CN109559054A - A kind of Phase of Electric Power Projects information processing system - Google Patents

A kind of Phase of Electric Power Projects information processing system Download PDF

Info

Publication number
CN109559054A
CN109559054A CN201811476080.2A CN201811476080A CN109559054A CN 109559054 A CN109559054 A CN 109559054A CN 201811476080 A CN201811476080 A CN 201811476080A CN 109559054 A CN109559054 A CN 109559054A
Authority
CN
China
Prior art keywords
phase
electric power
information
power projects
projects
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811476080.2A
Other languages
Chinese (zh)
Other versions
CN109559054B (en
Inventor
韩冰
张道金
于克林
张玉杰
刘长青
李爱丽
程晓晗
苏骞
颜景龙
刘丹烨
高伟
李德生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Shandon Province Electrical Power Co Wuli County Power Supply Co
Original Assignee
State Grid Shandon Province Electrical Power Co Wuli County Power Supply Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Shandon Province Electrical Power Co Wuli County Power Supply Co filed Critical State Grid Shandon Province Electrical Power Co Wuli County Power Supply Co
Priority to CN201811476080.2A priority Critical patent/CN109559054B/en
Publication of CN109559054A publication Critical patent/CN109559054A/en
Application granted granted Critical
Publication of CN109559054B publication Critical patent/CN109559054B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0637Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06395Quality analysis or management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/02Marketing; Price estimation or determination; Fundraising
    • G06Q30/0201Market modelling; Market analysis; Collecting market data
    • G06Q30/0206Price or cost determination based on market factors
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Development Economics (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Educational Administration (AREA)
  • Tourism & Hospitality (AREA)
  • Accounting & Taxation (AREA)
  • Finance (AREA)
  • Game Theory and Decision Science (AREA)
  • Health & Medical Sciences (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Data Mining & Analysis (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention provides a kind of Phase of Electric Power Projects information processing system, configures system-based data processing process, configures distributed processing mode, the Phase of Electric Power Projects information base data of processing input Phase of Electric Power Projects information early period to Phase of Electric Power Projects basic information;Systematic procedure data processing process is configured, distributed processing mode is configured to Phase of Electric Power Projects procedural information, obtains, integration, collects Phase of Electric Power Projects procedural information;Configuration system completion data processing process obtains, integration to Phase of Electric Power Projects completion information configuration distributed processing mode, collects Phase of Electric Power Projects completion information.A variety of task parallelisms execute, and avoid conflicting with each other, realize Phase of Electric Power Projects data processing and storage.Multistage segment data while synchronous progress data processing are realized, multi-party transmission is realized, it is multi-party to survive, it extracts and uses.The problems such as avoiding that save data time long, extracting that data time is long, and processing data time is long etc., provides data-handling efficiency.

Description

A kind of Phase of Electric Power Projects information processing system
Technical field
The present invention relates to power engineering monitoring field more particularly to a kind of Phase of Electric Power Projects information processing systems.
Background technique
With the rapid growth of China's economy, the trend of rapid growth is presented in electric power construction projects, and how this is just to doing well More stringent requirements are proposed for electric power construction projects management.Electric power construction projects are from being designed into a series of rings such as buying, manufacture, installation The progress of section, quality management, which just become, ensures that power equipment and electric power are built in electric power construction projects and electric power construction projects If each partitioned project in project, the completion on schedule of each subdivisional work, may insure entire construction speed and quality in this way.
In practice, some systems of Phase of Electric Power Projects information or program software are capable of providing is believed based on Phase of Electric Power Projects The processing of breath, storage, so as to the retention to construction information, for subsequent use.But since Phase of Electric Power Projects information is complicated, and And data information by sending in many ways, and it is multi-party to survive, it extracts and uses.It will cause system processes data overlong time in this way, that is, save The problems such as data time is long, and extraction data time is long, processing data time length etc. be normally carried out data can not using influence The use of Phase of Electric Power Projects information.
Summary of the invention
In order to overcome the deficiencies in the prior art described above, the present invention provides a kind of Phase of Electric Power Projects information processing system, It include: basic data processing scheduler module, process data processing scheduler module and completion data processing scheduler module;
Basic data processing scheduler module matches Phase of Electric Power Projects basic information for configuring system-based data processing process Set distributed processing mode, the Phase of Electric Power Projects information base data of processing input Phase of Electric Power Projects information early period;
Process data processing scheduler module matches Phase of Electric Power Projects procedural information for configuring systematic procedure data processing process Distributed processing mode is set, obtains, integration, collects Phase of Electric Power Projects procedural information;
Completion data processing scheduler module matches Phase of Electric Power Projects completion information for configuring system completion data processing process Distributed processing mode is set, obtains, integration, collects Phase of Electric Power Projects completion information.
Preferably, basic data processing scheduler module is also used to obtain the basic data of Phase of Electric Power Projects, electric power of equipment The profile data of route line and Phase of Electric Power Projects, power engineering place on line, power engineering cloth bar position, power engineering are drawn Line position, power engineering earthing position, power engineering family table information, power engineering service conductor information, power engineering wall load information, Power engineering electricity box information, cable passage, cable duct information, cable markup information and low-voltage platform area placement information form electricity Power engineering construction design drawing, and modification is provided, it inquires, increases port newly;
It is also used to obtain the design scheme of power construction information, power equipment contract information and power equipment construction information carry out It is corresponding, it forms power equipment construction information design data and manages library, store to the design data storage area of database;
The additions and deletions for also providing for power equipment construction contract, which change, looks into port, collects to each power equipment construction contract, Power equipment construction information and power engineering project information are corresponded, forms contract management library, and provide to each electricity Contract inputting, contract editor, change to the contract and the contract of power equipment construction Project contract inquire port;
It is also used to obtain power equipment project under construction project verification information, information on bidding, bid information and contract information, and will be above-mentioned Information is stored to the basic information storage area of database;
It is also used to obtain the essential information of power equipment to be onstructed, essential information includes: power equipment signal, and power equipment is used On the way, power equipment function, power equipment fundamental importance, power equipment construction technology information, power equipment mounting process, electric power are set Standby debud mode;The essential information of power equipment to be onstructed is stored to the basic information storage area of database;It is also used to obtain The title material information of power equipment work progress and the dosage information of each title material, above- mentioned information are stored to data The basic information storage area in library.
Preferably, process data processing scheduler module also provide for Phase of Electric Power Projects information read procedure data processing into Journey and process data processing process is write, and read procedure data processing process and to write process data processing process be parallel processing Process;
It is also used to provide the process examination and approval procedure information processing process obtained in work progress, process inspection based on keyword extraction Survey backlog information treatment progress, procedural image information processing process and procedure file information processing process, and by above- mentioned information It is stored by writing process data processing process to the process storage area of database;
It is also used to based on each power equipment project under construction predetermined period information processing process of keyword extraction;It is mentioned based on keyword It takes and obtains the default monitoring point information processing process of each progress in project predetermined period.
Preferably, process data processing scheduler module also provides for multiport writing based on Phase of Electric Power Projects information Number of passes is according to treatment progress, carries out by Phase of Electric Power Projects information writing system, and to the Phase of Electric Power Projects information of writing system Storage, analysis and processing.
Preferably, completion data processing scheduler module also provide for power engineering completion read procedure data processing process with And it is completed and writes process data processing process, and completion read procedure data processing process and be completed and write process data processing process and be Parallel processing process;
Be also used to obtain power equipment completion information, completion write process data processing process by power equipment completion information store to The completion storage area of database;Completion writes process data processing process and is also used to return the power equipment project under construction of completion Collection arranges, and generates final acceptance of construction report;
Be also used to obtain power equipment settlement information, completion write process data processing process by power equipment settlement information store to The clearing storage area of database.
Preferably, process data processing scheduler module is also used to monitor the operation data of Phase of Electric Power Projects equipment, and with Threshold value is compared;The environmental data of Phase of Electric Power Projects is monitored, and is compared with threshold value;It is related to monitor Phase of Electric Power Projects Demographic data's position data and healthy data monitor Phase of Electric Power Projects video data, monitor Phase of Electric Power Projects vehicle Operation data, and be compared with threshold value;
It is also used to analyze above-mentioned data mode, when a certain data or a few a data superthresholds, issues warning note;
It is also used to configuration surroundings data analysis curve, construction speed curve and construction speed network analysis chart.
Preferably, process data processing scheduler module is also used to obtain working as multiple Phase of Electric Power Projects project management assessments Initial assessment data are assessed in preceding data parameters and Phase of Electric Power Projects project management, execute risk variance analysis, are also based on The identical Phase of Electric Power Projects project management state pre-existed executes risk variance analysis;
It is also used to establish Phase of Electric Power Projects test point quality grade of evaluation mechanism, realizes multiple Phase of Electric Power Projects project managements In equivalent parameter, based on parameter preset and formerly existing identical Phase of Electric Power Projects item argument execution detects point mass Grade evaluates mechanism;
By each parameter of each Phase of Electric Power Projects project of evaluation analysis, with each Phase of Electric Power Projects item argument of determination Meet the current quality levels of quality requirement and each Phase of Electric Power Projects project.
Preferably, process data processing scheduler module is also used to during Phase of Electric Power Projects, tracking, monitoring electric power work Journey construction executive condition, carries out summarizing system to the payment of Phase of Electric Power Projects total packet subcontract and Phase of Electric Power Projects cost Meter;
By to currently having carried out Phase of Electric Power Projects cost payout Information Statistics, comparative analysis Phase of Electric Power Projects objective cost With the presence or absence of deviation;
If there is no costvariation, then continue to track, and monitors Phase of Electric Power Projects project and generated cost;
There is deviation as Phase of Electric Power Projects project has generated cost, then calls Phase of Electric Power Projects project to generate cost and be biased Row variance analysis;
It finds out Phase of Electric Power Projects project and the key factor of deviation occurs, pass through inventory, the amount of labour used, equipment machine-team and engineering Progress amount carries out data analysis and shows, use for reference.
Phase of Electric Power Projects project correction data are obtained, according to Phase of Electric Power Projects project correction data, adjust electric power work Journey construction project cost plan;
It is also used to analyze Phase of Electric Power Projects project cost trend according to Phase of Electric Power Projects Project Cost Plan;Root Work meter is determined according to Phase of Electric Power Projects project cost budget adjustment result and Phase of Electric Power Projects project cost budget adjustment It draws.
As can be seen from the above technical solutions, the invention has the following advantages that
The present invention provides basic data processing scheduler module, process data processing scheduler module and completion data processing process Module.Different operating period, different construction stages are based on progress and quality requirement by system, and based on different function, or Multiple stage computers are used in construction to connect by communication network, under the unified management control of system, are completed in phase Extensive information handling task.
A variety of task parallelisms execute in the present invention, avoid conflicting with each other, realize Phase of Electric Power Projects data processing and storage It deposits.
Multistage segment data while synchronous progress data processing are realized, realizes multi-party transmission, multi-party to survive, extraction makes With.The problems such as avoiding that save data time long, extracting that data time is long, and processing data time is long etc., provides data processing effect Rate.
Detailed description of the invention
In order to illustrate more clearly of technical solution of the present invention, attached drawing needed in description will be made below simple Ground introduction, it should be apparent that, drawings in the following description are only some embodiments of the invention, for ordinary skill For personnel, without creative efforts, it is also possible to obtain other drawings based on these drawings.
Fig. 1 is Phase of Electric Power Projects information processing system overall schematic;
Fig. 2 is Phase of Electric Power Projects information processing system embodiment schematic diagram.
Specific embodiment
It in order to make the invention's purpose, features and advantages of the invention more obvious and easy to understand, below will be with specific Examples and drawings, the technical solution protected to the present invention are clearly and completely described, it is clear that implementation disclosed below Example is only a part of the embodiment of the present invention, and not all embodiment.Based on the embodiment in this patent, the common skill in this field Art personnel all other embodiment obtained without making creative work belongs to the model of this patent protection It encloses.
The present embodiment provides a kind of Phase of Electric Power Projects information processing systems, as depicted in figs. 1 and 2, comprising: basic data Treatment progress module 1, process data processing scheduler module 2 and completion data processing scheduler module 3;
Basic data processing scheduler module 1 is for configuring system-based data processing process, to Phase of Electric Power Projects basic information Configure distributed processing mode, the Phase of Electric Power Projects information base data of processing input Phase of Electric Power Projects information early period;
Process data processing scheduler module 2 is for configuring systematic procedure data processing process, to Phase of Electric Power Projects procedural information Distributed processing mode is configured, obtains, integration, collects Phase of Electric Power Projects procedural information;
Completion data processing scheduler module 3 is for configuring system completion data processing process, to Phase of Electric Power Projects completion information Distributed processing mode is configured, obtains, integration, collects Phase of Electric Power Projects completion information.
In embodiment provided by the invention, basic data processing scheduler module 1 is also used to obtain the base of Phase of Electric Power Projects The profile data of plinth data, electric power of equipment route line and Phase of Electric Power Projects, power engineering place on line, power engineering cloth bar Position, power engineering bracing wire position, power engineering earthing position, power engineering family table information, power engineering service conductor information, electricity Power engineering wall carries on a shoulder pole information, power engineering electricity box information, cable passage, cable duct information, cable markup information and low-voltage platform area Placement information forms Phase of Electric Power Projects design drawing, and provides modification, inquires, and increases port newly;
It is also used to obtain the design scheme of power construction information, power equipment contract information and power equipment construction information carry out It is corresponding, it forms power equipment construction information design data and manages library, store to the design data storage area of database;
The additions and deletions for also providing for power equipment construction contract, which change, looks into port, collects to each power equipment construction contract, Power equipment construction information and power engineering project information are corresponded, forms contract management library, and provide to each electricity Contract inputting, contract editor, change to the contract and the contract of power equipment construction Project contract inquire port;
It is also used to obtain power equipment project under construction project verification information, information on bidding, bid information and contract information, and will be above-mentioned Information is stored to the basic information storage area of database;
It is also used to obtain the essential information of power equipment to be onstructed, essential information includes: power equipment signal, and power equipment is used On the way, power equipment function, power equipment fundamental importance, power equipment construction technology information, power equipment mounting process, electric power are set Standby debud mode;The essential information of power equipment to be onstructed is stored to the basic information storage area of database;It is also used to obtain The title material information of power equipment work progress and the dosage information of each title material, above- mentioned information are stored to data The basic information storage area in library.
It was read it should be further noted that process data processing scheduler module also provides for Phase of Electric Power Projects information Number of passes is according to treatment progress and writes process data processing process, and read procedure data processing process and write process data processing into Journey is parallel processing process;
It is also used to provide the process examination and approval procedure information processing process obtained in work progress, process inspection based on keyword extraction Survey backlog information treatment progress, procedural image information processing process and procedure file information processing process, and by above- mentioned information It is stored by writing process data processing process to the process storage area of database;
It is also used to based on each power equipment project under construction predetermined period information processing process of keyword extraction;It is mentioned based on keyword It takes and obtains the default monitoring point information processing process of each progress in project predetermined period.
Process data processing scheduler module also provides for multiport and writes process data based on Phase of Electric Power Projects information Treatment progress is stored by Phase of Electric Power Projects information writing system, and to the Phase of Electric Power Projects information of writing system, point Analysis and processing.
In embodiment provided by the invention, completion data processing scheduler module also provides for power engineering completion read procedure Process data processing process is write in data processing process and completion, and process is write in completion read procedure data processing process and completion Data processing process is parallel processing process;
Be also used to obtain power equipment completion information, completion write process data processing process by power equipment completion information store to The completion storage area of database;Completion writes process data processing process and is also used to return the power equipment project under construction of completion Collection arranges, and generates final acceptance of construction report;
Be also used to obtain power equipment settlement information, completion write process data processing process by power equipment settlement information store to The clearing storage area of database.
In embodiment provided by the invention, process data processing scheduler module is also used to monitor Phase of Electric Power Projects equipment Operation data, and be compared with threshold value;The environmental data of Phase of Electric Power Projects is monitored, and is compared with threshold value;Monitoring electricity Power engineering construction related personnel's Data Position data and healthy data monitor Phase of Electric Power Projects video data, monitoring The operation data of Phase of Electric Power Projects vehicle, and be compared with threshold value;
It is also used to analyze above-mentioned data mode, when a certain data or a few a data superthresholds, issues warning note;
It is also used to configuration surroundings data analysis curve, construction speed curve and construction speed network analysis chart.
In embodiment provided by the invention, process data processing scheduler module is also used to obtain multiple Phase of Electric Power Projects items Initial assessment data are assessed in the current data parameter of mesh management assessment and Phase of Electric Power Projects project management, execute risk deviation Analysis executes risk variance analysis also based on formerly existing identical Phase of Electric Power Projects project management state;
It is also used to establish Phase of Electric Power Projects test point quality grade of evaluation mechanism, realizes multiple Phase of Electric Power Projects project managements In equivalent parameter, based on parameter preset and formerly existing identical Phase of Electric Power Projects item argument execution detects point mass Grade evaluates mechanism;
By each parameter of each Phase of Electric Power Projects project of evaluation analysis, with each Phase of Electric Power Projects item argument of determination Meet the current quality levels of quality requirement and each Phase of Electric Power Projects project.
In embodiment provided by the invention, process data processing scheduler module is also used to during Phase of Electric Power Projects, Tracking, monitoring Phase of Electric Power Projects executive condition, to the payment of Phase of Electric Power Projects total packet subcontract and Phase of Electric Power Projects Cost carries out collect statistics;
By to currently having carried out Phase of Electric Power Projects cost payout Information Statistics, comparative analysis Phase of Electric Power Projects objective cost With the presence or absence of deviation;
If there is no costvariation, then continue to track, and monitors Phase of Electric Power Projects project and generated cost;
There is deviation as Phase of Electric Power Projects project has generated cost, then calls Phase of Electric Power Projects project to generate cost and be biased Row variance analysis;
It finds out Phase of Electric Power Projects project and the key factor of deviation occurs, pass through inventory, the amount of labour used, equipment machine-team and engineering Progress amount carries out data analysis and shows, use for reference.
Phase of Electric Power Projects project correction data are obtained, according to Phase of Electric Power Projects project correction data, adjust electric power work Journey construction project cost plan;
It is also used to analyze Phase of Electric Power Projects project cost trend according to Phase of Electric Power Projects Project Cost Plan;Root Work meter is determined according to Phase of Electric Power Projects project cost budget adjustment result and Phase of Electric Power Projects project cost budget adjustment It draws.
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest scope of cause.

Claims (8)

1. a kind of Phase of Electric Power Projects information processing system characterized by comprising basic data processing scheduler module, process Data processing scheduler module and completion data processing scheduler module;
Basic data processing scheduler module matches Phase of Electric Power Projects basic information for configuring system-based data processing process Set distributed processing mode, the Phase of Electric Power Projects information base data of processing input Phase of Electric Power Projects information early period;
Process data processing scheduler module matches Phase of Electric Power Projects procedural information for configuring systematic procedure data processing process Distributed processing mode is set, obtains, integration, collects Phase of Electric Power Projects procedural information;
Completion data processing scheduler module matches Phase of Electric Power Projects completion information for configuring system completion data processing process Distributed processing mode is set, obtains, integration, collects Phase of Electric Power Projects completion information.
2. Phase of Electric Power Projects information processing system according to claim 1, which is characterized in that
Basic data processing scheduler module is also used to obtain the basic data of Phase of Electric Power Projects, electric power of equipment route line and electricity The profile data of power engineering construction, power engineering place on line, power engineering cloth bar position, power engineering bracing wire position, electric power ENG land position, power engineering family table information, power engineering service conductor information, power engineering wall carry on a shoulder pole information, power engineering table Case information, cable passage, cable duct information, cable markup information and low-voltage platform area placement information form Phase of Electric Power Projects Design drawing, and modification is provided, it inquires, increases port newly;
It is also used to obtain the design scheme of power construction information, power equipment contract information and power equipment construction information carry out It is corresponding, it forms power equipment construction information design data and manages library, store to the design data storage area of database;
The additions and deletions for also providing for power equipment construction contract, which change, looks into port, collects to each power equipment construction contract, Power equipment construction information and power engineering project information are corresponded, forms contract management library, and provide to each electricity Contract inputting, contract editor, change to the contract and the contract of power equipment construction Project contract inquire port;
It is also used to obtain power equipment project under construction project verification information, information on bidding, bid information and contract information, and will be above-mentioned Information is stored to the basic information storage area of database;
It is also used to obtain the essential information of power equipment to be onstructed, essential information includes: power equipment signal, and power equipment is used On the way, power equipment function, power equipment fundamental importance, power equipment construction technology information, power equipment mounting process, electric power are set Standby debud mode;The essential information of power equipment to be onstructed is stored to the basic information storage area of database;It is also used to obtain The title material information of power equipment work progress and the dosage information of each title material, above- mentioned information are stored to data The basic information storage area in library.
3. Phase of Electric Power Projects information processing system according to claim 1 or 2, which is characterized in that
Process data processing scheduler module also provides for Phase of Electric Power Projects information read procedure data processing process and write Number of passes is according to treatment progress, and read procedure data processing process and to write process data processing process be parallel processing process;
It is also used to provide the process examination and approval procedure information processing process obtained in work progress, process inspection based on keyword extraction Survey backlog information treatment progress, procedural image information processing process and procedure file information processing process, and by above- mentioned information It is stored by writing process data processing process to the process storage area of database;
It is also used to based on each power equipment project under construction predetermined period information processing process of keyword extraction;It is mentioned based on keyword It takes and obtains the default monitoring point information processing process of each progress in project predetermined period.
4. Phase of Electric Power Projects information processing system according to claim 3, which is characterized in that
Process data processing scheduler module also provides for multiport and writes process data processing based on Phase of Electric Power Projects information Process is stored by Phase of Electric Power Projects information writing system, and to the Phase of Electric Power Projects information of writing system, analysis and Processing.
5. Phase of Electric Power Projects information processing system according to claim 1 or 2, which is characterized in that
Completion data processing scheduler module also provides for power engineering completion read procedure data processing process and is completed to write Number of passes according to treatment progress, and completion read procedure data processing process and being completed write process data processing process be parallel processing into Journey;
Be also used to obtain power equipment completion information, completion write process data processing process by power equipment completion information store to The completion storage area of database;Completion writes process data processing process and is also used to return the power equipment project under construction of completion Collection arranges, and generates final acceptance of construction report;
Be also used to obtain power equipment settlement information, completion write process data processing process by power equipment settlement information store to The clearing storage area of database.
6. Phase of Electric Power Projects information processing system according to claim 1, which is characterized in that
Process data processing scheduler module is also used to monitor the operation data of Phase of Electric Power Projects equipment, and is compared with threshold value It is right;The environmental data of Phase of Electric Power Projects is monitored, and is compared with threshold value;Monitor Phase of Electric Power Projects related personnel data bit Data and healthy data are set, Phase of Electric Power Projects video data is monitored, monitors the operation number of Phase of Electric Power Projects vehicle According to, and be compared with threshold value;
It is also used to analyze above-mentioned data mode, when a certain data or a few a data superthresholds, issues warning note;
It is also used to configuration surroundings data analysis curve, construction speed curve and construction speed network analysis chart.
7. Phase of Electric Power Projects information processing system according to claim 1, which is characterized in that
Process data processing scheduler module is also used to obtain the current data parameter of multiple Phase of Electric Power Projects project management assessments And initial assessment data are assessed in Phase of Electric Power Projects project management, execute risk variance analysis, also based on formerly existing phase Same Phase of Electric Power Projects project management state executes risk variance analysis;
It is also used to establish Phase of Electric Power Projects test point quality grade of evaluation mechanism, realizes multiple Phase of Electric Power Projects project managements In equivalent parameter, based on parameter preset and formerly existing identical Phase of Electric Power Projects item argument execution detects point mass Grade evaluates mechanism;
By each parameter of each Phase of Electric Power Projects project of evaluation analysis, with each Phase of Electric Power Projects item argument of determination Meet the current quality levels of quality requirement and each Phase of Electric Power Projects project.
8. Phase of Electric Power Projects information processing system according to claim 3, which is characterized in that
Process data processing scheduler module is also used to during Phase of Electric Power Projects, and tracking, monitoring Phase of Electric Power Projects execute Situation carries out collect statistics to the payment of Phase of Electric Power Projects total packet subcontract and Phase of Electric Power Projects cost;
By to currently having carried out Phase of Electric Power Projects cost payout Information Statistics, comparative analysis Phase of Electric Power Projects objective cost With the presence or absence of deviation;
If there is no costvariation, then continue to track, and monitors Phase of Electric Power Projects project and generated cost;
There is deviation as Phase of Electric Power Projects project has generated cost, then calls Phase of Electric Power Projects project to generate cost and be biased Row variance analysis;
It finds out Phase of Electric Power Projects project and the key factor of deviation occurs, pass through inventory, the amount of labour used, equipment machine-team and engineering Progress amount carries out data analysis and shows, use for reference;
Phase of Electric Power Projects project correction data are obtained, according to Phase of Electric Power Projects project correction data, adjustment power engineering is applied Work Project Cost Plan;
It is also used to analyze Phase of Electric Power Projects project cost trend according to Phase of Electric Power Projects Project Cost Plan;Root Work meter is determined according to Phase of Electric Power Projects project cost budget adjustment result and Phase of Electric Power Projects project cost budget adjustment It draws.
CN201811476080.2A 2018-12-04 2018-12-04 Electric power engineering construction information processing system Active CN109559054B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811476080.2A CN109559054B (en) 2018-12-04 2018-12-04 Electric power engineering construction information processing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811476080.2A CN109559054B (en) 2018-12-04 2018-12-04 Electric power engineering construction information processing system

Publications (2)

Publication Number Publication Date
CN109559054A true CN109559054A (en) 2019-04-02
CN109559054B CN109559054B (en) 2022-05-27

Family

ID=65868898

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811476080.2A Active CN109559054B (en) 2018-12-04 2018-12-04 Electric power engineering construction information processing system

Country Status (1)

Country Link
CN (1) CN109559054B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110196925A (en) * 2019-04-19 2019-09-03 北京戴纳实验科技有限公司 A kind of information retrieval system for laboratory engineering design
CN110930025A (en) * 2019-11-21 2020-03-27 中国十九冶集团有限公司 Project management system for engineering construction
CN111260242A (en) * 2020-02-05 2020-06-09 国网北京市电力公司 Evaluation system and method
CN113159486A (en) * 2021-01-19 2021-07-23 深圳市都信建设监理有限公司 Electronic prevention and control project quality supervision method and system

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130024245A1 (en) * 2008-12-01 2013-01-24 Trimble Navigation Limited Management of materials on a construction site
CN203165006U (en) * 2013-01-23 2013-08-28 上海电信工程有限公司 Engineering project management system
CN104537452A (en) * 2014-11-04 2015-04-22 无锡鹰智科技有限公司 Electric power project computer management system
CN104809591A (en) * 2015-05-11 2015-07-29 东北电力大学 Electric power construction engineering supervision mechanism based on big data
CN104850940A (en) * 2015-04-29 2015-08-19 国网辽宁省电力有限公司鞍山供电公司 Completion settlement making method and completion settlement making system based on project whole-process management
CN105303332A (en) * 2015-11-30 2016-02-03 国家电网公司 Electric power engineering project management system
CN108320127A (en) * 2017-12-20 2018-07-24 国网山东省电力公司聊城供电公司 A kind of power engineering term computer management system
CN108898360A (en) * 2018-06-22 2018-11-27 中国能源建设集团安徽电力建设第工程有限公司 A kind of power engineering wisdom building site integrated control information system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130024245A1 (en) * 2008-12-01 2013-01-24 Trimble Navigation Limited Management of materials on a construction site
CN203165006U (en) * 2013-01-23 2013-08-28 上海电信工程有限公司 Engineering project management system
CN104537452A (en) * 2014-11-04 2015-04-22 无锡鹰智科技有限公司 Electric power project computer management system
CN104850940A (en) * 2015-04-29 2015-08-19 国网辽宁省电力有限公司鞍山供电公司 Completion settlement making method and completion settlement making system based on project whole-process management
CN104809591A (en) * 2015-05-11 2015-07-29 东北电力大学 Electric power construction engineering supervision mechanism based on big data
CN105303332A (en) * 2015-11-30 2016-02-03 国家电网公司 Electric power engineering project management system
CN108320127A (en) * 2017-12-20 2018-07-24 国网山东省电力公司聊城供电公司 A kind of power engineering term computer management system
CN108898360A (en) * 2018-06-22 2018-11-27 中国能源建设集团安徽电力建设第工程有限公司 A kind of power engineering wisdom building site integrated control information system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郭云鹏: "电网工程项目进度管理信息化模式研究", 《华东电力》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110196925A (en) * 2019-04-19 2019-09-03 北京戴纳实验科技有限公司 A kind of information retrieval system for laboratory engineering design
CN110930025A (en) * 2019-11-21 2020-03-27 中国十九冶集团有限公司 Project management system for engineering construction
CN111260242A (en) * 2020-02-05 2020-06-09 国网北京市电力公司 Evaluation system and method
CN113159486A (en) * 2021-01-19 2021-07-23 深圳市都信建设监理有限公司 Electronic prevention and control project quality supervision method and system

Also Published As

Publication number Publication date
CN109559054B (en) 2022-05-27

Similar Documents

Publication Publication Date Title
CN109559054A (en) A kind of Phase of Electric Power Projects information processing system
US10488829B2 (en) Method for integrating individual load forecasts into a composite load forecast to present a comprehensive, synchronized and harmonized load forecast
US10510029B2 (en) Multi-interval dispatch system tools for enabling dispatchers in power grid control centers to manage changes
US10460264B2 (en) Method for evaluating operational and financial performance for dispatchers using after the fact analysis
US10128655B2 (en) System tools for integrating individual load forecasts into a composite load forecast to present a comprehensive, synchronized and harmonized load forecast
RU2518178C2 (en) System and method for control of electric power system
US9251479B2 (en) Multi-interval dispatch method for enabling dispatchers in power grid control centers to manage changes
RU2525859C2 (en) Controlling power outage and faulty state of electrical power system
CN110245035A (en) A kind of link trace method and device
US20110029142A1 (en) System tools that provides dispatchers in power grid control centers with a capability to make changes
US20110055287A1 (en) System tools for evaluating operational and financial performance from dispatchers using after the fact analysis
CN107195013A (en) The O&M automation method for inspecting and its system of a kind of fine granularity control
CN101639687B (en) Integrated technology quality control system and realization method thereof
CN110990391A (en) Integration method and system of multi-source heterogeneous data, computer equipment and storage medium
CN103559562A (en) Power grid intelligent operation system and achieving method thereof
CN108053095A (en) A kind of electrical energy power quality disturbance affair character extracting method and system
CN109523124A (en) Asset data processing method, device, computer equipment and storage medium
CN114511147A (en) Line loss monitoring and early warning method, device, equipment and storage medium
CN107181626A (en) Distributed storage group system network bandwidth monitoring method and system
US9997956B1 (en) Systems, apparatus, and methods for automatic generation control islanded operation
CN103577933A (en) Data monitoring method and device based on cigarette manufacturing data integration environment
CN109741047A (en) Charging system on a kind of line
CN109978503A (en) Data processing method based on micro services
CN101605049A (en) The processing method of network management data statistical analysis index and device, data management system
CN113468239A (en) Method and system for realizing internet of things industry usage statistics based on rule engine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant