut side slope, be also possible to roadside Side slope can also be other natures or Artificial Side-slope etc., and the present invention does not refer in particular to a certain type side slope specifically, as long as having The slope surface of certain slope requires all in present invention protection right.
Further, in the step 3, the section configuration in gutter can be the arc-shaped of rule, rectangle, trapezoidal etc., It can also be other irregular section configurations, discharge section shape of the present invention does not refer in particular to a certain shape specifically, as long as setting The different shape gutter of meter can satisfy slope drainage requirement all in present invention protection right.
Further, in the step 3, the surface in excavated gutter is arranged, occur gutter surface should not larger Uneven face, while avoiding the angular bare rock exposure in gutter surface.
Further, when conditions permit, the surface in gutter can be smoothed out with material, the floating of gutter surface is used Material can be cement, pitch, rubber etc..
Further, in the step 4, the material of binding is iron wire/steel wire/ageing-resistant rope etc..
Further, in the step 5, used geomembrane can be HDPE geomembrane, be also possible to other materials Geomembrane, the present invention do not refer in particular to the geomembrane of a certain material specifically, as long as can reach the geomembrane of antiseepage requirement all at this In invention protection right.
Further, in the step 4 and step 5, the width a of geotextiles and geomembrane according to side slope physical length and is applied Work is easy to operate and determines, the present invention does not refer in particular to the width of a certain geotextiles and geomembrane specifically, wants as long as meeting Practical Project The width for constructing operation simplicity of summing is all in present invention protection right.
Further, in the step 4 and step 5, the practical plagioclase of geotextiles and geomembrane is according to side slope actual height H Easy with constructing operation and determine, the present invention does not refer in particular to the plagioclase of a certain geotextiles and geomembrane specifically, as long as meeting practical work The plagioclase of range request and constructing operation simplicity is all in present invention protection right.
Further, in the step 6, the width b for connecting geomembrane can carry out selection determination, this hair according to actual needs The bright width for not refering in particular to a certain connection geomembrane specifically, as long as the width for meeting Practical Project requirement and constructing operation simplicity all exists The present invention protects in right.
Further, in the step 6, the lap width c of adjacent two width geomembrane and connection geomembrane will meet safety It is required that lap width c will guarantee adjacent two width geomembrane and connect the firm and reliable connection between geomembrane, the present invention is not specific special Refer to a certain lap width c value, as long as meeting the width for capableing of firm and reliable connection between adjacent two width geomembrane and connection geomembrane All in present invention protection right.
Further, in the step 6, adjacent two width geomembrane and connection geomembrane between connection type, can be used Hot melt is welded, and be can also be used and is attached by binding hole using Binding material.
Further, Binding material is iron wire, steel wire, ageing-resistant rope etc..
Further, in the step 7, in the anchoring groove on the connection geomembrane top of adjacent two width geomembrane junction Steel nail/reinforcing bar is stamped, is first fixed on wirerope on the steel nail/reinforcing bar anchored, then sand (soil) bag that sand (soil) will be housed is every Fixation spaced apart on a steel cord, the geomembrane in slope surface to be fixed.
Further, in the step 7, adjacent two width geomembrane can also be on the connection geomembrane of junction in slope surface Steel nail/reinforcing bar is stamped at interval of certain distance geomembrane is fixed.
Further, in the step 7, the geomembrane in slope surface is fixed, can also be used sand (soil) bag and steel nail/ Both reinforcing bars, which alternate, is fixed geomembrane.
Further, in the step 8, geotextiles and geomembrane one end in gutter are routed at backfill, and are pressed Below geotextiles and geomembrane in slope surface.
Further, in the step 8, the geomembrane at side slope slope foot uses sand (soil) bag to be pressed in back at a certain distance On banketing, realize that the geomembrane at side slope slope foot is fixed.
Further, in the step 8, the geomembrane at side slope slope foot at a certain distance squeezes into back steel nail/reinforcing bar It bankets in following rock, can also realize that the geomembrane at side slope slope foot is fixed.
Further, in the step 8, the other end of geotextiles and geomembrane in gutter is routed to one outside gutter Set a distance, and in gutter geotextiles and geomembrane at interval of certain distance using sand (soil) bag or steel nail/reinforcing bar into Row is fixed.
After adopting the above technical scheme, the present invention has the advantages that compared with prior art.
The present invention utilizes the barrier characteristics of geomembrane, carries out geomembrane as antiseepage substrate side slope slope surface at antiseepage Reason, achieve the purpose that prevent water (rainfall) penetrate into side slope, the present invention have construction is simple, be laid with it is high-efficient, at low cost, operation peace Entirely, the advantages that good seepage-proof property, the present invention almost can block water (rainfall) to penetrate into the slopes of side slope completely, make side slope slopes It is not influenced by water (rainfall), greatly improves the stability of side slope slopes.
A specific embodiment of the invention is described in further detail with reference to the accompanying drawing.
Detailed description of the invention
The a part of attached drawing as the application, for providing further understanding of the invention, of the invention is schematic Examples and descriptions thereof are used to explain the present invention, but does not constitute an undue limitation on the present invention.Obviously, the accompanying drawings in the following description Only some embodiments to those skilled in the art without creative efforts, can be with Other accompanying drawings can also be obtained according to these attached drawings.In the accompanying drawings:
Fig. 1 a is the hot-melt adhesive paste schematic diagram in the embodiment of the present invention 1 between adjacent geomembrane;
Fig. 1 b is the binding connected mode schematic diagram in the embodiment of the present invention 1 between adjacent geomembrane;
Fig. 1 c is the side slope surface leakage preventing structure schematic diagram of A-A section in Fig. 1 a;
Fig. 2 a is the hot-melt adhesive paste schematic diagram in the embodiment of the present invention 2 between adjacent geomembrane;
Fig. 2 b is the binding connected mode schematic diagram in the embodiment of the present invention 2 between adjacent geomembrane;
Fig. 2 c is the side slope surface leakage preventing structure schematic diagram of A-A section in Fig. 2 a;
Fig. 3 a is the hot-melt adhesive paste schematic diagram in the embodiment of the present invention 3 between adjacent geomembrane;
Fig. 3 b is the binding connected mode schematic diagram in the embodiment of the present invention 3 between adjacent geomembrane;
Fig. 3 c is the side slope surface leakage preventing structure schematic diagram of A-A section in Fig. 3 a;
Fig. 3 d is the side slope surface leakage preventing structure schematic diagram of B-B section in Fig. 3 a;
In figure: 1, side slope surface;2, anchoring groove;3, backfill;4, gutter;5, geotextiles;6, geomembrane;7, it backfills Soil;8, geomembrane is connected;9, hole is bound;10, Binding material;11, it heats;12, steel nail/reinforcing bar;13, wirerope;14, sand (soil) Bag;15, adjacent next step platform.
It should be noted that these attached drawings and verbal description are not intended to the design model limiting the invention in any way It encloses, but illustrates idea of the invention by referring to specific embodiments for those skilled in the art.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, the technical solution in embodiment is clearly and completely described, the following examples are intended to illustrate the invention, but It is not intended to limit the scope of the invention.
Embodiment 1
As shown in Figure 1, a kind of side slope surface seepage prevention design method, comprising the following steps:
Step 1, smooth side slope surface 1 makes slope surface biggish uneven face do not occur, while avoiding having point in slope surface The bare rock at angle occurs, and excavation and anchorage ditch 2 simultaneously;
Step 2, backfill 3 is carried out at the bottom of slope of each platform, accomplishes inclined-plane, and carry out hand compaction, to increase side The stability on slope;
Step 3, gutter 4 is carried out in next adjacent platforms 15 to excavate, the section configuration in gutter can be circular arc Shape/rectangle/trapezoidal/other irregular shapes, 4 surface evening of gutter, conditions permit can smooth out 4 spent material of gutter, The material used can be cement/pitch/rubber etc.;
Step 4, it is first laid with one layer of geotextiles 5 on side slope surface 1, prevents geomembrane 6 from being scratched by the rock in slope surface, rises To the protective effect to geomembrane 6, adjacent two width geotextiles 5 are connected by binding hole 9 using Binding material 10, gutter Section configuration can be arc-shaped/rectangle/trapezoidal/other irregular shapes, 4 surface evening of gutter, conditions permit can will 4 spent material of gutter smoothes out, and the material used can be cement/pitch/rubber etc.;
Step 5, the geomembrane 6 of HDPE/ other materials, geotextiles 5 and geotechnique then in the geotextiles laid are laid with 6 top of film will be compacted by anchoring groove 2 and with backfill 7, and reserve certain length, and geotextiles 5 and geomembrane 6 Lower part to be taped against next adjacent platforms 15 always 4 position of gutter until;
Step 6, the junction between adjacent two width geomembrane 6 is flexibly connected using the connection geomembrane 8 of 70cm wide, soil The lap of splice of work film 6 and geomembrane 8 is 15cm, and reserves certain deflection, be can be used between geomembrane 6 and geomembrane 8 Hot melt 11 is welded, and be can also be used between geomembrane 6 and geomembrane 8 and is attached by binding hole 9 using Binding material 10, Binding material is iron wire/steel wire/ageing-resistant rope etc.;
Step 7, the geomembrane 6 in slope surface is fixed using sand (soil) bag 14, in the company of every adjacent two width geomembrane 6 Steel nail/reinforcing bar 12 is stamped in the anchoring groove 2 on the place of connecing top, the sand pocket (14) for filling sand is fixed on wirerope 13 at interval of 1m On, then wirerope 13 is fixed on the steel nail 12 anchored, the geomembrane 6 in slope surface to be fixed, the soil in slope surface Work film 6 can also stamp steel nail/reinforcing bar 12 at interval of 1m in slope surface and be fixed, and prevent the geomembrane 6 in slope surface along slope Face slips off, while the geomembrane 6 in slope surface being avoided to be wiped off by strong wind;Geomembrane 6 at side slope slope foot is also adopted at a certain distance It is pushed down with sand (soil) bag 14;
Step 8, in the gutter 4 excavated, geotextiles 5 is first laid with, re-lay geomembrane 6, and in gutter 4 Geotextiles 5 and geomembrane 6 are fixed, and the geomembrane 6 of gutter two sides is also pushed down using sand (soil) bag 14 at a certain distance It is fixed.
Embodiment 2
As shown in Fig. 2, a kind of side slope surface seepage prevention design method, comprising the following steps:
Step 1, smooth side slope surface 1 makes slope surface biggish uneven face do not occur, while avoiding having point in slope surface The bare rock at angle occurs, and excavation and anchorage ditch 2 simultaneously;
Step 2, backfill 3 is carried out at the bottom of slope of each platform, accomplishes inclined-plane, and carry out hand compaction, to increase side The stability on slope;
Step 3, gutter 4 is carried out in next adjacent platforms 15 to excavate, the section configuration in gutter can be circular arc Shape/rectangle/trapezoidal/other irregular shapes, 4 surface evening of gutter, conditions permit can smooth out 4 spent material of gutter, The material used can be cement/pitch/rubber etc.;;
Step 4, it is first laid with one layer of geotextiles 5 on side slope surface 1, prevents geomembrane 6 from being scratched by the rock in slope surface, rises To the protective effect to geomembrane 6, adjacent two width geotextiles 5 are connected by binding hole 9 using Binding material 10, gutter Section configuration can be arc-shaped/rectangle/trapezoidal/other irregular shapes, 4 surface evening of gutter, conditions permit can will 4 spent material of gutter smoothes out, and the material used can be cement/pitch/rubber etc.;
Step 5, the geomembrane 6 of HDPE/ other materials, geotextiles 5 and geotechnique then in the geotextiles laid are laid with 6 top of film will be compacted by anchoring groove 2 and with backfill 7, and reserve certain length, and geotextiles 5 and geomembrane 6 Lower part to be taped against next adjacent platforms 15 always 4 position of gutter until;
Step 6, the junction between adjacent two width geomembrane 6 is flexibly connected using the connection geomembrane 8 of 70cm wide, soil The lap of splice of work film 6 and geomembrane 8 is 15cm, and reserves certain deflection, be can be used between geomembrane 6 and geomembrane 8 Hot melt 11 is welded, and be can also be used between geomembrane 6 and geomembrane 8 and is attached by binding hole 9 using Binding material 10, Binding material is iron wire/steel wire/ageing-resistant rope etc.;
Step 7, the geomembrane 6 in slope surface is fixed using steel nail/reinforcing bar 12, prevents 6 edge of geomembrane in slope surface Slope surface slip off, while the geomembrane 6 in slope surface being avoided to be wiped off by strong wind;Geomembrane 6 at side slope slope foot is at a certain distance Also it is pushed down using sand (soil) bag 14;
Step 8, in the gutter 4 excavated, geotextiles 5 is first laid with, re-lay geomembrane 6, and in gutter 4 Geotextiles 5 and geomembrane 6 are fixed, and the geomembrane 6 of gutter two sides is also pushed down using sand (soil) bag 14 at a certain distance It is fixed.
Embodiment 3
As shown in figure 3, a kind of side slope surface seepage prevention design method, comprising the following steps:
Step 1, smooth side slope surface 1 makes slope surface biggish uneven face do not occur, while avoiding having point in slope surface The bare rock at angle occurs, and excavation and anchorage ditch 2 simultaneously;
Step 2, backfill 3 is carried out at the bottom of slope of each platform, accomplishes inclined-plane, and carry out hand compaction, to increase side The stability on slope;
Step 3, gutter 4 is carried out in next adjacent platforms 15 to excavate, the section configuration in gutter can be circular arc Shape/rectangle/trapezoidal/other irregular shapes, 4 surface evening of gutter, conditions permit can smooth out 4 spent material of gutter, The material used can be cement/pitch/rubber etc.;
Step 4, it is first laid with one layer of geotextiles 5 on side slope surface 1, prevents geomembrane 6 from being scratched by the rock in slope surface, rises To the protective effect to geomembrane 6, adjacent two width geotextiles 5 are connected by binding hole 9 using Binding material 10, gutter Section configuration can be arc-shaped/rectangle/trapezoidal/other irregular shapes, 4 surface evening of gutter, conditions permit can will 4 spent material of gutter smoothes out, and the material used can be cement/pitch/rubber etc.;
Step 5, the geomembrane 6 of HDPE/ other materials, geotextiles 5 and geotechnique then in the geotextiles laid are laid with 6 top of film will be compacted by anchoring groove 2 and with backfill 7, and reserve certain length, and geotextiles 5 and geomembrane 6 Lower part to be taped against next adjacent platforms 15 always 4 position of gutter until;
Step 6, the junction between adjacent two width geomembrane 6 is flexibly connected using the connection geomembrane 8 of 70cm wide, soil The lap of splice of work film 6 and geomembrane 8 is 15cm, and reserves certain deflection, be can be used between geomembrane 6 and geomembrane 8 Hot melt 11 is welded, and be can also be used between geomembrane 6 and geomembrane 8 and is attached by binding hole 9 using Binding material 10, Binding material is iron wire/steel wire/ageing-resistant rope etc.;
Step 7, the geomembrane 6 in slope surface is alternateed and is fixed using sand (soil) bag 14 and steel nail/reinforcing bar 12, prevented Only the geomembrane 6 in slope surface is slipped off along slope surface, while the geomembrane 6 in slope surface being avoided to be wiped off by strong wind;At side slope slope foot Geomembrane (6) is also pushed down using sand (soil) bag 14 at a certain distance;
Step 8, in the gutter 4 excavated, geotextiles 5 is first laid with, re-lay geomembrane 6, and in gutter 4 Geotextiles 5 and geomembrane 6 are fixed, and the geomembrane 6 of gutter two sides is also pushed down using sand (soil) bag 14 at a certain distance It is fixed.
The above is only presently preferred embodiments of the present invention, is not intended to limit the present invention in any form, though So the present invention has been disclosed as a preferred embodiment, and however, it is not intended to limit the invention, any technology people for being familiar with this patent Member without departing from the scope of the present invention, when the technology contents using above-mentioned prompt make it is a little change or be modified to The equivalent embodiment of equivalent variations, but anything that does not depart from the technical scheme of the invention content, it is right according to the technical essence of the invention Any simple modification, equivalent change and modification made by above embodiments, in the range of still falling within the present invention program.

Claims (10)

1. a kind of side slope surface seepage prevention design method, which comprises the following steps:
Step 1, smooth side slope surface (1), avoids slope surface from biggish uneven and wedge angle bare rock occur, and excavate anchor Gu Gou (2);
Step 2, backfill (3) are carried out at the slope foot of side slope surface, accomplishes inclined-plane, and carry out hand compaction;
Step 3, gutter (4) are excavated on next adjacent platforms (15), arranges the surface of gutter (4), avoids gutter (4) there is biggish uneven and wedge angle bare rock in surface;
Step 4, one layer of geotextiles (5) is laid on side slope surface (1), adjacent two width geotextiles (5) are connected by improving bud grafting Together;
Step 5, geomembrane (6) are laid on geotextiles (5), the top of geotextiles (5) and geomembrane (6) will pass through anchoring groove (2) and with backfill (7) it is compacted, and to reserve certain length, the lower part Yao Puzhi of geotextiles (5) and geomembrane (6) Gutter (4);
Step 6, the junction between adjacent two width geomembrane (6) is flexibly connected using the connection geomembrane (8) of one fixed width;
Step 7, the geomembrane (6) in slope surface is fixed;
Step 8, in the gutter (4) excavated, geotextiles (5) first is laid with, are re-layed geomembrane (6), and to gutter (4) Interior geotextiles (5) and geomembrane (6) are fixed.
2. a kind of side slope surface seepage prevention design method according to claim 1, which is characterized in that the side slope surface (1) For the side slope of opencut, the side slope of roadside, Artificial Side-slope or other natural slopes.
3. a kind of side slope surface seepage prevention design method according to claim 1, which is characterized in that the gutter (4) Section configuration is the arc-shaped, rectangle of rule, trapezoidal or other geometries.
4. a kind of side slope surface seepage prevention design method according to claim 1, which is characterized in that the step 3 and step 4 Between further include step 31: the surface of gutter (4) is smoothed out, smoothing out the material used is cement, pitch or rubber.
5. a kind of side slope surface seepage prevention design method according to claim 4, which is characterized in that adjacent in the step 4 Two width geotextiles (5) are linked together by binding hole (9) using Binding material (10), Binding material (10) be iron wire, steel wire, Ageing-resistant rope.
6. a kind of side slope surface seepage prevention design method according to claim 1, which is characterized in that the geomembrane (6) is HDPE geomembrane or other materials geomembrane;The width a of the geotextiles (5) and geomembrane (6) according to side slope physical length and Constructing operation determines that the practical plagioclase of geotextiles (5) and geomembrane (6) is according to side slope actual height H and constructing operation come really It is fixed;The width b of connection geomembrane (8) carries out selection determination according to actual needs.
7. a kind of side slope surface seepage prevention design method according to claim 1, which is characterized in that the adjacent two width geotechnique Film (6) and the lap width c for connecting geomembrane (8) will meet safety requirements, and lap width c will guarantee adjacent two width geomembrane (6) firm and reliable connection between geomembrane (8);Geomembrane (6) with connect between geomembrane (8) by hot melt (11) welding connect It connects or is attached by binding hole (9) using Binding material (10), Binding material (10) is iron wire, steel wire, ageing-resistant rope.
8. a kind of side slope surface seepage prevention design method according to claim 1, which is characterized in that the step 7 are as follows: in phase Steel nail/reinforcing bar (12) are stamped in the anchoring groove (2) on connection geomembrane (8) top of adjacent two width geomembrane (6) junctions, first by steel Cord (13) is fixed on the steel nail/reinforcing bar (12) anchored, then sand (soil) bag (14) of sand (soil) will be housed at interval of certain Distance is fixed on wirerope (13), the geomembrane (6) in slope surface to be fixed.
9. a kind of side slope surface seepage prevention design method according to claim 1, which is characterized in that step 7 are as follows: in junction Connection geomembrane (8) on stamp steel nail/reinforcing bar (12) at interval of certain distance the geomembrane (6) in slope surface be fixed.
10. a kind of side slope surface seepage prevention design method according to claim 1, which is characterized in that in the step 8, row Geotextiles (5) and geomembrane (6) one end in ditch (4) are routed at backfill (3), and are pressed in the geotextiles in slope surface (5) With geomembrane (6) in the following, the geomembrane (6) at slope foot is pushed down using sand (soil) bag (14) fix or use steel at a certain distance Nail/reinforcing bar (12) is squeezed into the rock of backfill (3) below and is fixed, and the other end of geotextiles (5) and geomembrane (6) is routed to row Ditch (4) outer certain distance, and in gutter (4) geotextiles (5) and geomembrane (6) at interval of certain distance use sand (soil) bag (14) or steel nail/reinforcing bar (12) are fixed.
CN201811471042.8A 2018-12-04 2018-12-04 A kind of side slope surface seepage prevention design method Pending CN109629580A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811471042.8A CN109629580A (en) 2018-12-04 2018-12-04 A kind of side slope surface seepage prevention design method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811471042.8A CN109629580A (en) 2018-12-04 2018-12-04 A kind of side slope surface seepage prevention design method

Publications (1)

Publication Number Publication Date
CN109629580A true CN109629580A (en) 2019-04-16

Family

ID=66070789

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811471042.8A Pending CN109629580A (en) 2018-12-04 2018-12-04 A kind of side slope surface seepage prevention design method

Country Status (1)

Country Link
CN (1) CN109629580A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110565488A (en) * 2019-08-31 2019-12-13 上海宝冶集团有限公司 Temporary road macadam paving method
CN112627203A (en) * 2020-12-25 2021-04-09 南昌航空大学 Construction method of ecological protection structure of soil slope
CN113338347A (en) * 2021-04-30 2021-09-03 中国有色金属工业昆明勘察设计研究院有限公司 Fixing device suitable for vertical impermeable film laying of slag storage and construction method
CN114622578A (en) * 2022-03-16 2022-06-14 中国水利水电第五工程局有限公司 Seepage-proofing structure for sandy side slope and construction method thereof
RU2797225C1 (en) * 2023-01-09 2023-05-31 Акционерное общество "ВНИИ Галургии" (АО "ВНИИ Галургии") Method for discharge of salt disposal waste during its recultivation

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755709A (en) * 2018-06-05 2018-11-06 昆明理工大学 A kind of open-pit slope antiseepage drainage system

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755709A (en) * 2018-06-05 2018-11-06 昆明理工大学 A kind of open-pit slope antiseepage drainage system

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110565488A (en) * 2019-08-31 2019-12-13 上海宝冶集团有限公司 Temporary road macadam paving method
CN112627203A (en) * 2020-12-25 2021-04-09 南昌航空大学 Construction method of ecological protection structure of soil slope
CN113338347A (en) * 2021-04-30 2021-09-03 中国有色金属工业昆明勘察设计研究院有限公司 Fixing device suitable for vertical impermeable film laying of slag storage and construction method
CN113338347B (en) * 2021-04-30 2024-02-06 中国有色金属工业昆明勘察设计研究院有限公司 Fixing device suitable for paving vertical impermeable film of slag warehouse and construction method
CN114622578A (en) * 2022-03-16 2022-06-14 中国水利水电第五工程局有限公司 Seepage-proofing structure for sandy side slope and construction method thereof
RU2797225C1 (en) * 2023-01-09 2023-05-31 Акционерное общество "ВНИИ Галургии" (АО "ВНИИ Галургии") Method for discharge of salt disposal waste during its recultivation

Similar Documents

Publication Publication Date Title
CN109629580A (en) A kind of side slope surface seepage prevention design method
CN103882884B (en) A kind of anchor cable geo-grid retaining structure and construction method thereof
CN101298780A (en) High and light anchorage cable pile panel wall and construction method thereof
EP2867415B1 (en) Ground anchor assembly
CN103603369B (en) Construction method of anchor pile counterfort retaining wall
CN205977229U (en) Arcading tunnel non - flushes entrance to a cave structure suitable for bias voltage condition
CN105274922B (en) A kind of antiskid key steel-pipe pile composite construction and method for repairing landslide roadbed
CN102748040A (en) Main structure for metro long-span station and pillar arching construction method thereof
CN112127900A (en) Construction method for hidden half-wall and half-arch protection structure of exposed arch of shallow-buried bias tunnel penetrating through accumulation body
CN110017149A (en) A kind of ledge tunneling is suitable to build underground structure and construction method
CN109441456A (en) A kind of the tunnel structure and its construction method of weakness Facility-sliding strata
CN110439594A (en) A kind of tunnel deformation crack structure and construction method
CN207004570U (en) A kind of tunnel longitudinal drainage blind pipe fixed structure
CN105804097A (en) Cantilever structure way for treating landslides in cooperation with h-shaped anti-sliding piles and construction method of cantilever structure way
CN100513705C (en) Underground beam-pile frame construction for reinforcing side slope
NZ248291A (en) Inserted post and concrete floor undercut excavation method
CN111894026A (en) Tunnel type pile foundation bearing platform combined anchorage structure and installation method thereof
CN107060837B (en) A kind of Shallow-buried asymmetry formula shield arch construction method
CN109610505A (en) A kind of tunnel upper foundation pit construction method
KR102251982B1 (en) Retaining Wall System usable as building underground wall and it's Construction Method
CN209585055U (en) A kind of plain fill deep basal pit combined type soil nail wall
KR102129587B1 (en) New Messer Shield engineering method
CN114293567A (en) Construction method for improving bearing capacity of natural foundation by embedding basic raft plates into slope protection piles
CN107130610A (en) A kind of construction method of deep foundation pit support
CN109372519B (en) Tunneling construction method for hexagonal section of roadway

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190416

RJ01 Rejection of invention patent application after publication