CN109605568A - A kind of concrete and decoration material synchronize pour Integral molding device for insoles - Google Patents

A kind of concrete and decoration material synchronize pour Integral molding device for insoles Download PDF

Info

Publication number
CN109605568A
CN109605568A CN201910082532.7A CN201910082532A CN109605568A CN 109605568 A CN109605568 A CN 109605568A CN 201910082532 A CN201910082532 A CN 201910082532A CN 109605568 A CN109605568 A CN 109605568A
Authority
CN
China
Prior art keywords
framework
insoles
integral molding
decoration material
shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910082532.7A
Other languages
Chinese (zh)
Other versions
CN109605568B (en
Inventor
卜旺杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201910082532.7A priority Critical patent/CN109605568B/en
Publication of CN109605568A publication Critical patent/CN109605568A/en
Application granted granted Critical
Publication of CN109605568B publication Critical patent/CN109605568B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/08Producing shaped prefabricated articles from the material by vibrating or jolting
    • B28B1/087Producing shaped prefabricated articles from the material by vibrating or jolting by means acting on the mould ; Fixation thereof to the mould
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/0002Auxiliary parts or elements of the mould
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/0064Moulds characterised by special surfaces for producing a desired surface of a moulded article, e.g. profiled or polished moulding surfaces

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of concrete and decoration material synchronize pour Integral molding device for insoles, the first framework including upper end opening, the mould for being set to the first frame side wall inner surface, the layering dispenser being set to inside first framework and be set to above first framework for promoting the hoisting mechanism for being layered dispenser;The layering dispenser includes the second framework of upper and lower ends opening, and the second framework is equipped with several vertical reinforcement positioning devices.Decoration material and normal concrete are poured the building element for disposably producing decoration and moulding by the present invention simultaneously, it realizes incrustation Modeling Material and normal concrete main material disposably makes the component and single-item of decoration and moulding simultaneously, can revolution sexually revise existing building industry form of construction work, energy conservation and environmental protection time and labour saving material-saving substantially reduces cost compared with existing way, solves building trade and repeats construction problem.

Description

A kind of concrete and decoration material synchronize pour Integral molding device for insoles
Technical field
The invention belongs to building appliance technical field more particularly to a kind of concrete and decoration material synchronize pour integrated molding Device.
Background technique
Existing building construction and ancient architecture landscape industry construction majority in a manner of site operation based on, construction period asks safely The problems such as topic, construction delay, waste of material, noise pollution, is prominent, and multi-source is in repetition construction and each work post personnel and mechanical discipline Property difference do not concentrate mobility to cause greatly, moulding and decorative parts are even more cladding with later period multiple plaster leveling linked network nailing or paste The forms of construction work such as spraying are completed, and need to be completed a Xiang Houcai and be can be carried out the next item down construction and cannot carry out simultaneously, and the later period also holds It is easy to fall off to have hidden danger.
Summary of the invention
It is an object of the invention in view of the above shortcomings of the prior art, provide a kind of concrete and decoration material synchronize pour Integral molding device for insoles.
To solve the above problems, the technical solution used in the present invention is:
A kind of concrete and decoration material synchronize pour Integral molding device for insoles, the first framework including upper end opening, be set to it is described The mould of first frame side wall inner surface, the layering dispenser being set to inside first framework and it is set to described The hoisting mechanism for being used to be promoted the layering dispenser above one framework;The layering dispenser includes that several upper and lower ends are opened The second framework of mouth, the second framework are equipped with several vertical reinforcement positioning devices.
Further technical solution be further include shaking device, the shaking device is set to the second framework side On wall or the bottom wall outer of the first framework.
Further technical solution is that the vertical reinforcement positioning device is vertical reinforcement location hole, the vertical steel Muscle location hole runs through the side wall of the second framework vertically.
Further technical solution is that the vertical reinforcement positioning device is vertical reinforcement positioning pipe, the vertical steel Muscle positioning pipe is vertically arranged at second framework inside sidewalls upper end.
Further technical solution is, the second framework is equipped with several first feed pipe fixing devices and several the Two feed pipe fixing devices, the first feed pipe fixing device are vertically arranged at the second framework side-wall outer side, and described the Two feed pipe fixing devices are vertically arranged at the second framework inside sidewalls.
Further technical solution is that the hoisting mechanism includes be symmetrically disposed on first frame side wall first Side frame and the second side frame, the shaft being rotatably dispose between first side frame and the second side frame, described shaft one end pass through the Rocking handle is installed after one side frame, several hoisting ropes, the hoisting rope free end and the second framework are wound in the shaft Connection.
Further technical solution is that the hoisting mechanism includes be symmetrically disposed on first frame side wall first Side frame and the second side frame, the shaft being rotatably dispose between first side frame and the second side frame, described shaft one end pass through the Driven wheel is installed after one side frame, the driven wheel is connect by transmission belt with the capstan drive in driving motor output shaft, Several hoisting ropes are wound in the shaft, the hoisting rope free end is connect with the second framework.
Further technical solution is that several plectanes are provided in the shaft, and described hoisting rope one end and shaft are solid Fixed connection, the hoisting rope other end are fixedly connected after passing through the plectane with the second framework.
Further technical solution be further include inner template, the inner template is set to inside the second framework, institute Inner template lower end is stated to be fixedly connected with the bottom wall of the first framework.
Further technical solution is, first framework is square frame, the corresponding second framework also side of being Shape framework or first framework are the building element that circle produces decoration and moulding, realize incrustation Modeling Materials A shape framework, the corresponding second framework are also round framework to material simultaneously with normal concrete main material.
The beneficial effects of adopting the technical scheme are that the present invention by surface decoration material (white cement and add Color cement class gypsum etc.) and normal concrete pour disposably make the component and single-item of decoration and moulding simultaneously, can revolution Existing building industry form of construction work is sexually revised, energy conservation and environmental protection time and labour saving material-saving substantially reduces cost compared with existing way, solves Building trade repeats construction problem.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the embodiment of the present invention 1;
Fig. 2 is that the embodiment of the present invention 1 removes the structural schematic diagram after a side wall;
Fig. 3 is the structural schematic diagram of the embodiment of the present invention 3;
Fig. 4 is that the embodiment of the present invention 3 removes the structural schematic diagram after a side wall;
Fig. 5 is the structural schematic diagram of the embodiment of the present invention 5;
Fig. 6 is that the embodiment of the present invention 5 removes the structural schematic diagram after a side wall.
In figure: 1, the first framework;2, mould;3, second framework;4, the first feed pipe fixing device;5, the second feed Pipe fixing device;6, vertical reinforcement location hole;7, vertical reinforcement positioning pipe;8, the first side frame;9, the second side frame;10, shaft; 11, rocking handle;12, hoisting rope;13, plectane;14, driven wheel;15, transmission belt;16, driving motor;17, shaking device;18, internal model Plate;19, driving wheel.
Specific embodiment
Embodiments of the present invention are described in further detail with reference to the accompanying drawings and examples.Following embodiment is used for Illustrate the present invention, but cannot be used to limit the scope of the invention.
Embodiment 1: as depicted in figs. 1 and 2, a kind of concrete and decoration expect synchronize pour Integral molding device for insoles, including it is upper First framework 1 of end opening, is set to first framework at the mould 2 for being set to 1 side wall inner surfaces of the first framework Layering dispenser inside 1 and be set to 1 top of the first framework for promoting the hoisting mechanism of the layering dispenser; The layering dispenser includes the second framework 3 of upper and lower ends opening, and the second framework 3 is equipped with several vertical reinforcements Positioning device.
First framework 1 is square frame, and the corresponding second framework 3 is also square frame (such as Fig. 1 and Fig. 2), For processing wall body construction.
The vertical reinforcement positioning device is vertical reinforcement location hole 6, perpendicular needed for the vertical reinforcement location hole 6 is controllable Run through the side wall of the second framework 3 vertically to reinforcing bar.
The second framework 3 is equipped with several first feed pipe fixing devices 4 and several second feed pipe fixing devices 5, The first feed pipe fixing device 4 is vertically arranged at 3 side-wall outer side of second framework, the second feed pipe fixing device 5 are vertically arranged at 3 inside sidewalls of second framework.
The hoisting mechanism include be symmetrically disposed on 1 side wall of the first framework the first side frame 8 and the second side frame 9, turn The dynamic shaft 10 being set between first side frame 8 and the second side frame 9, described 10 one end of shaft are pacified after passing through the first side frame 8 Equipped with rocking handle 11, two hoisting ropes 12 are wound in the shaft 10,12 free end of hoisting rope and the second framework 3 connect It connects.
There are two plectanes 13, described 12 one end of hoisting rope to be fixedly connected with shaft 10 for setting in the shaft, the promotion 12 other ends of restricting are fixedly connected after passing through the plectane 13 with the second framework 3.
In the present embodiment, the second framework 3 can also be replaced using partition, the second frame when such as component being single side moulding Body 3 is just needed using partition, and the isolation that second framework 3 or partition close between two kinds of materials when playing different materials feed is made With different materials uniformly merge after second framework 3 or partition promotion.The hoisting mechanism, which also can be used, is far longer than the first framework 1 The prior art independent hoist device (hydraulic or screw rod gantry type etc.) convenient for other sizes use, details are not described herein.
In use, prefabricated mould 2 is fixed on 1 side wall inner surfaces of the first framework, second framework 3 is placed in first Inside framework 1, required vertical reinforcement is inserted into vertical reinforcement location hole 6, while being put into required transverse steel, decoration material is given It is fixed in expects pipe insertion the first feed pipe fixing device 4, it will be in concrete feed pipe insertion the second feed pipe fixing device 5 It is fixed, starting charging gear fills material requested by decoration material feed pipe and cement feed pipe simultaneously, and filling material arrives It is vibrated when at second framework 2/3rds three by vibrating head, by layers of material shake to smooth, then hand rocking handle 11 promotes the Two frameworks 3, vibrating head is normally open when promotion, and material feeding is promoted to pause when need to put transverse steel position, is put into transverse steel After continue, it is synchronous with feeding coal to promote speed for control when promotion, promotes stopping promotion after material feeding to required position and is fed, wait shake Dynamic stick shakes layers of material to smooth stops vibration for second framework 3 after being lifted out completely in material again, wait concrete and Decoration material solidification (such as 3 hours of steam-cured need) demoulds afterwards.
Embodiment 2: itself the difference from embodiment 1 is that, the second framework 3 there are two or it is more than two, for processing Form the component being made of a variety of materials.First framework 1 is round framework, and the corresponding second framework 3 is also circle (not shown), for processing cylindrical member.It of courses, the rule such as first framework 1 or T, L or irregular Special-shaped framework, the corresponding second framework 3 may be the regular or irregular special-shaped framework such as T, L, for processing T, L isotactic Then or irregularly abnormity component, the determines according to actual conditions shape of the first framework 1 and second framework 3.
Embodiment 3: as shown in Figure 3 and Figure 4, a kind of concrete and decoration expect synchronize pour Integral molding device for insoles, including it is upper First framework 1 of end opening, is set to first framework at the mould 2 for being set to 1 side wall inner surfaces of the first framework Layering dispenser inside 1 and be set to 1 top of the first framework for promoting the hoisting mechanism of the layering dispenser; The layering dispenser includes the second framework 3 of upper and lower ends opening, and the second framework 3 is equipped with several vertical reinforcements Positioning device.
First framework 1 is square frame, and the corresponding second framework 3 is also square frame (such as Fig. 3 and Fig. 4), For processing wall body construction.
The vertical reinforcement positioning device is vertical reinforcement location hole 6, and the vertical reinforcement location hole 6 is vertical needed for controlling Reinforcing bar runs through the side wall of the second framework 3 vertically.
The second framework 3 is equipped with several first feed pipe fixing devices 4 and several second feed pipe fixing devices 5, The first feed pipe fixing device 4 is vertically arranged at 3 side-wall outer side of second framework, the second feed pipe fixing device 5 are vertically arranged at 3 inside sidewalls of second framework.
The hoisting mechanism include be symmetrically disposed on 1 side wall of the first framework the first side frame 8 and the second side frame 9, turn The dynamic shaft 10 being set between first side frame 8 and the second side frame 9, described 10 one end of shaft are pacified after passing through the first side frame 8 Equipped with driven wheel 14, the driven wheel 14 is sequentially connected by the driving wheel 19 on transmission belt 15 and 16 output shaft of driving motor, Two hoisting ropes 12 are wound in the shaft 10,12 free end of hoisting rope is connect with the second framework 3.
There are two plectanes 13, described 12 one end of hoisting rope to be fixedly connected with shaft 10 for setting in the shaft, the promotion 12 other ends of restricting are fixedly connected after passing through the plectane 13 with the second framework 3.
In the present embodiment, the second framework 3 can also be replaced using partition, the second frame when such as component being single side moulding Body 3 is just needed using partition.
In use, prefabricated mould 2 is fixed on 1 side wall inner surfaces of the first framework, second framework 3 is placed in first Inside framework 1, required vertical reinforcement is inserted into vertical reinforcement location hole 6, while being put into required transverse steel, decoration material is given It is fixed in expects pipe insertion the first feed pipe fixing device 4, it will be in concrete feed pipe insertion the second feed pipe fixing device 5 It is fixed, starting charging gear fills material requested by decoration material feed pipe and concrete feed pipe simultaneously, fills material It is vibrated when at second framework 2/3rds three by vibrating head, by layers of material shake to smooth, then starts driving motor 16, Second framework 3 is promoted, vibrating head is normally open when promotion, and material feeding is promoted to pause when need to put transverse steel position, is put into cross Continue after to reinforcing bar, it is synchronous with feeding coal to promote speed for control when promotion, promotes stopping promotion after material feeding to required position and gives Layers of material is shaken to smooth after vibrating head and second framework 3 is stopped to vibration after being lifted out completely in material again by material, is waited mixed The solidifying native and solidification of decoration material (such as 3 hours of steam-cured need) demoulding afterwards.
Embodiment 4: the difference of itself and embodiment 3 is that there are two the second frameworks 3 or more than two, for processing Form the component being made of a variety of materials.First framework 1 is round framework, and the corresponding second framework 3 is also circle (not shown), for processing cylindrical member.It of courses, the rule such as first framework 1 or T, L or irregular Special-shaped framework, the corresponding second framework 3 may be the regular or irregular special-shaped framework such as T, L, for processing T, L isotactic Then or irregularly abnormity component, the determines according to actual conditions shape of the first framework 1 and second framework 3.
Embodiment 5: as shown in Figure 5 and Figure 6, a kind of concrete and decoration expect synchronize pour Integral molding device for insoles, including it is upper First framework 1 of end opening, is set to first framework at the mould 2 for being set to 1 side wall inner surfaces of the first framework Layering dispenser inside 1 and be set to 1 top of the first framework for promoting the hoisting mechanism of the layering dispenser; The layering dispenser includes the second framework 3 of upper and lower ends opening, and the second framework 3 is equipped with several vertical reinforcements Positioning device.
Synchronize to pour Integral molding device for insoles further include shaking device 17 and inner template 18 for the concrete and decoration material, described Shaking device 17 is vibrating motor, and the shaking device 17 is set to 3 upper end of second framework (as shown in Figure 6) or the first frame The bottom wall outer (not shown) of body 1.The inner template 18 is set to inside the second framework 3, under the inner template 18 End be fixedly connected with the side wall of the first framework 1, the effect of the inner template 18 is to form cavity, cavity be in order to material-saving saving at This, can also be added the materials such as some sound insulations, fire prevention, draining, the wall for depending on needing to do whether setting of the inner template 18 Body thickness, general thickness of wall body (such as 30 centimeters or more), which is all compared, to be suitble to reserve cavity.
First framework 1 is square frame, and the corresponding second framework 3 is also square frame (such as Fig. 5 and Fig. 6), For processing wall body construction.
The vertical reinforcement positioning device is vertical reinforcement positioning pipe 7, and the vertical reinforcement positioning pipe 7 is vertically arranged at institute State 3 inside sidewalls of second framework.
The second framework 3 is equipped with several first feed pipe fixing devices 4 and several second feed pipe fixing devices 5, The first feed pipe fixing device 4 is vertically arranged at 3 side-wall outer side of second framework, the second feed pipe fixing device 5 are vertically arranged at 3 inside sidewalls of second framework.
The hoisting mechanism include be symmetrically disposed on 1 side wall of the first framework the first side frame 8 and the second side frame 9, turn The dynamic shaft 10 being set between first side frame 8 and the second side frame 9, described 10 one end of shaft are pacified after passing through the first side frame 8 Equipped with driven wheel 14, the driven wheel 14 is sequentially connected by the driving wheel 19 on transmission belt 15 and 16 output shaft of driving motor, Two hoisting ropes 12 are wound in the shaft 10,12 free end of hoisting rope is connect with the second framework 3.
There are two plectanes 13, described 12 one end of hoisting rope to be fixedly connected with shaft 10 for setting in the shaft, the promotion 12 other ends of restricting are fixedly connected after passing through the plectane 13 with the second framework 3.
In the present embodiment, the second framework 3 can also be replaced using partition, the second frame when such as component being single side moulding Body 3 is just needed using partition.
In use, prefabricated mould 2 is fixed on 1 side wall inner surfaces of the first framework, by prefabricated inner template 18 are fixed on 1 bottom wall inner surface of the first framework, and second framework 3 is placed in inside the first framework 1, required vertical reinforcement are inserted into vertical In reinforcing bar positioning pipe 7, while being put into required transverse steel, will decoration material feed pipe insertion first feed pipe fixing device 4 in into Row is fixed, and will be fixed in concrete feed pipe insertion the second feed pipe fixing device 5, starting charging gear passes through decoration material Feed pipe and concrete feed pipe fill material requested simultaneously, when filling material at second framework 2/3rds three, starting shock Then device 17 starts driving motor 16 by layers of material shake to smooth, promote second framework 3, and shaking device 17 is when promotion Normally open, material feeding are promoted to pause when need to put transverse steel position, are continued after being put into transverse steel, and control promotes speed when promotion , promotion material feeding to required position after stopping promotion and feed synchronous with feeding coal are spent, arrives layers of material shake to shaking device 17 It is smooth that second framework 3 is stopped to vibration after being lifted out completely in material again, wait concrete and decoration material solidification (such as steam-cured need 3 hours) it demoulds afterwards.
Embodiment 6: the difference of itself and embodiment 5 is that there are two the second frameworks 3 or more than two, for processing Form the component being made of a variety of materials.First framework 1 is round framework, and the corresponding second framework 3 is also circle (not shown), for processing cylindrical member.It of courses, the rule such as first framework 1 or T, L or irregular Special-shaped framework, the corresponding second framework 3 may be the regular or irregular special-shaped framework such as T, L, for processing T, L isotactic Then or irregularly abnormity component, the determines according to actual conditions shape of the first framework 1 and second framework 3.
Finally, it should be noted that the above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although Present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that: it still may be used To modify to technical solution documented by previous embodiment or equivalent replacement of some of the technical features;And These are modified or replaceed, the spirit and model of technical solution of the embodiment of the present invention that it does not separate the essence of the corresponding technical solution It encloses.

Claims (10)

1. a kind of concrete with decoration material synchronize pour Integral molding device for insoles, it is characterised in that: the first frame including upper end opening Body (1), the mould (2) for being set to the first framework (1) side wall inner surfaces are set to the first framework (1) inside Layering dispenser and be set to above first framework (1) for promoted it is described layering dispenser hoisting mechanism;Institute The second framework (3) that layering dispenser includes several upper and lower ends openings is stated, the second framework (3) is equipped with several vertical steels Muscle positioning device.
2. a kind of concrete according to claim 1 with decoration material synchronize pour Integral molding device for insoles, it is characterised in that: also Including shaking device (17), the shaking device (17) is set on the second framework (3) side wall or the bottom of the first framework (1) On the outside of wall.
3. a kind of concrete according to claim 1 with decoration material synchronize pour Integral molding device for insoles, it is characterised in that: institute Stating vertical reinforcement positioning device is vertical reinforcement location hole (6), and the vertical reinforcement location hole (6) runs through second frame vertically The side wall of body (3).
4. a kind of concrete according to claim 1 with decoration material synchronize pour Integral molding device for insoles, it is characterised in that: institute Stating vertical reinforcement positioning device is vertical reinforcement positioning pipe (7), and the vertical reinforcement positioning pipe (7) is vertically arranged at described second Framework (3) inside sidewalls.
5. a kind of concrete according to claim 1 with decoration material synchronize pour Integral molding device for insoles, it is characterised in that: institute It states second framework (3) and is equipped with several first feeds pipe fixing device (4) and several second feeds pipe fixing device (5), it is described First feed pipe fixing device (4) is vertically arranged at the second framework (3) side-wall outer side, the second feed pipe fixing device (5) second framework (3) inside sidewalls are vertically arranged at.
6. a kind of concrete according to claim 1 with decoration material synchronize pour Integral molding device for insoles, it is characterised in that: institute Stating hoisting mechanism includes that the first side frame (8) for being symmetrically disposed on the first framework (1) side wall and the second side frame (9), rotation are set The shaft (10) being placed between first side frame (8) and the second side frame (9), described shaft (10) one end pass through the first side frame (8) be equipped with after rocking handle (11), be wound with several hoisting ropes (12) on the shaft (10), hoisting rope (12) free end with Second framework (3) connection.
7. a kind of concrete according to claim 1 with decoration material synchronize pour Integral molding device for insoles, it is characterised in that: institute Stating hoisting mechanism includes that the first side frame (8) for being symmetrically disposed on the first framework (1) side wall and the second side frame (9), rotation are set The shaft (10) being placed between first side frame (8) and the second side frame (9), described shaft (10) one end pass through the first side frame (8) it is equipped with after driven wheel (14), the driven wheel (14) passes through the master on transmission belt (15) and driving motor (16) output shaft Driving wheel (19) is sequentially connected, and is wound with several hoisting ropes (12) on the shaft (10), hoisting rope (12) free end and institute State second framework (3) connection.
8. a kind of concrete according to claim 6 or 7 with decoration material synchronize pour Integral molding device for insoles, feature exists In: it is provided with several plectanes (13) on the shaft (10), described hoisting rope (12) one end is fixedly connected with shaft (10), described Hoisting rope (12) other end passes through the plectane (13) and is fixedly connected afterwards with the second framework (3).
9. a kind of concrete according to claim 1 with decoration material synchronize pour Integral molding device for insoles, it is characterised in that: also Including inner template (18), it is internal that the inner template (18) is set to the second framework (3), inner template (18) lower end and the The bottom wall of one framework (1) is fixedly connected.
10. a kind of concrete according to claim 1 with decoration material synchronize pour Integral molding device for insoles, it is characterised in that: First framework (1) is square frame, and the corresponding second framework (3) is also square frame or first framework It (1) is round framework, the corresponding second framework (3) is also round framework.
CN201910082532.7A 2019-01-28 2019-01-28 Synchronous pouring integrated device for concrete and decorative material Active CN109605568B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910082532.7A CN109605568B (en) 2019-01-28 2019-01-28 Synchronous pouring integrated device for concrete and decorative material

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910082532.7A CN109605568B (en) 2019-01-28 2019-01-28 Synchronous pouring integrated device for concrete and decorative material

Publications (2)

Publication Number Publication Date
CN109605568A true CN109605568A (en) 2019-04-12
CN109605568B CN109605568B (en) 2024-05-14

Family

ID=66017463

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910082532.7A Active CN109605568B (en) 2019-01-28 2019-01-28 Synchronous pouring integrated device for concrete and decorative material

Country Status (1)

Country Link
CN (1) CN109605568B (en)

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0673877A (en) * 1992-08-27 1994-03-15 East Japan Railway Co Moving type formwork used for concrete structure
RU2033510C1 (en) * 1993-06-30 1995-04-20 Юрий Алексеевич Белов Method for installation of monolithic multilayer wall structures from concrete mixes
KR200311957Y1 (en) * 2003-02-11 2003-05-09 조희수 The mold panel using as a concret wall
RU2288838C1 (en) * 2005-05-06 2006-12-10 Дмитрий Юрьевич Бузин Method of manufacture of the wall products made out of the light concretes with the facial finish layer and the products manufactured by this method
JP2009263893A (en) * 2008-04-22 2009-11-12 Aica Kogyo Co Ltd Concrete repair layer structure
CN102704643A (en) * 2012-06-20 2012-10-03 中国十七冶集团有限公司 Manufacturing method for rinsing exposed aggregate colorful concrete external-hung wallboard
CN205325929U (en) * 2015-12-09 2016-06-22 重庆飞强混凝土有限公司 Closely knit mould that fills of concrete layering
CN205935640U (en) * 2016-08-02 2017-02-08 驻马店市永泰建筑节能材料设备有限公司 -in -place mould , foam concrete self preservation temperature composite wall structure
CN107009509A (en) * 2017-05-15 2017-08-04 中冶建工集团有限公司 A kind of rain perforaled strainer preparation method
CN107882334A (en) * 2017-11-24 2018-04-06 黄淮学院 A kind of casting method with protective layer concrete filled steel tube
CN108824812A (en) * 2018-06-11 2018-11-16 贵州建工集团第建筑工程有限责任公司 A kind of cast-in-place fair-faced concrete wall pours and maintenance process
CN209887852U (en) * 2019-01-28 2020-01-03 卜旺杰 Concrete and decorative material pour integrated into one piece device in step

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0673877A (en) * 1992-08-27 1994-03-15 East Japan Railway Co Moving type formwork used for concrete structure
RU2033510C1 (en) * 1993-06-30 1995-04-20 Юрий Алексеевич Белов Method for installation of monolithic multilayer wall structures from concrete mixes
KR200311957Y1 (en) * 2003-02-11 2003-05-09 조희수 The mold panel using as a concret wall
RU2288838C1 (en) * 2005-05-06 2006-12-10 Дмитрий Юрьевич Бузин Method of manufacture of the wall products made out of the light concretes with the facial finish layer and the products manufactured by this method
JP2009263893A (en) * 2008-04-22 2009-11-12 Aica Kogyo Co Ltd Concrete repair layer structure
CN102704643A (en) * 2012-06-20 2012-10-03 中国十七冶集团有限公司 Manufacturing method for rinsing exposed aggregate colorful concrete external-hung wallboard
CN205325929U (en) * 2015-12-09 2016-06-22 重庆飞强混凝土有限公司 Closely knit mould that fills of concrete layering
CN205935640U (en) * 2016-08-02 2017-02-08 驻马店市永泰建筑节能材料设备有限公司 -in -place mould , foam concrete self preservation temperature composite wall structure
CN107009509A (en) * 2017-05-15 2017-08-04 中冶建工集团有限公司 A kind of rain perforaled strainer preparation method
CN107882334A (en) * 2017-11-24 2018-04-06 黄淮学院 A kind of casting method with protective layer concrete filled steel tube
CN108824812A (en) * 2018-06-11 2018-11-16 贵州建工集团第建筑工程有限责任公司 A kind of cast-in-place fair-faced concrete wall pours and maintenance process
CN209887852U (en) * 2019-01-28 2020-01-03 卜旺杰 Concrete and decorative material pour integrated into one piece device in step

Also Published As

Publication number Publication date
CN109605568B (en) 2024-05-14

Similar Documents

Publication Publication Date Title
CN101508144B (en) Concrete casting production technique with energy-saving environmental-protection function
CN105971166A (en) Novel formed steel frame gypsum board non-dismantling formwork
CN200954654Y (en) Multifunction automatic production-line for plaster light hollow wall-board and building brick
CN209482591U (en) Prefabricated molds shell structure column construction structure
CN104563282B (en) Integral constructing method of house body structure and wall structure and house
CN102433958A (en) Prefabricated wall board construction member
CN110000892A (en) A kind of production technology of prefabricated component stair
CN103669872A (en) Walling method and walling device
CN109605568A (en) A kind of concrete and decoration material synchronize pour Integral molding device for insoles
CN209887852U (en) Concrete and decorative material pour integrated into one piece device in step
CN207888889U (en) Prefabricated components integrated production line
CN206753086U (en) A kind of small-sized assembled architecture component hanging apparatus
CN103590515B (en) A kind of self-balancing precast surface, cast-in-place core filler wall
CN206287319U (en) A kind of production line of precast concrete
CN112177364A (en) Wall building device capable of automatically laying bricks
CN111421664A (en) High-efficiency concrete prefabricated part manufacturing equipment and manufacturing method
CN202689327U (en) Partition board with built-in light filler or built-in empty holes
CN203684687U (en) Walling device
CN205552818U (en) String is surely from carrying formula cutting machine
CN102312578B (en) Integral vibration-free pouring and constructing method
CN106914984A (en) A kind of construction method of prefabricated composite construction board
CN103741855B (en) A kind of preparation method of composite light noggin piece
CN203418621U (en) Building wallboard production machine
CN103758266B (en) A kind of light filling structure manufacture method
CN207177281U (en) A kind of fibre cement formwork system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant