CN102521697A - Power grid informatization evaluating lab management system - Google Patents

Power grid informatization evaluating lab management system Download PDF

Info

Publication number
CN102521697A
CN102521697A CN2011104162919A CN201110416291A CN102521697A CN 102521697 A CN102521697 A CN 102521697A CN 2011104162919 A CN2011104162919 A CN 2011104162919A CN 201110416291 A CN201110416291 A CN 201110416291A CN 102521697 A CN102521697 A CN 102521697A
Authority
CN
China
Prior art keywords
test
module
project
management
management module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011104162919A
Other languages
Chinese (zh)
Inventor
徐晖
魏理豪
王甜
魏东辉
张若曦
朱奕
欧阳金亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Information Center of Guangdong Power Grid Co Ltd
Original Assignee
Information Center of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Information Center of Guangdong Power Grid Co Ltd filed Critical Information Center of Guangdong Power Grid Co Ltd
Priority to CN2011104162919A priority Critical patent/CN102521697A/en
Publication of CN102521697A publication Critical patent/CN102521697A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a power grid informatization evaluating lab management system, comprising a test commission module, a project plan module, a demand management module, an example management module, an execution management module, a defect management module, a report management module, a sample flow management module, an equipment management module, a progress management module, a work amount analysis module, a quality management module, a statistical analysis module, a knowledge base module, a document library module and a system management module. According to the embodiment disclosed by the invention, the quality management control and the omnibearing statistic data analysis of a power grid informatization evaluating lab on whole life cycle of software can be satisfied.

Description

Electric network information evaluation and test laboratory room managing system
Technical field
The present invention relates to field of computer technology, relate in particular to a kind of electric network information evaluation and test laboratory room managing system.
Background technology
Quickening along with power industry informatization paces; Information-based application in power industry more and more widely, relevant with it business support system and platform are scale, complicated development trend, and be increasingly high to the quality requirements of corresponding software; Therefore the ways and means to software quality assurance requires also increasingly high; The various places grid company is set up electrical network evaluation and test laboratory in succession along with the scope and the degree of depth of security information construction are being expanded gradually, carries out the test job of each application software of electric network informationization; Become authority's in the system informationization detection and assessment centers, informationalized high speed development is played the effect that escorts.
Power informatization is evaluated and tested breadboard development; Management that should first implementation specificationization; Set up the evaluation and test operation flow, formulate the management regulation, information-based system, performance appraisal and the incentive system that adapt with it, important Construction of Information System project is set up introduced evaluation and test troop participation mechanism; From the normalization of system guarantee evaluation and test work, real auxiliary to power informatization work.
Information-based evaluation and test is progressively goed deep into, is launched on a large scale; Information-based evaluation and test laboratory progressively faces some new challenges at aspects such as ladder of management, proprietary technology researchs; Project is many, type is general, data are big, personnel are wide because information-based evaluation and test laboratory evaluation and test project day by day becomes; Thereby press for the support of the management platform of a cover standard evaluation and test laboratory room managing system and standard; Realize standardization, the procedure of all test events of evaluation and test laboratory, the management of electronization,, and real-time decision information is provided for company management's layer so that can immediately control test event progress, risk.
Domestic many grid company have all been set up the evaluation and test laboratory at present; But face problems; Problem such as concentrate on mainly that breadboard location is unintelligible, standard disunity, original manual management mode, process can't be measured, index can't quantize, the existence of these problems causes in the power informatization process, lacks effectively evaluation and test data; Cause and to the startup of using project foundation to be provided; Process of construction can't be estimated after can't monitoring, implementing, and does not really play power informatization and evaluates and tests breadboard existence value, has restricted breadboard development especially.
Summary of the invention
The present invention proposes a kind of electric network information evaluation and test laboratory room managing system, can satisfy electric network information evaluation and test laboratory to quality management and control and omnibearing statistical data analysis to the Life cycle of software.
The embodiment of the invention provides a kind of electric network information evaluation and test laboratory room managing system, comprising:
The test commit module is used to receive test application form and the testing requirement table that the consigner submits to, through after examining, with the testing requirement import system;
Project scheduling module is used to receive the test plan table that the project leader submits to, through after examining, with the test plan import system;
The demand management module is used for the import system demand, and testing requirement is analyzed, and sets up testing requirement association and testing requirement traceback matrix;
The case management module is used for setting up test case association and test case traceback matrix according to testing requirement establishment test case;
Carry out administration module, be used for generating the test execution collection, implementation of test cases, record test execution state and the process of submitting defective to from test case;
The defect management module is used for the test defect information according to tester's submission, generates Problem Analysis Report;
The Reports Administration module is used for Problem Analysis Report is evaluated, and generates test report and submits to the consigner.
Further, said electric network information evaluation and test laboratory room managing system also comprises:
The sample circulation administration module is used for the certificate of entrustment Samples Submitted are managed;
Device management module is used for equipment is managed, and comprises procurement request, equipment acceptance, device registration, use registration, verification maintenance and the management of equipment maintenance of equipment;
The progress control module is used for the progress msg of management project plan and task, the comparative information of programming phase and actual stage progress, the comparative information of plan target and actual task progress;
The workload analysis module is used for the arrangement situation of display systems all items personnel, task;
Quality management module is used for when formulating the project scheduling, and the quality index that setting item will be collected, and given mass target zone through the data that produce in the assembled item process, are checked the situation of this each index ' s quality of project;
Statistical analysis module comprises project statistical study in certain concrete project and the system; The statistical content of concrete a certain project comprises: performance indicators analysis, project data analysis and test data analysis;
Base module is used to store the knowledge of reference value;
The document library module is used for the stored items document;
System management module is used to support the operation of total system.
The electric network information evaluation and test laboratory room managing system that the embodiment of the invention provides can satisfy electric network information evaluation and test laboratory to quality management and control and omnibearing statistical data analysis to the Life cycle of software.Realization provides the test job workflow management, to equipment control, progress control, workload analysis, quality management, statistical study and cooperation management to test trust, demand management, case management, execution management, defect management, Reports Administration, the sample circulation process of test event; The management of test data is provided, test event is carried out comprehensive management and data collection analysis and tap/dip deep into, reach acceptable quality level to guarantee software; Technical support platform performance test job workflow management; The software requirement centralized management guarantees that software reaches acceptable quality level, and effectively elevator system is to the supporting capacity of business; The vertical management and control ability of enhanced quality; For decision-making provides effective foundation, reduce cost of investment simultaneously, fully guaranteed corporate information system in design, to develop and move each stage controlled in order.
Description of drawings
Fig. 1 is the structural representation of the electric network information evaluation and test laboratory room managing system that provides of the embodiment of the invention one;
Fig. 2 is the structural representation of the electric network information evaluation and test laboratory room managing system that provides of the embodiment of the invention two;
Fig. 3 is the module cooperation relation figure of the electric network information evaluation and test laboratory room managing system that provides of the embodiment of the invention three.
Embodiment
To combine the accompanying drawing in the embodiment of the invention below, the technical scheme in the embodiment of the invention is carried out clear, intactly description, obviously, described embodiment only is the present invention's part embodiment, rather than whole embodiment.Based on the embodiment among the present invention, those of ordinary skills are not making the every other embodiment that is obtained under the creative work prerequisite, all belong to the scope of the present invention's protection.
Referring to Fig. 1, be the structural representation of the electric network information evaluation and test laboratory room managing system that provides of the embodiment of the invention one.
The electric network information evaluation and test laboratory room managing system that the embodiment of the invention provides comprises:
The test commit module is used to receive test application form and the testing requirement table that the consigner submits to, through after examining, with the testing requirement import system;
Wherein, the test application form operation platform that comprises software require, information such as developing instrument, system's characteristics, main functional modules.For example, the operation platform requirement is: 2G internal memory, 80G hard disk, Window server2003 operating system; Developing instrument is: Eclipse; System's characteristics are: response speed is fast; Main functional modules is: mail transmission/reception, official document transmitting-receiving, data management and client information management.
Project scheduling module is used to receive the test plan table that the project leader submits to, through after examining, with the test plan import system;
The demand management module is used for the import system demand, and testing requirement is analyzed, and sets up testing requirement association and testing requirement traceback matrix;
The case management module is used for setting up test case association and test case traceback matrix according to testing requirement establishment test case;
Carry out administration module, be used for generating the test execution collection, implementation of test cases, record test execution state and the process of submitting defective to from test case;
The defect management module is used for the test defect information according to tester's submission, generates Problem Analysis Report;
The Reports Administration module is used for Problem Analysis Report is evaluated, and generates test report and submits to the consigner.
Referring to Fig. 2, be the structural representation of the electric network information evaluation and test laboratory room managing system that provides of the embodiment of the invention two.
Further, the electric network information evaluation and test laboratory room managing system that provides of the embodiment of the invention also comprises:
The sample circulation administration module is used for the certificate of entrustment Samples Submitted are managed;
Device management module is used for equipment is managed, and comprises procurement request, equipment acceptance, device registration, use registration, verification maintenance and the management of equipment maintenance of equipment;
The progress control module is used for the progress msg of management project plan and task, the comparative information of programming phase and actual stage progress, the comparative information of plan target and actual task progress;
The workload analysis module is used for the arrangement situation of display systems all items personnel, task;
Quality management module is used for when formulating the project scheduling, and the quality index that setting item will be collected, and given mass target zone through the data that produce in the assembled item process, are checked the situation of this each index ' s quality of project;
Statistical analysis module comprises project statistical study in certain concrete project and the system; The statistical content of concrete a certain project comprises: performance indicators analysis, project data analysis and test data analysis;
Base module is used to store the knowledge of reference value;
The document library module is used for the stored items document;
System management module is used to support the operation of total system.
Below in conjunction with Fig. 3, the electric network information evaluation and test laboratory room managing system that the embodiment of the invention is provided is described in detail.
Referring to Fig. 3, be the module cooperation relation figure of the electric network information evaluation and test laboratory room managing system that provides of the embodiment of the invention three.
1, test commit module
Operation flow is following:
1.1, " test application form " made a report in electrical network Intranet login system by the consigner, and need to submit to " testing requirement " (this testing requirement comprises the test specification of native system and concrete system requirements) simultaneously; When change takes place system requirements, need on system requirements, indicate the change sign;
1.2, the Project Manager fills in " test application approval table " receiving after test is entrusted, and tested tissue entrusts evaluation, the role who participates in evaluation has: person in charge of the technology aspect, quality control supervisor, Project Manager, testing group member;
1.3, evaluation accomplishes the back and goes up audit by the person in charge of the technology aspect at " test application approval table " and sign, and on " test application form ", fill in the laboratory suggestion;
1.4, pass through when evaluation, the person in charge of the technology aspect also need assign the project manager simultaneously when completing " test order ticket ";
1.5, the consigner can land platform and check " test application form " evaluation node, understands review comment, review comment is divided into to be accepted commission and does not accept commission;
1.6, project registered on support platform by the project manager, technical routine responsible official and program member simultaneously;
1.7, the project leader need do affirmation to " testing requirement " table after designated, after confirming to accomplish, submits to the project manager, is committed to the person in charge of the technology aspect after being checked by the project manager, sign on " testing requirement " table by the person in charge of the technology aspect;
1.8, " testing requirement " confirm that the back imports support platform by the project leader with system requirements;
1.9, the flow process of test application change: walk approval process (not needing meeting and net to sign); Submit to " test application change application and evaluation table " to the project leader by the consigner; Submit to project manager's audit (but not needing signature) after project leader's signature, submit to person in charge of the technology aspect's signature again by the project manager and examine; Examine through coming the change of implementation system demand later on by electrical network; The process consigner who examines can login platform and check;
1.10, need not be committed to document administrator and manage filing through the test application of examining;
1.11, the Project Manager after receiving sample, can fill in " sample circulation card " and initiate the sample circulation flow process.
2, project scheduling module
Operation flow is following:
2.1, the project leader writes " test plan " first draft, accomplish the back and initiate " test plan " and evaluate;
2.2, evaluation back project leader revises document according to review comment, and fills in " test plan evaluation table ", transfers to project manager's affirmation of signing;
2.3, be committed to the quality control supervisor after the project manager signature and examine signature, transfer to the person in charge of the technology aspect at last and sign after examination;
2.4, after evaluation is accomplished, the state of test plan is become evaluation passes through, submit to the project manager by the project leader and check;
2.5, the project manager submits to the person in charge of the technology aspect after checking and examines signature;
2.6, the person in charge of the technology aspect examines and submits to the quality owner after the signature and ratify signature;
2.7, approval accomplish after the state of test plan become effectively;
2.8, after " test plan " finalize a text, the project leader carries out allocating task according to " test plan ", the project team member receives an assignment and begins and carries out;
2.9, when " test plan " needs change, revise " test plan " by the project leader, and submit to the project manager to examine amended " test plan "; The project leader proposes the modification application of " test plan ", carries out examining of " test plan " change by the project manager.
3, demand management module
The demand management module mainly is the importing to system requirements, and to the analysis of testing requirement, mainly comprises: the importing of system requirements; The testing requirement registration; The testing requirement evaluation; The testing requirement change; Testing requirement association and testing requirement traceback matrix.Operation flow is following:
3.1, the program member is according to the system requirements establishments testing requirement of " testing requirement " table;
3.2, the project leader, submit to " testing requirement " first draft to evaluate;
3.3, the reviewer is responsible for " testing requirement " evaluation, the mode of evaluation is the meeting evaluation and conutersigns dual mode on the net;
3.4, evaluation passes through, project leader change " testing requirement " state then, and upload the relative recording " evaluation meeting advice note " " evaluation meeting record " " evaluation attendance sheet " in the evaluation course; Do not pass through like evaluation, then return the program member and revise;
3.5, the testing requirement of person in charge of the technology aspect to passing through, sign;
3.6, the project leader is changed to " effectively " to the state of the testing requirement of having signed word;
3.7, the testing requirement state is " effectively ", testing requirement such as need change, then the program member edits testing requirement, state is replaced as " newly-built " from " effectively ";
3.8, the program member, regularly the testing requirement of change is submitted to the project leader and examines;
3.9, the project leader examines the testing requirement of change, the state of examining through testing requirement is " effectively "; Do not examine and revise through then returning to the program member.
4, case management module
Test case mainly comprises contents such as test case essential information, test case evaluation, test case change, test case association and test case traceback matrix.Then main operation flow is following:
4.1, testing group member according to " testing requirement " establishment " test case ";
4.2, the project leader initiates evaluation to " test case " first draft, and the tested tissue group membership evaluates;
4.3, the reviewer evaluates " test case " first draft, the project leader makes amendment to the state of evaluation use-case and uploads the evaluation relative recording;
4.4, evaluation back program member revises test case according to review comment, the project leader fills in " test case evaluation table ", transfers to project manager's affirmation of signing;
4.5, be committed to the quality control supervisor after the project manager signature and examine signature, transfer to the person in charge of the technology aspect at last and sign after examination;
4.6, the project leader initiates to examine to the use-case that passes through of evaluation, submits to the project manager to check;
4.7, the project manager checks test case, but do not sign, and submits to the person in charge of the technology aspect after checking;
4.8, the person in charge of the technology aspect submits to the quality owner after examining signature;
4.9, the quality owner ratify the signature;
4.10, the project leader approval is accomplished after the test case state be changed to " effectively ";
4.11, state changes for the test case such as the need of " effectively ", testing group member direct modification test case then, the state of test case is replaced as " newly-built " automatically from " effectively ";
4.12, testing group member regularly to the change use-case initiate to examine;
4.13, the project leader examines the change use-case of submitting to;
4.14, as examine through, then the project leader is changed to " effectively " to the test case state, as not revising through then returning the testing group member.
5, carry out administration module
The modes such as test execution collection, cross-correlation, defective checking that from use-case, generate generate test case and carry out collection, tester's implementation of test cases, record test execution state and the process of submitting defective to.Then operation flow is:
5.1, the project leader formulates the test execution catalogue according to " test plan ", " test case " and " testing requirement ", formulates the test execution collection then;
5.2, the project leader is according to test execution set content allocating task;
5.3, testing group member is according to task, carries out test, output " executive logging " and defect record.
6, defect management module
Operation flow is following:
6.1, the tester submits defective to;
6.2, the project leader derives " testing problem report ", tissue " testing problem report " evaluation, and fill in " testing problem report evaluation table ";
6.3, the role of the questionnaire that takes one's test evaluation comprises: person in charge of the technology aspect, quality control supervisor, project team member, project manager;
6.4, the reviewer evaluates " testing problem report ", produces " testing problem report evaluation table ", the project leader goes up signature at " testing problem report evaluation table ", submits to the quality control supervisor again and confirms signature, submits to person in charge of the technology aspect's signature at last and examines;
6.5, the tester makes amendment to defective according to the feedback opinion of " testing problem report evaluation table ", revise accomplish after, the project leader exports as " testing problem report " with state for the defective of " evaluation through ";
6.6, the project leader with " testing problem report " submit to the consigner confirm the signature after submit to the tester confirm the signature, transfer to the person in charge of the technology aspect at last and examine signature;
6.7, after " testing problem report " audit, the tester submits " Problem Analysis Report " to, submits to quality control supervisor's affirmation of signing after the signature.
7, Reports Administration module
Operation flow is following:
7.1, the project team member selects test report template to write " test report ";
7.2, the evaluation of project leader tissue " test report ", fill in " test report evaluation table ";
7.3, the personnel that participate in evaluation have: quality owner, person in charge of the technology aspect, quality control supervisor, project team member, Laboratory Chief (optional);
7.4, evaluation back project leader goes up fill substance and signature at " test report evaluation table ", submits to quality control supervisor's affirmation of signing again, examines signature by the quality owner at last;
7.5, after test report evaluation passes through; Initiate the approval process of " test report " by the project leader; " test report " is committed to the person in charge of the technology aspect and examines signature after project manager's signature, transfer to the quality owner again and ratify signature, signed and issued by the responsible official of mechanism approval at last.
7.6, when the consigner submits test report to, can submit " customer satisfaction survey table " to, the consigner can fill in " customer satisfaction survey table " on platform.
8, sample circulation administration module
Operation flow is following:
8.1, when the Project Manager receives consigner's Samples Submitted, need check sample, and fill in " sample circulation card " content, confirm signature;
8.2, when filling in " sample circulation card ", system generates sample circulation card numbering automatically;
8.3, during test implementation, give the tester by the Project Manager with sample, and fill in " sample circulation card " by the tester, confirm signature;
8.4, after inspection closes, the tester need fill in " sample circulation card ", state and signature are closed in confirmatory sample inspection;
8.5, after test accomplishes, the tester submits to the document administrator filing with sample, fills in " sample circulation card " by document administrator, and confirms signature.
9, device management module
Equipment control comprises procurement request, equipment acceptance, device registration, use registration, verification maintenance and the ME several sections of equipment.Mainly be responsible for the management implementation of equipment by equipment manager.
10, progress control module
Operation flow is following:
10.1, after task begins, the task owner needs to feed back every day the current task Percent Complete, system carries out tabulate statistics to the data that everyone fills in;
10.2, show contrast situation, the progress of each task and the contrast situation of actual task progress of contrast situation, each periodic plan progress and actual stage target advance of progress and the actual progress of overall planning in the target advance control; Through contrast, whether the progress of can finding postpones, the responsible official of the stage of delay, the task of delay and task;
10.3, the fulfiling ahead of schedule or delay to have different signs to be distinguished of actual progress.
11, workload analysis module
Workload analysis is to be unit with the total system, shows the arrangement situation of all items personnel, task in this system.Main Business Stream has:
A, task person chart: through the situation of inquiring about, checking project task arrangement personnel;
B, personnel's task list: through inquiring about, check the situation of personnel placement task;
C, the task of not arranging personnel: the task in the displaying project is not also arranged personnel's situation;
D, personnel check table the duration: through personnel is unit, can check the available time of personnel, for the arrangement of project task provides reference;
E, personnel distribute saturation analysis: the analyst participates in the participation of project, weighs personnel's task amount.
12, quality management module
The project manager is when formulating the project scheduling, and the quality index that setting item will be collected, and given mass target zone through the data that produce in the assembled item process, are checked the situation of this each index ' s quality of project.And, take corresponding counter-measure according to the quality situation.
13, statistical analysis module
Statistical analysis module is divided into project statistical study in certain concrete project and the system; In certain concrete project, be divided into three major types, comprise: performance indicators analysis, project data analysis and test data analysis.
The concrete business of statistical analysis module is:
13.1, the statistical content of concrete a certain project:
A), performance indicators analysis: first setting item rank or other performance parameter of individual's level in the system; Project leader or other people select to want the index of checking; System enumerates out with selected performance indicators value, also can a plurality of people's identical desired value be compared; Can the performance indicators result be derived, and the function of mail transmission etc. is provided;
B), project data analysis: be in same project, totally check the situation of project, mainly comprise: contents such as the task of project overview, project, project work component analysis, project process management;
C), test data analysis: mainly between version with version in test data analyze, mainly comprise: defective is seriously registered statistical contents such as distribution situation, each functional module defect distribution situation.
13.2, project statistics in the system, the distribution situation of mainly showing progress, workload and the defective order of severity, defect type and the defect state of projects.
14, base module
Operation flow is following:
14.1, the user finds to have the knowledge of reference value, can submit the knowledge warehouse-in to, needs document administrator to examine before the warehouse-in;
14.2, wait to examine through after, knowledge warehouse-in, knowledge will directly be distributed on knowledge base.
15, document library module
Operation flow is following:
15.1, after project accomplishes, the project leader submits project document filing application to;
15.2, document administrator examines the document of submitting filing to, audit through after directly document is filed to corresponding document and is pressed from both sides by document administrator;
15.3, after the project document filing, the program member only consults the authority of project document, can not download, duplicate, but not program member such as need is consulted document and then need be submitted to document to borrow request slip;
15.4, the person in charge of the technology aspect examines document and borrows application, examine through after, system will borrow request slip automatically and submit to document administrator, the document administrator opening is consulted the authority of document and is given the applicant.
16, system management module
The system management function module is as the basis of whole technique support platform operation.Wherein, employee's management, Role Management, rights management, workflow management, data dictionary etc. are shared as basic data.The system-based data are bases of system's operation, and these data are managed in the system management function module, and other functional modules need read these basic datas and move.
The electric network information evaluation and test laboratory room managing system that the embodiment of the invention provides is building in the design, relies on two bases:
(1), power informatization service basic
Rely on test and assess breadboard business characteristic, development trend, management mode, construction requirements of present power informatization and carry out the investigation and the analysis of localization; Platform must be combined closely with the business of power informatization, for auxiliary quality assurance and safety assurance to the power informatization business development provides active data to support.
(2), test process is observed CNAS approval laboratory standard
Rely on the requirement of Chinese conformity assessment authorized by state committee (CNAS) to the software evaluation industry; Adopting " quality requirements of the commercial stock of soft project software product quality requirements and evaluation (SQuaRE) (COTS) software product and test detailed rules and regulations " GB/T 25000.51-2010, " infotech/software product evaluation/mass property and guide for use thereof " GB/T 16260.2-1996 is the basis, abbreviates CNAS as.
The electric network information evaluation and test laboratory room managing system that the embodiment of the invention provides can satisfy electric network information evaluation and test laboratory to quality management and control and omnibearing statistical data analysis to the Life cycle of software.Realization provides the test job workflow management, to equipment control, progress control, workload analysis, quality management, statistical study and cooperation management to test trust, demand management, case management, execution management, defect management, Reports Administration, the sample circulation process of test event; The management of test data is provided, test event is carried out comprehensive management and data collection analysis and tap/dip deep into, reach acceptable quality level to guarantee software; Technical support platform performance test job workflow management; The software requirement centralized management guarantees that software reaches acceptable quality level, and effectively elevator system is to the supporting capacity of business; The vertical management and control ability of enhanced quality; For decision-making provides effective foundation, reduce cost of investment simultaneously, fully guaranteed corporate information system in design, to develop and move each stage controlled in order.
The above is a preferred implementation of the present invention; Should be pointed out that for those skilled in the art, under the prerequisite that does not break away from the principle of the invention; Can also make some improvement and retouching, these improvement and retouching also are regarded as protection scope of the present invention.

Claims (7)

1. an electric network information evaluation and test laboratory room managing system is characterized in that, comprising:
The test commit module is used to receive test application form and the testing requirement table that the consigner submits to, through after examining, with the testing requirement import system;
Project scheduling module is used to receive the test plan table that the project leader submits to, through after examining, with the test plan import system;
The demand management module is used for the import system demand, and testing requirement is analyzed, and sets up testing requirement association and testing requirement traceback matrix;
The case management module is used for setting up test case association and test case traceback matrix according to testing requirement establishment test case;
Carry out administration module, be used for generating the test execution collection, implementation of test cases, record test execution state and the process of submitting defective to from test case;
The defect management module is used for the test defect information according to tester's submission, generates Problem Analysis Report;
The Reports Administration module is used for Problem Analysis Report is evaluated, and generates test report and submits to the consigner.
2. electric network information evaluation and test laboratory room managing as claimed in claim 1 system is characterized in that said system also comprises:
The sample circulation administration module is used for the certificate of entrustment Samples Submitted are managed;
Device management module is used for equipment is managed, and comprises procurement request, equipment acceptance, device registration, use registration, verification maintenance and the management of equipment maintenance of equipment.
3. electric network information evaluation and test laboratory room managing as claimed in claim 2 system is characterized in that said system also comprises:
The progress control module is used for the progress msg of management project plan and task, the comparative information of programming phase and actual stage progress, the comparative information of plan target and actual task progress.
4. electric network information evaluation and test laboratory room managing as claimed in claim 3 system is characterized in that said system also comprises:
The workload analysis module is used for the arrangement situation of display systems all items personnel, task;
Quality management module is used for when formulating the project scheduling, and the quality index that setting item will be collected, and given mass target zone through the data that produce in the assembled item process, are checked the situation of this each index ' s quality of project.
5. electric network information evaluation and test laboratory room managing as claimed in claim 4 system is characterized in that said system also comprises statistical analysis module; Said statistical analysis module comprises project statistical study in certain concrete project and the system; The statistical content of concrete a certain project comprises: performance indicators analysis, project data analysis and test data analysis.
6. electric network information evaluation and test laboratory room managing as claimed in claim 5 system is characterized in that said system also comprises:
Base module is used to store the knowledge of reference value;
The document library module is used for the stored items document.
7. like each described electric network information evaluation and test laboratory room managing system of claim 1~6, it is characterized in that said system also comprises:
System management module is used to support the operation of total system.
CN2011104162919A 2011-12-13 2011-12-13 Power grid informatization evaluating lab management system Pending CN102521697A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011104162919A CN102521697A (en) 2011-12-13 2011-12-13 Power grid informatization evaluating lab management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011104162919A CN102521697A (en) 2011-12-13 2011-12-13 Power grid informatization evaluating lab management system

Publications (1)

Publication Number Publication Date
CN102521697A true CN102521697A (en) 2012-06-27

Family

ID=46292608

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011104162919A Pending CN102521697A (en) 2011-12-13 2011-12-13 Power grid informatization evaluating lab management system

Country Status (1)

Country Link
CN (1) CN102521697A (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103226758A (en) * 2013-05-08 2013-07-31 灏域联华科技(北京)有限公司 Project development management method
CN103473627A (en) * 2013-08-20 2013-12-25 国家电网公司 Data processing method for requirement change management of operation and maintenance system
CN105354141A (en) * 2015-11-16 2016-02-24 北京用友政务软件有限公司 EMT test case management system and method
CN107357738A (en) * 2017-08-30 2017-11-17 郑州云海信息技术有限公司 A kind of flexible and efficient requirement management systems and method
CN107909347A (en) * 2017-11-24 2018-04-13 郑州云海信息技术有限公司 One kind test material information sharing system and method
CN108052450A (en) * 2017-12-15 2018-05-18 四川汉科计算机信息技术有限公司 Avionic software integration test verification platform
CN108984415A (en) * 2018-07-26 2018-12-11 郑州云海信息技术有限公司 A kind of product use-case persistence maintenance system and management method
CN109086206A (en) * 2018-07-27 2018-12-25 长沙软工信息科技有限公司 A kind of software detection systems and method, electronic equipment
CN109242363A (en) * 2018-11-01 2019-01-18 大连飞创信息技术有限公司 Full life cycle test management platform based on multiple quality control models
CN109492898A (en) * 2018-11-05 2019-03-19 山东鼎安检测技术有限公司 A kind of assay calibration management system based on IMIS
CN109816349A (en) * 2019-01-29 2019-05-28 广州华源创兴计算机服务有限公司 A kind of test verification management platform
CN109858926A (en) * 2019-01-09 2019-06-07 湖北凌晖信息科技有限公司 A kind of software Design, Inc.'s client management system
CN110609775A (en) * 2019-07-26 2019-12-24 上海千检信息技术服务有限公司 Method for displaying test process, server, user side and laboratory side
CN111400159A (en) * 2018-12-29 2020-07-10 北京奇虎科技有限公司 Test report processing method and device, electronic equipment and computer storage medium
CN112446801A (en) * 2020-10-28 2021-03-05 国网辽宁省电力有限公司 System and method for effectively improving data quality of power system
CN113570340A (en) * 2021-07-30 2021-10-29 苏州工业园区测绘地理信息有限公司 Online mapping service entrusting system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1629850A (en) * 2003-12-16 2005-06-22 上海电器科学研究所(集团)有限公司 A control method for laboratory test process management system
CN101847227A (en) * 2009-03-24 2010-09-29 鸿富锦精密工业(深圳)有限公司 Product test management system and method
US20100280962A1 (en) * 2009-02-23 2010-11-04 Chan Louisa Y Automation system and method for a web-based implementation portal

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1629850A (en) * 2003-12-16 2005-06-22 上海电器科学研究所(集团)有限公司 A control method for laboratory test process management system
US20100280962A1 (en) * 2009-02-23 2010-11-04 Chan Louisa Y Automation system and method for a web-based implementation portal
CN101847227A (en) * 2009-03-24 2010-09-29 鸿富锦精密工业(深圳)有限公司 Product test management system and method

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103226758A (en) * 2013-05-08 2013-07-31 灏域联华科技(北京)有限公司 Project development management method
CN103473627A (en) * 2013-08-20 2013-12-25 国家电网公司 Data processing method for requirement change management of operation and maintenance system
CN105354141A (en) * 2015-11-16 2016-02-24 北京用友政务软件有限公司 EMT test case management system and method
CN107357738A (en) * 2017-08-30 2017-11-17 郑州云海信息技术有限公司 A kind of flexible and efficient requirement management systems and method
CN107909347A (en) * 2017-11-24 2018-04-13 郑州云海信息技术有限公司 One kind test material information sharing system and method
CN108052450A (en) * 2017-12-15 2018-05-18 四川汉科计算机信息技术有限公司 Avionic software integration test verification platform
CN108984415A (en) * 2018-07-26 2018-12-11 郑州云海信息技术有限公司 A kind of product use-case persistence maintenance system and management method
CN109086206A (en) * 2018-07-27 2018-12-25 长沙软工信息科技有限公司 A kind of software detection systems and method, electronic equipment
CN109242363A (en) * 2018-11-01 2019-01-18 大连飞创信息技术有限公司 Full life cycle test management platform based on multiple quality control models
CN109242363B (en) * 2018-11-01 2022-05-13 大商所飞泰测试技术有限公司 Full life cycle test management platform based on multiple quality control models
CN109492898A (en) * 2018-11-05 2019-03-19 山东鼎安检测技术有限公司 A kind of assay calibration management system based on IMIS
CN111400159A (en) * 2018-12-29 2020-07-10 北京奇虎科技有限公司 Test report processing method and device, electronic equipment and computer storage medium
CN109858926A (en) * 2019-01-09 2019-06-07 湖北凌晖信息科技有限公司 A kind of software Design, Inc.'s client management system
CN109816349A (en) * 2019-01-29 2019-05-28 广州华源创兴计算机服务有限公司 A kind of test verification management platform
CN110609775A (en) * 2019-07-26 2019-12-24 上海千检信息技术服务有限公司 Method for displaying test process, server, user side and laboratory side
CN112446801A (en) * 2020-10-28 2021-03-05 国网辽宁省电力有限公司 System and method for effectively improving data quality of power system
CN113570340A (en) * 2021-07-30 2021-10-29 苏州工业园区测绘地理信息有限公司 Online mapping service entrusting system

Similar Documents

Publication Publication Date Title
CN102521697A (en) Power grid informatization evaluating lab management system
Huang et al. Owner’s role in construction safety: Guidance model
Dao et al. Project complexity assessment and management tool
US20090307064A1 (en) Performance management system
CN108694513A (en) A kind of assay calibration laboratory certificate management system and method
CN107767016A (en) A kind of digitlization staff evaluation evaluation system based on wireless network handheld terminal
CN106296028A (en) Clinical laboratory employee management system and standardized management method thereof
Lai et al. Performance indicators for facilities operation and maintenance (Part 2) Shortlisting through a focus group study
Ibrahim Effects of internal control, corporate governance, organizational culture, and management audit on managerial performance: Evidence from Indonesia.
CN115878679A (en) Scientific research result management system
Irfan et al. The Improving Model of the Quality of Financial Statements and Successful Implementation of Local Financial Information Systems
Tam et al. Using Gaussian and hyperbolic distributions for quality improvement in construction: Case study approach
Adamu Online Clearance System
Tong Evaluating the performance of Safety Management System within South African Aviation Industry
Juliadi et al. Determinants Test of the Effectiveness of Fixed Asset Management in Mataram City Government
Al Yarda et al. Implementation of E-Archives at the Faculty of Communication and Information Technology Using the Web-Based Waterfall Method
Maggay Student Information and Accounting System of Cagayan State University–Lasam Campus, Philippines
Dakay et al. Improving Integration of Databases and Data Sets Supporting Quality Management in a Higher Education Institution: A Project Post Mortem Analysis
Pambudi et al. The Role of Project Manager Competency in Construction Project Success: A Scoping Review Perspective of PT. MMS Group
Samuels et al. Independent Data for Quality-Management Design
Mawansyah et al. Build a Construction Management Application Based on PHP, JavaScript, CSS, MySQL, and Bootstrap
Khudin et al. Accreditation Automation as a Temporary Legality of Madrasah Quality
Gonnova et al. Electronic Monitoring Systems As Tools for Managing Implementation of Framework CIS Documents
Ha Identification and Ranking of Factors Effects on Evaluation of Internal Controls of Vietnam Independent Auditors in Auditing the Financial Statements of Construction Enterprises
Nasution et al. The Influence of Participation in Budgeting, Budget Evaluation, and Accountability Accounting on Managerial Performance in Regional Apparatus Organizations (Opd) Deli Serdang Regency

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120627