CN109615324A - One kind being based on the project management method of " wisdom management " system - Google Patents
One kind being based on the project management method of " wisdom management " system Download PDFInfo
- Publication number
- CN109615324A CN109615324A CN201811484979.9A CN201811484979A CN109615324A CN 109615324 A CN109615324 A CN 109615324A CN 201811484979 A CN201811484979 A CN 201811484979A CN 109615324 A CN109615324 A CN 109615324A
- Authority
- CN
- China
- Prior art keywords
- management
- project
- wisdom
- management method
- examination
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000007726 management method Methods 0.000 title claims abstract description 110
- 238000000034 method Methods 0.000 claims abstract description 26
- 230000008569 process Effects 0.000 claims abstract description 21
- 238000010276 construction Methods 0.000 claims description 14
- 238000007689 inspection Methods 0.000 claims description 13
- 238000011156 evaluation Methods 0.000 claims description 7
- 238000011002 quantification Methods 0.000 claims description 6
- 238000012549 training Methods 0.000 claims description 6
- 230000000694 effects Effects 0.000 abstract description 3
- 230000003068 static effect Effects 0.000 abstract description 3
- 238000004458 analytical method Methods 0.000 abstract description 2
- 238000012550 audit Methods 0.000 description 4
- 230000000977 initiatory effect Effects 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 3
- 230000008901 benefit Effects 0.000 description 2
- 208000006335 Lisch epithelial corneal dystrophy Diseases 0.000 description 1
- 239000000470 constituent Substances 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000008676 import Effects 0.000 description 1
- 238000011835 investigation Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 230000008520 organization Effects 0.000 description 1
- 238000013439 planning Methods 0.000 description 1
- 238000004886 process control Methods 0.000 description 1
- 230000009897 systematic effect Effects 0.000 description 1
- 238000012795 verification Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Engineering & Computer Science (AREA)
- Entrepreneurship & Innovation (AREA)
- Operations Research (AREA)
- Economics (AREA)
- Marketing (AREA)
- Data Mining & Analysis (AREA)
- Quality & Reliability (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a kind of project management methods for being based on " wisdom management " system, including management cloud module and air control module.Managing cloud module includes " wisdom management " end system PC and cell phone application end, and air control module includes static risk level and dynamic risk level.By combing operational module according to the process of specification, make operational module procedure;It is several modules by job analysis, makes management modularization, and the overall process of client and company's real-time query Supervision Implementation, achieve the effect that supervision process transparence;Professional help is provided for a line supervisor again, and provides expert team to difficult and complicated cases and supports, reaches field work specialization;By the data of process collection, system automatic arranging is specification document data, keeps operational data information-based.
Description
Technical field
The present invention relates to " wisdom management " system regions, more particularly to a kind of project management for being based on " wisdom management " system
Method.
Background technique
The positioning of " wisdom management " system is not only auxiliary tool, but integrated management service supplier, passes through division
Evaluation unit, tracking project plan, progress, use of funds situation meet project team's scene standardized stream process control;Real-time progress
It checks, meet the engineering supervision demand of owner and construction unit, system should be not only practical, but also has certain advance, because
This should select mature technology, and for these technologies within the long period from now on, it is out-of-date not answer;And the structure system of Systematic selection
It can gradually be extended and according to the development of technology using update, superior technique.
But existing project management has the following problems;
1, construction site and management act generate distance, it will breed security-hidden trouble, even result in quality safety thing
Therefore;
2, supervision process does not accomplish transparence, and every aspect is caused to lack basic trust to management;
3, effect of the management in engineering construction is lower than people's expection, supervisor's technical level and moral level year by year under
Drop;
4, fraud, the data of applying for checking and examination are fabricated etc. and to cause data that can not trace to the source, also can be to quality may occurring and safety accident is buried
Lower secret worry.
Summary of the invention
In view of the above-mentioned problems, the present invention provides a kind of project management methods for being based on " wisdom management " system.
In order to solve the above technical problems, the technical scheme adopted by the invention is that: the project management method includes two pieces of moulds
Block: management cloud module and air control module, the management cloud module include " wisdom management " end PC and " wisdom management " end APP, institute
Stating air control module includes static risk level and dynamic risk level.
Preferably, described " wisdom management " end PC includes workbench, project management, knowledge, system, setting and message.
Preferably, described " wisdom management " end APP include project, it is pending, conveniently clap, knowledge base and I.
Preferably, the project management includes establishment of item, evaluation unit, bill of quantities, personal management, progress pipe
Reason, process apply for checking and examination, management through quantification, the other station in scene, tissue examination, safety management, real time monitoring, risk source tracking, on-the-spot make an inspection tour,
Notification instruction, project meeting, System Documents, training of telling somebody what one's real intentions are, examines management and report library at project briefing.
Preferably, the knowledge includes data bank and Ask-Answer Community.
Preferably, the system comprises Engineering Division management, process management, unit in charge of construction's management, information management, Ren Yuanguan
Reason, rights management, operation log, parameter setting and day gas management.
Preferably, the setting includes that personal information is arranged and releases.
Preferably, the project includes personal management, progress control, management through quantification, process is applied for checking and examination, scene side is stood, scene
It makes an inspection tour, examine management, notification instruction, tissue examination, project meeting, training of telling somebody what one's real intentions are, System Documents, project briefing and report library.
Preferably, the message includes that message informing and message are checked.
Preferably, the knowledge includes data bank and question and answer.
Preferably, it is described I include personal information be arranged and exit.
By the above-mentioned description of this invention it is found that compared to the prior art, the present invention has the advantage that
A kind of project management method being based on " wisdom management " system of the invention, passes through the stream by operational module according to specification
Cheng Jinhang combing, makes operational module procedure;Be several modules by job analysis, make management modularization, and client and
The overall process of company's real-time query Supervision Implementation, achievees the effect that supervision process transparence;It is provided specially for a line supervisor again
Industry helps, and provides expert team to difficult and complicated cases and support, reaches field work specialization;By the data of process collection, system
Automatic arranging is specification document data, keeps operational data information-based.
Detailed description of the invention
Fig. 1 is " wisdom management " PC end frame figure of the invention;
Fig. 2 is " wisdom management " APP end frame figure of the invention.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right
The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and
It is not used in the restriction present invention.
Embodiment 1
One kind being based on the project management method of " wisdom management " system, and the item-function of the management cloud module includes:
1, create project: project manager being capable of new add items;The essential information of edit item.
2, evaluation unit: the evaluation unit of each unit in charge of construction (contract section) is set;It can import to have by Excel and comment
Order member;Maintenance can be edited by system library;The process and bill of quantities of each subdivisional work are set.
3, bill of quantities bill of quantities: is set for each unit in charge of construction (contract section);Project amount project is adjustable
Unit and quantity.
4, personal management: project personnel are managed;Personnel are added for project;It can withdraw from the sentries personnel for item setup;It compiles
Collect human roles and permission;Viewer person's trend of work.
5, progress progress control: is set for each unit in charge of construction (contract section);Progress includes annual plan and monthly plan;
It is applied for checking and examination the case where completing according to projected conditions and process, forms plan and compared with practical, generate curve of progress.
6, process is applied for checking and examination: unit in charge of construction initiates process and applies for checking and examination;By specially supervising the corresponding inspector of distribution;Inspector fills in
Check and acceptance result, and feed back to upper level.
7, management through quantification: management through quantification includes audit account and measure machine account;It is applied for checking and examination the subdivisional work of completion according to process
Project amount enters in audit account;After manual examination and verification, into measure machine account.
8, the other station in scene: management person initiates the other station in scene according to distribution;According to the actual situation, other station result is filled in;And
Side station result is fed back into upper level.
9, tissue examination: promoter's initiation tissue inspection;Related personnel fills in inspection result, and inspection result is summarized
After feed back to upper level.
10, safety management: the related management of secure context, including security organization structure chart, rules and regulations, examine examination & approval,
Safety inspection and examination train and tell somebody what one's real intentions are, security log, safe accredited, safety patrol, Safety Supervision file, check feedback and lead to
Report, risk source tracking and Safety Supervision instruction or notice.11, on-the-spot make an inspection tour: on-the-spot make an inspection tour is initiated;According to the actual situation, it fills out
Write tour result;And upper level is fed back to by result is maked an inspection tour.
12, it notification instruction: issuees a notice instruction to unit in charge of construction;It is issued after the manager's audit of notification instruction Items in order.
13, project briefing: record project briefing.
14, project meeting: initiating project meeting, will notify meeting participant;The related data of post-meeting note meeting.
15, preparation of document: the relevant management file of project is managed, including surveillance planning, supervision regulations, quality pipe
Manage file, progress control file, safety management file, other management files.
16, tell somebody what one's real intentions are training: initiation is told somebody what one's real intentions are training, will notice meeting participant;The related data of post-meeting note meeting.
17, it examines management: declaring for unit in charge of construction's initiation is examined;Examination & approval can specially supervise oneself feedback opinion,
Other people's feedback opinions can be distributed to, special prison is then aggregated into.
18, library: the file generated in system is managed collectively, comprising: supervision diary, applies for checking and examination at management monthly magazine
Report, progress report, other station report, audit report, tour report etc..
19, workbench: as the homepage and summary page after login, displaying project and personnel's summarizes data.
20, engineering classification divides: being managed to evaluation unit, generates system evaluation unit.
21, process management: the corresponding process inspection of subdivisional work is managed.
22, unit in charge of construction manages: being managed to unit in charge of construction's information.
23, New Management: the data bank of Help Center, Ask-Answer Community are managed.
24, meteorological data: system obtains the weather data of item location automatically.
25, parameter setting: system parameter is configured.
26, user management: enterprise staff is managed.
27, operation log: all operation logs of system are managed.
28, data bank: the presentation data library in the form of picture and text or attachment.
29, for encountering problems in real work, problem can Ask-Answer Community: be initiated;It can also help to answer other people
Enquirement.
Embodiment 2
One kind being based on the project management method of " wisdom management " system, which includes:
Static risk level:
1, it is directed to constituent parts engineering, introduces the LECD table made in advance;
2, it triggers and stops, applied for checking and examination according to first segment, other station triggering, then according to the last one knot that applies for checking and examination of construction unit
Beam;
3, it by statistical unit project progress situation, determines and which stage to distinguish different risk class of each stage in.
Dynamic risk level:
1, by making an inspection tour, applying for checking and examination, other station introduce, can choose which specific problem, these problems are one of risk
Point;
2, it when issuing a notice, instructing, indicates and brings risk class size;
3, foeign element influences, and the risk class of whole project may be promoted, such as hurricane, flood, continuous high temperature day
Gas etc.;
4, human factor influences, such as management of project manager ability, the level of technical staff, the management level of supervisor;
5, risk source tracks, and by carrying out regular follow-up investigations to the risk source of setting, checks that situation is also the one of risk
Part
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention
Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.
Claims (11)
1. one kind is based on the project management method of " wisdom management " system, which includes two pieces of modules: management cloud
Module and air control module, the management cloud module include " wisdom management " end system PC and the end APP, and the air control module includes quiet
State risk level and dynamic risk level.
2. a kind of project management method for being based on " wisdom management " system according to claim 1, it is characterised in that: described
" wisdom management " end PC includes workbench, project management, knowledge, system, setting and message.
3. a kind of project management method for being based on " wisdom management " system according to claim 1, it is characterised in that: described
" wisdom management " end APP include project, it is pending, conveniently clap, knowledge base and I.
4. a kind of project management method for being based on " wisdom management " system according to claim 2, it is characterised in that: described
Project management include establishment of item, evaluation unit, bill of quantities, personal management, progress control, process apply for checking and examination, management through quantification,
Live other station, safety management, on-the-spot make an inspection tour, notification instruction, project briefing, project meeting, System Documents, is told somebody what one's real intentions are at tissue examination
Training examines management and report library.
5. a kind of project management method for being based on " wisdom management " system according to claim 2, it is characterised in that: described
Knowledge includes data bank and Ask-Answer Community.
6. a kind of project management method for being based on " wisdom management " system according to claim 2, it is characterised in that: described
System includes Engineering Division management, process management, unit in charge of construction's management, information management, personal management, rights management, operation day
Will, parameter setting and day gas management.
7. a kind of project management method for being based on " wisdom management " system according to claim 2, it is characterised in that: described
Setting includes that personal information is arranged and releases.
8. a kind of project management method for being based on " wisdom management " system according to claim 3, it is characterised in that: described
Project includes personal management, progress control, management through quantification, process is applied for checking and examination, the other station in scene, on-the-spot make an inspection tour, examination & approval manage, notice refers to
Enable, tissue examination, project meeting, training of telling somebody what one's real intentions are, System Documents, project briefing and report library.
9. a kind of project management method for being based on " wisdom management " system according to claim 3, it is characterised in that: described
Message includes that message informing and message are checked.
10. a kind of project management method for being based on " wisdom management " system according to claim 3, it is characterised in that: institute
Stating knowledge includes data bank and question and answer.
11. a kind of project management method for being based on " wisdom management " system according to claim 3, it is characterised in that: institute
State me includes that personal information is arranged and exits.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811484979.9A CN109615324A (en) | 2018-12-06 | 2018-12-06 | One kind being based on the project management method of " wisdom management " system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811484979.9A CN109615324A (en) | 2018-12-06 | 2018-12-06 | One kind being based on the project management method of " wisdom management " system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109615324A true CN109615324A (en) | 2019-04-12 |
Family
ID=66007267
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811484979.9A Pending CN109615324A (en) | 2018-12-06 | 2018-12-06 | One kind being based on the project management method of " wisdom management " system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109615324A (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110428176A (en) * | 2019-08-05 | 2019-11-08 | 中国电力企业联合会电力建设技术经济咨询中心 | Project progress checking method and system |
CN111401853A (en) * | 2020-03-24 | 2020-07-10 | 上海捷规建筑工程咨询有限公司 | Intelligent construction project management system based on BIM |
WO2020228211A1 (en) * | 2019-05-14 | 2020-11-19 | 南京聚智达信息科技有限公司 | Enterprise work progress query system |
CN111985802A (en) * | 2020-08-15 | 2020-11-24 | 武汉华胜工程建设科技有限公司 | Construction project inspection method, system, intelligent terminal and storage medium |
CN112232761A (en) * | 2020-09-27 | 2021-01-15 | 广西绿能电力勘察设计有限公司 | Infrastructure application system and method |
CN112669009A (en) * | 2020-12-30 | 2021-04-16 | 南昌路兴交通工程监理咨询有限公司 | Project management method based on intelligent supervision system |
CN113033963A (en) * | 2021-03-02 | 2021-06-25 | 国网江苏省电力有限公司南通供电分公司 | Supervision monitoring intelligent platform system |
CN114037316A (en) * | 2021-11-17 | 2022-02-11 | 北京中百信信息技术股份有限公司 | Information system engineering supervision project risk situation query method |
CN115471101A (en) * | 2022-09-26 | 2022-12-13 | 国网江苏省电力有限公司南通供电分公司 | Mobile visual supervision platform |
CN116797179A (en) * | 2023-07-06 | 2023-09-22 | 宁波市盛达工程管理咨询有限公司 | Monitoring system, method and readable storage medium for whole life cycle of building engineering |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102521709A (en) * | 2011-12-22 | 2012-06-27 | 上海建科工程咨询有限公司 | Building construction quality safety online risk management system |
CN106169131A (en) * | 2016-05-16 | 2016-11-30 | 北京诺士诚国际工程项目管理有限公司 | Project management cloud platform system based on the Internet |
US20170053244A1 (en) * | 2015-08-22 | 2017-02-23 | Salim B. KHALIL | Automated, integrated and complete computer program/project management solutions standardizes and optimizes management processes and procedures utilizing customizable and flexible systems and methods |
CN108470271A (en) * | 2018-03-08 | 2018-08-31 | 北京华通天畅工程监理咨询有限公司 | A kind of engineering project total management system |
CN108683673A (en) * | 2018-05-22 | 2018-10-19 | 厦门港湾咨询监理有限公司 | Long-range multiple terminals Supervision Organization work service managing and control system |
-
2018
- 2018-12-06 CN CN201811484979.9A patent/CN109615324A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102521709A (en) * | 2011-12-22 | 2012-06-27 | 上海建科工程咨询有限公司 | Building construction quality safety online risk management system |
US20170053244A1 (en) * | 2015-08-22 | 2017-02-23 | Salim B. KHALIL | Automated, integrated and complete computer program/project management solutions standardizes and optimizes management processes and procedures utilizing customizable and flexible systems and methods |
CN106169131A (en) * | 2016-05-16 | 2016-11-30 | 北京诺士诚国际工程项目管理有限公司 | Project management cloud platform system based on the Internet |
CN108470271A (en) * | 2018-03-08 | 2018-08-31 | 北京华通天畅工程监理咨询有限公司 | A kind of engineering project total management system |
CN108683673A (en) * | 2018-05-22 | 2018-10-19 | 厦门港湾咨询监理有限公司 | Long-range multiple terminals Supervision Organization work service managing and control system |
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2020228211A1 (en) * | 2019-05-14 | 2020-11-19 | 南京聚智达信息科技有限公司 | Enterprise work progress query system |
CN110428176B (en) * | 2019-08-05 | 2020-10-30 | 中国电力企业联合会电力建设技术经济咨询中心 | Project progress auditing method and system |
CN110428176A (en) * | 2019-08-05 | 2019-11-08 | 中国电力企业联合会电力建设技术经济咨询中心 | Project progress checking method and system |
CN111401853A (en) * | 2020-03-24 | 2020-07-10 | 上海捷规建筑工程咨询有限公司 | Intelligent construction project management system based on BIM |
CN111401853B (en) * | 2020-03-24 | 2024-06-04 | 上海捷规建筑工程咨询有限公司 | Intelligent construction project management system based on BIM |
CN111985802A (en) * | 2020-08-15 | 2020-11-24 | 武汉华胜工程建设科技有限公司 | Construction project inspection method, system, intelligent terminal and storage medium |
CN112232761B (en) * | 2020-09-27 | 2023-11-14 | 广西绿能电力勘察设计有限公司 | Infrastructure application system and method |
CN112232761A (en) * | 2020-09-27 | 2021-01-15 | 广西绿能电力勘察设计有限公司 | Infrastructure application system and method |
CN112669009A (en) * | 2020-12-30 | 2021-04-16 | 南昌路兴交通工程监理咨询有限公司 | Project management method based on intelligent supervision system |
CN113033963A (en) * | 2021-03-02 | 2021-06-25 | 国网江苏省电力有限公司南通供电分公司 | Supervision monitoring intelligent platform system |
CN114037316B (en) * | 2021-11-17 | 2023-04-07 | 北京中百信信息技术股份有限公司 | Information system engineering supervision project risk situation query method |
CN114037316A (en) * | 2021-11-17 | 2022-02-11 | 北京中百信信息技术股份有限公司 | Information system engineering supervision project risk situation query method |
CN115471101A (en) * | 2022-09-26 | 2022-12-13 | 国网江苏省电力有限公司南通供电分公司 | Mobile visual supervision platform |
CN116797179A (en) * | 2023-07-06 | 2023-09-22 | 宁波市盛达工程管理咨询有限公司 | Monitoring system, method and readable storage medium for whole life cycle of building engineering |
CN116797179B (en) * | 2023-07-06 | 2024-05-24 | 宁波市盛达工程管理咨询有限公司 | Monitoring system, method and readable storage medium for whole life cycle of building engineering |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109615324A (en) | One kind being based on the project management method of " wisdom management " system | |
CN104361445B (en) | Labour's real-time management system and management method | |
CN115375146B (en) | Digital construction integrated platform | |
CN102521697A (en) | Power grid informatization evaluating lab management system | |
CN111178680B (en) | Wind power plant engineering quality overall process management system, method and equipment | |
CN109784613A (en) | Electric power field work managing and control system anti-violating the regulations | |
CN103412745B (en) | A kind of exploitation and application platform | |
CN113469544A (en) | Risk control method and system for safety operation | |
CN110399363B (en) | Problem data full life cycle data quality management method and system | |
CN110717731A (en) | Safety inspection problem tracking closed loop system | |
CN111861799A (en) | Intelligent construction site management system and method | |
CN111598411A (en) | Intelligent safety control system for operation site of transformer substation | |
CN111768172A (en) | Engineering safety supervision traceability system based on block chain | |
CN109801416A (en) | A kind of total dimension computer lab management method of building together based on big data analysis | |
CN108280592A (en) | A kind of hazardous waste standardization supervise and examine appraisal management system and method | |
CN112016803A (en) | Cross-professional power grid risk safety management and control system fusing operation big data | |
Rija et al. | The internal control systems integrated into the various profiles of governance, audit, risk and compliance | |
CN114186955A (en) | Standardized management system for safety production | |
CN117787885A (en) | Enterprise safety production management method and system | |
Domingues et al. | Integrated Management Systems: the vision from the perspective of the Occupational Health and Safety System | |
CN111860895A (en) | BIM-based bridge auxiliary facility operation maintenance management system | |
CN111667243A (en) | Business audit system based on ERP system | |
CN112381494B (en) | Intelligent supervision system and method for urban construction | |
CN116362535A (en) | Dual pre-control method and device for risk classification management and control and hidden trouble investigation | |
CN115860495A (en) | Emergency plan processing method, device, equipment, medium and product |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190412 |
|