CN109541459A - 一种发电机电磁兼容性试验方法 - Google Patents
一种发电机电磁兼容性试验方法 Download PDFInfo
- Publication number
- CN109541459A CN109541459A CN201811159403.5A CN201811159403A CN109541459A CN 109541459 A CN109541459 A CN 109541459A CN 201811159403 A CN201811159403 A CN 201811159403A CN 109541459 A CN109541459 A CN 109541459A
- Authority
- CN
- China
- Prior art keywords
- generator
- synchronous generator
- load
- grid
- synchronous
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R31/00—Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
- G01R31/34—Testing dynamo-electric machines
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Tests Of Circuit Breakers, Generators, And Electric Motors (AREA)
Abstract
本发明公开了一种发电机电磁兼容性试验方法,解决了发电机进行电源线传导发射的电磁兼容试验时受拖动变频器等影响的问题。将变频拖动电动机(1)、同步发电机(6)、被试发电机(12)拖动到额定转速,合上被试发电机的负载开关,使其带水电阻、电抗器负载,负载功率为1兆瓦;通过调节励磁电流使同步发电机的电压达到待并电网电压,满足并网同期条件后,按下并网开关,使同步发电机(6)并入电网;降低变频拖动电动机(1)的输出转矩,使被试发电机(12)的1兆瓦负载逐渐转移至同步发电机上;根据电源线传导发射的不同项目,对负载大小的要求调节负载开关,满足电磁兼容负载测试要求。本发明避免了变频器等设备运行的电磁干扰。
Description
技术领域
本发明涉及一种发电机电磁兼容性的试验方法,特别涉及一种可克服电源线传导电磁信号的发电机电磁兼容性的试验方法。
背景技术
目前,新型发电机研制完成后,按照“军用设备和分系统电磁发射和敏感度要求”等相关标准,需进行发电机的电磁兼容性考核,尤其是电源线传导发射。利用电流法测试的试验项目,易受试验场地电磁环境等诸多因素影响。目前,发电机生产厂家的试验系统基本采用变频器驱动变频电动机的试验方案,这种试验系统在发电机进行电磁兼容试验时,发电机无法与造成环境干扰的变频器、拖动机、辅助电源等有效隔开,所以这些设备运行中产生的大量电磁辐射会对电磁兼容试验造成严重影响,使试验测试结果不合格。
发明内容
本发明提供了一种发电机电磁兼容性试验方法,解决了发电机进行电源线传导发射的电磁兼容试验时受拖动变频器等影响的技术问题。
本发明是通过以下技术方案解决以上技术问题的:
一种发电机电磁兼容性试验方法,包括以下步骤:
第一步、启动变频器整流单元,将变频拖动电动机、同步发电机、被试发电机拖动到额定转速,待被试发电机建立空载电压后,合上被试发电机的负载开关,使其带水电阻、电抗器负载,负载功率为1兆瓦;
第二步、将同步发电机起励建压,将其励磁控制系统设定为恒励磁模式(FCR),通过调节励磁电流使同步发电机的电压达到待并电网电压,满足并网同期条件后,按下并网开关,使同步发电机并入电网,此时同步发电机做发电机运行;
第三步、降低变频拖动电动机的输出转矩,使被试发电机的1兆瓦负载逐渐转移至同步发电机上,该过程中同步发电机的运行状态由发电机状态转变为电动机状态,通过同步发电机的励磁控制系统的界面,当监测同步发电机所带负载大于1兆瓦负载时,停止变频器整流单元的运行,此时所有的负载全由同步发电机承担;
第四步、根据电源线传导发射的不同项目,对负载大小的要求调节负载开关,满足电磁兼容负载测试要求,此时全部负载由电网提供,避免了变频器等设备运行的电磁干扰;
第五步、测试项目完成后,逐渐减小同步发电机所带负载,最后分开并网开关,试验完成。
本发明通过提供了一种发电机电磁兼容试验装置及试验方法,在增加少数设备的情况下,使“电源线传导发射”项目顺利通过。同时,该试验方法也可用于试验系统的扩容使用,提升设备负载试验能力。
附图说明
图1是本发明的机械连接结构示意图。
具体实施方式
下面结合附图对本发明进行详细说明:
一种发电机励磁装置电磁兼容试验装置,包括变频拖动电动机1、同步发电机/电动机6,同步发电机/电动机为双轴伸,励磁控制系统3、被试发电机12,变频拖动电动机1输出端依次通过齿轮箱2和联轴器4与同步发电机/电动机6驱动端5机械连接在一起,在同步发电机/电动机6的非驱动端7和被试发电机驱动端11上均设置有联轴器8和10,两者通过万向节9连接。
一种发电机电磁兼容性试验方法,包括以下步骤:
第一步、启动变频器整流单元,将变频拖动电动机1、同步发电机6、被试发电机12拖动到额定转速,待被试发电机12建立空载电压后,合上被试发电机12的负载开关,使其带水电阻、电抗器负载,负载功率为1兆瓦;
第二步、将同步发电机6起励建压,将其励磁控制系统3设定为恒励磁模式FCR,通过调节励磁电流使同步发电机6的电压达到待并电网电压,满足并网同期条件后,按下并网开关,使同步发电机6并入电网,此时同步发电机6做发电机运行;
第三步、降低变频拖动电动机1的输出转矩,使被试发电机12的1兆瓦负载逐渐转移至同步发电机6上,该过程中同步发电机6的运行状态由发电机状态转变为电动机状态,通过同步发电机6的励磁控制系统3的界面,当监测同步发电机6所带负载大于1兆瓦负载时,停止变频器整流单元的运行,此时所有的负载全由同步发电机6承担;
第四步、根据电源线传导发射的不同项目,对负载大小的要求调节负载开关,满足电磁兼容负载测试要求,此时全部负载由电网提供,避免了变频器等设备运行的电磁干扰;
第五步、测试项目完成后,逐渐减小同步发电机6所带负载,最后分开并网开关,试验完成。
Claims (1)
1.一种发电机电磁兼容性试验方法,包括以下步骤:
第一步、启动变频器整流单元,将变频拖动电动机(1)、同步发电机(6)、被试发电机(12)拖动到额定转速,待被试发电机(12)建立空载电压后,合上被试发电机(12)的负载开关,使其带水电阻、电抗器负载,负载功率为1兆瓦;
第二步、将同步发电机(6)起励建压,将其励磁控制系统(3)设定为恒励磁模式(FCR),通过调节励磁电流使同步发电机(6)的电压达到待并电网电压,满足并网同期条件后,按下并网开关,使同步发电机(6)并入电网,此时同步发电机(6)做发电机运行;
第三步、降低变频拖动电动机(1)的输出转矩,使被试发电机(12)的1兆瓦负载逐渐转移至同步发电机(6)上,该过程中同步发电机(6)的运行状态由发电机状态转变为电动机状态,通过同步发电机(6)的励磁控制系统(3)的界面,当监测同步发电机(6)所带负载大于1兆瓦负载时,停止变频器整流单元的运行,此时所有的负载全由同步发电机(6)承担;
第四步、根据电源线传导发射的不同项目,对负载大小的要求调节负载开关,满足电磁兼容负载测试要求,此时全部负载由电网提供,避免了变频器等设备运行的电磁干扰;
第五步、测试项目完成后,逐渐减小同步发电机(6)所带负载,最后分开并网开关,试验完成。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811159403.5A CN109541459B (zh) | 2019-02-20 | 2019-02-20 | 一种发电机电磁兼容性试验方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811159403.5A CN109541459B (zh) | 2019-02-20 | 2019-02-20 | 一种发电机电磁兼容性试验方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109541459A true CN109541459A (zh) | 2019-03-29 |
CN109541459B CN109541459B (zh) | 2020-12-29 |
Family
ID=65843539
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811159403.5A Active CN109541459B (zh) | 2019-02-20 | 2019-02-20 | 一种发电机电磁兼容性试验方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109541459B (zh) |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20080084218A1 (en) * | 2006-10-04 | 2008-04-10 | Hailey Jeffrey C | System and Method for Information Handling System Peripheral EMC Test |
CN201837711U (zh) * | 2010-08-24 | 2011-05-18 | 上海奥波电子有限公司 | 一种电动机加载性能测试系统 |
CN102967787A (zh) * | 2012-12-04 | 2013-03-13 | 中国北方车辆研究所 | 一种动态机电混合系统的电磁干扰测试装置 |
CN204177934U (zh) * | 2014-11-10 | 2015-02-25 | 上海马拉松·革新电气有限公司 | 同轴反馈式多电压发电机测试装置 |
CN205080238U (zh) * | 2015-10-21 | 2016-03-09 | 辽宁荣信电气传动技术有限责任公司 | 一种高压变频器实现同步电机运行试验平台拓扑结构 |
CN205749731U (zh) * | 2016-06-03 | 2016-11-30 | 广州市诚臻电子科技有限公司 | 一种用于电磁兼容测试的发电机驱动系统 |
CN205826828U (zh) * | 2016-07-26 | 2016-12-21 | 上海中科深江电动车辆有限公司 | 模拟整车负载装置及包括其的电动汽车电磁干扰测试系统 |
CN206038861U (zh) * | 2016-09-09 | 2017-03-22 | 华域汽车电动系统有限公司 | 一种电动汽车电机系统电磁兼容测试装置 |
CN107991556A (zh) * | 2017-11-22 | 2018-05-04 | 中国汽车技术研究中心 | 电动汽车的电驱动系统电机轴向传导发射测试系统及方法 |
CN109188281A (zh) * | 2018-09-30 | 2019-01-11 | 中船重工电机科技股份有限公司 | 同频同压发电机可靠性试验装置及试验方法 |
CN208459503U (zh) * | 2018-07-13 | 2019-02-01 | 广州普励检测技术有限公司 | 一种电磁兼容测试的电机加载系统 |
-
2019
- 2019-02-20 CN CN201811159403.5A patent/CN109541459B/zh active Active
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20080084218A1 (en) * | 2006-10-04 | 2008-04-10 | Hailey Jeffrey C | System and Method for Information Handling System Peripheral EMC Test |
CN201837711U (zh) * | 2010-08-24 | 2011-05-18 | 上海奥波电子有限公司 | 一种电动机加载性能测试系统 |
CN102967787A (zh) * | 2012-12-04 | 2013-03-13 | 中国北方车辆研究所 | 一种动态机电混合系统的电磁干扰测试装置 |
CN204177934U (zh) * | 2014-11-10 | 2015-02-25 | 上海马拉松·革新电气有限公司 | 同轴反馈式多电压发电机测试装置 |
CN205080238U (zh) * | 2015-10-21 | 2016-03-09 | 辽宁荣信电气传动技术有限责任公司 | 一种高压变频器实现同步电机运行试验平台拓扑结构 |
CN205749731U (zh) * | 2016-06-03 | 2016-11-30 | 广州市诚臻电子科技有限公司 | 一种用于电磁兼容测试的发电机驱动系统 |
CN205826828U (zh) * | 2016-07-26 | 2016-12-21 | 上海中科深江电动车辆有限公司 | 模拟整车负载装置及包括其的电动汽车电磁干扰测试系统 |
CN206038861U (zh) * | 2016-09-09 | 2017-03-22 | 华域汽车电动系统有限公司 | 一种电动汽车电机系统电磁兼容测试装置 |
CN107991556A (zh) * | 2017-11-22 | 2018-05-04 | 中国汽车技术研究中心 | 电动汽车的电驱动系统电机轴向传导发射测试系统及方法 |
CN208459503U (zh) * | 2018-07-13 | 2019-02-01 | 广州普励检测技术有限公司 | 一种电磁兼容测试的电机加载系统 |
CN109188281A (zh) * | 2018-09-30 | 2019-01-11 | 中船重工电机科技股份有限公司 | 同频同压发电机可靠性试验装置及试验方法 |
Non-Patent Citations (1)
Title |
---|
蔡恒等: "汽车发电机电磁干扰形成机理及测试技术研究", 《汽车工程学报》 * |
Also Published As
Publication number | Publication date |
---|---|
CN109541459B (zh) | 2020-12-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104076280A (zh) | 一种交流发电机的测试系统 | |
CN104076279B (zh) | 一种交流发电机的测试装置 | |
EP2296265B1 (en) | System for detecting generator winding faults | |
CN102447265B (zh) | 带回馈功能功率单元的加载装置及方法 | |
CN102507209A (zh) | 一种串联增程式纯电动汽车动力总成可靠性试验台架 | |
CN104460656A (zh) | 一种风力发电机组变桨距控制系统综合测试平台及其测试方法 | |
CN207181563U (zh) | 一种电机控制器射频抗干扰测试装置 | |
CN106841900B (zh) | 微型电磁发电机定子绕组的故障检测装置及方法 | |
WO2018045631A1 (zh) | 内燃机车牵引变流柜调试系统 | |
CN103490779A (zh) | 永磁交流发电机模拟器 | |
CN103344915B (zh) | 同步电机温升测试系统及方法 | |
CN109541459A (zh) | 一种发电机电磁兼容性试验方法 | |
CN207380157U (zh) | 风机变桨驱动器老化测试系统 | |
CN103630838A (zh) | 一种双馈发电机对拖温升试验方法及装置 | |
CN211653022U (zh) | 一种集成式滑环测试平台 | |
CN205404757U (zh) | 一种新型双馈风力发电机试验平台 | |
CN102818953B (zh) | 风况模拟系统及其在风电机组试验台上实现的方法 | |
CN208984737U (zh) | 一种便于测试的电力变压器绕组变形测试装置 | |
CN206114805U (zh) | 风机变桨驱动器自动测试系统 | |
CN212514921U (zh) | 一种采煤机摇臂加载试验装置 | |
CN203422453U (zh) | 一种交流发电机的测试装置 | |
CN201583612U (zh) | 调压器开环试验装置 | |
CN203204922U (zh) | 大型风机缩比模型教学实训实验台 | |
CN206353187U (zh) | 充电机负载测试验证装置 | |
CN206236536U (zh) | 电流互感器 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |