CN109457566A CN201811641639.2A CN201811641639A CN109457566A CN 109457566 A CN109457566 A CN 109457566A CN 201811641639 A CN201811641639 A CN 201811641639A CN 109457566 A CN109457566 A CN 109457566A
Authority
CN
China
Prior art keywords
drainpipe
assembled
porous
permeable
aggregate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811641639.2A
Other languages
Chinese (zh)
Inventor
段云锋
杨英健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Lvhe Environment Science And Technology Co Ltd
Original Assignee
Jiangsu Lvhe Environment Science And Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Lvhe Environment Science And Technology Co Ltd filed Critical Jiangsu Lvhe Environment Science And Technology Co Ltd
Priority to CN201811641639.2A priority Critical patent/CN109457566A/en
Publication of CN109457566A publication Critical patent/CN109457566A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/22Gutters; Kerbs ; Surface drainage of streets, roads or like traffic areas
    • E01C11/224Surface drainage of streets
    • E01C11/225Paving specially adapted for through-the-surfacing drainage, e.g. perforated, porous; Preformed paving elements comprising, or adapted to form, passageways for carrying off drainage
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a kind of assembled gap porous pavements, belong to field of road construction.A kind of assembled gap porous pavement of the invention, it from bottom to top successively include plain soil layer, porous base course, permeable isolation filter layer, screed-coat and permeable road deck, the plain soil layer is equipped with discharge structure, and the porous base course is assembled by the building block of interlocking-type base;The permeable road deck is assembled by interlocking clearance type water-permeable brick.A kind of assembled gap porous pavement of the invention, the construction of seepage pavement is convenient, short construction period, and it is conducive to recycle, the cost that porous pavement is laid with is low, and the permeable effect of the porous pavement is good, and structural strength is high, the porous pavement drainage effect is good simultaneously, can alleviate the pressure of sewerage system.

Description

A kind of assembled gap porous pavement
Technical field
The present invention relates to a kind of porous pavements, more specifically to a kind of assembled gap porous pavement.
Background technique
With the continuous quickening of urbanization process, the continuous improvement of industrialization degree, hard surfacing paves area in city It is continuously increased with site coverage, ground rainwater run-off is caused to increase, lower milliosmolarity is reduced, and flood takes place frequently, harm aggravation.City is built It builds and closes most soils with the road of the layings such as cement, prevent valuable natural precipitation increasingly loses from penetrating into soil The groundwater resources of consumption cannot get timely compensation.Since 21st century, in order to adapt to environmental change and reply nature calamity Evil, it is new generation of city storm water man- agement concept that " sponge city " concept, which is suggested, refer to city adapt to environmental change and Coping with rainwater bring natural calamity etc. has good " elasticity ", water suction, water storage, infiltration, water purification when raining, when needing It by the water stored " release " and is used, promotes urban ecological system function and reduces the generation of Urban Flood Waterlogging.Construction Sponge city can make city realize nature accumulation, naturally osmotic, self-purification, it is also possible to realize that reparation city is aquatic State, protection and the original urban ecological environment of improvement.
In recent years, in the process of construction in sponge city, water-permeable brick has been increasingly becoming one of research and development focus, and water-permeable brick is big Amount is laid on urban ground, so that city rainy day rainwater can smoothly be permeated the ground.But it is this only simple on road surface There is structure sheaf water permeable ability and carrying energy under many defects, such as water-permeable brick in single permeable mode for being laid with water-permeable brick Power is weaker, and when rainwater penetrates into structure sheaf below by water-permeable brick, structure sheaf below usually can be too late because of lower infiltration When and lead to road frost boiling, very big the use for affecting road.
Existing number of patent application is the patent of CN201820090051.1, and authorized announcement date is on September 28th, 2018, practical New Name are as follows: a kind of permeable pavement structure, this application are related to a kind of permeable pavement structure, and the permeable pavement structure is under To upper successively by soil matrix, drainage blanket, graded broken stone layer, concrete permeable layer, permeable geotextiles, screed-coat and road deck group At, and road deck two sides are provided with infiltration gutter above screed-coat;It is also installed between the drainage blanket and graded broken stone layer There is the perforated drain pipe being connected with municipal drainage pipeline.The permeable pavement structure of this application, can be realized the rain on pavement Water carries out lower infiltration by a plurality of lower infiltration approach, which has bearing capacity is high, water permeable ability is strong, water-holding capacity is strong etc. Feature.But in the actual construction process, the graded broken stone of this application is compacted difficult, is laid with graded broken stone layer operation more It is cumbersome, and it is long to be laid with the time, and its structure durability is also relatively low after the completion of construction, is easy to happen the situations such as damage, this nothing It is doubtful to greatly increase road surfacing cost and maintenance cost.
Summary of the invention
1. technical problems to be solved by the inivention
For porous pavement above shortcomings in the prior art, the present invention provides a kind of permeable road in assembled gap The porous base course in face, the porous pavement is formed by base's building block assembly, and permeable road deck can also be by interlocking clearance type water-permeable brick Assembled, the porous base course of porous pavement and permeable road deck are formed using splicing structure, convenient, construction period of constructing It is short, and be conducive to recycle, the cost that porous pavement is laid with is low, and the permeable effect of the porous pavement is good, and structural strength is high, together When the porous pavement drainage effect it is good, the pressure of sewerage system can be alleviated.
2. technical solution
In order to achieve the above objectives, technical solution provided by the invention are as follows:
A kind of assembled gap porous pavement of the invention, successively include from bottom to top plain soil layer, porous base course, it is permeable every From filter layer, screed-coat and permeable road deck, the plain soil layer is equipped with discharge structure, and the porous base course is by interlocking The building block of formula base is assembled.
Further, the discharge structure includes the aggregate french drain set on plain soil layer and the row in aggregate french drain Water pipe one, the aggregate french drain upper surface and porous base course lower surface flush, the drainpipe one are equipped with perforation, use So that the water penetration in porous base course is into drainpipe one.
Further, the discharge structure further includes sump, and the sump is connected to drainpipe, and described Sump be equipped with drainpipe two, enter the water in drainpipe in sump and be discharged by drainpipe two.
Further, the drainpipe one is transversely or longitudinal in plain soil layer, and the sump is equipped with Multiple, multiple sumps are spaced apart along one length direction of drainpipe.
Further, the distance between two neighboring described sump is 20~30m.
Further, anti-package geotextiles, the anti-package geotextiles are equipped between the aggregate french drain and plain soil layer It is wrapped in the periphery of aggregate french drain.
Further, direction earthwork grille is additionally provided between the plain soil layer and porous base course.
Further, base's building block includes the block main body of generally rectangle, and the one of the block main body To protrusion is equipped on opposite side middle part, the both ends of the protrusion, which are respectively equipped with, extends to the another of block main body To the recessed portion of opposite flank, the length of the protrusion is twice of recessed portion length, adjacent two pieces of block main bodies it is recessed It is complementary with the shape of protrusion after concave portion split, form protrusion and the recessed portion of adjacent block main body in the horizontal direction mutually Lock;The lower section of the protrusion is equipped with upper nip portion, and the lower part of the recessed portion is equipped with lower nip portion, the upper pressing Portion is complementary with the shape of lower nip portion, forms protrusion and the recessed portion of adjacent block main body in vertical direction and interlocks.
Further, the permeable road deck is assembled by interlocking clearance type water-permeable brick.
Further, the aggregate french drain is made of building recycling aggregate.
3. beneficial effect
Using technical solution provided by the invention, compared with existing well-known technique, there is following remarkable result:
(1) a kind of assembled gap porous pavement of the invention, which includes plain soil layer, porous base course, permeable Filter layer, screed-coat and permeable road deck is isolated, wherein porous base course is assembled by the building block of interlocking-type base, entire saturating Water-base is assembled, convenient, short construction period of constructing, and this kind of porous base course can be recycled, and encounter road reformation Base's building block knocked-down packing is transported to other roads, it is very easy to use, reduce the cost of road pavement.
(2) a kind of assembled gap porous pavement of the invention, discharge structure include set on plain soil layer aggregate french drain and Drainpipe one in aggregate french drain, the drainpipe one are equipped with perforation, and the water energy in porous base course enough passes through perforation infiltration Into drainpipe one, the water when the water in plain soil layer is more in porous base course can be discharged in time by drainpipe one, can It avoids making on sewage overflows to road surface because of the hypervolia in porous base course and plain soil layer, meanwhile, aggregate french drain can be fine Ground is seeped water and is filtered, be conducive to the infiltration of water, while can be avoided rainwater, municipal sewage etc. in a large amount of impurity directly with Drainpipe one contacts, and can be avoided the perforation on a large amount of impurity blocking drainpipes one.
(3) a kind of assembled gap porous pavement of the invention, discharge structure further includes sump, the sump and draining Pipe connection, and sump is equipped with drainpipe two, rainwater, the municipal sewage etc. in drainpipe one can be entered by drainpipe one Collected into sump and stored, so as to be then exhausted from after so that rainwater, municipal sewage etc. is reached a certain amount, is increased The storage capacity of porous pavement alleviates the pressure of sewerage system.
(4) a kind of assembled gap porous pavement of the invention, drainpipe one is transversely or longitudinal in plain soil layer, Sump be equipped with it is multiple, multiple sumps are spaced apart along one length direction of drainpipe, and multiple sumps being spaced apart can Rainwater catchment and storage are carried out in multiple places, further improves the storage capacity of porous pavement.
(5) a kind of assembled gap porous pavement of the invention is equipped with anti-package geotextiles between aggregate french drain and plain soil layer, Anti-package geotextiles are wrapped in the periphery of aggregate french drain, and anti-package geotextiles can play a role in filtering, and allow water through mistake simultaneously Filter sand stone can be avoided aggregate french drain and be blocked.
(6) a kind of assembled gap porous pavement of the invention, is additionally provided with two-way geotechnique between plain soil layer and porous base course Grid, direction earthwork grille increase the bearing capacity and shear resistance of entire porous pavement, ground can be effectively prevent to generate It collapses, simultaneously bi-directionally TGXG utilizes vegetation growth, can effectively prevent soil erosion.
(7) a kind of assembled gap porous pavement of the invention, base's building block after mounting can be in horizontal and vertical sides It is interlocked to being formed, the anti-pressure ability of porous base course greatly improved, and the porous base course being laid with has splendid permeable and water conservation Performance, and phenomena such as be not in sagging;Meanwhile using intermediate protrusion, the interlocking structure of two sides recess, not only structure letter It is single, it is easy to make, practice of construction is greatly facilitated, and base's building block overall structural strength is high, not easy to break, anti-pressure ability By force.
(8) a kind of assembled gap porous pavement of the invention, permeable road deck are filled by interlocking clearance type water-permeable brick and are spelled It fills, the assembled permeable road deck water permeability of interlocking clearance type water-permeable brick is good, and rainwater, municipal sewage etc. can lead to Interlocking clearance type water-permeable brick quickly lower infiltration is crossed, can be avoided permeable road deck surface area water, while assembled permeable road It is convenient that supercrust is equally constructed, and is conducive to recycle, and permeable road deck structural strength is high, and durability is good.
(9) a kind of assembled gap porous pavement of the invention, aggregate french drain are made of recycling aggregate, and aggregate french drain can Discarded aggregate is recycled, waste utilization is realized, stock utilization is improved, alleviates environment to a certain extent Pollution, realizes energy conservation and environmental protection, while also reducing the laying cost of porous pavement.
Detailed description of the invention
Label declaration in schematic diagram:
Fig. 1 is a kind of overall structure transverse direction schematic cross-sectional view of assembled gap porous pavement of the invention;
Fig. 2 is a kind of overall structure longitudinal direction schematic cross-sectional view of assembled gap porous pavement of the invention;
Fig. 3 is the distribution schematic diagram of the sump in the present invention;
Fig. 4 is the overall structure diagram of the porous base course in the present invention;
Fig. 5 is the overall structure diagram of the block main body in the present invention.
Label declaration in schematic diagram:
1, permeable road deck;2, screed-coat;3, permeable isolation filter layer;4, porous base course;5, direction earthwork grille;6, Plain soil layer;7, aggregate french drain;8, drainpipe one;9, anti-package geotextiles;10, sump;11, drainpipe two;41, block main body; 411, protrusion;412, recessed portion;4111, upper nip portion;4112, chamfering inclined-plane;4121, lower nip portion;413, facial chamfering.
Specific embodiment
To further appreciate that the contents of the present invention, the present invention is described in detail in conjunction with the accompanying drawings and embodiments.
Embodiment
In conjunction with shown in Fig. 1 to Fig. 5, a kind of assembled gap porous pavement of the present embodiment successively includes element from bottom to top Soil layer 6, porous base course 4, permeable isolation filter layer 3, screed-coat 2 and permeable road deck 1, wherein plain soil layer 6 is equipped with draining Structure, furthermore, it is desirable to illustrate, the porous base course 4 of the present embodiment is assembled by the building block of interlocking-type base, entire saturating Water-base 4 is assembled, compared with the prior art the middle structure using graded broken stone, the 4 assembly side of porous base course of the present embodiment Just, convenient, the short construction period of construction, and this kind of porous base course 4 can be recycled, it directly will be former when encountering road reformation Each base's building block knocked-down packing of porous base course 4 is transported at other site of road carries out assembly again, very easy to use, greatly The cost of road pavement is reduced greatly, and the structure of graded broken stone in the prior art is difficult to be recycled.
Specifically, as a preferred embodiment, base's building block of the present embodiment includes the block main body 41 of generally rectangle, It is equipped with protrusion 411 in the middle part of the opposite side of a pair of the block main body 41, planar junction can be used in another pair opposite flank Structure, the both ends of protrusion 411 are respectively equipped with the recessed portion 412 for extending to another pair opposite flank of block main body 41, protrusion 411 length is twice of 412 length of recessed portion, after 412 split of recessed portion of adjacent two pieces of block main bodies 41 with protrusion 411 Shape it is complementary, so that protrusion 411 and the recessed portion 412 of adjacent block main body 41 is formed interlocking in the horizontal direction, that is, adjacent two A complete sunk structure complementary with 411 shape of protrusion, protrusion are formed after 412 split of recessed portion of block block main body 41 411 can accurately bond with the complete sunk structure, in this way, after several block main bodies 41 are assembled into porous base course 4, it is each Block main body 41 is mutually locked in 4 horizontal direction of porous base course being laid with first.Also, the lower section of protrusion 411 is equipped with upper The lower part of nip portion 4111, recessed portion 412 is equipped with lower nip portion 4121, and the shape of upper nip portion 4111 and lower nip portion 4121 is mutual It mends, forms protrusion 411 and the recessed portion 412 of adjacent block main body 41 in vertical direction and interlock, that is, in several building block masters After body 41 is assembled into road surface, protrusion 411 on the recessed portion 412 for being pressed together on adjacent block main body 41 perpendicular to road surface direction, To make each block main body 41 also mutually compress in the vertical direction.In this way, base builds when base's building block in part is pressurized The pressure that block is born can be distributed in the building block of periphery base, so that the resistance to compression energy of porous base course 4 after laying greatly improved Power.Base's building block of the porous base course 4 of the present embodiment can form in horizontal and vertical direction interlock after mounting, greatly improve The anti-pressure ability of porous base course 4.When being laid with porous base course 4, without being laid with the bases such as concrete layer knot on plain soil layer 6 Structure enormously simplifies the pavement process of porous base course 4, and the porous base course 4 as made of base's building block assembly laying has pole Good permeable and water retention property, and it is less prone to phenomena such as sagging, meanwhile, using intermediate protrusion, the interlocking knot of two sides recess Structure is not only simple in structure, easy to make, greatly facilitates practice of construction, and base's building block overall structural strength is high, not easily broken It splits, anti-pressure ability is strong.More specifically, above-mentioned upper nip portion 4111 is constituted from 411 lower part of protrusion to the tapered plane of contract, Lower nip portion 4121 is made of the tapered plane that 412 lower part of recessed portion outwardly protrudes, upper nip portion 4111 and adjacent block main body 1 Lower nip portion 4121 can mutually bond, also, pass through chamfering inclined-plane 4112 between protrusion 411 and the recessed portion at both ends 412 Transition.Using the above structure, make base's building block integrally without obvious weak area, 411 structural strength of protrusion is high, and makes letter It is single, it is laid with easy to assembly.In addition, in the present embodiment, the top surface edge of block main body 41 is additionally provided with facial chamfering 413, thoroughly It is strong that water-base 4 is laid with three-dimensional sense, and easily facilitates the rain penetration of base's building block junction.In the present embodiment, porous base course 4 With a thickness of 20cm.When production, which is preferably made of permeable aggregate, for example, by using concrete coarse aggregate by cement Adhesive bonding forms, and is made and is produced of full-automatic mechanical, and manufactured base's building block porosity is high, and water penetration is strong, is fabricated to This is low, and structural strength is high, can reach 5~10MPa.
Further, the permeable road deck 1 of the present embodiment is also fabricated construction, and the permeable road deck 1 is by interlocking Clearance type water-permeable brick is assembled, and 1 preferred thickness of permeable road deck of the present embodiment is 6cm, that is, uses the interlocking of 6cm thickness Clearance type water-permeable brick is assembled.It is good to interlock assembled 1 water permeability of permeable road deck of clearance type water-permeable brick, rainwater, Municipal sewage etc. can be seeped by the way that interlocking clearance type water-permeable brick is quickly lower, can be avoided permeable 1 surface area water of road deck, simultaneously It is convenient that assembled permeable road deck 1 is equally constructed, and is conducive to recycle, and 1 structural strength of permeable road deck is high, Durability is good.Since interlocking clearance type permeable brick structure has been the prior art, details are not described herein again.
Above-mentioned discharge structure includes the aggregate french drain 7 set on plain soil layer 6 and the drainpipe 1 in aggregate french drain 7, 7 upper surface of aggregate french drain and 4 lower surface flush of porous base course, drainpipe 1 is equipped with perforation, to make in porous base course 4 Water penetration into drainpipe 1, which may be connected directly to sewerage system, and aggregate french drain 7 is set to and is draining The outside of pipe 1, the cross-sectional shape of the aggregate french drain 7 of the present embodiment are preferably rectangle, and the aggregate of rectangular cross-sectional shape is blind Ditch 7 is convenient for setting in plain soil layer 6.Aggregate french drain 7 can be seeped water and be filtered well, be conducive to the infiltration of water, simultaneously The a large amount of impurity that can be avoided in rainwater, municipal sewage etc. are directly contacted with drainpipe 1, can be avoided a large amount of impurity blocking rows Perforation on water pipe 1.It should be strongly noted that the aggregate french drain 7 of the present embodiment is made of building recycling aggregate, aggregate is blind Ditch 7 can be recycled discarded aggregate, realize waste utilization, improve stock utilization, subtract to a certain extent Light environmental pollution, realizes energy conservation and environmental protection, while also reducing the laying cost of porous pavement, it is further preferred that this implementation The aggregate french drain 7 of example is made of recycling common brick aggregate, and common brick aggregate water-retaining property is preferable, can quickly receive in porous base course 4 Water simultaneously slowly penetrates into drainpipe 1, and discarded common brick aggregate is also relatively conventional, and quantity is more.Due on aggregate french drain 7 Surface and 4 lower surface flush of porous base course, thus the water energy in porous base course 4 enough directly and quickly penetrates into aggregate french drain 7, And enter in the drainpipe 1 in aggregate french drain 7, certainly, the water in plain soil layer 6 can similarly pass through the row of penetrating into of perforating In water pipe 1, when the water put aside in plain soil layer 6 is more, rainwater in porous base course 4 etc. can be direct by drainpipe 1 It is discharged in time, can be avoided the hypervolia in factor soil layer 6 and in porous base course 4 and make on sewage overflows to road surface.This The drainpipe 1 of embodiment is also connected to the positions such as grass planting ditch, provides moisture content for vegetation, while shunting to rainwater etc., Mitigate the pressure of sewerage system.
Further, anti-package geotextiles 9, the anti-package geotextiles 9 are equipped between above-mentioned aggregate french drain 7 and plain soil layer 6 It is wrapped in the periphery of aggregate french drain 7, anti-package geotextiles 9 can play a role in filtering, and penetrate water while filtering sandstone, energy Aggregate french drain 7 is enough avoided to be blocked.
Certainly, under the weather conditions such as heavy rain, the discharge pressure of sewerage system is larger, at this point, in drainpipe 1 Water may be difficult to enter in sewerage system, thus, in order to preferably drain, the discharge structure of the present embodiment is also set up There is sump 10, which is connected to drainpipe 8, and the sump 10 is equipped with drainpipe 2 11, to make drainpipe 8 In water enter in sump 10 and be discharged by drainpipe 2 11, in the present embodiment, the setting direction of drainpipe 2 11 It is preferably vertical with one 8 setting direction of drainpipe.Rainwater, municipal sewage in drainpipe 1 etc. can by drainpipe 1 into Enter and collected and stored into sump 10, so as to be then exhausted from after so that rainwater, municipal sewage etc. is reached a certain amount, increases The big storage capacity of porous pavement, when sewerage system draining is obstructed, can smoothly enter into drainpipe 1 It is discharged in sump 10 without being badly in need of, alleviates the pressure of sewerage system.Specifically, in the present embodiment, it drains Pipe 1 transversely or it is longitudinal be set in plain soil layer 6, above-mentioned sump 10 is equipped with multiple, and multiple sumps 10 are along drainpipe One 8 length directions are spaced apart, and multiple sumps 10 being spaced apart can carry out rainwater catchment and storage, contracting in multiple places The length of the flow path in drainpipe 1 such as short rainwater, municipal sewage, reduces the pressure of water in drainpipe 1, makes Rainwater, the municipal sewage etc. obtained in plain soil layer 6 can penetrate into time in drainpipe 1, further improve porous pavement Storage capacity.As a preferred embodiment, the distance between two neighboring sump 10 of the present embodiment is 20~30m, herein The distance between two neighboring sump 10 refers to the distance between two neighboring 10 center of sump, above-mentioned each drainpipe 2 11 are arranged in the center position of each sump 10, and the distance between two neighboring drainpipe 2 11 is also 20~30m, The sump 10 under can preferably store the water in drainpipe 1, reach preferably water storage effect, while the distance The setting of sump 10 will not be made excessively intensive.
It is additionally provided with direction earthwork grille 5 between above-mentioned plain soil layer 6 and porous base course 4, direction earthwork grille 5 increases whole The bearing capacity and shear resistance of a porous pavement can effectively prevent ground to generate and collapse, and simultaneously bi-directionally TGXG 5 utilizes Vegetation growth can effectively prevent soil erosion.Meanwhile above-mentioned screed-coat 2 is preferably made of medium coarse sand, permeable isolation filtering Layer 3 is made of permeable geotextiles, at the same time, the screed-coat 2 of the present embodiment with a thickness of 3~5cm.
A kind of assembled gap porous pavement of the invention, the porous base course and water channel supercrust of the porous pavement are to spell Dress is formed, convenient, short construction period of constructing, and is conducive to recycle, and the cost that porous pavement is laid with is low, and the porous pavement Permeable effect is good, and structural strength is high, while the porous pavement drainage effect is good, can alleviate the pressure of sewerage system.
Schematically the present invention and embodiments thereof are described above, description is not limiting, institute in attached drawing What is shown is also one of embodiments of the present invention, and actual structure is not limited to this.So if the common skill of this field Art personnel are enlightened by it, without departing from the spirit of the invention, without creatively designing and the technical solution Similar frame mode and embodiment, are within the scope of protection of the invention.

Claims (10)

1. a kind of assembled gap porous pavement, from bottom to top successively includes plain soil layer (6), porous base course (4), permeable was isolated Filtering layer (3), screed-coat (2) and permeable road deck (1), the plain soil layer (6) are equipped with discharge structure, it is characterised in that: The porous base course (4) is assembled by the building block of interlocking-type base.
2. a kind of assembled gap porous pavement according to claim 1, it is characterised in that: the discharge structure includes Aggregate french drain (7) set on plain soil layer (6) and the drainpipe one (8) in aggregate french drain (7), the aggregate french drain (7) Upper surface and porous base course (4) lower surface flush, the drainpipe one (8) is equipped with perforation, to make porous base course (4) In water penetration into drainpipe one (8).
3. a kind of assembled gap porous pavement according to claim 2, it is characterised in that: the discharge structure also wraps It includes sump (10), the sump (10) is connected to drainpipe (8), and the sump (10) is equipped with drainpipe two (11), to make the water in drainpipe (8) enter in sump (10) and be discharged by drainpipe two (11).
4. a kind of assembled gap porous pavement according to claim 3, it is characterised in that: the drainpipe one (8) Transversely or longitudinal in plain soil layer (6), the sump (10) is equipped with multiple, multiple described sump (10) edges Drainpipe one (8) length direction is spaced apart.
5. a kind of assembled gap porous pavement according to claim 4, it is characterised in that: two neighboring described catchments The distance between well (10) is 20~30m.
6. a kind of assembled gap porous pavement according to claim 5, it is characterised in that: the aggregate french drain (7) Anti-package geotextiles (9) are equipped between plain soil layer (6), the anti-package geotextiles (9) are wrapped in the periphery of aggregate french drain (7).
7. a kind of assembled gap porous pavement according to claim 6, it is characterised in that: the plain soil layer (6) and Direction earthwork grille (5) are additionally provided between porous base course (4).
8. a kind of assembled gap porous pavement described in any one according to claim 1~7, it is characterised in that: described Base's building block includes the block main body (41) of generally rectangle, in the middle part of the opposite side of a pair of the block main body (41) on It is equipped with protrusion (411), the both ends of the protrusion (411) are respectively equipped with another pair phase for extending to block main body (41) To the recessed portion (412) of side, the length of the protrusion (411) is twice of recessed portion (412) length, adjacent two pieces of blocks It is complementary with the shape of protrusion (411) after recessed portion (412) split of block main body (41), make protrusion (411) and adjacent block The recessed portion (412) of main body (41) forms interlocking in the horizontal direction;The lower section of the protrusion (411) is equipped with upper nip portion (4111), the lower part of the recessed portion (412) is equipped with lower nip portion (4121), the upper nip portion (4111) and lower pressing The shape in portion (4121) is complementary, forms protrusion (411) and the recessed portion (412) of adjacent block main body (41) in vertical direction Interlocking.
9. a kind of assembled gap porous pavement according to claim 8, it is characterised in that: the permeable road deck (1) assembled by interlocking clearance type water-permeable brick.
10. a kind of assembled gap porous pavement according to claim 2, it is characterised in that: the aggregate french drain (7) It is made of building recycling aggregate.
CN201811641639.2A 2018-12-29 2018-12-29 A kind of assembled gap porous pavement Pending CN109457566A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811641639.2A CN109457566A (en) 2018-12-29 2018-12-29 A kind of assembled gap porous pavement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811641639.2A CN109457566A (en) 2018-12-29 2018-12-29 A kind of assembled gap porous pavement

Publications (1)

Publication Number Publication Date
CN109457566A true CN109457566A (en) 2019-03-12

Family

ID=65615676

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811641639.2A Pending CN109457566A (en) 2018-12-29 2018-12-29 A kind of assembled gap porous pavement

Country Status (1)

Country Link
CN (1) CN109457566A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110424216A (en) * 2019-07-03 2019-11-08 金华市中天城建绿色再生资源有限公司 The green road trails construction that permeable and water storage combines
CN110438859A (en) * 2019-09-05 2019-11-12 中建中新建设工程有限公司 A kind of the precast concrete road and its construction method of draining of catchmenting
CN110965418A (en) * 2019-12-17 2020-04-07 福建海峡环保资源开发有限公司 Novel gap permeable pavement structure and construction process thereof
CN115233516A (en) * 2022-08-08 2022-10-25 中国建筑土木建设有限公司 Turnover type temporary ground structure and construction method thereof

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202787009U (en) * 2012-09-05 2013-03-13 浙江建盛市政园林有限公司 Frost boiling damage treatment structure for bituminous concrete pavement
CN103669167A (en) * 2013-12-31 2014-03-26 北京东方园林股份有限公司 Permeable pavement structure
CN204530365U (en) * 2015-03-24 2015-08-05 扬州大学 There is the permeable road structure of curb
CN106758669A (en) * 2016-12-09 2017-05-31 福建工程学院 A kind of ecological permeable road surface
CN206666965U (en) * 2017-03-31 2017-11-24 中交三公局第三工程有限公司 A kind of bicycle lane pervious concrete pavement
CN107386050A (en) * 2017-09-14 2017-11-24 江苏绿和环境科技有限公司 A kind of fabricated permeable sidewalk base course building block
CN206887675U (en) * 2017-06-26 2018-01-16 四川交投建设工程股份有限公司 A kind of macrovoid dewatering and noise reduction asphalt surface course structure
CN107988867A (en) * 2017-12-30 2018-05-04 南京理工大学泰州科技学院 A kind of novel water permeable road and its construction method
CN207919282U (en) * 2018-01-19 2018-09-28 长春市城建维护股份有限公司 A kind of permeable pavement structure
CN209958165U (en) * 2018-12-29 2020-01-17 江苏绿和环境科技有限公司 Assembled gap permeable pavement

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202787009U (en) * 2012-09-05 2013-03-13 浙江建盛市政园林有限公司 Frost boiling damage treatment structure for bituminous concrete pavement
CN103669167A (en) * 2013-12-31 2014-03-26 北京东方园林股份有限公司 Permeable pavement structure
CN204530365U (en) * 2015-03-24 2015-08-05 扬州大学 There is the permeable road structure of curb
CN106758669A (en) * 2016-12-09 2017-05-31 福建工程学院 A kind of ecological permeable road surface
CN206666965U (en) * 2017-03-31 2017-11-24 中交三公局第三工程有限公司 A kind of bicycle lane pervious concrete pavement
CN206887675U (en) * 2017-06-26 2018-01-16 四川交投建设工程股份有限公司 A kind of macrovoid dewatering and noise reduction asphalt surface course structure
CN107386050A (en) * 2017-09-14 2017-11-24 江苏绿和环境科技有限公司 A kind of fabricated permeable sidewalk base course building block
CN107988867A (en) * 2017-12-30 2018-05-04 南京理工大学泰州科技学院 A kind of novel water permeable road and its construction method
CN207919282U (en) * 2018-01-19 2018-09-28 长春市城建维护股份有限公司 A kind of permeable pavement structure
CN209958165U (en) * 2018-12-29 2020-01-17 江苏绿和环境科技有限公司 Assembled gap permeable pavement

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张波;谭剑松;高曙光;: "多雨山区高速公路排水设计浅析", 华东公路, no. 03, pages 51 - 56 *
秦健;: "透水性人行道铺装结构设计和适用范围", 中国市政工程, no. 05, pages 11 - 13 *
谭剑松;: "黔彭(黔江至彭水段)高速公路路基路面排水技术浅谈", 西南公路, no. 01, pages 39 - 45 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110424216A (en) * 2019-07-03 2019-11-08 金华市中天城建绿色再生资源有限公司 The green road trails construction that permeable and water storage combines
CN110438859A (en) * 2019-09-05 2019-11-12 中建中新建设工程有限公司 A kind of the precast concrete road and its construction method of draining of catchmenting
CN110965418A (en) * 2019-12-17 2020-04-07 福建海峡环保资源开发有限公司 Novel gap permeable pavement structure and construction process thereof
CN115233516A (en) * 2022-08-08 2022-10-25 中国建筑土木建设有限公司 Turnover type temporary ground structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN109457566A (en) A kind of assembled gap porous pavement
CN106638918A (en) Construction method for sponge city rainwater collection system
CN106917522B (en) A kind of Outdoor Parking position system based on sponge the idea of the city
CN206571217U (en) Outdoor Parking position system based on sponge the idea of the city
CN104313967A (en) Drainage and seepage type felting composite structure
CN110042724A (en) Collapsible Loess District road sponge facility rainwater catchment system and exhaust system
CN205347914U (en) Interlocking formula ecology concrete road surface brick that permeates water with water conservancy diversion hole
CN209958165U (en) Assembled gap permeable pavement
CN109403181A (en) A kind of porous pavement
CN110904979A (en) Highway cutting side slope ecological protection system
CN201865023U (en) Closed waterproof type central dividing strip for highway
CN215210279U (en) Modular permeable pavement system
CN207700330U (en) A kind of concave herbaceous field grass-planting ecological ditch
CN109826065A (en) A kind of high-fill roadbed guard system and its construction method
CN211646422U (en) Highway cutting side slope ecological protection system
CN208362838U (en) A kind of porous pavement
CN208792470U (en) A kind of grass-planting ecological ditch
CN208748463U (en) A kind of town road rainwater infiltration storage row's integral system
CN207727719U (en) Ooze storage row's rainwater piping lane
CN102487695A (en) Green belt for roads
CN202202227U (en) Urban road brick curb and road and flower bed rainwater drainage combined system
CN209602919U (en) The porous pavement of Double-layer water-filtering under a kind of sponge city
CN209482083U (en) A kind of assembled gap porous pavement with rain water collecting system
CN209602906U (en) The waterproof floor tile reconstruction structure in sponge city
CN211285126U (en) Environment-friendly garden permeable road structure with rainwater collection function

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination