CN109468946A - A kind of steel construction temporary fastening device and technique for large-scale bent cap free cantilever erection - Google Patents

A kind of steel construction temporary fastening device and technique for large-scale bent cap free cantilever erection Download PDF

Info

Publication number
CN109468946A
CN109468946A CN201811335669.0A CN201811335669A CN109468946A CN 109468946 A CN109468946 A CN 109468946A CN 201811335669 A CN201811335669 A CN 201811335669A CN 109468946 A CN109468946 A CN 109468946A
Authority
CN
China
Prior art keywords
fastening device
temporary fastening
bent cap
steel
steel construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811335669.0A
Other languages
Chinese (zh)
Other versions
CN109468946B (en
Inventor
查义强
卫张震
金钱华
张玉富
吴建兵
李逸之
姚力
黄兵
黄杰
夏恺恺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Investment Construction Development Co Ltd Of Shanghai Highway
Shanghai Greenland Construction Group Co Ltd
Original Assignee
Investment Construction Development Co Ltd Of Shanghai Highway
Shanghai Greenland Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Investment Construction Development Co Ltd Of Shanghai Highway, Shanghai Greenland Construction Group Co Ltd filed Critical Investment Construction Development Co Ltd Of Shanghai Highway
Publication of CN109468946A publication Critical patent/CN109468946A/en
Application granted granted Critical
Publication of CN109468946B publication Critical patent/CN109468946B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

The present invention relates to a kind of steel construction temporary fastening devices and technique for large-scale bent cap free cantilever erection, it is characterized in that, steel construction temporary fastening device ontology is the cuboid steel structure member being assembled by several steel plates, the top of cuboid steel structure member is equipped with lifting lug, the front side wall of cuboid steel structure member is equipped with fining twisted steel anchor plate, the bottom of fining twisted steel anchor plate is equipped with sash plate, the rear wall of cuboid steel structure member is equipped with vertical stiffener, the left side of cuboid steel structure member is equipped with left side otic placode, one end end of left side otic placode is equipped with pin stick fixation hole, the right side of cuboid steel structure member is equipped with right side otic placode, one end end of right side otic placode also is provided with pin stick fixation hole, steel construction temporary fastening device is fixed on bent cap by pin stick fixation hole on the otic placode of the left and right sides and dedicated pin stick.The present invention realizes ultra-wide large size bent cap without support, the target without cast in situs, and easy construction, significant effect greatly shortens construction period.

Description

A kind of steel construction temporary fastening device and technique for large-scale bent cap free cantilever erection
[technical field]
It is specifically a kind of for large-scale bent cap free cantilever erection the present invention relates to bent cap segment free cantilever erection technical field is related to Temporary fastening device and its technique.
[background technique]
In the prior art, it is influenced by transporting and lifting condition, 200 tons or more of large-scale bent cap is difficult to disposably prefabricated install At.In previous engineering, often using method cast-in-place or that partial precast part is cast-in-place, need to set up temporary support and scene Casting concrete has an impact site traffic and surrounding enviroment, and construction period is relatively long.
[summary of the invention]
It is an object of the invention to overcome technical problem of the existing technology, in order to realize ultra-wide large size bent cap without support, nothing The target of cast in situs provides a kind of steel construction temporary fastening device and its technique for large-scale bent cap free cantilever erection.3
To achieve the above object, a kind of steel construction temporary fastening device for large-scale bent cap free cantilever erection is designed, including Steel construction temporary fastening device ontology, which is characterized in that the steel construction temporary fastening device ontology is spelled by several steel plates The top of the cuboid steel structure member dressed up, cuboid steel structure member is equipped with lifting lug, the front side of cuboid steel structure member Wall is equipped with fining twisted steel anchor plate, and the bottom of fining twisted steel anchor plate is equipped with sash plate, cuboid steel structure member Rear wall be equipped with vertical stiffener, the left side of cuboid steel structure member is equipped with left side otic placode, one end end of left side otic placode Equipped with pin stick fixation hole, the right side of cuboid steel structure member is equipped with right side otic placode, and one end end of right side otic placode also is provided with pin Stick fixation hole, steel construction temporary fastening device are fixed on bent cap by pin stick fixation hole on the otic placode of the left and right sides and dedicated pin stick On.
The left side otic placode is symmetrically set up with right side otic placode, and pin stick fixation hole side is equipped with stiffening plate.
The top of steel construction temporary fastening device is equipped with lifting lug, is connect using lifting lug with hoisting machine.
A kind of technique of the steel construction temporary fastening device for large-scale bent cap free cantilever erection, which is characterized in that will be large-scale Bent cap is divided into several small-sized bent cap segments, matches prefabricated construction, and the bent cap segment to free cantilever erection matches prefabricated complete in precasting yard At reserved pin hole is on each section bent cap segment to connect steel construction temporary fastening device;Steel construction temporary fastening device is pairs of It uses, one group of steel construction temporary fastening device is installed on assembled bent cap segment, another group of steel construction temporary fastening device peace Loaded on bent cap segment to be assembled, steel construction temporary fastening device passes through pin stick fixation hole on its left and right sides otic placode and dedicated Rigid pins stick is fixed on bent cap;Segment to be spelled is lifted to matching split state by steel construction temporary fastening device, uses epoxy It is glued seam.
The fining twisted steel of respective numbers is penetrated between a pair of of temporary fastening device, and jack is set in case tensioning; Multi-stage prestress fining twisted steel, while unloading hook step by step, until suspension hook unloads completely, boom segments are fixed temporarily completion;To After the completion of permanent prestressing tendon tensioning, a fining twisted steel is put, recycling and reusing is carried out to temporary fastening device.
When assembled boom segments, epoxy resin mortar is smeared in Mosaic face, the joint form is the vertical piece of corbel type.
A kind of steel construction temporary fastening device and technique for large-scale bent cap free cantilever erection of the invention, realizes ultra-wide Large-scale bent cap greatly shortens construction period without support, the target without cast in situs, easy construction, significant effect.
[Detailed description of the invention]
Fig. 1 is the device of the invention perspective view
Fig. 2 is main view
Fig. 3 is rearview
Fig. 4 is otic placode structure chart
Fig. 5 is side view
Description of symbols in figure
1 lifting lug, 2 fining twisted steel anchor plates, 3 sash plates, 4 left side otic placodes, 5 left side pin stick fixation holes, 6 right side otic placodes, 7 Sell stick fixation hole, 8 vertical stiffeners, 9 fining twisted steel fixation holes in right side.
[specific embodiment]
Technical solution of the present invention is further elaborated now in conjunction with accompanying drawings and embodiments, it is believed that for a person skilled in the art It is clear.
As shown in Figs. 1-5, a kind of steel construction temporary fastening device for large-scale bent cap free cantilever erection, including steel construction face When fixed device noumenon, which is characterized in that the steel construction temporary fastening device ontology is the length being assembled by several steel plates Cube steel structure member, the top of cuboid steel structure member are equipped with lifting lug, and the front side wall of cuboid steel structure member is equipped with essence Screw-thread steel anchor plate is rolled, the bottom of fining twisted steel anchor plate is equipped with sash plate, the rear wall of cuboid steel structure member Equipped with vertical stiffener, the left side of cuboid steel structure member is equipped with left side otic placode, and one end end of left side otic placode is equipped with pin stick The right side of fixation hole, cuboid steel structure member is equipped with right side otic placode, and one end end of right side otic placode also is provided with pin stick fixation hole, Steel construction temporary fastening device is fixed on bent cap by pin stick fixation hole on the otic placode of the left and right sides and dedicated pin stick.
The left side otic placode is symmetrically set up with right side otic placode, and pin stick fixation hole side is equipped with stiffening plate.
The top of steel construction temporary fastening device is equipped with lifting lug, is connect using lifting lug with hoisting machine.
A kind of technique of the steel construction temporary fastening device for large-scale bent cap free cantilever erection, which is characterized in that will be large-scale Bent cap is divided into several small-sized bent cap segments, matches prefabricated construction, and the bent cap segment to free cantilever erection matches prefabricated complete in precasting yard At reserved pin hole is on each section bent cap segment to connect steel construction temporary fastening device;Steel construction temporary fastening device is pairs of It uses, one group of steel construction temporary fastening device is installed on assembled bent cap segment, another group of steel construction temporary fastening device peace Loaded on bent cap segment to be assembled, steel construction temporary fastening device passes through pin stick fixation hole on its left and right sides otic placode and dedicated Rigid pins stick is fixed on bent cap;Segment to be spelled is lifted to matching split state by steel construction temporary fastening device, uses epoxy It is glued seam.
The fining twisted steel of respective numbers is penetrated between a pair of of temporary fastening device, and jack is set in case tensioning; Multi-stage prestress fining twisted steel, while unloading hook step by step, until suspension hook unloads completely, boom segments are fixed temporarily completion;To After the completion of permanent prestressing tendon tensioning, a fining twisted steel is put, recycling and reusing is carried out to temporary fastening device.
When assembled boom segments, epoxy resin mortar is smeared in Mosaic face, the joint form is the vertical piece of corbel type.
Embodiment
Technique of the invention is used for Shanghai S7 highway new construction, tries to explore in the full precast assembly technical field of bridge, Make a breakthrough in the fields such as the high block construction of bent cap and buried anchor technique, abutment precast assembly technology.
Large-scale bent cap is divided into several small-sized segments by the technology, matches prefabricated construction, and Mosaic face uses epoxy glue seam, connects Slit formula is the vertical piece of corbel type.The miniaturization of segment is readily transported and lifts;Matching prefabricated construction may insure seam It is uniformly closely connected;Mosaic face can guarantee the quality and rapid construction of seam using performance of epoxy bonded.
The especially pioneering vertical piece of corbel type is effectively reduced without the difficulty of construction for supporting vertical piece and wind construction Danger, construction is simple is quick, and quality is easy to guarantee, through inquiring, not yet finds the application precedent for having such piece in the world at present, opens The beginning of industry is created.
In the design R&D process of section assembling bent cap, pass through analysis and multiple groups scaled model comparative test, designer Member continues to optimize the design drawing and arrangement and method for construction of bent cap, it is ensured that bent cap segment free cantilever erection according to test and result of study The application success of technology.
The successful installation of first batch of segment free cantilever erection bent cap indicates that this technology has been smoothly completed from theoretical, design, examination The conversion process that demonstration constructed and produced in batches construction to initial workpiece is tested, one phase of Jiang S7 highway, the second stage of the project and military project road are overhead It is promoted and applied on a large scale in the projects such as engineering.The maturation of the bent cap segment free cantilever erection technology especially vertical piece of corbel type Using to propulsion bridge prefabrication assembling members miniaturization and lightweight, cancellation support system, raising construction convenience and safety Degree reduces influence to traffic and suffers from positive and long-range meaning, also further to push building industrialization and all-round popularization Another solid technical foundation is laid using bridge prefabrication assembled technology, there is landmark meaning.

Claims (6)

1. a kind of steel construction temporary fastening device for large-scale bent cap free cantilever erection, including steel construction temporary fastening device sheet Body, which is characterized in that the steel construction temporary fastening device ontology is the cuboid steel construction structure being assembled by several steel plates Part, the top of cuboid steel structure member are equipped with lifting lug, and the front side wall of cuboid steel structure member is anchored equipped with fining twisted steel Plate, the bottom of fining twisted steel anchor plate are equipped with sash plate, and the rear wall of cuboid steel structure member, which is equipped with, vertically puts more energy into Plate, the left side of cuboid steel structure member are equipped with left side otic placode, and one end end of left side otic placode is equipped with pin stick fixation hole, cuboid The right side of steel structure member is equipped with right side otic placode, and one end end of right side otic placode also is provided with pin stick fixation hole, and steel construction is temporarily solid Determine device to be fixed on bent cap by pin stick fixation hole on the otic placode of the left and right sides and dedicated pin stick.
2. a kind of steel construction temporary fastening device for large-scale bent cap free cantilever erection as described in claim 1, feature exist In the left side otic placode is symmetrically set up with right side otic placode, and pin stick fixation hole side is equipped with stiffening plate.
3. a kind of steel construction temporary fastening device for large-scale bent cap free cantilever erection as described in claim 1, feature exist In the top of steel construction temporary fastening device is equipped with lifting lug, is connect using lifting lug with hoisting machine.
4. a kind of technique of the steel construction temporary fastening device for large-scale bent cap free cantilever erection, which is characterized in that cover large size Beam is divided into several small-sized bent cap segments, matches prefabricated construction, and the bent cap segment to free cantilever erection matches prefabricated completion in precasting yard, Pin hole is reserved on each section bent cap segment to connect steel construction temporary fastening device;
Steel construction temporary fastening device uses in pairs, and one group of steel construction temporary fastening device is installed on assembled bent cap segment, Another group of steel construction temporary fastening device is installed on bent cap segment to be assembled, and steel construction temporary fastening device passes through its left and right two It picks up the ears the pin stick fixation hole on plate and Special rigid pin stick is fixed on bent cap;It is lifted by steel construction temporary fastening device wait spell Segment is to matching split state, with epoxy glue seam.
5. a kind of technique of the steel construction temporary fastening device for large-scale bent cap free cantilever erection as claimed in claim 4, It is characterized in that, the fining twisted steel of respective numbers is penetrated between a pair of of temporary fastening device, and jack is set in case tensioning; Multi-stage prestress fining twisted steel, while unloading hook step by step, until suspension hook unloads completely, boom segments are fixed temporarily completion;To After the completion of permanent prestressing tendon tensioning, a fining twisted steel is put, recycling and reusing is carried out to temporary fastening device.
6. a kind of technique of the steel construction temporary fastening device for large-scale bent cap free cantilever erection as claimed in claim 4, It is characterized in that, when assembled boom segments, smears epoxy resin mortar in Mosaic face, the joint form is the vertical piece of corbel type.
CN201811335669.0A 2018-04-12 2018-11-11 Steel structure temporary fixing device and process for large-scale bent cap cantilever assembly Active CN109468946B (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201810326572 2018-04-12
CN2018103265727 2018-04-12

Publications (2)

Publication Number Publication Date
CN109468946A true CN109468946A (en) 2019-03-15
CN109468946B CN109468946B (en) 2024-04-12

Family

ID=65672127

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811335669.0A Active CN109468946B (en) 2018-04-12 2018-11-11 Steel structure temporary fixing device and process for large-scale bent cap cantilever assembly

Country Status (1)

Country Link
CN (1) CN109468946B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110318342A (en) * 2019-07-12 2019-10-11 上海城建市政工程(集团)有限公司 A kind of precast segment bent cap free cantilever erection constructing device

Citations (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06137086A (en) * 1992-10-29 1994-05-17 Maeda Corp Lining method of shield tunnel having rectangular section
JPH0953394A (en) * 1995-08-15 1997-02-25 P C Kk Method of connecting tensile wire member of concrete member, device therefor, and integrally connected structure
JPH09291795A (en) * 1996-04-25 1997-11-11 Nippon Steel Corp Steel segment, its joint structure and jointing method
CN201695343U (en) * 2010-01-07 2011-01-05 中交第二公路工程局有限公司 Universal lifting appliance for variable span precast beam
KR101163456B1 (en) * 2011-10-24 2012-07-18 주식회사 인터컨스텍 The splicing method of segmental prestressed concrete box beam
CN102767141A (en) * 2012-07-27 2012-11-07 中铁十一局集团有限公司 Construction method for huge capping beam utilizing reinforced concrete thin wall as permanent formwork
JP2013174075A (en) * 2012-02-24 2013-09-05 Nippon Steel Topy Bridge Co Ltd Reconstruction technique for bridge girder
CN203213022U (en) * 2013-04-26 2013-09-25 中铁第一勘察设计院集团有限公司 Mobile temporary prestress tensioning anchor block
CN203411908U (en) * 2013-08-12 2014-01-29 中铁二局股份有限公司 Temporary tensioned prestress anchoring device
CN103866698A (en) * 2014-03-14 2014-06-18 中铁十一局集团有限公司 Symmetrical suspension splicing bridge support seat end pseudo-suspension splicing construction method
CN204357139U (en) * 2014-12-04 2015-05-27 中国建筑第八工程局有限公司 Suspender
CN204530421U (en) * 2015-03-30 2015-08-05 上海市城市建设设计研究总院 For the prefabricated case beam that the bent cap of falling T bridge floor continuous structure construction pedestal beam body is closely connected
WO2015120622A1 (en) * 2014-02-14 2015-08-20 李勇 Chordless truss element method and combined-node bridge
CN105178194A (en) * 2015-09-10 2015-12-23 重庆市轨道交通设计研究院有限责任公司 Continuous beam type rail construction method
CN105568850A (en) * 2015-12-24 2016-05-11 上海市城市建设设计研究总院 Prefabricated crash barrier connecting structure facilitating installation of telescopic device and assembling method thereof
CN106320164A (en) * 2016-08-22 2017-01-11 上海应用技术学院 Large prefabricated assembly cap beam with corbel structure and construction method
CN106436583A (en) * 2016-10-14 2017-02-22 中铁十局集团有限公司 Large-cantilever bent cap tensioning anchorage temporary support device and construction method thereof
CN106835997A (en) * 2017-03-21 2017-06-13 中国葛洲坝集团第二工程有限公司 Steel box-girder lifts interim accurate positioning device and localization method
CN206970007U (en) * 2017-06-20 2018-02-06 中国建筑第八工程局有限公司 Hanging apparatus
CN107724246A (en) * 2017-11-03 2018-02-23 天津市东泽天润建筑有限公司 The interim contraposition fixing device and its application method of a kind of steel box-girder segmented assembly
CN209292871U (en) * 2018-04-12 2019-08-23 上海公路投资建设发展有限公司 A kind of steel construction temporary fastening device for large-scale bent cap free cantilever erection

Patent Citations (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06137086A (en) * 1992-10-29 1994-05-17 Maeda Corp Lining method of shield tunnel having rectangular section
JPH0953394A (en) * 1995-08-15 1997-02-25 P C Kk Method of connecting tensile wire member of concrete member, device therefor, and integrally connected structure
JPH09291795A (en) * 1996-04-25 1997-11-11 Nippon Steel Corp Steel segment, its joint structure and jointing method
CN201695343U (en) * 2010-01-07 2011-01-05 中交第二公路工程局有限公司 Universal lifting appliance for variable span precast beam
KR101163456B1 (en) * 2011-10-24 2012-07-18 주식회사 인터컨스텍 The splicing method of segmental prestressed concrete box beam
JP2013174075A (en) * 2012-02-24 2013-09-05 Nippon Steel Topy Bridge Co Ltd Reconstruction technique for bridge girder
CN102767141A (en) * 2012-07-27 2012-11-07 中铁十一局集团有限公司 Construction method for huge capping beam utilizing reinforced concrete thin wall as permanent formwork
CN203213022U (en) * 2013-04-26 2013-09-25 中铁第一勘察设计院集团有限公司 Mobile temporary prestress tensioning anchor block
CN203411908U (en) * 2013-08-12 2014-01-29 中铁二局股份有限公司 Temporary tensioned prestress anchoring device
WO2015120622A1 (en) * 2014-02-14 2015-08-20 李勇 Chordless truss element method and combined-node bridge
CN103866698A (en) * 2014-03-14 2014-06-18 中铁十一局集团有限公司 Symmetrical suspension splicing bridge support seat end pseudo-suspension splicing construction method
CN204357139U (en) * 2014-12-04 2015-05-27 中国建筑第八工程局有限公司 Suspender
CN204530421U (en) * 2015-03-30 2015-08-05 上海市城市建设设计研究总院 For the prefabricated case beam that the bent cap of falling T bridge floor continuous structure construction pedestal beam body is closely connected
CN105178194A (en) * 2015-09-10 2015-12-23 重庆市轨道交通设计研究院有限责任公司 Continuous beam type rail construction method
CN105568850A (en) * 2015-12-24 2016-05-11 上海市城市建设设计研究总院 Prefabricated crash barrier connecting structure facilitating installation of telescopic device and assembling method thereof
CN106320164A (en) * 2016-08-22 2017-01-11 上海应用技术学院 Large prefabricated assembly cap beam with corbel structure and construction method
CN106436583A (en) * 2016-10-14 2017-02-22 中铁十局集团有限公司 Large-cantilever bent cap tensioning anchorage temporary support device and construction method thereof
CN106835997A (en) * 2017-03-21 2017-06-13 中国葛洲坝集团第二工程有限公司 Steel box-girder lifts interim accurate positioning device and localization method
CN206970007U (en) * 2017-06-20 2018-02-06 中国建筑第八工程局有限公司 Hanging apparatus
CN107724246A (en) * 2017-11-03 2018-02-23 天津市东泽天润建筑有限公司 The interim contraposition fixing device and its application method of a kind of steel box-girder segmented assembly
CN209292871U (en) * 2018-04-12 2019-08-23 上海公路投资建设发展有限公司 A kind of steel construction temporary fastening device for large-scale bent cap free cantilever erection

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
上海市装配式建筑发展推进平台: "上海S7公路预制拼装技术再获突破,国内首批节段悬臂拼装盖梁成功安装", pages 1 - 7, Retrieved from the Internet <URL:4、http://m.sohu.com/a/207915735_737550? Strategyid=00014> *
吴建兵;张玉富;杨光强;: "浅谈桥梁预制拼装中的立柱施工工艺", 城市道桥与防洪, no. 10 *
陈潭生;: "跨线箱形预应力混凝土门式墩盖梁施工技术", 建筑技术开发, no. 09, 20 September 2016 (2016-09-20) *
马少军;尹杉;戴平志;: "预制节块逐跨拼装桥梁施工工艺研究", 市政技术, no. 03, 10 May 2006 (2006-05-10) *
马雪梅;: "上跨京沪高速铁路钢盖梁制造与吊装施工技术", 铁道建筑, no. 08, 20 August 2013 (2013-08-20) *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110318342A (en) * 2019-07-12 2019-10-11 上海城建市政工程(集团)有限公司 A kind of precast segment bent cap free cantilever erection constructing device

Also Published As

Publication number Publication date
CN109468946B (en) 2024-04-12

Similar Documents

Publication Publication Date Title
CN108774948A (en) A kind of segment free cantilever erection pier cap beam and its assembling method
CN105586867A (en) Installation method for over-length over-weight steel reinforcement cage
CN108423565B (en) The erection and Demolition Construction method of U-shaped twin beams gantry crane with hook
CN209292871U (en) A kind of steel construction temporary fastening device for large-scale bent cap free cantilever erection
CN109468946A (en) A kind of steel construction temporary fastening device and technique for large-scale bent cap free cantilever erection
CN109989590B (en) Auxiliary fixing device for mounting roof overlong steel beam and hoisting method of steel beam
CN116837967A (en) Construction method of large-span cable-stayed truss structure
CN208563093U (en) A kind of segment free cantilever erection pier cap beam
CN106988344B (en) Construction method of assembled trolley for cast-in-place section of fabricated station
CN209292870U (en) A kind of girder pre-stressed reinforced bar stretching platform of preform lid
CN212561623U (en) Turnover post-cast strip support-changing force transmission device
CN212270959U (en) Reusable truss type supporting structure
CN112095780A (en) Upper cover structure system applied to track operation line and implementation method thereof
JPS62130995A (en) Turbine housing
CN217711127U (en) High-altitude large-cantilever arc-shaped steel structure
Dekker et al. Direct air-cooled condenser support platform at Matimba Power Station
CN115125995B (en) Construction method for entrance and exit ring frames of assembled station
CN218292772U (en) Civil engineering main part construction quick assembly disassembly template
CN214460561U (en) Connecting piece-free assembled foundation
CN112922025B (en) Reverse construction method of underground structure
CN216615504U (en) Temporary locking device for bridge folding
CN107558729B (en) The rear pouring tape construction method that girder is built by the big area roof of post-cast strip
CN220166643U (en) Prefabricated box girder for expressway
CN216108601U (en) Repeatedly usable&#39;s assembled retaining wall
CN211689962U (en) Support-free construction supporting device for steel-concrete composite beam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant