Prior art keywords
connector
cage guide
connection structure
side plate
long hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811296856.2A
Other languages
Chinese (zh)
Inventor
孙扬
安建英
郭相参
王鹏飞
过曾明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China ENFI Engineering Corp
Original Assignee
China ENFI Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China ENFI Engineering Corp filed Critical China ENFI Engineering Corp
Priority to CN201811296856.2A priority Critical patent/CN109339796A/en
Publication of CN109339796A publication Critical patent/CN109339796A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D7/00Shaft equipment, e.g. timbering within the shaft
    • E21D7/02Arrangement of guides for cages in shafts; Connection of guides for cages to shaft walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses the connection structure of cage guide and with its mine shaft equipment.Wherein the connection structure of cage guide is used to the cage guide being connected to buntons, which includes: the first connector, and first connector is adapted to be attached on the buntons;Second connector, second connector are adapted to be attached on the cage guide, and second connector is connected with first connector;Wherein, the tie point position of first connector and second connector is adjustable, so that link position of the cage guide on the buntons is adjustable.The connection structure adjustability of the cage guide is good, is easy to guarantee construction precision.

Description

The connection structure of cage guide and mine shaft equipment with it
Technical field
The present invention relates to mine fields, specifically, the present invention relates to the connection structure of cage guide and with its mine Shaft equipment.
Background technique
Vertical shaft is mine and other underground engineerings enter the logistics corridor of the underground space and the key of underground space development Project of primary importance;Recently as the increase of shaft depths, all difficulties have been highlighted in vertical shaft design.Steel guide is mentioned as vertical shaft Container guide frame is risen, has come to have played irreplaceable role always;With the increase of mine shaft depth, the promotion speed of container Directly affect economic benefit.With the increase for promoting speed, pit shaft Steel Structural Design science, installation accuracy etc. are proposed Higher requirement, the even challenge to original structure design.How under the premise of guaranteeing that structure is safe and reliable, steel is improved Cage guide installation accuracy;Meanwhile meeting the science of steel guide connection and the realizability of actual installation, this is to perplex structure always One problem of design.
, many factors such as mechanization degree lower, environment poor, measurement accuracy be not easy guarantee narrow by shaft space Limitation realizes that high accuracy install pit shaft steel construction is a difficult technical work.Existing cage guide connection structure design exists Adjustability is poor, installation accuracy guarantees difficult, live punching secondary damage structure and is easy to cause brokenly component surface erosion resistant coating Many deficiencies such as bad solve to improve cage guide installation accuracy to be to solve one of the key technical problems that deep shaft high-speed smooth is promoted.
Summary of the invention
The present invention is directed to solve at least some of the technical problems in related technologies.For this purpose, of the invention One purpose is the connection structure for proposing cage guide and the mine shaft equipment with it.The connection structure adjustability of the cage guide It is good, it is easy to guarantee construction precision.
In one aspect of the invention, the present invention proposes a kind of connection structure of cage guide, and the connection structure is used for The cage guide is connected on buntons, according to an embodiment of the invention, the connection structure of the cage guide includes: the first connector, First connector is adapted to be attached on the buntons;Second connector, second connector are adapted to be attached to described On cage guide, and second connector is connected with first connector;Wherein, first connector and second connection The tie point position of part is adjustable, so that link position of the cage guide on the buntons is adjustable.
The connection structure of cage guide according to an embodiment of the present invention, first by the first connector and the second connector respectively with tank Road beam and cage guide are connected and fixed, then the first connector and the second connector are fixed, and realize the connection of cage guide and buntons. Wherein, the tie point position of the first connector and the second connector is adjustable, and the relative position of cage guide and buntons is made to be easier to adjust Section, to be easier to guarantee construction precision.Meanwhile each component can be assembled directly at the construction field (site) after prefabrication, be saved Go the damage and anti-corrosion damage layer at the scene to processes such as component punchings, so as to avoid element structure.As a result, using the present invention The connection structure design of the cage guide of embodiment can either effectively promote installation accuracy, and be beneficial to guarantee installation progress, promote work Journey economy and social benefit.
In addition, the connection structure of cage guide according to the above embodiment of the present invention can also have following additional technology special Sign:
In some embodiments of the invention, first connector include the first side plate and the second side plate, described first Side plate is arranged in a mutually vertical manner with second side plate, and first side plate is connected with the buntons, second side plate and institute The second connector is stated to be connected.
In some embodiments of the invention, the connection structure of the cage guide further comprises: bolt kit, the bolt External member is suitable for fixed second side plate and second connector.
In some embodiments of the invention, include the first long hole on second side plate, wrapped on second connector Include the second long hole;First long hole extends along the width direction of second side plate, and second long hole connects along described second The length direction of fitting extends;First long hole and second long hole are equipped with, to pass through the bolt kit First long hole and second long hole are attached fixation to second side plate and second connector.
In some embodiments of the invention, the bolt kit, first long hole and second long hole include Two, two first long holes are separately positioned on the both ends of second side plate, and two second long holes are separately positioned on The both ends of second connector.
In some embodiments of the invention, the connection structure of the cage guide further comprises: adjusting gasket, the adjusting Gasket is arranged between second side plate and second connector.
In some embodiments of the invention, corresponding with first long hole and second long hole in the adjusting gasket Position have opening.
In another aspect of this invention, the invention proposes a kind of mine shaft equipments.According to an embodiment of the invention, institute It states and is equipped with cage guide and buntons in the pit shaft of mine shaft equipment, the described connection structure is solid through the foregoing embodiment for the cage guide It is scheduled on the buntons.
Mine shaft equipment according to an embodiment of the present invention makes by using the connection structure of the cage guide of above-described embodiment The relative position of cage guide and buntons is easier to adjust, to be easier to guarantee construction precision.Meanwhile each component in connection structure After prefabrication, it can directly be assembled, be saved at the scene to processes such as component punchings, so as to avoid structure at the construction field (site) The damage of part structure and anti-corrosion damage layer.Mine shaft equipment according to an embodiment of the present invention by using above-described embodiment tank The connection structure in road can either effectively promote installation accuracy, and be beneficial to guarantee installation progress, promote engineering economy and society Benefit.
In addition, mine shaft equipment according to the above embodiment of the present invention can also have the following additional technical features:
In some embodiments of the invention, the connection structure includes multiple, and multiple connection structures are along the tank The length direction in road is arranged.
Additional aspect and advantage of the invention will be set forth in part in the description, and will partially become from the following description Obviously, or practice through the invention is recognized.
Detailed description of the invention
Above-mentioned and/or additional aspect of the invention and advantage will become from the description of the embodiment in conjunction with the following figures Obviously and it is readily appreciated that, in which:
Fig. 1 is the structural schematic diagram of the connection structure of cage guide according to an embodiment of the present invention;
Fig. 2 is another viewing angle constructions schematic diagram of the connection structure of cage guide according to an embodiment of the present invention;
Fig. 3 is another viewing angle constructions schematic diagram of the connection structure of cage guide according to an embodiment of the present invention;
Fig. 4 is the structural schematic diagram of the first connector in the connection structure of cage guide according to an embodiment of the present invention;
Fig. 5 is the structural schematic diagram of the second connector in the connection structure of cage guide according to an embodiment of the present invention;
Fig. 6 is the structural schematic diagram of adjusting gasket in the connection structure of cage guide according to an embodiment of the present invention.
Specific embodiment
The embodiment of the present invention is described below in detail, examples of the embodiments are shown in the accompanying drawings, wherein from beginning to end Same or similar label indicates same or similar element or element with the same or similar functions.Below with reference to attached The embodiment of figure description is exemplary, it is intended to is used to explain the present invention, and is not considered as limiting the invention.
In the description of the present invention, it is to be understood that, term " center ", " longitudinal direction ", " transverse direction ", " length ", " width ", " thickness ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside", etc. instruction Orientation or positional relationship be based on the orientation or positional relationship shown in the drawings, be merely for convenience of description the present invention and simplification retouch It states, rather than the device or element of indication or suggestion meaning must have a particular orientation, be constructed and operated in a specific orientation, Therefore it is not considered as limiting the invention.
In addition, term " first ", " second " are used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance Or implicitly indicate the quantity of indicated technical characteristic.Define " first " as a result, the feature of " second " can be expressed or Implicitly include at least one this feature.In the description of the present invention, the meaning of " plurality " is at least two, such as two, three It is a etc., unless otherwise specifically defined.
In the present invention unless specifically defined or limited otherwise, the terms such as " installation ", " connected ", " connection ", " fixation " It shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or is integral;It can be mechanical connection, It is also possible to be electrically connected;It can be directly connected, can also can be inside two elements indirectly connected through an intermediary The interaction relationship of connection or two elements, unless otherwise restricted clearly.For the ordinary skill in the art, The specific meanings of the above terms in the present invention can be understood according to specific conditions.
In the present invention unless specifically defined or limited otherwise, fisrt feature in the second feature " on " or " down " can be with It is that the first and second features directly contact or the first and second features pass through intermediary mediate contact.Moreover, fisrt feature exists Second feature " on ", " top " and " above " but fisrt feature be directly above or diagonally above the second feature, or be merely representative of First feature horizontal height is higher than second feature.Fisrt feature can be under the second feature " below ", " below " and " below " One feature is directly under or diagonally below the second feature, or is merely representative of first feature horizontal height less than second feature.
In one aspect of the invention, the present invention proposes a kind of connection structure of cage guide, with reference to Fig. 1~3, the connection Structure is used to cage guide 1 being connected to buntons 2, according to an embodiment of the invention, the connection structure of the cage guide includes: the first company Fitting 3 and the second connector 4.Wherein, the first connector 3 is adapted to be attached on buntons 2;Second connector 4 is adapted to be attached to On cage guide 1, and the second connector 4 is connected with the first connector 3;The tie point position of first connector 3 and the second connector 4 can It adjusts, so that position of the cage guide 1 on buntons 2 is adjustable.
The connection structure of cage guide according to an embodiment of the present invention, first by the first connector and the second connector respectively with tank Road beam and cage guide are connected and fixed, then the first connector and the second connector are fixed, and realize the connection of cage guide and buntons. Wherein, the tie point position of the first connector and the second connector is adjustable, and the relative position of cage guide and buntons is made to be easier to adjust Section, to be easier to guarantee construction precision.Meanwhile each component can be assembled directly at the construction field (site) after prefabrication, be saved Go the damage and anti-corrosion damage layer at the scene to processes such as component punchings, so as to avoid element structure.As a result, using the present invention The connection structure design of the cage guide of embodiment can either effectively promote installation accuracy, and be beneficial to guarantee installation progress, promote work Journey economy and social benefit.
According to an embodiment of the invention, can be by the method for welding respectively by the first connector and buntons, the second company Fitting is attached with cage guide.And then cage guide and cage guide are realized by the way that the first connector and the second connector to be connected and fixed again The connection of beam.As a result, when needing to adjust the relative position of cage guide and buntons, it is connect by using the first connector with second The long hole reserved on part is adjusted, to improve construction precision and efficiency.
According to an embodiment of the invention, the structure of cage guide and buntons is not particularly restricted.It is more according to the present invention Embodiment, cage guide can use square steel or other fashioned iron, and buntons can use I-steel or other fashioned iron.
It is described in detail below with reference to the connection structure of Fig. 1~6 pair cage guide according to an embodiment of the present invention:
According to an embodiment of the invention, the first connector 3 includes the first side plate 31 and the second side plate 32, the first side plate 31 with Second side plate 32 is arranged in a mutually vertical manner, and the first side plate 31 is connected with buntons 2, and the second side plate 32 is connected with the second connector 4.Such as Shown in Fig. 1, the section of the first connector 3 in the direction of the width is L shape, and the first side plate 31 and the second side plate 32 are respectively formed as L Two sides of shape.Wherein, the first side plate 31 can be welded on buntons 2.
According to an embodiment of the invention, the connection structure of cage guide of the invention can further include: spiral shell with reference to Fig. 1 Bolt external member 5.Bolt kit 5 is suitable for fixing the second side plate 32 and the second connector 4.
It include the first long hole 6 on the second side plate 32 according to an embodiment of the invention, with reference to Figure 4 and 5, on the second connector 4 Including the second long hole 7;First long hole 6 extends along the width direction of the second side plate 32, length of second long hole 7 along the second connector 4 Direction is spent to extend;First long hole 6 and second long hole 7 are equipped with, to make bolt kit 5 pass through the first long hole 6 and the Two long holes 7 are attached fixation to the second side plate 32 and the second connector 4.First on second side plate 32 and the second connector 4 Long hole 6 and the second long hole 7 can be prefabricated in the factory to obtain, and avoid component caused by being punched out at the construction field (site) to component Structural damage.In addition, the first long hole 6 and the second long hole 7 extend in different directions respectively, combination significantly improves first The adjustable freedom degree of connector 3 and the second connector 4 when connecting installation, to further make the opposite of cage guide 1 and buntons 2 Position can easily be accommodated, and be conducive to improve construction precision.
According to an embodiment of the invention, bolt kit 5, the first long hole 6 and the second long hole 7 may each comprise two, two First long hole 6 is separately positioned on the both ends of the second side plate 32, and two the second long holes 7 are separately positioned on the both ends of the second connector 4. It using two bolt kits 5 is used to that the second side plate 32 and the second connector 4 to be fixed in each connection structure as a result, On the one hand the adjustable extent that can be further improved component, on the other hand also helps cage guide 1 and stablizing for buntons 2 is fixed.
According to an embodiment of the invention, the connection structure of cage guide of the invention can further include: adjusting gasket 8, Adjusting gasket 8 is arranged between the second side plate 32 and the second connector 4.As a result, by controlling to adjust the thickness of gasket 8, hold very much The spacing for easily adjusting the second side plate 32 and the second connector 4, so that cage guide 1 and the relative position of buntons 2 further be made to be easy to It adjusts, is conducive to improve construction precision.
According to an embodiment of the invention, as shown in fig. 6, corresponding with the first long hole 6 and the second long hole 7 in adjusting gasket 8 Position has opening 9.As a result, when being attached using bolt kit 5 to the second side plate 32 and the second connector 4, bolt sleeve Part can pass through opening 9.In some embodiments, adjusting gasket 8 can be formed by elastic material.Pass through control bolt sleeve as a result, The tightening of part is loosened, and the thickness of adjusting gasket 8 can be directly controlled.In further embodiments, adjusting gasket 8 can be by rigidity Material is formed, and adjusts the relative position of cage guide 1 and buntons 2 by directly selecting the gasket of different-thickness.To further Convenient for the adjusting of 2 relative position of cage guide 1 and buntons.
In summary, the connection structure of cage guide according to an embodiment of the present invention passes through the first long hole, the second long hole and bolt The cooperation of external member realizes buntons and is bolted entirely with cage guide, is three-dimensional adjustable, overcomes original Steel Structural Design and adjust difficulty The problem of, it solves vertical shaft installation accuracy and guarantees one of difficult point.Meanwhile buntons is welded and fixed with the first connector in advance, tank Road is welded and fixed with the second connector in advance, and for all components after prefabrication, construction site need to only carry out the first connector, Two connectors and the connection of the bolt of adjusting gasket are saved at the scene to processes such as component punchings, so as to avoid element structure Damage and anti-corrosion damage layer.Installation essence can either effectively be promoted using the connection structure design of the cage guide of the embodiment of the present invention Degree, and be beneficial to guarantee installation progress, promote engineering economy and social benefit.
In another aspect of this invention, the invention proposes a kind of mine shaft equipments.According to an embodiment of the invention, should Cage guide and buntons are equipped in the pit shaft of mine shaft equipment, wherein cage guide through the foregoing embodiment fix by the connection structure On buntons.
Mine shaft equipment according to an embodiment of the present invention makes by using the connection structure of the cage guide of above-described embodiment The relative position of cage guide and buntons is easier to adjust, to be easier to guarantee construction precision.Meanwhile each component in connection structure After prefabrication, it can directly be assembled, be saved at the scene to processes such as component punchings, so as to avoid structure at the construction field (site) The damage of part structure.Mine shaft equipment according to an embodiment of the present invention by using the cage guide of above-described embodiment connection knot Structure can either effectively promote installation accuracy, and be beneficial to guarantee installation progress, promote engineering economy and social benefit.
According to an embodiment of the invention, connection structure may include it is multiple, multiple connection structures can be along the length direction of cage guide Setting.
It should be noted that mine shaft equipment of the invention has the whole of the connection structure of cage guide described above Feature and advantage, this is no longer going to repeat them.
In the description of this specification, reference term " one embodiment ", " some embodiments ", " example ", " specifically show The description of example " or " some examples " etc. means specific features, structure, material or spy described in conjunction with this embodiment or example Point is included at least one embodiment or example of the invention.In the present specification, schematic expression of the above terms are not It must be directed to identical embodiment or example.Moreover, particular features, structures, materials, or characteristics described can be in office It can be combined in any suitable manner in one or more embodiment or examples.In addition, without conflicting with each other, the skill of this field Art personnel can tie the feature of different embodiments or examples described in this specification and different embodiments or examples It closes and combines.
Although the embodiments of the present invention has been shown and described above, it is to be understood that above-described embodiment is example Property, it is not considered as limiting the invention, those skilled in the art within the scope of the invention can be to above-mentioned Embodiment is changed, modifies, replacement and variant.

Claims (9)

1. a kind of connection structure of cage guide, the connection structure is used to the cage guide being connected to buntons, which is characterized in that Include:
First connector, first connector are adapted to be attached on the buntons;
Second connector, second connector are adapted to be attached on the cage guide, and second connector and described first Connector is connected;
Wherein, the tie point position of first connector and second connector is adjustable, so that the cage guide is in the tank Link position on road beam is adjustable.
2. the connection structure of cage guide according to claim 1, which is characterized in that first connector includes the first side plate With the second side plate, first side plate is arranged in a mutually vertical manner with second side plate, first side plate and the buntons phase Even, second side plate is connected with second connector.
3. the connection structure of cage guide according to claim 2, which is characterized in that further comprise:
Bolt kit, the bolt kit are suitable for fixed second side plate and second connector.
4. the attachment device of cage guide according to claim 3, which is characterized in that include first long on second side plate Hole includes the second long hole on second connector;First long hole extends along the width direction of second side plate, described Second long hole extends along the length direction of second connector;First long hole and second long hole are equipped with, with Just the bolt kit is made to pass through first long hole and second long hole to second side plate and second connector It is attached fixation.
5. the connection structure of cage guide according to claim 4, which is characterized in that the bolt kit, first long hole It include two with second long hole, two first long holes are separately positioned on the both ends of second side plate, two institutes State the both ends that the second long hole is separately positioned on second connector.
6. the connection structure of cage guide according to claim 4 or 5, which is characterized in that further comprise:
Adjusting gasket, the adjusting gasket are arranged between second side plate and second connector.
7. the connection structure of cage guide according to claim 6, which is characterized in that long with described first in the adjusting gasket Hole and the corresponding position of second long hole have opening.
8. a kind of mine shaft equipment, which is characterized in that be equipped with cage guide and buntons, institute in the pit shaft of the mine shaft equipment Cage guide is stated to be fixed on the buntons by the described in any item connection structures of claim 1~7.
9. mine shaft equipment according to claim 8, which is characterized in that the connection structure includes multiple, Duo Gesuo The length direction that connection structure is stated along the cage guide is arranged.
CN201811296856.2A 2018-11-01 2018-11-01 The connection structure of cage guide and mine shaft equipment with it Pending CN109339796A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811296856.2A CN109339796A (en) 2018-11-01 2018-11-01 The connection structure of cage guide and mine shaft equipment with it

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811296856.2A CN109339796A (en) 2018-11-01 2018-11-01 The connection structure of cage guide and mine shaft equipment with it

Publications (1)

Publication Number Publication Date
CN109339796A true CN109339796A (en) 2019-02-15

Family

ID=65313684

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811296856.2A Pending CN109339796A (en) 2018-11-01 2018-11-01 The connection structure of cage guide and mine shaft equipment with it

Country Status (1)

Country Link
CN (1) CN109339796A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109987477A (en) * 2019-04-10 2019-07-09 中国恩菲工程技术有限公司 Cage guide fixed structure
CN111824913A (en) * 2020-07-24 2020-10-27 中国矿业大学 Magnetorheological type cage guide and cage guide beam connecting structure and mine shaft equipment

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5533701A (en) * 1994-12-08 1996-07-09 Trank; Robert D. Foldable stabilizing bracket for compressed air tanks
CN2849173Y (en) * 2005-11-30 2006-12-20 中国矿业大学 Expansion cage guide of annular pipe vertical well
CN203820241U (en) * 2014-02-12 2014-09-10 中煤西安设计工程有限责任公司 Telescopic steel rail shaft guide
CN108049875A (en) * 2018-01-22 2018-05-18 中国恩菲工程技术有限公司 The connection structure of cage guide and with its mine shaft equipment
CN208019706U (en) * 2018-03-08 2018-10-30 肥城白庄煤矿有限公司 Fixture for rigid cage guide beam reparation
CN209195409U (en) * 2018-11-01 2019-08-02 中国恩菲工程技术有限公司 The connection structure of cage guide and mine shaft equipment with it

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5533701A (en) * 1994-12-08 1996-07-09 Trank; Robert D. Foldable stabilizing bracket for compressed air tanks
CN2849173Y (en) * 2005-11-30 2006-12-20 中国矿业大学 Expansion cage guide of annular pipe vertical well
CN203820241U (en) * 2014-02-12 2014-09-10 中煤西安设计工程有限责任公司 Telescopic steel rail shaft guide
CN108049875A (en) * 2018-01-22 2018-05-18 中国恩菲工程技术有限公司 The connection structure of cage guide and with its mine shaft equipment
CN208019706U (en) * 2018-03-08 2018-10-30 肥城白庄煤矿有限公司 Fixture for rigid cage guide beam reparation
CN209195409U (en) * 2018-11-01 2019-08-02 中国恩菲工程技术有限公司 The connection structure of cage guide and mine shaft equipment with it

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109987477A (en) * 2019-04-10 2019-07-09 中国恩菲工程技术有限公司 Cage guide fixed structure
CN109987477B (en) * 2019-04-10 2024-03-15 中国恩菲工程技术有限公司 Cage guide fixing structure
CN111824913A (en) * 2020-07-24 2020-10-27 中国矿业大学 Magnetorheological type cage guide and cage guide beam connecting structure and mine shaft equipment
CN111824913B (en) * 2020-07-24 2021-07-13 中国矿业大学 Magnetorheological type cage guide and cage guide beam connecting structure and mine shaft equipment

Similar Documents

Publication Publication Date Title
CN205804591U (en) A kind of node connected for precast concrete frame column assembled
CN109339796A (en) The connection structure of cage guide and mine shaft equipment with it
US10544014B2 (en) Method for hoisting and transporting assemblies in underground nuclear power plant
CN209195409U (en) The connection structure of cage guide and mine shaft equipment with it
CN103758115A (en) Composite material fold-line-shaped plate connecting structure
CN103821157A (en) Wallboard lattice type steel cover box and method for constructing underwater bearing platform steel cover box
CN111989286B (en) Box girder, in particular crane girder, and crane and method for producing same
CN208734702U (en) A kind of reassembling type T-bolt
CN205804363U (en) A kind of floating, fixing convertible pile foundation in water construction platform device
CN104192707B (en) Coke oven door flip horizontal special tool
CN110805024A (en) Prefabricated guide wall of underground continuous wall
CN106948262B (en) A kind of Orthotropic Steel Bridge Deck structure with lateral binder
CN202688882U (en) Cofferdam lowering positioning platform for double-wall steel cofferdam construction of deep-water bridge pier
JP2012232651A (en) Knockdown pontoon
CN210262912U (en) Assembled river course ecological frame type retaining wall
CN209799020U (en) steel bar formwork integrated wall and coupling beam mechanical connection structure
CN109881790A (en) Steel bar template integrated wall adds movable reinforcing bar connecting structure and installation method
CN210289321U (en) Auxiliary mounting device for crossed oblique material node board of power transmission tower
CN208797543U (en) A kind of open caisson of overhanging type bracket staggered floor transposition cable laying
CN209907606U (en) Reinforcing bar template integrated wall additional movable reinforcing bar connecting structure
CN203755323U (en) Wall plate lattice type steel boxed cofferdam
CN207568074U (en) A kind of secondary structure member reinforcing steel bar connecting node
CN215210985U (en) Underground continuous wall with stronger shearing resistance along depth direction
CN102535507A (en) Combined tower base
CN202467171U (en) Architectural aluminum alloy mould plate component

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination