CN109577989A - A kind of novel deeps mines shaft wall structure and construction method - Google Patents

A kind of novel deeps mines shaft wall structure and construction method Download PDF

Info

Publication number
CN109577989A
CN109577989A CN201811526090.2A CN201811526090A CN109577989A CN 109577989 A CN109577989 A CN 109577989A CN 201811526090 A CN201811526090 A CN 201811526090A CN 109577989 A CN109577989 A CN 109577989A
Authority
CN
China
Prior art keywords
layer
chemical pulp
liquid layer
wall structure
shaft wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811526090.2A
Other languages
Chinese (zh)
Other versions
CN109577989B (en
Inventor
李树忱
王鹏程
马鹏飞
周慧颖
王曼灵
支斌
赵世森
万泽恩
李阳
段壮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University
Original Assignee
Shandong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University filed Critical Shandong University
Priority to CN201811526090.2A priority Critical patent/CN109577989B/en
Publication of CN109577989A publication Critical patent/CN109577989A/en
Application granted granted Critical
Publication of CN109577989B publication Critical patent/CN109577989B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a kind of novel deeps mines shaft wall structure and construction methods, including multilayer, it is successively concrete lining course and anchor note composite layer from inside to outside, it is successively to reinforce chemical pulp liquid layer and cement slurry liquid layer outward that the anchor, which infuses composite layer from shaft wall structure,;So that script is the Sidewall Surrounding Rock in load source after grouting and reinforcing, as a part of bearing structure, carried jointly with concrete lining.Anchor note complex gives full play to country rock self-bearing capacity, and structure efficiency is high;Foam filling layer shock resistance load.The complicated bad border of deep underground engineering can be preferably applicable in.

Description

A kind of novel deeps mines shaft wall structure and construction method
Technical field
The present invention relates to a kind of new supporting structures, and in particular to a kind of novel deeps mines shaft wall structure and construction Method.
Technical background
With the reduction of superficial part resource, domestic and international mine all subsequently enters deep resource mining state.It is opened from Chinese Resources From the point of view of adopting, decades lasting extensive resource exploitation makes superficial part mineral resources tend to be exhausted, mining mineral resource by Stepping enters 1000~2000m with deep level.Proposed in " " 13 " national science and technology innovation planning " " deep space, deep-sea, deep ground, It is dark blue " four deep strategies, the significance level of deep ground engineering is mentioned into the status same with aerospace engineering.Large-scale mineral reserve exploitation with The steady implementation of deep ground strategy brings a large amount of deep engineering construction, but deep formation has high-ground stress, High-geotemperature, height Permeate the special engineerings geological conditions such as hydraulic pressure.
Deep engineering crustal stress is high, and there are bumps.Traditional excavation and Lining Technique is difficult to meet deep vertical shaft Engineering construction requirement.Existing 600m~1000m with the deep basic full section drill burst method construction of deep shaft, single cycle drilling depth 2m with It is interior, steel and concrete structure support.But as depth increases, crustal stress increases, and the lining thickness of design requirement is also increasing, so that Influence the economy and applicability of deep shaft construction.And construction speed is slow, the duration is longer.When encountering bump, tradition branch Protection structure adaptibility to response is insufficient, cannot resist the rock blast hazards such as rock burst.The presence of these problems, that is, radiography rings construction progress, There is higher risk again.
Summary of the invention
In order to solve the technical problems existing in the prior art, the invention discloses a kind of novel deeps mines shaft walls Structure.
The present invention is achieved by the following technical solutions:
A kind of novel deeps mines shaft wall structure, including multilayer, are successively concrete lining course and anchor from inside to outside Composite layer is infused, it is successively to reinforce chemical pulp liquid layer and superfine cement slurry layer outward that the anchor, which infuses composite layer from shaft wall structure,; The complete penetration reinforcement chemical pulp liquid layer of the cement slurry liquid layer;So that being originally the Sidewall Surrounding Rock in load source in grouting and reinforcing Afterwards, it as a part of bearing structure, is carried jointly with concrete lining.
It further, is foaming water blockoff chemical pulp between the reinforcing chemical pulp liquid layer and the concrete lining course Liquid layer.
Further, foam filling layer is additionally provided between the anchor note composite layer and concrete lining course.
Further, the foam filling layer is poured using foamed concrete material, that is, has certain anti-impact Ground pressure energy power is hit, and there is good drainage.
Further, the thickness of the foaming water blockoff chemical pulp liquid layer, reinforcing chemical pulp liquid layer and cement slurry liquid layer closes System is: being followed successively by superfine cement slurry layer thickness > foaming water blockoff chemical pulp liquid layer thickness > reinforcing chemical pulp liquid layer thickness;It is described Superfine cement slurry layer permeate entire foaming water blockoff chemical pulp liquid layer completely and reinforce chemical pulp liquid layer, the reinforcing chemistry Slurry layer is set to the position of the close concrete lining course of foaming water blockoff chemical pulp liquid layer.
Proximal end infuses rear for blocking the dynamic water in crack using foamed material using foaming water blockoff chemical pulp liquid layer The superfine cement material of slurry is not easy washout, and provides skeleton for the reinforcement material that next step reinforces chemical pulp liquid layer;Reinforce chemistry The reinforcement material of slurry layer fills, so it reinforces chemical pulp liquid layer for reinforcing proximal end country rock in the gap of foamed material Thickness be less than foaming water blockoff chemical pulp liquid layer thickness;Distally material reinforced range is maximum, considers economy and applicability, adopts Slip casting, which is carried out, with superfine cement forms superfine cement slurry layer.
This thickness be after concrete lining calculate.It is not self-existent between every layer, but be overlapped mutually 's.
Further, the foamed material selects silicate foamed material.
Further, the reinforcement material selects strengthening of silicate material.
Further, the concrete lining is logical uses plain concrete, sets up ingate or stratum and is relatively crushed distinguishingly Armored concrete can be used in section, and construction is using conventional construction of concrete lining method, but concrete-lined thickness is able to Greatly reduce.
The construction of the construction method of novel deeps mines shaft wall structure in the present invention, the anchor note composite layer uses Anchor pole carries out slip casting.
Common grouted anchor bar can be used in the anchor pole, preferably uses energy absorbing type grouted anchor bar.
The anchor infuses compound body construction, and the reinforcing of stratum crushing section can be used anchor pole cooperation steel mesh and be reinforced.
Beneficial effects of the present invention:
Anchor is formed by the united system slip casting of more materials and infuses complex, is strengthened a certain range of around Sidewall Surrounding Rock Breaking surrounding rock.Originally it is the breaking surrounding rock in load source, becomes complete structure by reinforcing, the ability with bearing load, from And country rock self-bearing capacity is given full play to, structure efficiency is high;Foam filling layer belongs to yield supporting structure, it allows biggish change Shape can effectively absorb energy, therefore can be with shock resistance load.The complicated bad border of deep underground engineering can be preferably applicable in.
Detailed description of the invention
The accompanying drawings constituting a part of this application is used to provide further understanding of the present application, and the application's shows Meaning property embodiment and its explanation are not constituted an undue limitation on the present application for explaining the application.
Fig. 1 is that the composite shaft lining structural schematic diagram come is disclosed in one or more embodiment;
Fig. 2 is novel deep shaft support structural facades figure;
Fig. 3 is the structural relation figure for anchoring composite layer;
1 traditional borehole wall supporting in figure, 2 concrete lining courses, 3 foam filling layers, 4 anchoring composite layers, 4-1 reinforce chemical pulp Liquid layer, 4-2 foaming water blockoff chemical pulp liquid layer, 4-3 superfine cement slurries, 5 unguyed fragmented rock bodies, 6 bolt grouting pipes, 7 anchor poles.
Specific embodiment
It is noted that following detailed description is all illustrative, it is intended to provide further instruction to the application.Unless another It indicates, all technical and scientific terms used herein has usual with the application person of an ordinary skill in the technical field The identical meanings of understanding.
It should be noted that term used herein above is merely to describe specific embodiment, and be not intended to restricted root According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singular Also it is intended to include plural form, additionally, it should be understood that, when in the present specification using term "comprising" and/or " packet Include " when, indicate existing characteristics, step, operation, device, component and/or their combination;
As background technique is introduced, it is high that deep engineering crustal stress exists in the prior art, and there are bumps.It passes The excavation and Lining Technique of system are difficult to meet deep work shaft construction requirement.Existing 600m~1000m is with deep deep shaft Basic full section drill burst method is constructed, within single cycle drilling depth 2m, steel and concrete structure support.But as depth increases, crustal stress increases Greatly, the lining thickness of design requirement is also increasing, so that influence the economy and applicability of deep shaft construction.And construction speed Slowly, the duration is longer.When encountering bump, traditional supporting construction adaptibility to response is insufficient, cannot resist the bumps such as rock burst Disaster.The presence of these problems, that is, radiography rings construction progress, and has higher risk, in order to solve technical problem as above, this Application proposes a kind of novel deeps mines shaft wall structure and construction method.
Embodiment 1:
As shown in Figure 1, country rock is more complete when country rock Burst Tendency is higher, front water content stratum item abundant is excavated Under part, the deep shaft supporting construction of use is respectively as follows: anchor note composite layer 4, foam filling layer 3 and plain concrete from outside to inside Lining cutting layer 2;Anchor infuses complex from shaft wall structure successively outward by shallow and deep, divides sequence using foaming water blockoff chemical grout, adds Gu chemical grout and superfine cement slurries carry out slip casting.So that script is the Sidewall Surrounding Rock in load source after grouting and reinforcing, make For a part of bearing structure, carried jointly with concrete lining.
Wherein anchor infuses compound body construction and uses bolt grouting;Common grouted anchor bar can be used in anchor pole, preferably uses energy-absorbing Type grouted anchor bar.
The foamed material of foaming water blockoff chemical pulp liquid layer is quickly truncated and blocks dynamic water for foaming, be next step silicic acid Salt reinforcement material provides skeleton, improves retention ratio for subsequent superfine cement slurries slip casting, the gas of generation also helps subsequent note The sub-percolation again of slurry.
The reinforcement material for reinforcing chemical pulp liquid layer is used to reinforce proximal end country rock, fills in the gap of foamed material, so Its thickness for reinforcing chemical pulp liquid layer is less than the thickness of foaming water blockoff chemical pulp liquid layer;
The superfine cement slurries of superfine cement slurry layer are for reinforcing distal end country rock.Distally material reinforced range is maximum, examines Consider economy and applicability, slip casting is carried out using superfine cement and forms superfine cement slurry layer.
Foaming water blockoff chemical pulp liquid layer 4-2, the thickness relationship for reinforcing chemical pulp liquid layer 4-1 and cement slurry liquid layer 4-3 are: according to Secondary is superfine cement slurry layer thickness > foaming water blockoff chemical pulp liquid layer thickness > reinforcing chemical pulp liquid layer thickness;The ultra-fine water Mud liquid layer permeates entire foaming water blockoff chemical pulp liquid layer completely and reinforces chemical pulp liquid layer, and the reinforcing chemical pulp liquid layer is set It is placed in the position of the close concrete lining course of foaming water blockoff chemical pulp liquid layer.
Foam water blockoff chemical pulp liquid layer, reinforce chemical pulp liquid layer, superfine cement slurry layer thickness be from concrete lining Start calculation afterwards.It is not self-existent between every layer, but be overlapped mutually.Specific relationship is anchor as shown in Figure 3 Gu number is divided into three layers to three layers of composite layer from left to right, the thickness and relationship of each layer are respectively labeled as reinforcing chemical pulp liquid layer 4-1, Foam water blockoff chemical pulp liquid layer 4-2, superfine cement slurry layer 4-3, it is through persilicate foamed material slip casting first, and range is hair The region that bubble water blockoff chemical pulp liquid layer 4-2 is covered, followed by strengthening of silicate material slip casting, range are to reinforce chemical pulp liquid layer The region that 4-1 is covered, is finally superfine cement slip casting, and range is the region that superfine cement slurry layer 4-3 is covered.
It is further preferred that foamed material selects silicate foamed material.
It is further preferred that the reinforcement material selects strengthening of silicate material.
Foam filling layer 3 allows biggish deformation, can effectively absorb energy, poured using foamed concrete material and At, that is, with having certain shock resistance pressure energy power, and there is good drainage.
The effect of plain concrete lining cutting layer 6 is primarily to provide supporting.
Anchor pole cooperation steel mesh can be used to use for stratum crushing section in figure.
The construction that anchor infuses composite layer uses bolt grouting;Common grouted anchor bar can be used in anchor pole, preferably uses energy absorbing type Grouted anchor bar;Specific grouting method is first slip casting foaming water blockoff chemical pulp liquid layer, then grouting and reinforcing chemical pulp liquid layer, finally Slip casting superfine cement slurry layer.
Embodiment 2
As shown in Fig. 2, the small section construction of buried depth, can not construct foam filling layer, simultaneously when bump-prone property is low Country rock is relatively broken, excavates front water content and enriches, and deep shaft supporting construction is respectively as follows: anchor note 4 He of composite layer from outside to inside The solidifying native lining cutting layer 2 of reinforcing bar;Anchor infuses composite layer 4 from shaft wall structure successively outward by shallow and deep, and sequence is divided to use the water blockoff that foams It learns slurries, reinforce chemical grout and the progress slip casting of superfine cement slurries.So that being originally the Sidewall Surrounding Rock in load source in slip casting After reinforcing, as a part of bearing structure, carried jointly with concrete lining.
Wherein the construction of anchor note composite layer uses bolt grouting;Common grouted anchor bar can be used in anchor pole, preferred using suction Energy type grouted anchor bar, specific implementation method are same as Example 1.
It is same as Example 1 that anchor infuses effect, mutual thickness relationship of each section of composite layer 4 etc..
The difference of the embodiment 1 and embodiment 1 is the plain concrete lining cutting layer 2 in embodiment 1 being modified as steel The solidifying native lining cutting layer 2 of muscle, eliminates foam filling layer 3.
Embodiment 3:
Country rock Burst Tendency is higher, and country rock is more complete, excavates under the less formation condition of front water content, the depth of use Shaft support structure is respectively as follows: anchor note composite layer 4 from outside to inside, and (composite layer 4 is including reinforcing chemical pulp liquid layer and commonly Cement grout grouting and reinforcing layer eliminates foaming water blockoff chemical pulp liquid layer), foam filling layer 3 and plain concrete lining cutting layer 26;Anchor Composite layer 4 is infused from shaft wall structure successively outward by shallow and deep, divide sequence using reinforcing chemical grout and superfine cement slurries into Row slip casting.So that script is the Sidewall Surrounding Rock in load source after grouting and reinforcing, as a part of bearing structure, with concrete Lining cutting carries jointly.
Wherein the construction of anchor note composite layer 4 uses bolt grouting;Common grouted anchor bar can be used in anchor pole, preferred using suction It can type grouted anchor bar.
The foam filling layer 2, is poured using foamed concrete material, that is, with having certain shock resistance pressure energy Power, and there is good drainage.
Reinforce embodiment and thickness relationship of chemical pulp liquid layer and ordinary cement slurry liquid grout reinforcing layer etc. and implementation Reinforcing chemical pulp liquid layer in example 1 is identical with superfine cement slurry layer, only by the material of the superfine cement slurry layer in embodiment 1 Material has been substituted for ordinary cement slurries.
The foregoing is merely preferred embodiment of the present application, are not intended to limit this application, for the skill of this field For art personnel, various changes and changes are possible in this application.Within the spirit and principles of this application, made any to repair Change, equivalent replacement, improvement etc., should be included within the scope of protection of this application.

Claims (10)

1. a kind of novel deeps mines shaft wall structure, which is characterized in that be successively concrete lining from inside to outside including multilayer Course and anchor infuse composite layer, and it is successively to reinforce chemical pulp liquid layer and cement grout outward that the anchor, which infuses composite layer from shaft wall structure, Layer;The complete penetration reinforcement chemical pulp liquid layer of the cement slurry liquid layer.
2. novel deeps mines shaft wall structure as described in claim 1, which is characterized in that in the reinforcing chemical pulp It is foaming water blockoff chemical pulp liquid layer between liquid layer and the concrete lining course.
3. novel deeps mines shaft wall structure as claimed in claim 2, which is characterized in that the foaming water blockoff chemistry The thickness relationship of slurry layer, reinforcing chemical pulp liquid layer and cement slurry liquid layer is: superfine cement slurry layer thickness > foaming water blockoff chemistry Slurry layer thickness > reinforcing chemical pulp liquid layer thickness;The superfine cement slurry layer permeates entire foaming water blockoff chemical pulp completely Liquid layer and reinforcing chemical pulp liquid layer, the reinforcing chemical pulp liquid layer are set to the close concrete of foaming water blockoff chemical pulp liquid layer The position of lining cutting layer.
4. novel deeps mines shaft wall structure as claimed in claim 3, which is characterized in that the foamed material selection Silicate foamed material.
5. novel deeps mines shaft wall structure as claimed in claim 3, which is characterized in that the reinforcement material selection Strengthening of silicate material.
6. novel deeps mines shaft wall structure as described in claim 1, which is characterized in that infuse composite layer in the anchor Foam filling layer is additionally provided between concrete lining course.
7. novel deeps mines shaft wall structure as claimed in claim 6, which is characterized in that the foam filling layer makes It is poured with foamed concrete material into.
8. novel deeps mines shaft wall structure as described in claim 1, which is characterized in that the concrete lining course is logical Using plain concrete, setting up the more broken Special zone of ingate or stratum can be used armored concrete.
9. the construction method of novel deeps mines shaft wall structure a method as claimed in any one of claims 1-8, which is characterized in that institute The construction for the anchor note composite layer stated is using bolt grouting.
10. construction method as claimed in claim 9, which is characterized in that the anchor pole uses common grouted anchor bar or suction It can type grouted anchor bar.
CN201811526090.2A 2018-12-13 2018-12-13 Novel deep mine shaft wall structure and construction method Active CN109577989B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811526090.2A CN109577989B (en) 2018-12-13 2018-12-13 Novel deep mine shaft wall structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811526090.2A CN109577989B (en) 2018-12-13 2018-12-13 Novel deep mine shaft wall structure and construction method

Publications (2)

Publication Number Publication Date
CN109577989A true CN109577989A (en) 2019-04-05
CN109577989B CN109577989B (en) 2020-08-25

Family

ID=65928510

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811526090.2A Active CN109577989B (en) 2018-12-13 2018-12-13 Novel deep mine shaft wall structure and construction method

Country Status (1)

Country Link
CN (1) CN109577989B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110145313A (en) * 2019-05-27 2019-08-20 中国恩菲工程技术有限公司 It is adapted to the vertical shaft composite supporting construction of mine deep stratum and high stress areas
CN110424968A (en) * 2019-07-04 2019-11-08 北京科技大学 A kind of pit shaft reinforcement means based on anchor note anti-corrosion measure
CN113202480A (en) * 2021-06-16 2021-08-03 中国矿业大学 Combined bearing double-layer well wall and construction method thereof
WO2022032862A1 (en) * 2020-08-14 2022-02-17 中煤建设集团有限公司 Multi-layer functional gradient vertical shaft wall structure and construction process therefor
CN117388440A (en) * 2023-10-23 2024-01-12 中国矿业大学 Device and method for grouting process test and effect detection between double-layer well walls

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103174428A (en) * 2013-03-15 2013-06-26 金川集团股份有限公司 Method of implementing grouting and water plugging of shaft through chemical grout
CN206246122U (en) * 2016-10-18 2017-06-13 中国矿业大学 The system of the preventing and treating coal mine shaft lining shaft deformation destruction of stratum settlement compatibility of deformation
CN207377561U (en) * 2017-07-25 2018-05-18 马钢(集团)控股有限公司 The bad water-bearing layer positioning targeting slip casting Mine Shaft Lining of rock section and constructing device
CN108119143A (en) * 2017-12-20 2018-06-05 湖南科技大学 A kind of vertical shaft working surface cement soluble glass paste combines grouting method with chemical grout double-round curtain
CN108119144A (en) * 2017-12-19 2018-06-05 湖南科技大学 A kind of different restoring and fastening methods based on the classification of shaft wall fracture degree
CN108915735A (en) * 2018-06-21 2018-11-30 安徽理工大学 Slopes wall construction method for supporting and slopes wall support system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103174428A (en) * 2013-03-15 2013-06-26 金川集团股份有限公司 Method of implementing grouting and water plugging of shaft through chemical grout
CN206246122U (en) * 2016-10-18 2017-06-13 中国矿业大学 The system of the preventing and treating coal mine shaft lining shaft deformation destruction of stratum settlement compatibility of deformation
CN207377561U (en) * 2017-07-25 2018-05-18 马钢(集团)控股有限公司 The bad water-bearing layer positioning targeting slip casting Mine Shaft Lining of rock section and constructing device
CN108119144A (en) * 2017-12-19 2018-06-05 湖南科技大学 A kind of different restoring and fastening methods based on the classification of shaft wall fracture degree
CN108119143A (en) * 2017-12-20 2018-06-05 湖南科技大学 A kind of vertical shaft working surface cement soluble glass paste combines grouting method with chemical grout double-round curtain
CN108915735A (en) * 2018-06-21 2018-11-30 安徽理工大学 Slopes wall construction method for supporting and slopes wall support system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张飞龙 等: "注浆技术在立井井筒维修中的应用", 《神华科技》 *
郑翠敏等: "复杂地质条件下副井施工防治水技术和工艺实践", 《黄金》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110145313A (en) * 2019-05-27 2019-08-20 中国恩菲工程技术有限公司 It is adapted to the vertical shaft composite supporting construction of mine deep stratum and high stress areas
CN110424968A (en) * 2019-07-04 2019-11-08 北京科技大学 A kind of pit shaft reinforcement means based on anchor note anti-corrosion measure
CN110424968B (en) * 2019-07-04 2020-07-17 北京科技大学 Shaft reinforcing method based on anchoring and grouting anti-corrosion measures
WO2022032862A1 (en) * 2020-08-14 2022-02-17 中煤建设集团有限公司 Multi-layer functional gradient vertical shaft wall structure and construction process therefor
CN113202480A (en) * 2021-06-16 2021-08-03 中国矿业大学 Combined bearing double-layer well wall and construction method thereof
CN117388440A (en) * 2023-10-23 2024-01-12 中国矿业大学 Device and method for grouting process test and effect detection between double-layer well walls

Also Published As

Publication number Publication date
CN109577989B (en) 2020-08-25

Similar Documents

Publication Publication Date Title
CN109577989A (en) A kind of novel deeps mines shaft wall structure and construction method
CN204552747U (en) A kind of coal mine shaft lining shaft wall structure
CN103089275B (en) Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN105041325A (en) Construction method of high-tension water-rich extra-large-section weak breccia tunnel
CN108798702B (en) Supporting method for large-section soft rock large-deformation tunnel
CN102758642A (en) Long-span tunnel overlapping carrying arch structure for upper-soft and lower-hard stratum and construction method thereof
CN103898916B (en) Mini stake Composite Braced Retaining Structure and construction method
CN103291305B (en) Quick and low-cost artificial fake roof construction method for ground mine
CN101709651A (en) Grouting water blocking method for undersea tunnel
CN105781573A (en) Railway down-traversing highway tunnel double-layer casing pipe reinforcement double-pipe shed follow-pipe drilling construction method
CN211258623U (en) Water-rich weak surrounding rock tunnel supporting system crossing fault fracture zone
CN103233751A (en) Double-layer anchoring and balancing arch supporting system for coal roadway with extremely-weak top plates
CN107965341A (en) A kind of large-section underground pipe canopy pipe network concrete support method
CN109595029A (en) Goaf partial stowage supporting structure and its construction method under the conditions of tight roof
CN103362117A (en) Full-section grouting method for grouting section
CN108374672B (en) A method of reinforcing Deep Mine soft coal level roadway surrounding rock
CN107642041A (en) The hollow clump of piles anchorage of super-large diameter
CN107605509A (en) Sand-pebble layer small curve radius shallow tunnel subsurface excavation method advanced supporting construction method
CN109209443A (en) A kind of construction method of breaking surrounding rock tunnel structure
CN205225280U (en) A combined supporting structure that is used for steel -pipe pile bar planting tunnel composite lining of soft base
CN103939115A (en) Semi-subsurface excavation method construction shed tunnel method and structure
CN207513614U (en) Shallow tunnel subsurface excavation method advance support structure and combined type advanced tubule
CN104863613B (en) Rocky stratum tunneling underground structure flash joist anchor draws just branch structure and construction method
CN207484290U (en) The hollow clump of piles anchorage of super-large diameter
Tian et al. Study on the deformation failure mechanism and coupling support technology of soft rock roadways in strong wind oxidation zones

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant