CN109356042A - A kind of replacing and rectificating method after pier slope - Google Patents

A kind of replacing and rectificating method after pier slope Download PDF

Info

Publication number
CN109356042A
CN109356042A CN201811197022.6A CN201811197022A CN109356042A CN 109356042 A CN109356042 A CN 109356042A CN 201811197022 A CN201811197022 A CN 201811197022A CN 109356042 A CN109356042 A CN 109356042A
Authority
CN
China
Prior art keywords
pier
beam body
deviation
slope
replacing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811197022.6A
Other languages
Chinese (zh)
Inventor
任智勤
朱益军
张耿耿
李志磊
江甫
涂杰文
王彬
张燕青
刘漳
黄岳斌
陈伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Communications Construction Group Co Ltd
Original Assignee
Zhejiang Communications Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Communications Construction Group Co Ltd filed Critical Zhejiang Communications Construction Group Co Ltd
Priority to CN201811197022.6A priority Critical patent/CN109356042A/en
Publication of CN109356042A publication Critical patent/CN109356042A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention provides the replacing and rectificating method after a kind of pier slope, steps 1) jacking apparatus is installed in pier coping portion to be rectified a deviation, top beam body is jacked by jacking apparatus;2) the 1) step jack interim slideway be set in the gap to be formed, to reduce constraint of the superstructure to bridge pier, and transverse direction and longitudinal direction constraint is carried out to top beam body;3) stake to there is offset carries out the unloading of soil body unilateral side, generates the soil lateral pressure contrary with pier slope, resets bridge pier tentatively;4) counter-force mechanism is set between the beam body in pier cap beam to be rectified a deviation and thereon, the nut on counter-force mechanism is twisted by torque spanner, by screw displacement, pull on the reaction force of portion's beam body generation, bridge pier to be rectified a deviation is drawn to vertical position;5) last bridge pier restores to the original state.The present invention solves the problems, such as the generation and power transmission of huge correction strength, while correction thrust is reduced to can manually be acted at double, easy for construction, short construction period, at low cost, correction result controllable precise.

Description

A kind of replacing and rectificating method after pier slope
Technical field
The present invention relates to bridge maintaining technology, a kind of replacing and rectificating method after referring specifically to beam bridge pier slope belongs to bridge Beam conserves reinforcement construction technology field.
Background technique
In existing highway bridge structure type, there are beam bridge, arch bridge, cable-stayed bridge, suspension bridge and composite bridge, wherein with beam bridge It is most commonly seen.For beam bridge during construction and operation, itself original vertical bridge pier will appear fore-and-aft tilt phenomenon, generate this Phenomenon generally has following reason:
1, due to the presence of embankment bottom silty clay weak intercalated layer, column offset is induced.After weak intercalated layer meets water immersion Very weak, in addition many factors such as the preloading of top embankment and vehicular load influence, the creeping deformation of side slope of embankment leads to bridge Pier inclination.
2, superstructure (namely beam body) is applied with horizontal thrust to bridge pier.
It is bent cap above bridge pier in beam bridge structure, is seat structure between bent cap and beam body, is between bent cap and support Bearing pad stone between bearing pad stone and support and is steel plate between beam body and support.When beam bottom steel plate does not install level, bridge pier There are bias-pressure phenomenons for upper seat, as soon as the self weight of beam body can generate a horizontal component F, the appearance of horizontal component F at support It may make pier slope.
Pier slope accident is actually rare at present, processing method also rare research.One of method be on the ground or Earth anchor is arranged in abutment, is cooperated using wirerope or steel strand wires and centre-hole jack, bridge pier of rectifying a deviation, but difficulty of construction is big, Measure is complicated, and construction cost is high.
Summary of the invention
In view of the above shortcomings of the prior art, the object of the present invention is to provide a kind of easy for construction, short construction period, Replacing and rectificating method after bridge pier fore-and-aft tilt at low cost.
In order to achieve the above-mentioned object of the invention, the present invention adopts the following technical scheme:
A kind of replacing and rectificating method after pier slope, this method comprises the following steps:
Step 1) installs jacking apparatus in pier coping portion to be rectified a deviation, and jacks the beam body on top by jacking apparatus, makes beam body Gap is formed between bridge pier upper seat;
After interim slideway is set in the gap that step 2) is formed between the beam body and support of jacking, cancel jacking apparatus branch Support force falls in beam body on interim slideway, while carrying out temporary spacing measure to top beam body;
Step 3) carries out the unloading of soil body unilateral side, generates the lateral soil contrary with pier slope to there are the stakes of deviation Pressure resets bridge pier tentatively;
Counter-force mechanism is arranged between beam body in pier cap beam to be rectified a deviation and thereon after bridge pier tentatively resets in step 4), leads to The reaction force for crossing the generation of top beam body draws bridge pier to be rectified a deviation to vertical position;The counter-force mechanism includes the first fixing component With the second fixing component, tensioning system includes at least a set of screw-and-nut component, and a set of screw-and-nut component includes a screw rod And-nut, the first fixing component and the second fixing component are respectively attached on box beam and pier cap beam to be rectified a deviation, and It is positioned to relative to each other along the axis direction of screw rod, screw rod one end is arranged in the second fixing component, and the other end can be slid through First fixing component back spin is screwed with nut, driving nut rotation, and top beam body and the first fixing component remain stationary, and screw rod drives Second fixing component is mobile towards the first fixing component so that it is relocated, and then realizes the correction to inclination bridge pier;
Step 5) removes counter-force mechanism after rectifying a deviation bridge abutment correcting in place, and starting jacking apparatus makes beam body opposing lower portions branch Seat is hanging, removes the interim slideway of the 2) step setting, then cancels jacking apparatus support force and fall beam body and remove jacking apparatus, The temporary spacing measure for cancelling the 2) step, makes all spannings be restored to state before correction.
Preferably, the interim slideway includes stainless steel plate, and the polyfluortetraethylene plate on the downside of stainless steel plate.
Preferably, silicone grease layer is arranged between stainless steel plate and polyfluortetraethylene plate again.
Preferably, excavating in the step 3) to the bridge pier side soil body, it is high to excavate slope to bottom binder or less Degree, slope ratio of slope are 1:1, and it is the step-like of 2m that slope surface, which is excavated into width,.
Preferably, the measure for carrying out temporary spacing to beam body includes cross spacing and longitudinal spacing, cross spacing is used For fashioned iron to beam body cross spacing and guiding, longitudinal spacing is that expansion joint is fixed.
Preferably, adding slideway on the basis of former support, respectively there is one section of inclined-plane in slideway front and back end, and inclined-plane interface uses Arc transition, and 2 °~3 ° of the beam bottom angle of cut, unavailable broken line linking avoids that line occurs because angle is mutated in sliding pressurized process Property contact and concentrated stress, to damage interim slide surface
Preferably, the first fixing component is located on pier cap beam to be rectified a deviation, bearing pad stone is withstood, and use angle steel pair It is fixed;Second fixing component is set to small box girder beam bottom, is connect using bolt with box beam bottom plate.
Preferably, the tensioning system has stress measurement device.
Preferably, tensioning system includes 4~6 sets of screw-and-nut components.
Preferably, before implementing this method should vertical misalignment amount to bridge pier carry out repetition measurement, when repetition measurement, at least adopts Comparison is measured with two different modes, to determine the accurate offset value for preceding bridge pier of constructing, so that it is determined that bridge pier entangles Offset value
The superstructure that the present invention treats the correspondence spanning of correction bridge pier carries out longitudinal spacing, to form a fulcrum, mesh Be horizontal thrust when will tilt the correction of bridge pier by counter-force mechanism, power dispersion is transmitted on other bridge piers and abutment. It because correction thinking of the invention is to transmit the force to the bridge pier for needing to rectify a deviation by counter-force mechanism, i.e., is not directly to push away bridge pier, But by effect of the torque spanner to nut, the active force of generation is bridge pier thrust, so before needing to carry out step 4) Phase prepares.At this time stress integrally need as a whole with resist torque spanner twisting nut generate huge thrust, and by Power is not whole active.The temporary consolidation measure of stress entirety mainly has, and the expansion joint between two spannings is by welding consolidation or adopts It is withstood with jack.Generate the thrust that the extruding that the active force contrary with pier slope is mainly the earthwork generates, operation letter It is single to be easy to implement.
Compared with prior art, the invention has the following beneficial effects:
1, temporary spacing is carried out to the superstructure of all spannings of inclination correction pier opposite direction, entangling for bridge pier will be tilted Inclined horizontal thrust is transmitted on each bridge pier, is solved the power transmission of huge correction strength and is born problem.
2, interim slideway is formed with steel plate, stainless steel plate and tetrafluoro slide plate, frictional resistance becomes 0.05~0.08 times, will rectify a deviation Thrust be reduced to can manually act at double, it is easy for construction.
3, jacking whole process uses synchronizer, bridge pier bottom mount stress detection device, it is ensured that bridge structure and applies Work overall process safety.
4, to bridge pier side soil excavation, certain correction thrust of earth is generated, the difficulty of follow-up work is reduced.
5, counter-force mechanism structure is simple, only can manually operate, and single operation displacement controls precision height, to original structure Damage it is small, construction infection is small, at low cost, short construction period, at low cost, correction result controllable precise.
Detailed description of the invention
Fig. 1 is bridge abutment correcting schematic diagram provided by the invention;
Fig. 2 is the structural schematic diagram of interim slideway provided by the invention;
Fig. 3 is the schematic diagram of soil unilateral side unloading in step 3) provided by the invention;
Fig. 4 is the structural schematic diagram of counter-force mechanism provided by the invention;
Fig. 5 is the main view and side view of the first fixing component provided by the invention;
Fig. 6 is the side view and main view of the second fixing component provided by the invention.
Specific embodiment
Fig. 1 depicts the replacing and rectificating method after pier slope provided by the invention, as shown in Figure 1, and specific implementation Step are as follows:
1) jacking apparatus is installed in pier coping portion to be rectified a deviation, will be pushed up in the beam body 4 wait rectify a deviation on bridge pier by jacking apparatus It rises, makes to form gap between 1 upper seat 5 of beam body 4 and bridge pier.Due to being equipped with support 5 and bearing pad stone, top at the top of bridge pier 4 Structure (i.e. beam body) is pressed on support 5;And the presence of support and bearing pad stone, it there is between top beam body 4 and pier cap beam Certain overhead space, the space, that is, mountable jacking apparatus, there are many implementations of jacking apparatus, such as the celebrating of Zhejiang Province dragon The jacking apparatus used in the inclination correction of highway dragon's fountain intercommunication Large Bridge Pier;
2) 1) step jack original support be transformed in the gap to be formed, interim slideway 6 is set, to reduce top Constraint of the structure to bridge pier;Specifically, as shown in Fig. 2, interim slideway 6 includes stainless steel plate 61 and polyfluortetraethylene plate 62, no Rust steel plate 61 is located on polyfluortetraethylene plate, and silicone grease layer is arranged between stainless steel plate 61 and polyfluortetraethylene plate 62 again, so that Stainless steel plate and polyfluortetraethylene plate are freely slidable, and then cancelling jacking apparatus support force falls in beam body on interim slideway; Stainless steel plate, polyfluortetraethylene plate and silicone grease layer are set, it is therefore an objective to form an interim slide surface, make between beam body 4 and bridge pier 1 Coefficient of friction minimize, mitigate the thrust of the 4) step significantly.In addition, interim slide surface cannot fully rely on former support, need Slideway is added on the basis of former support, respectively there is one section of inclined-plane in slideway front and back end, and inclined-plane interface uses arc transition, hands over beam bottom 2 °~3 ° of angle, unavailable broken line linking avoid that linear contact and concentrated stress occurs because angle is mutated in sliding pressurized process, To damage interim slide surface.
Temporary spacing measure is carried out to top beam body simultaneously, the temporary spacing of beam body includes cross spacing and longitudinal spacing, About beam body horizontal and vertical limit implementation there are many;In the present embodiment, cross spacing structure is using fashioned iron to beam Body cross spacing and guiding, in addition the position limiting structure and box beam contact surface use stainless steel and tetrafluoro board group to close to reduce frictional resistance Power, longitudinal spacing are that expansion joint is fixed, i.e. welding is consolidated or withstood using jack;
3) active force for making the recovery of pier slope, concrete implementation mode are generated are as follows: as shown in figure 3, bridge pier divides are as follows: 11- pier stud, 12- binder, 13- pile foundation excavate the bridge pier side soil body to there are the stakes of deviation, excavate slope to bottom system 12 or less height of beam, slope ratio of slope are 1:1, and it is the step-like of 2m that slope surface, which is excavated into width, i.e., is unloaded by carrying out unilateral side to soil It carries, results from the contrary soil lateral pressure of pier slope;
4) counter-force mechanism 3 is set between 4 body of beam in bridge pier to be rectified a deviation and thereon, the reaction generated by top beam body 4 Power draws bridge pier to be rectified a deviation to vertical position;As shown in Figure 1, the counter-force mechanism 3 includes the first fixing component 31 with reference to Fig. 4 With the second fixing component 32, tensioning system includes at least a set of screw-and-nut component, and a set of screw-and-nut component includes a spiral shell Bar 33 and-nut 34, nut 34 are threaded io the screw rod 32;First fixing component and the second fixing component difference are attached It connects in box beam and pier cap beam 2 to be rectified a deviation, and is positioned to relative to each other along the axis direction of screw rod 33, as shown in Figure 1, 33 one end of screw rod is fixed in the second fixing component 32, and the other end is slidably disposed through 31 back spin of the first fixing component and is screwed with spiral shell Mother, driving nut rotation, the top beam body and the first fixing component of limit remain stationary, and screw rod 33 translates, and at this time second Fixed structure 32 can be relocated under the action of screw rod 33 relative to the first fixing component 31, and then be realized to inclination bridge pier Correction;
In the present embodiment, torque spanner twists the nut on counter-force mechanism, by screw displacement, pulls on the generation of portion's beam body Reaction force draws bridge pier to be rectified a deviation to vertical position;And first fixing component 31 and the second fixing component 32 specific structure And there are many ways of realization of box beam and the fixed form of bent cap, in the present embodiment, with reference to Fig. 5, the first fixing component Be made of horizontal steel plate 311, inclined steel plate 312 and the connection of vertical steel plate 313, specifically, with bolt 314 by horizontal steel plate with The connection of box beam bottom plate;With reference to Fig. 6, the second fixing component includes the steel plate that pier cap beam is fixed on by bolt 320 and angle steel 321 322, steel plate 322 is equipped with bolt hole 3220 and is used for fastening screw, and steel plate is equipped with a plurality of steel plate ribs 323, the steel plate 322 The bearing pad stone on bent cap is withstood simultaneously;Tensioning system is accompanied with pair using fining twisted steel and corresponding nut composition on screw rod The stress meter answered twists nut, pulls power transmission screw rod 33.
In addition, the thrust due to bridge abutment correcting is very big, a usual counter force system is difficult to meet the requirements, therefore, the present invention The counter-force mechanism of offer and corresponding screw rod usually have 4-6 set, and the resultant force that all counter-force mechanisms are formed pushes bridge pier to reset together. Movement is synchronized them by manual operation in operating process.
Counter-force mechanism 3 of the present invention, its significance lies in that: 1, by torque spanner, apply torque to nut;2, pass through nut Rotation generates pulling force to screw rod;By the leverage twice of both of the above, power is amplified to the degree that can push bridge pier.
5) after rectifying a deviation bridge abutment correcting in place, counter-force mechanism is removed, starting jacking apparatus keeps beam body opposing lower portions support outstanding Sky, removes the interim slide surface of the 2) step setting, then cancels jacking apparatus support force and fall beam body and remove jacking apparatus, takes The temporary spacing measure for the 2) step that disappears, makes all spannings be restored to state before correction.
Three steps of front of the invention belong to preliminary preparation, are all for 4) step service.
Before pier stud deviation rectification, pile foundation is done in correction bridge pier and is completely detected, it is ensured that structure safety, and constructed in reset Cheng Zhong copes with bridge pier basal crack, and counter-force mechanism carries out all-the-way tracking observation by the box beam bottom plate evil of dress, finds fortuitous event, It should stop resetting immediately, can continue to reset work after ascertaining the reason.Meanwhile bridge pier should be uninterruptedly monitored in reseting procedure Column deviation amount, discovery fortuitous event can continue to reset work after should ascertaining the reason.
It can specifically be carried out by following requirement:
(1) before starting to repair punishment should the vertical misalignment amount to bridge pier carry out repetition measurement, when repetition measurement, at least adopts Comparison is measured with two different modes, to determine the accurate offset value for preceding bridge pier of constructing, so that it is determined that bridge pier entangles Offset value.
(2) control, restricted speed are carried out to traffic on bridge.
(3) counter-force mechanism is installed.
(4) correction punishment carried out to the pier stud rectified a deviation of needs, during deviation rectification, coping with main force part, (T beam is horizontal Partition and bridge pier bottom) carry out disease monitoring.
(5) after the completion of deviation rectification work, the phase between the upper and lower steel plate of all supports (wedge steel plate and bearing pad stone) is detected To positional relationship, original position is restored to determination.
When pier stud spends tolerance value 0.3%H vertically and determines no more than 20mm.It is wanted it is believed that bridge abutment correcting resets to meet It asks.
After the completion of examination, terminate traffic control.
Bridge pier of the present invention can return to normal position, be based primarily upon the following 1, by the way that interim slide surface is arranged, make beam Coefficient of friction between body and bridge pier minimizes, and mitigates thrust when correction significantly;2, deviation is influenced by external force, correction Before eliminate generate deviation active force.
The present invention is suitable for the deviation rectification after concrete beam bridge pier slope, comprising: structure after simply supported girder bridge, first freely-supported Bridge floor continuous bridge, continuous bridge etc. after continuous bridge, first freely-supported.
Finally, it is stated that the above examples are only used to illustrate the technical scheme of the present invention and are not limiting, although referring to compared with Good embodiment describes the invention in detail, those skilled in the art should understand that, it can be to skill of the invention Art scheme is modified or replaced equivalently, and without departing from the objective and range of technical solution of the present invention, should all be covered at this In the scope of the claims of invention.

Claims (10)

1. the replacing and rectificating method after a kind of pier slope, it is characterised in that: this method comprises the following steps:
Step 1) installs jacking apparatus in pier coping portion to be rectified a deviation, and jacks the beam body on top by jacking apparatus, makes beam body and bridge Gap is formed between socle support;
After interim slideway is set in the gap that step 2) is formed between the beam body and support of jacking, cancel jacking apparatus support force It falls in beam body on interim sliding support, while temporary spacing measure is carried out to top beam body;
Step 3) carries out the unloading of soil body unilateral side, generates the soil lateral pressure contrary with pier slope to there are the stakes of deviation, Reset bridge pier tentatively;
After bridge pier tentatively resets counter-force mechanism is arranged between beam body in pier cap beam to be rectified a deviation and thereon, by upper in step 4) The reaction force that portion's beam body generates draws bridge pier to be rectified a deviation to vertical position;The counter-force mechanism includes the first fixing component and the Two fixing components, tensioning system include at least a set of screw-and-nut component, a set of screw-and-nut component include a screw rod with And-nut, the first fixing component and the second fixing component are respectively attached on box beam and pier cap beam to be rectified a deviation, and fixed Position is relative to each other at the axis direction along screw rod, and screw rod one end is arranged in the second fixing component, and the other end can be slid through the One fixing component back spin is screwed with nut, and driving nut rotation, top beam body and the first fixing component remain stationary, and screw rod drives the Two fixing components are mobile towards the first fixing component so that it is relocated, and then realizes the correction to inclination bridge pier;
Step 5) removes counter-force mechanism after rectifying a deviation bridge abutment correcting in place, and starting jacking apparatus keeps beam body opposing lower portions support outstanding Sky, removes the interim slideway of the 2) step setting, then cancels jacking apparatus support force and fall beam body and remove jacking apparatus, cancels The temporary spacing measure of the 2) step, makes all spannings be restored to state before correction.
2. the replacing and rectificating method after pier slope according to claim 1, it is characterised in that: the interim slideway includes Stainless steel plate, and the polyfluortetraethylene plate on the downside of stainless steel plate.
3. the replacing and rectificating method after pier slope according to claim 1, it is characterised in that: stainless steel plate and polytetrafluoro Silicone grease layer is set again between vinyl plate.
4. the replacing and rectificating method after pier slope according to claim 1, it is characterised in that: right in the step 3) The bridge pier side soil body is excavated, and slope to bottom binder or less height is excavated, and slope ratio of slope is 1:1, and slope surface, which is excavated into width, is 2m's is step-like.
5. the replacing and rectificating method after pier slope according to claim 1, it is characterised in that: temporarily limited beam body The measure of position includes cross spacing and longitudinal spacing, and cross spacing is using fashioned iron to beam body cross spacing and guiding, longitudinal spacing It is that expansion joint is fixed.
6. the replacing and rectificating method after pier slope according to claim 1, it is characterised in that: in former support in step 2) On the basis of add slideway, respectively there is one section of inclined-plane in slideway front and back end, and inclined-plane interface uses arc transition, with 2 ° of the beam bottom angle of cut~ 3 °, unavailable broken line linking avoids that linear contact and concentrated stress occurs because angle is mutated in sliding pressurized process, to damage Bad interim slide surface.
7. the replacing and rectificating method after pier slope according to claim 1, it is characterised in that: the first fixing component is located at On pier cap beam to be rectified a deviation, bearing pad stone is withstood, and it is fixed using angle steel;Second fixing component is set to small box girder Beam bottom is connect using bolt with box beam bottom plate.
8. the replacing and rectificating method after pier slope according to claim 1, it is characterised in that: the tensioning system has Stress measurement device.
9. the replacing and rectificating method after pier slope according to claim 1, it is characterised in that: tensioning system includes 4~6 Cover screw-and-nut component.
10. the replacing and rectificating method after pier slope according to claim 1, it is characterised in that: before implementing this method Should vertical misalignment amount to bridge pier carry out repetition measurement, when repetition measurement, at least measures comparison using two different modes, with The accurate offset value for determining bridge pier before constructing, so that it is determined that the correction magnitude of bridge pier.
CN201811197022.6A 2018-10-15 2018-10-15 A kind of replacing and rectificating method after pier slope Pending CN109356042A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811197022.6A CN109356042A (en) 2018-10-15 2018-10-15 A kind of replacing and rectificating method after pier slope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811197022.6A CN109356042A (en) 2018-10-15 2018-10-15 A kind of replacing and rectificating method after pier slope

Publications (1)

Publication Number Publication Date
CN109356042A true CN109356042A (en) 2019-02-19

Family

ID=65349430

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811197022.6A Pending CN109356042A (en) 2018-10-15 2018-10-15 A kind of replacing and rectificating method after pier slope

Country Status (1)

Country Link
CN (1) CN109356042A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110331676A (en) * 2019-07-22 2019-10-15 湖南聚创建筑科技有限公司 A kind of pile-column flexible pier Deviation Correction Construction device and its construction method
CN110820817A (en) * 2019-10-11 2020-02-21 福建省建科工程技术有限公司 Bridge pier stud pile foundation combination deviation rectifying method
CN110983995A (en) * 2019-12-06 2020-04-10 中铁四院集团岩土工程有限责任公司 Beam body jacking method for high-speed railway bridge
CN111877168A (en) * 2020-07-20 2020-11-03 长沙理工大学 Torsion correction method for lattice type steel main beam of combined cable-stayed bridge
CN111926685A (en) * 2020-08-19 2020-11-13 中铁二院工程集团有限责任公司 Shear force conversion component for transversely moving high-speed railway continuous beam and conversion method
CN111979933A (en) * 2020-09-14 2020-11-24 长沙市公路桥梁建设有限责任公司 Elastic limiting stopper for bridge deviation correction and bridge with automatic deviation correction function
WO2021022671A1 (en) * 2019-08-07 2021-02-11 湖南联智桥隧技术有限公司 Device for preventing pier deviation of high-pier bridge having large longitudinal slope
CN112813852A (en) * 2021-01-05 2021-05-18 四川交投建设工程股份有限公司 Repairing and reinforcing method for bridge deck subsidence of in-service bridge
CN113668410A (en) * 2021-08-25 2021-11-19 郑州大学 Pier deviation rectifying method using main beam to provide counter force
CN113931086A (en) * 2021-10-28 2022-01-14 湖南省通和工程有限公司 Pier deviation rectifying construction process
CN114016369A (en) * 2021-12-03 2022-02-08 浙江数智交院科技股份有限公司 Deviation correcting device and beam body structure
CN114561881A (en) * 2022-03-17 2022-05-31 浙江科技学院 Longitudinal deviation-rectifying and resetting method suitable for soft soil foundation bridge
CN114855654A (en) * 2022-06-27 2022-08-05 四川路桥桥梁工程有限责任公司 Stable inclined pier construction method without interrupting traffic operation

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103821090A (en) * 2014-02-27 2014-05-28 武汉中交试验检测加固工程有限责任公司 Deviation correcting and resetting method for inclined bridge pier
CN104032764A (en) * 2014-06-13 2014-09-10 上海市基础工程集团有限公司 Press-in type sunk well reaction system
CN204212071U (en) * 2014-10-16 2015-03-18 武汉二航路桥特种工程有限责任公司 A kind of pier stud anchor structure
JP2015209587A (en) * 2014-04-30 2015-11-24 株式会社クニムネ Electrode panel for electric anticorrosion
CN205840332U (en) * 2016-06-30 2016-12-28 广东合迪科技股份有限公司 Hang mould positioner
CN107386688A (en) * 2017-09-09 2017-11-24 上海先达特种土木工程有限公司 Wedge-shaped temporary support
CN206784394U (en) * 2017-04-25 2017-12-22 江苏长江机械化基础工程公司 A kind of T-shaped screw rod prestressing force counter-force anchor device
CN207362718U (en) * 2017-08-29 2018-05-15 中铁(贵州)市政工程有限公司 A kind of bridge abutment correcting device
CN108221718A (en) * 2018-03-05 2018-06-29 湖南省交通规划勘察设计院有限公司 The bridge pier small axial dimension deviation correcting device and method for correcting error of beam body transverse direction deviation

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103821090A (en) * 2014-02-27 2014-05-28 武汉中交试验检测加固工程有限责任公司 Deviation correcting and resetting method for inclined bridge pier
JP2015209587A (en) * 2014-04-30 2015-11-24 株式会社クニムネ Electrode panel for electric anticorrosion
CN104032764A (en) * 2014-06-13 2014-09-10 上海市基础工程集团有限公司 Press-in type sunk well reaction system
CN204212071U (en) * 2014-10-16 2015-03-18 武汉二航路桥特种工程有限责任公司 A kind of pier stud anchor structure
CN205840332U (en) * 2016-06-30 2016-12-28 广东合迪科技股份有限公司 Hang mould positioner
CN206784394U (en) * 2017-04-25 2017-12-22 江苏长江机械化基础工程公司 A kind of T-shaped screw rod prestressing force counter-force anchor device
CN207362718U (en) * 2017-08-29 2018-05-15 中铁(贵州)市政工程有限公司 A kind of bridge abutment correcting device
CN107386688A (en) * 2017-09-09 2017-11-24 上海先达特种土木工程有限公司 Wedge-shaped temporary support
CN108221718A (en) * 2018-03-05 2018-06-29 湖南省交通规划勘察设计院有限公司 The bridge pier small axial dimension deviation correcting device and method for correcting error of beam body transverse direction deviation

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110331676B (en) * 2019-07-22 2021-08-17 湖南聚创建筑科技有限公司 Pile column type flexible pier deviation rectifying construction device and construction method thereof
CN110331676A (en) * 2019-07-22 2019-10-15 湖南聚创建筑科技有限公司 A kind of pile-column flexible pier Deviation Correction Construction device and its construction method
WO2021022671A1 (en) * 2019-08-07 2021-02-11 湖南联智桥隧技术有限公司 Device for preventing pier deviation of high-pier bridge having large longitudinal slope
CN110820817A (en) * 2019-10-11 2020-02-21 福建省建科工程技术有限公司 Bridge pier stud pile foundation combination deviation rectifying method
CN110983995A (en) * 2019-12-06 2020-04-10 中铁四院集团岩土工程有限责任公司 Beam body jacking method for high-speed railway bridge
CN111877168A (en) * 2020-07-20 2020-11-03 长沙理工大学 Torsion correction method for lattice type steel main beam of combined cable-stayed bridge
CN111877168B (en) * 2020-07-20 2021-10-01 长沙理工大学 Torsion correction method for lattice type steel main beam of combined cable-stayed bridge
CN111926685B (en) * 2020-08-19 2022-02-22 中铁二院工程集团有限责任公司 Shear force conversion component for transversely moving high-speed railway continuous beam and conversion method
CN111926685A (en) * 2020-08-19 2020-11-13 中铁二院工程集团有限责任公司 Shear force conversion component for transversely moving high-speed railway continuous beam and conversion method
CN111979933A (en) * 2020-09-14 2020-11-24 长沙市公路桥梁建设有限责任公司 Elastic limiting stopper for bridge deviation correction and bridge with automatic deviation correction function
CN112813852A (en) * 2021-01-05 2021-05-18 四川交投建设工程股份有限公司 Repairing and reinforcing method for bridge deck subsidence of in-service bridge
CN113668410A (en) * 2021-08-25 2021-11-19 郑州大学 Pier deviation rectifying method using main beam to provide counter force
CN113931086A (en) * 2021-10-28 2022-01-14 湖南省通和工程有限公司 Pier deviation rectifying construction process
CN113931086B (en) * 2021-10-28 2023-12-05 湖南省通和工程有限公司 Pier deviation rectifying construction process
CN114016369A (en) * 2021-12-03 2022-02-08 浙江数智交院科技股份有限公司 Deviation correcting device and beam body structure
CN114016369B (en) * 2021-12-03 2024-03-12 浙江数智交院科技股份有限公司 Deviation correcting device and beam structure
CN114561881A (en) * 2022-03-17 2022-05-31 浙江科技学院 Longitudinal deviation-rectifying and resetting method suitable for soft soil foundation bridge
CN114561881B (en) * 2022-03-17 2024-05-28 浙江科技学院 Longitudinal deviation correcting and resetting method suitable for soft soil foundation bridge
CN114855654A (en) * 2022-06-27 2022-08-05 四川路桥桥梁工程有限责任公司 Stable inclined pier construction method without interrupting traffic operation
CN114855654B (en) * 2022-06-27 2024-02-23 四川路桥桥梁工程有限责任公司 Stable inclined pier construction method without interrupting traffic operation

Similar Documents

Publication Publication Date Title
CN109356042A (en) A kind of replacing and rectificating method after pier slope
CN103821090B (en) Replacing and rectificating method after pier slope
CN105863362B (en) A kind of deviation correcting device for being used to tilt electric power pylon
CN100540809C (en) The replacing supporters for continuous beam without breaking off traffic method
WO2009087469A2 (en) Method and system for raising a building structure
CN103726450B (en) Supported Slab Bridge rises method and adjustable height combination mat stone structure thereof
CN204849607U (en) A continuous beam string basket pre -compaction device for bridge construction
CN101929338B (en) Hydraulic fan-shaped support system for controlling steel frame deformation in tunnel construction
CN107130515A (en) A kind of board-like bridge extension joint of Long span shock resistance multi-directional deflection comb shape
CN114561881B (en) Longitudinal deviation correcting and resetting method suitable for soft soil foundation bridge
CN110374349A (en) A kind of impaired armored concrete cylinder underpins processing unit and its application method
CN113718665A (en) Bridge pier changing method
CN1165234A (en) Method for jacking and correcting deviation of building broken pillar
CN209353211U (en) A kind of abutment suitable for Through Steel suspension bridge
CN214328534U (en) 0# block bracket pre-pressing device of continuous rigid frame bridge
CN205259051U (en) Railway existing line large -span crossbeam system of making somebody a mere figurehead
CN209853576U (en) Multi-direction adjustable track fixing device
CN201412171Y (en) Sector hydraulic support system used for controlling great deformation of steel frame in tunnel construction
CN210216455U (en) Inclined support assembly of building envelope
CN210031846U (en) Lattice column support system capable of implementing prestress compensation
CN111851153A (en) Supporting device and using method thereof
CN207919602U (en) Excavation of foundation pit closes on the supporting construction of existing shallow foundation
CN101736693A (en) Construction process for casting large-tonnage box beam in site by support pier method
CN111827096A (en) Overturn-preventing reinforcing device for single-column pier viaduct
CN109736371A (en) A kind of structures and methods that active control is displaced by disturbance building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190219