CN109339062A - The guard method and its protection structure that fuel gas conduit is intersected above when thermal pipe is laid with - Google Patents

The guard method and its protection structure that fuel gas conduit is intersected above when thermal pipe is laid with Download PDF

Info

Publication number
CN109339062A
CN109339062A CN201811484967.6A CN201811484967A CN109339062A CN 109339062 A CN109339062 A CN 109339062A CN 201811484967 A CN201811484967 A CN 201811484967A CN 109339062 A CN109339062 A CN 109339062A
Authority
CN
China
Prior art keywords
brick wall
burning line
laid
gravel
fuel gas
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811484967.6A
Other languages
Chinese (zh)
Inventor
宗成海
宋连胜
裴继宏
栾继春
李思春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ji'nan Heat Group Co Ltd
Original Assignee
Ji'nan Heat Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ji'nan Heat Group Co Ltd filed Critical Ji'nan Heat Group Co Ltd
Priority to CN201811484967.6A priority Critical patent/CN109339062A/en
Publication of CN109339062A publication Critical patent/CN109339062A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/12Back-filling of foundation trenches or ditches
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/06Accessories therefor, e.g. anchors

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses guard methods and its protection structure that fuel gas conduit when thermal pipe laying is intersected above; verify burning line position; hand excavation is used in 3 meters of burning line; after digging out the groove that heating pipeline is installed in burning line lower part enough; in burning line lower part, wooden gusseted is set; smooth burning line lower channel, backfill 200mm gravel do trench liner, are then laid with heating pipeline;Reduce damage of the channel bottom of out-of-flatness to heating pipeline, brick wall supporting is set in burning line two sides, brick wall trench liner as described in step 3 is laid with upwards, and level is higher than burning line tube top on brick wall;Brick wall plays the role of protecting burning line, supports the pressure of the soil layer from surrounding, while cutting down the pressure that road surface transmitting comes, back-filling in layers gravel, and gravel is backfilled to higher than brick wall top, and is tamped with water pouring;Gravel is backfilled to higher than brick wall top, and is tamped with water pouring.

Description

The guard method and its protection structure that fuel gas conduit is intersected above when thermal pipe is laid with
Technical field
The present invention relates to cross over line protection technique fields when heating pipeline construction, fire when specifically thermal pipe is laid with The guard method and its protection structure that tracheae intersects above.
Background technique
Major part urban district central heating now starts from eighties of last century, and when design lacks long-term plan, along with the time is remote Seriously corroded, heating season problem take place frequently.Heating network transformation needs take leave of " patch maintenance ", be not where be broken repair where, and It is to redesign transformation, it is long-standing is expected to the heating of solution old residential area.And most of problem is what part was used for heat unit Boiler is relatively backward, power output is not high;Complete auxiliaries equipment and pipe network are long neglected and in disrepair, and operational efficiency is relatively low.
Simultaneously because urban construction needs, the various pipelines of different time laying can be encountered when pipe network upgrading And route, higher risk is exactly burning line, and burning line migration is lost more than gain, combustion gas route and heating pipeline phase It hands over.Excavate to change by design requirement and fill out miscellaneous fill and plain fill and backfill qualified gravel, in order to guarantee burning line and construction site Safety, it is necessary to which protective treatment is carried out to natural gas pipeline.
Summary of the invention
The present invention be exactly in order to solve deficiencies of the prior art, provide thermal pipe be laid with when fuel gas conduit above The guard method and its protection structure of intersection.Entire work progress and structural defence burning line are injury-free, use simultaneously The reasonable Arrangements such as brick wall, sandy gravel stratum ensure that burning line not by external pressure.
The technical scheme adopted by the invention to solve the technical problem is that:
The guard method that intersects above of fuel gas conduit when thermal pipe is laid with, the guard method the following steps are included:
Step 1: verifying burning line position, hand excavation is used in 3 meters of burning line;
Determine the specific location of burning line.It is excavated within the scope of 3 meters of pipeline and uses hand excavation, it is careful, and reinforce Observation, in order to avoid damage burning line.
Step 2: wood is arranged in burning line lower part after digging out the groove that heating pipeline is installed in burning line lower part enough Matter gusseted;
Step 3: smooth burning line lower channel, backfill 200mm gravel does trench liner, is then laid with heating pipeline; Reduce damage of the channel bottom of out-of-flatness to heating pipeline.
Step 4: brick wall supporting is arranged in burning line two sides, brick wall trench liner as described in step 3 is laid with upwards, Level is higher than burning line tube top on brick wall;Brick wall plays the role of protecting burning line, supports the soil layer from surrounding Pressure, while cut down road surface transmitting come pressure.
Step 5: back-filling in layers gravel, gravel is backfilled to higher than brick wall top, and is tamped with water pouring;Gravel backfill is supreme It is tamped in brick wall top, and with water pouring;This mode can make sandy gravel stratum bury brick wall, so that the stress from ground point It dissipates, protects the stability of burning line and heating pipeline.
Step 6: disposing 30mm thick steel plate in the upper plane that step 5 generates;
C30 concrete layer is filled out Step 7: filling on the steel plate of step 6, then uses blacktop capping;
Brick wall is parallel to burning line in the step 4, and the brick wall is away from nearest burning line axle center distance 300mm, brick wall are risen in burning line tube top 300mm, and the brick wall is 37 brick walls.
Concrete layer described in the step seven is 600mm.
Gravel in the step 5 is backfilled to higher than brick wall top 100mm.This height be be laid with when be higher by 100mm, and It is not that the height after tamping is poured with water.In practice of construction, it is basic consistent with brick wall height that rear sandy gravel stratum is tamped with water pouring.
The protection structure used in the guard method that fuel gas conduit is intersected above when thermal pipe is laid with, including the ditch after excavating The trench liner of trench bottom, the trench liner top are equipped with heating pipeline, are equipped with nesting on the trench liner The brick wall of heating pipeline, the brick wall are two stifled, and two stifled brick walls are located at burning line two sides in parallel, on the stifled brick wall of described two Plane is higher by burning line tube top;
Outside is equipped with sandy gravel stratum in the brick wall, and plane is stamped steel plate, the steel plate top on the brick wall Filling is filled with C30 concrete layer, and the concrete layer top is equipped with blacktop.The beneficial effects of the present invention are:
1, entire work progress and structural defence burning line are injury-free while reasonable using brick wall, sandy gravel stratum etc. Arrangement ensure that burning line not by external pressure.
2, trench liner reduces damage of the channel bottom of out-of-flatness to heating pipeline.
3, gravel is backfilled to higher than brick wall top, and is tamped with water pouring;This mode can make sandy gravel stratum cover brick wall It buries, so that the stress from ground disperses, protects the stability of burning line and heating pipeline.
4, the effect of concrete, steel plate is also supporting role, ensure that heating pipeline not by the pressure from road surface.
5, brick wall plays the role of protecting burning line, supports the pressure of the soil layer from surrounding, while cutting down thermal pipe The pressure that line and road surface transmitting come.
Detailed description of the invention
Fig. 1 is the layout view of present invention protection structure.
In figure: 1- burning line, 2- heating pipeline, 3- brick wall, 4- sandy gravel stratum, 5- concrete layer, 6- steel plate, 7- groove pad Layer, 8- blacktop.
Specific embodiment
In order to clearly illustrate the technical characterstic of this programme, below by specific embodiment, and its attached drawing is combined, to this Invention is described in detail.Following disclosure provides many different embodiments or example is used to realize different knots of the invention Structure.In order to simplify disclosure of the invention, hereinafter the component of specific examples and setting are described.In addition, the present invention can be with Repeat reference numerals and/or letter in different examples.This repetition is that for purposes of simplicity and clarity, itself is not indicated Relationship between various embodiments and/or setting is discussed.It should be noted that illustrated component is not necessarily to scale in the accompanying drawings It draws.Present invention omits the descriptions to known assemblies and treatment technology and process to avoid the present invention is unnecessarily limiting.Art The orientation or positional relationship of the instructions such as language "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outside" is It is based on the orientation or positional relationship shown in the drawings, is merely for convenience of description of the present invention and simplification of the description, rather than instruction or dark Show that signified device or element must have a particular orientation, be constructed and operated in a specific orientation, therefore should not be understood as pair Limitation of the invention.In addition, term " first ", " second ", " third " are used for description purposes only, and it should not be understood as instruction or dark Show relative importance.In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " peace Dress ", " connected ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integrally Connection;It can be mechanical connection, be also possible to be electrically connected;Can be directly connected, can also indirectly connected through an intermediary, It can be the connection inside two elements.For the ordinary skill in the art, above-mentioned art can be understood with concrete condition The concrete meaning of language in the present invention.
The guard method that intersects above of fuel gas conduit when thermal pipe is laid with, the guard method the following steps are included:
Step 1: verifying 1 position of burning line, hand excavation is used in 3 meters of burning line;
Determine the specific location of burning line 1.It is excavated within the scope of 3 meters of pipeline and uses hand excavation, it is careful, and reinforce Observation, in order to avoid damage burning line 1.
Step 2: being arranged after digging out the groove that heating pipeline 2 is installed in 1 lower part of burning line enough in 1 lower part of burning line Wooden gusseted;
Step 3: smooth 1 lower channel of burning line, backfill 200mm gravel does trench liner 7, is then laid with thermal pipe Line 2;Reduce damage of the channel bottom of out-of-flatness to heating pipeline.
Step 4: 3 supporting of brick wall is arranged in 1 two sides of burning line, the trench liner 7 as described in step 3 of brick wall 3 is upward It is laid with, level is higher than 1 tube top of burning line on brick wall 3;Brick wall 3 plays the role of protecting burning line 1, and support is from week The pressure of the soil layer enclosed, while cutting down the pressure that road surface transmitting comes.
Step 5: back-filling in layers gravel, gravel is backfilled to be pushed up higher than brick wall 3, and is tamped with water pouring;
Gravel is backfilled to be pushed up higher than brick wall 3, and is tamped with water pouring;This mode can make sandy gravel stratum 4 cover brick wall 3 It buries, so that the stress from ground disperses, protects the stability of burning line 1 and heating pipeline 2.
Step 6: disposing 30mm thick steel plate 6 in the upper plane that step 5 generates;
C30 concrete layer 5 is filled out Step 7: filling on the steel plate 6 of step 6, then uses 8 capping of blacktop;
Brick wall 3 is parallel to burning line 1 in the step 4, and the brick wall 3 is away from nearest 1 axle center distance of burning line For 300mm, brick wall 3 is risen in 1 tube top 300mm of burning line, and the brick wall 3 is 37 brick walls.
Concrete layer 5 is described in the step seven with a thickness of 600mm.
Gravel in the step 5, which is backfilled to, pushes up 100mm higher than brick wall 3.
The protection structure used in the guard method that fuel gas conduit is intersected above when thermal pipe is laid with, including the ditch after excavating The trench liner 7 of trench bottom, 7 top of trench liner are equipped with heating pipeline 2, are equipped on the trench liner 7 The brick wall of nested heating pipeline 2, the brick wall 3 are two stifled, and two stifled brick walls 3 are located at 1 two sides of burning line in parallel, described two Plane is higher by 1 tube top of burning line on stifled brick wall 3;
Outside is equipped with sandy gravel stratum 4 in the brick wall 3, and plane is stamped steel plate 6, the steel plate 6 on the brick wall 3 Top fills and is filled with C30 concrete layer 5, and 5 top of concrete layer is equipped with blacktop 8.
The above embodiment is a preferred embodiment of the present invention, but embodiments of the present invention are not by above-described embodiment Limitation, other any changes, modifications, substitutions, combinations, simplifications made without departing from the spirit and principles of the present invention, It should be equivalent substitute mode, be included within the scope of the present invention.

Claims (5)

  1. The guard method that fuel gas conduit is intersected above when 1. thermal pipe is laid with, characterized in that the guard method includes following Step:
    Step 1: verifying burning line position, hand excavation is used in 3 meters of burning line;
    Step 2: being arranged wooden three in burning line lower part after digging out the groove that heating pipeline is installed in burning line lower part enough Angle support;
    Step 3: smooth burning line lower channel, backfill 200mm gravel does trench liner, is then laid with heating pipeline;
    Step 4: brick wall supporting is arranged in burning line two sides, brick wall trench liner as described in step 3 is laid with upwards, brick wall Upper level is higher than burning line tube top;
    Step 5: back-filling in layers gravel, gravel is backfilled to higher than brick wall top, and is tamped with water pouring;
    Step 6: disposing 30mm thick steel plate in the upper plane that step 5 generates;
    C30 concrete layer is filled out Step 7: filling on the steel plate of step 6, then uses blacktop capping.
  2. The guard method that fuel gas conduit is intersected above when 2. thermal pipe according to claim 1 is laid with, characterized in that described Brick wall is parallel to burning line in step 4, and the brick wall is 300mm away from nearest burning line axle center distance, and brick wall is risen In burning line tube top 300mm, the brick wall is 37 brick walls.
  3. The guard method that fuel gas conduit is intersected in lower section when 3. thermal pipe according to claim 1 is laid with, characterized in that described The step of seven in concrete layer be 600mm.
  4. The guard method that fuel gas conduit is intersected in lower section when 4. thermal pipe according to claim 1 is laid with, characterized in that described Gravel in step 5 is backfilled to higher than brick wall top 100mm.
  5. 5. the protection structure used in the guard method that fuel gas conduit is intersected above when being laid with according to thermal pipe described in right 1, It is characterized in, the trench liner including the channel bottom after excavating, the trench liner top is equipped with heating pipeline, described The brick wall of nested heating pipeline is equipped on trench liner, the brick wall is two stifled, and two stifled brick walls are located at burning line in parallel Two sides, plane is higher by burning line tube top on the stifled brick wall of described two;
    Outside is equipped with sandy gravel stratum in the brick wall, and plane is stamped steel plate on the brick wall, and the steel plate top fills and fills out There is C30 concrete layer, the concrete layer top is equipped with blacktop.
CN201811484967.6A 2018-12-05 2018-12-05 The guard method and its protection structure that fuel gas conduit is intersected above when thermal pipe is laid with Pending CN109339062A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811484967.6A CN109339062A (en) 2018-12-05 2018-12-05 The guard method and its protection structure that fuel gas conduit is intersected above when thermal pipe is laid with

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811484967.6A CN109339062A (en) 2018-12-05 2018-12-05 The guard method and its protection structure that fuel gas conduit is intersected above when thermal pipe is laid with

Publications (1)

Publication Number Publication Date
CN109339062A true CN109339062A (en) 2019-02-15

Family

ID=65303237

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811484967.6A Pending CN109339062A (en) 2018-12-05 2018-12-05 The guard method and its protection structure that fuel gas conduit is intersected above when thermal pipe is laid with

Country Status (1)

Country Link
CN (1) CN109339062A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110924435A (en) * 2019-12-16 2020-03-27 山东顺河路桥工程有限公司 Transverse pipeline fixing device under transverse structure and construction method thereof
CN112323854A (en) * 2019-08-05 2021-02-05 张继红 Forest type excavation construction method for subway station

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101565964A (en) * 2009-05-25 2009-10-28 青岛恒生源集团建设有限公司 Construction method for mounting outdoor embedded high-density polyethylene double-wall corrugated drain pipe
CN103235380A (en) * 2013-05-11 2013-08-07 中煤科工集团武汉设计研究院 Method for long-distance coal conveying pipeline and communication cable to pass through underground engineering pipeline
CN105155376A (en) * 2015-08-17 2015-12-16 苏州同尚工程设计咨询有限公司 Non-pressed pipeline reinforcing structure for road surface and construction method for non-pressed pipeline reinforcing structure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101565964A (en) * 2009-05-25 2009-10-28 青岛恒生源集团建设有限公司 Construction method for mounting outdoor embedded high-density polyethylene double-wall corrugated drain pipe
CN103235380A (en) * 2013-05-11 2013-08-07 中煤科工集团武汉设计研究院 Method for long-distance coal conveying pipeline and communication cable to pass through underground engineering pipeline
CN105155376A (en) * 2015-08-17 2015-12-16 苏州同尚工程设计咨询有限公司 Non-pressed pipeline reinforcing structure for road surface and construction method for non-pressed pipeline reinforcing structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112323854A (en) * 2019-08-05 2021-02-05 张继红 Forest type excavation construction method for subway station
CN112323854B (en) * 2019-08-05 2021-10-29 张继红 Forest type excavation construction method for subway station
CN110924435A (en) * 2019-12-16 2020-03-27 山东顺河路桥工程有限公司 Transverse pipeline fixing device under transverse structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN106641440B (en) A kind of transverse crossing railway line underground piping jacking construction method
CN105421470B (en) Assembled anchor pole arched framework combined type ecological revetment construction method
CN106436720A (en) Small-size deep foundation pit supporting structure for pipe jacking construction
CN109340453A (en) A kind of heat supply pipeline construction method
KR100748258B1 (en) In the troy line tube in high tension cable underground power line use a conduit line spatial-temporal method
CN104179194A (en) Integrated pipe trench in soft soil stratum and construction method of integrated pipe trench
CN105953078B (en) The protective device of high-pressure gas pipeline and guard method
CN104878719B (en) Mutual embedding reinforcement formula Ecological Retaining Wall construction method
CN109339062A (en) The guard method and its protection structure that fuel gas conduit is intersected above when thermal pipe is laid with
CN111851588A (en) Pipe jacking well structure and construction method thereof
CN101768960B (en) Bored concrete pile construction method of permafrost layer
KR101012640B1 (en) Method for constructing structure for underground tunnel
CN110924435A (en) Transverse pipeline fixing device under transverse structure and construction method thereof
CN110565686A (en) Construction method for penetrating river channel under pipe gallery
CN207512777U (en) Assembled underground pipe gallery
CN207331746U (en) A kind of underground pipe gallery
CN209368841U (en) The construction protection structure that fuel gas conduit is intersected above when thermal pipe is laid with
CN102433883A (en) Space-time conversion construction method of vertical underground pipe of deep foundation pit
CN106638668A (en) Underpinning system between underground connection passage and power pipeline and construction method of underpinning system
CN109339064A (en) The guard method and its protection structure of the parallel thermal pipe of fuel gas conduit when thermal pipe is laid with
CN105926660A (en) Construction method of wind power low pile bearing platform foundation in intertidal zone
CN110512594A (en) The simple and easy method of churning driven opportunity cavity pore-forming
CN209368842U (en) Structure is protected in the construction of the parallel thermal pipe of fuel gas conduit when thermal pipe is laid with
CN209368843U (en) Fuel gas conduit protects structure in the construction that lower section intersects when thermal pipe is laid with
JP6584979B2 (en) Construction method of underground tank structure, underground tank structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination