CN109460934A - The affairs of facing to manufacture teams and groups plan as a whole regulation method - Google Patents

The affairs of facing to manufacture teams and groups plan as a whole regulation method Download PDF

Info

Publication number
CN109460934A
CN109460934A CN201811376858.2A CN201811376858A CN109460934A CN 109460934 A CN109460934 A CN 109460934A CN 201811376858 A CN201811376858 A CN 201811376858A CN 109460934 A CN109460934 A CN 109460934A
Authority
CN
China
Prior art keywords
task
teams
groups
flow
mobile terminal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811376858.2A
Other languages
Chinese (zh)
Inventor
罗海波
李强
程寅
李威
任杰
李冬冬
詹长杰
张文清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Sichuan Electric Power Co Ltd
Original Assignee
State Grid Sichuan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Sichuan Electric Power Co Ltd filed Critical State Grid Sichuan Electric Power Co Ltd
Priority to CN201811376858.2A priority Critical patent/CN109460934A/en
Publication of CN109460934A publication Critical patent/CN109460934A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling

Abstract

The invention discloses the affairs of facing to manufacture teams and groups to plan as a whole regulation method, comprising the following steps: S1, acquisition all flow of transactions nodal informations of production team establish Task Scheduling Model;S2, task distribution is carried out by task scheduling server, and flow of task line is generated by Task Scheduling Model, be sent to mobile terminal;The task definition that S3, teams and groups personnel prompt according to mobile terminal passes sequentially through each flow nodes according to flow of task line and completes task, and one flow nodes of every completion, sends the confirmation message of corresponding flow nodes;S4, task scheduling server carry out record preservation to confirmation message;The task of completion is registered in performance electrical form together with corresponding teams and groups' personnel identity information and saves by S5, task scheduling server.It is realized supervision prompting and the content record of work, improves working efficiency in application, easily unified rationally overall planning can be carried out the treatment process to teams and groups' affairs.

Description

The affairs of facing to manufacture teams and groups plan as a whole regulation method
Technical field
The present invention relates to production team control technique fields, and in particular to the affairs of facing to manufacture teams and groups plan as a whole regulation side Method.
Background technique
At the regulation center of electric system, production team can all have various big and small affairs to need to handle daily And record, it is easy to appear work and intersects the case where carrying out, reduce the working efficiency of teams and groups, can not be completed in work in the stipulated time Hold, the case where work is forgotten and omitted is easy to happen in the case where working at the same time excessively, being badly in need of one kind can be to production team thing Business plan as a whole the technological means of regulation, Lai Tigao working efficiency.
Summary of the invention
The present invention in view of the deficienciess of the prior art, provide facing to manufacture teams and groups affairs plan as a whole regulation method, answer Used time easily the treatment process to teams and groups' affairs can carry out unified rationally overall planning, realize that the supervision of work is reminded And content record, improve working efficiency.
The invention is realized by the following technical scheme:
The affairs of facing to manufacture teams and groups plan as a whole regulation method, comprising the following steps:
S1, acquisition all flow of transactions nodal informations of production team, and each flow nodes information is imported into task schedule clothes Business device, establishes Task Scheduling Model;
S2, task distribution is carried out by task scheduling server, and task definition importing Task Scheduling Model is given birth to automatically At flow of task line, the task of distribution and its flow of task line are then sent to by corresponding people from teams and groups by task scheduling server The mobile terminal of member;
The task definition that S3, teams and groups personnel prompt according to mobile terminal passes sequentially through each process section according to flow of task line Point completion task, and one flow nodes of every completion, teams and groups personnel will pass through mobile terminal to task scheduling server transmission pair Answer the confirmation message of flow nodes;
S4, task scheduling server carry out record preservation to the confirmation message that mobile terminal is fed back, and according to confirmation message It follows up to the flow of task of teams and groups personnel, until task is completed;
The task of completion is registered in performance electricity by S5, task scheduling server together with corresponding teams and groups' personnel identity information It is saved in sub-table, and to teams and groups' personnel assignment next task and its corresponding flow of task line.
In application, it is by the unified distribution of task scheduling server progress task and the planning of execution process, can be very Concentration overall management easily is carried out to teams and groups' affairs, while the confirmation message that administrative staff can feed back by mobile terminal is real When grasp the Task Progress of corresponding mobile terminal teams and groups personnel, one task of every completions can be carried out next task and distribute, Teams and groups personnel can orderly carry out when handling affairs in this way, avoid to work because caused by affairs are excessive and intersect chaotic feelings Condition, working efficiency greatly improve.
Preferably, the flow nodes information includes location information corresponding to flow nodes, passes through task schedule service The task of device distribution includes sequential node task and random node task, when the task of distribution is sequential node task, then task Dispatch server according to its fix flow nodes sequence setting flow of task line, when distribution task be random node task, Then task scheduling server, will using the position of task the last one flow nodes on the mobile terminal of distribution as reference point A task node nearest from reference point carries out flow of task line gauge stroke as initial point in this subtask.
It preferably, can be by task scheduling server to mobile terminal during the existing task execution of mobile terminal Distributing emergency task and its flow of task line, mobile terminal is received existing task suspension after emergency task and is cached, Then it is carried out an urgent task according to the content of emergency task and flow of task line, after completing emergency task, mobile terminal opens again Dynamic stopped task.
Preferably, in step s 2, task scheduling server sets adjacent two tasks section according to the flow of task line of generation The deadline interval threshold of point, and it is sent to mobile terminal together with flow of task line.
Preferably, it is mobile when the used time of certain node is more than its corresponding time interval threshold value in teams and groups personnel execution task Terminal issues prompt information.
Preferably, the mobile terminal be equipped with human-computer interaction interface, for show task definition, current task node and Current task time on node.
Preferably, the mobile terminal is stored with the identity information of corresponding teams and groups personnel, and sets fingerprint identification module, often A task node is completed, teams and groups personnel carry out authentication, after authentication, mobile terminal by fingerprint identification module The identity information of corresponding teams and groups personnel is sent to task scheduling server together with the confirmation message of corresponding node.
Preferably, task scheduling server is the individual performance electrical form of each teams and groups' personnel assignment.
Preferably, it is respectively provided with speech talkback unit in task scheduling server and mobile terminal, passes through both ends speech talkback Unit distributes the preceding cooperation and communication with during task execution to carry out task.
The present invention has the advantage that and the utility model has the advantages that
1, the affairs of facing to manufacture teams and groups of the present invention plan as a whole regulation method, can easily process to teams and groups' affairs The unified rationally overall planning of Cheng Jinhang, avoids the occurrence of the mess that affairs excessively cause work intersection.
2, facing to manufacture teams and groups of the present invention affairs plan as a whole regulation method, can be effectively prevented affairs it is excessively miscellaneous and occur work Make to forget and process omits phenomenon.
3, the affairs of facing to manufacture teams and groups of the present invention plan as a whole regulation method, and the work to each teams and groups personnel may be implemented Supervision is reminded and content record, improves working efficiency.
Detailed description of the invention
Attached drawing described herein is used to provide to further understand the embodiment of the present invention, constitutes one of the application Point, do not constitute the restriction to the embodiment of the present invention.In the accompanying drawings:
Fig. 1 is implementation steps schematic diagram of the invention;
Fig. 2 is the overall planning step of sequential node task and random node task in embodiment.
Specific embodiment
To make the objectives, technical solutions, and advantages of the present invention clearer, below with reference to embodiment and attached drawing, to this Invention is described in further detail, and exemplary embodiment of the invention and its explanation for explaining only the invention, are not made For limitation of the invention.
Embodiment
As shown in Figure 1, the affairs of facing to manufacture teams and groups plan as a whole regulation method, comprising the following steps:
S1, acquisition all flow of transactions nodal informations of production team, and each flow nodes information is imported into task schedule clothes Business device, establishes Task Scheduling Model;
S2, task distribution is carried out by task scheduling server, and task definition importing Task Scheduling Model is given birth to automatically At flow of task line, the task of distribution and its flow of task line are then sent to by corresponding people from teams and groups by task scheduling server The mobile terminal of member;
The task definition that S3, teams and groups personnel prompt according to mobile terminal passes sequentially through each process section according to flow of task line Point completion task, and one flow nodes of every completion, teams and groups personnel will pass through mobile terminal to task scheduling server transmission pair Answer the confirmation message of flow nodes;
S4, task scheduling server carry out record preservation to the confirmation message that mobile terminal is fed back, and according to confirmation message It follows up to the flow of task of teams and groups personnel, until task is completed;
The task of completion is registered in performance electricity by S5, task scheduling server together with corresponding teams and groups' personnel identity information It is saved in sub-table, and to teams and groups' personnel assignment next task and its corresponding flow of task line.
As shown in Fig. 2, flow nodes information includes location information corresponding to flow nodes, pass through task scheduling server The task of distribution includes sequential node task and random node task, when the task of distribution is sequential node task, then task tune Spend server according to its fix flow nodes sequence setting flow of task line, when distribution task be random node task, then Task scheduling server incite somebody to action this using the position of task the last one flow nodes on the mobile terminal of distribution as reference point A task node nearest from reference point carries out flow of task line gauge stroke as initial point in subtask.Administrative staff exist in advance The carrying out fixed format in task scheduling server of the task is write, if task scheduling server judges that writing out for task is each There are logical order associations for flow nodes, then are considered as sequential node task, if what task scheduling server was judged to write out There is no logical order associations to be then considered as random node task for each flow nodes of task.Task Scheduling Model includes each flow nodes Between spatial relation, carrying out that reasonable flow of task line gauge draws to random node task by Task Scheduling Model can be with Effectively save the distance of walking about of teams and groups personnel.
During the existing task execution of mobile terminal, it can be distributed by task scheduling server to mobile terminal urgent Task and its flow of task line, mobile terminal are received existing task suspension after emergency task and are cached, then basis The content and flow of task line of emergency task carry out an urgent task, after completing emergency task, mobile terminal restarting pause Task.All emergency tasks set specific coding, are immediately performed emergency task if mobile terminal reads specific coding, To cope with the sudden emergency occurred in teams and groups' affairs regulation process.
In step s 2, task scheduling server sets the completion of adjacent two task node according to the flow of task line of generation Time interval threshold value, and it is sent to mobile terminal together with flow of task line, the use of certain node in teams and groups personnel execution task When be more than its corresponding time interval threshold value when, mobile terminal issue prompt information.The administrative staff at task scheduling server end It was found that can also actively trigger mobile terminal by task scheduling server when mobile terminal task execution is slow and issue prompt letter Breath.
Mobile terminal is equipped with human-computer interaction interface, for showing task definition, current task node and current task section The point used time.
Mobile terminal is stored with the identity information of corresponding teams and groups personnel, and sets fingerprint identification module, every to complete one Business node, teams and groups personnel carry out authentication by fingerprint identification module, and after authentication, mobile terminal will corresponding teams and groups The identity information of personnel is sent to task scheduling server together with the confirmation message of corresponding node.
Task scheduling server is the individual performance electrical form of each teams and groups' personnel assignment.
Be respectively provided with speech talkback unit in task scheduling server and mobile terminal, by both ends speech talkback unit come into Cooperation and communication before the distribution of row task and during task execution.
Later period generates if there is new flow of transactions node, then can continue to import task scheduling server to constantly improve Task Scheduling Model also needs in time to be modified Task Scheduling Model if there is flow of transactions node changes, to guarantee Its timeliness prevents from affecting subsequent task schedule and execution.
Above-described specific embodiment has carried out further the purpose of the present invention, technical scheme and beneficial effects It is described in detail, it should be understood that being not intended to limit the present invention the foregoing is merely a specific embodiment of the invention Protection scope, all within the spirits and principles of the present invention, any modification, equivalent substitution, improvement and etc. done should all include Within protection scope of the present invention.

Claims (9)

1. the affairs of facing to manufacture teams and groups plan as a whole regulation method, which comprises the following steps:
S1, acquisition all flow of transactions nodal informations of production team, and each flow nodes information is imported into task scheduling server, Establish Task Scheduling Model;
S2, task distribution is carried out by task scheduling server, and task definition importing Task Scheduling Model is automatically generated and is appointed Business flowline, is then sent to corresponding teams and groups personnel's for the task of distribution and its flow of task line by task scheduling server Mobile terminal;
It is complete to pass sequentially through each flow nodes according to flow of task line for the task definition that S3, teams and groups personnel prompt according to mobile terminal At task, and one flow nodes of every completion, teams and groups personnel will pass through mobile terminal and send corresponding stream to task scheduling server The confirmation message of Cheng Jiedian;
S4, task scheduling server carry out record preservation to the confirmation message that mobile terminal is fed back, and according to confirmation message to class The flow of task of group personnel follows up, until task is completed;
The task of completion is registered in performance electronic watch together with corresponding teams and groups' personnel identity information by S5, task scheduling server It is saved in lattice, and to teams and groups' personnel assignment next task and its corresponding flow of task line.
2. the affairs of facing to manufacture teams and groups according to claim 1 plan as a whole regulation method, which is characterized in that the process section Point information includes location information corresponding to flow nodes, includes that sequential node is appointed by the task that task scheduling server is distributed Business and random node task, when the task of distribution is sequential node task, the then process that task scheduling server is fixed according to it Node sequence sets flow of task line, and when the task of distribution is random node task, then task scheduling server is by the shifting of distribution The position of task the last one flow nodes is used as reference point in dynamic terminal, by this subtask from reference point recently one A task node carries out flow of task line gauge as initial point and draws.
3. the affairs of facing to manufacture teams and groups according to claim 1 plan as a whole regulation method, which is characterized in that in mobile terminal Existing task execution during, emergency task and its flow of task can be distributed to mobile terminal by task scheduling server Line, mobile terminal are received existing task suspension after emergency task and are cached, then according to the content of emergency task and Flow of task line carries out an urgent task, and after completing emergency task, mobile terminal restarts stopped task.
4. the affairs of facing to manufacture teams and groups according to claim 1 plan as a whole regulation method, which is characterized in that in step S2 In, task scheduling server sets the deadline interval threshold of adjacent two task node according to the flow of task line of generation, and It is sent to mobile terminal together with flow of task line.
5. the affairs of facing to manufacture teams and groups according to claim 4 plan as a whole regulation method, which is characterized in that teams and groups personnel hold When the used time of certain node is more than its corresponding time interval threshold value in row task, mobile terminal issues prompt information.
6. the affairs of facing to manufacture teams and groups according to claim 5 plan as a whole regulation method, which is characterized in that described mobile whole End is equipped with human-computer interaction interface, for showing task definition, current task node and current task time on node.
7. the affairs of facing to manufacture teams and groups according to claim 1 plan as a whole regulation method, which is characterized in that described mobile whole End is stored with the identity information of corresponding teams and groups personnel, and sets fingerprint identification module, one task node of every completion, teams and groups personnel Authentication is carried out by fingerprint identification module, after authentication, mobile terminal will correspond to the identity information of teams and groups personnel Task scheduling server is sent to together with the confirmation message of corresponding node.
8. the affairs of facing to manufacture teams and groups according to claim 1 plan as a whole regulation method, which is characterized in that task schedule clothes Business device is the individual performance electrical form of each teams and groups' personnel assignment.
9. the affairs of facing to manufacture teams and groups according to claim 1 plan as a whole regulation method, which is characterized in that in task schedule Server and mobile terminal are respectively provided with speech talkback unit, and task is carried out by both ends speech talkback unit and distributes preceding and task Cooperation and communication in implementation procedure.
CN201811376858.2A 2018-11-19 2018-11-19 The affairs of facing to manufacture teams and groups plan as a whole regulation method Pending CN109460934A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811376858.2A CN109460934A (en) 2018-11-19 2018-11-19 The affairs of facing to manufacture teams and groups plan as a whole regulation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811376858.2A CN109460934A (en) 2018-11-19 2018-11-19 The affairs of facing to manufacture teams and groups plan as a whole regulation method

Publications (1)

Publication Number Publication Date
CN109460934A true CN109460934A (en) 2019-03-12

Family

ID=65610904

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811376858.2A Pending CN109460934A (en) 2018-11-19 2018-11-19 The affairs of facing to manufacture teams and groups plan as a whole regulation method

Country Status (1)

Country Link
CN (1) CN109460934A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110705861A (en) * 2019-09-26 2020-01-17 山东鲁能软件技术有限公司 Management method and system based on mobile internet
CN112801319A (en) * 2021-02-01 2021-05-14 神州数码融信云技术服务有限公司 Operation and maintenance workflow propelling method
CN113705943A (en) * 2020-05-22 2021-11-26 纬创资通股份有限公司 Task management method and system based on voice talkback function and mobile device
CN116757562A (en) * 2023-08-22 2023-09-15 国联江森自控绿色科技(无锡)有限公司 Intelligent manufacturing scheduling method with self-learning capability

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102496088A (en) * 2011-12-14 2012-06-13 河北省电力公司通信中心 Method for improving executive force of power communication overhaul core flow
CN106549495A (en) * 2016-11-03 2017-03-29 合肥华义电气科技有限公司 A kind of power system method of real-time
CN106557471A (en) * 2015-09-24 2017-04-05 上海汽车集团股份有限公司 Method for scheduling task and device
CN107316146A (en) * 2017-06-27 2017-11-03 上海应用技术大学 A kind of production scheduling System and method for of resources of production scheduling
CN108520316A (en) * 2018-03-28 2018-09-11 南京智格电力科技有限公司 A kind of data-optimized processing method of overload alarm

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102496088A (en) * 2011-12-14 2012-06-13 河北省电力公司通信中心 Method for improving executive force of power communication overhaul core flow
CN106557471A (en) * 2015-09-24 2017-04-05 上海汽车集团股份有限公司 Method for scheduling task and device
CN106549495A (en) * 2016-11-03 2017-03-29 合肥华义电气科技有限公司 A kind of power system method of real-time
CN107316146A (en) * 2017-06-27 2017-11-03 上海应用技术大学 A kind of production scheduling System and method for of resources of production scheduling
CN108520316A (en) * 2018-03-28 2018-09-11 南京智格电力科技有限公司 A kind of data-optimized processing method of overload alarm

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110705861A (en) * 2019-09-26 2020-01-17 山东鲁能软件技术有限公司 Management method and system based on mobile internet
CN113705943A (en) * 2020-05-22 2021-11-26 纬创资通股份有限公司 Task management method and system based on voice talkback function and mobile device
CN113705943B (en) * 2020-05-22 2024-04-26 纬创资通股份有限公司 Task management method and system based on voice intercom function and mobile device
CN112801319A (en) * 2021-02-01 2021-05-14 神州数码融信云技术服务有限公司 Operation and maintenance workflow propelling method
CN116757562A (en) * 2023-08-22 2023-09-15 国联江森自控绿色科技(无锡)有限公司 Intelligent manufacturing scheduling method with self-learning capability
CN116757562B (en) * 2023-08-22 2023-12-05 国联江森自控绿色科技(无锡)有限公司 Intelligent manufacturing scheduling method with self-learning capability

Similar Documents

Publication Publication Date Title
CN109460934A (en) The affairs of facing to manufacture teams and groups plan as a whole regulation method
CN105354762B (en) Power customer service work order identification and distribution system and method
CN106874087A (en) A kind of block chain intelligence contract timed task dispatching method
CN103747092B (en) Vehicle after-sale management system and method
CN103886398B (en) Business monitoring method and system under a kind of cross-system isomerous environment
CN109345072A (en) Dispatching method for distribution branch line scheduling scenario
CN110706363A (en) Attendance scheduling system based on face recognition
CN103544060B (en) A kind of service dispatch system and method based on WEBSERVICE
CN106022487A (en) Intelligent device operation and maintenance management system
CN106127526A (en) Intelligent robot system and method for work thereof
CN104951863A (en) Method for intelligently extracting bid evaluation experts
CN108391022A (en) A kind of call processing method, electronic device and computer readable storage medium
CN110610319A (en) Intelligent scheduling system and method based on gas station user classification guidance
CN111598417A (en) Natural language processing-based electric power non-emergency repair order distribution method
CN101436065A (en) Substrate production plan generating method
CN106790678A (en) A kind of Transmission system and method for ensureing the consumption of significant data prioritised transmission
CN103326935B (en) The method and system that a kind of intelligence based on microblog is waited in turn
CN107330608B (en) Production scheduling method based on neuron network technology
CN102629345B (en) Chain type links up collaboration method, Apparatus and system
CN102664941A (en) Terminal reminding system and method
CN106530474A (en) Achievement method of queuing system management platform
CN102984272A (en) System and method for remotely controlling communication capacity of mobile terminal
CN109388482A (en) Dispatching method, device and the storage medium of task
CN107424405A (en) A kind of vehicle dispatch system and its application method
CN102750751B (en) Handover control system and method for railway crossing duty room of industrial and mining enterprises

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190312