CN109267573A - A kind of method that cast-in-situ bored pile pile crown is abolished - Google Patents

A kind of method that cast-in-situ bored pile pile crown is abolished Download PDF

Info

Publication number
CN109267573A
CN109267573A CN201811043854.2A CN201811043854A CN109267573A CN 109267573 A CN109267573 A CN 109267573A CN 201811043854 A CN201811043854 A CN 201811043854A CN 109267573 A CN109267573 A CN 109267573A
Authority
CN
China
Prior art keywords
pile crown
pile
hangs muscle
reinforcement cage
steel reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201811043854.2A
Other languages
Chinese (zh)
Inventor
赵卫政
薛玉文
王国祥
王政鑫
钱邦栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU XINGSHA CONSTRUCTION ENGINEERING GROUP Co Ltd
Original Assignee
JIANGSU XINGSHA CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU XINGSHA CONSTRUCTION ENGINEERING GROUP Co Ltd filed Critical JIANGSU XINGSHA CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority to CN201811043854.2A priority Critical patent/CN109267573A/en
Publication of CN109267573A publication Critical patent/CN109267573A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
    • E02D9/005Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof removing the top of placed piles of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same

Abstract

The present invention relates to a kind of methods that cast-in-situ bored pile pile crown is abolished; this method overcomes traditional construction method time-consuming and costly disadvantage of drawing water; by the vertical main reinforcement of stake top concrete segment; it wraps up in protective case; partition concrete bonds effect to main reinforcement; have many advantages, such as apparent save the cost, shorten the construction period, reduce security risk, reduce artificial, raising work efficiency, relatively traditional pile crown, which abolishes construction, biggish breakthrough.

Description

A kind of method that cast-in-situ bored pile pile crown is abolished
Technical field
The present invention relates to technical field of buildings, and in particular to a kind of method that cast-in-situ bored pile pile crown is abolished.
Background technique
Traditional construction method makes to play the part of out main reinforcement with the artificial of low price, break a heart concrete into pieces, the method encounters wage Go up or when level of ground water is high, it is time-consuming and draw water costly;Such as by the vertical main reinforcement of stake top concrete segment, wrap up in protective case, every The concrete chisel of cutting then need to only be broken to the effect that bonds of main reinforcement, can be easy to hang out as honeycomb briquette by disconnected concrete; The present invention is entangled main reinforcement using plastic tube mainly by the construction of drilled pile pile crown first during screwing steel bars cage completely, Plastic tube bottom end is bound with tied silk and is blocked.Pile crown is finally integrally hung out to pile crown ring cutting after having poured excavation.
Summary of the invention
Present invention aims at the present invention for time-consuming existing in the prior art and to draw water the problems such as costly, provides one The method that kind cast-in-situ bored pile pile crown is abolished.
To reach above-mentioned purpose, the technical solution adopted in the present invention is as follows:
A kind of method that cast-in-situ bored pile pile crown is abolished, comprising the following steps:
Step 1: main reinforcement is protected: main reinforcement being protected using plastic tube, isolation steel reinforcement cage and pile crown concrete Between bonding, plastic tube is protruded into cushion cap and entangles main reinforcement completely, and bottom end is blocked with adhesive tape on the plastic tube, simultaneously Plastic tube bottom end is bound with tied silk;
Step 2: production circulation hangs muscle: welding round hanging ring, another end reinforced and hook 1 reinforcing bar one end first Welding, reinforcing bar is connect with steel reinforcement cage to be connected using snap ring, according to the difference of hangs muscle length, adjusts snap ring to control the length of hangs muscle Degree;2 M16 nuts are welded at the hook mouth of bottom end, and nut is inserted into using the round steel bolt isometric with hangs muscle;
Step 3: steel reinforcement cage installation: when steel reinforcement cage is transferred, according to casing top and stake top absolute altitude, adjusting the length of circulation hangs muscle The hook that 2 recycle hangs muscle is hooked the reinforcement stirrup on top on the inside of steel reinforcement cage, finally with the reinforcing bar bolt isometric with hangs muscle by degree It is inserted into screw cap hole;When steel reinforcement cage positions, guarantee vertically, after the completion of drilled pile perfusion, snap ring to be unclamped, bolt is extracted, takes Hangs muscle is recycled out;
Step 4: the horizontal ring cutting processing of pile crown: after the completion of drilled pile construction, using minitype cutting machine in pile crown elevation location It carries out ring cutting one week, and in pile crown absolute altitude symmetric position drill two holes hole;
Step 5: carrying out pile crown splitting: being cleaved using the hole that hydraulic splitting machine has been drilled insertion pile crown;
Step 6: progress pile crown, which is hung, to be removed: hang removing to the pile crown that step 5 has cleaved using crane;
Step 7: to progress crotch processing at the top of steel reinforcement cage: being carried out using reinforcing bar of the Portable steel bar bending machine to pile crown curved Song processing.
From the above technical solution of the present invention shows that, the beneficial effects of the present invention are:
Compared with prior art, the invention has the following advantages that a kind of method that cast-in-situ bored pile pile crown is abolished of the present invention, Have many advantages, such as apparent save the cost, shortens the construction period, reduce security risk, reduce artificial, raising work efficiency, relatively traditional stake Head, which abolishes construction, biggish breakthrough.
Detailed description of the invention
Fig. 1 is plastics protection of pipe bar construction figure of the present invention;
Fig. 2 is present invention circulation hangs muscle schematic diagram;
Fig. 3 is structure chart when the present invention does not pour concrete;
Fig. 4 is structure chart when the present invention has poured concrete.
In figure: 1, main reinforcement;2, stirrup;3, plastic tube.
Specific embodiment
In order to make related personnel know more about technology contents of the invention, now specific embodiment is said in conjunction with institute's accompanying drawings It is bright as follows.
Referring to Fig.1-Fig. 4, a kind of method that cast-in-situ bored pile pile crown is abolished, comprising the following steps:
Step 1: to the protection of cushion cap main reinforcement is protruded into, reinforcing bar being protected using plastic tube, isolation steel reinforcement cage and pile crown are mixed Bonding between solidifying soil.Plastic tube is protruded into cushion cap main reinforcement to entangle completely, and bottom end is blocked with adhesive tape on the plastic tube.Together When wound plastic tube from falling off and spillage, plastic tube bottom end are bound with tied silk to prevent.
Step 2: production circulation hangs muscle, circulation 2 HRB400 φ 20mm reinforcing bars of hangs muscle, snap ring, hook welding assembly and At.Round hanging ring is welded 1 20mm reinforcing bar one end φ first, the fixation for steel reinforcement cage.Another φ 20mm is end reinforced It is welded with hook, for hanging steel reinforcement cage.Reinforcing bar is connect with steel reinforcement cage to be connected using snap ring, can according to the difference of hangs muscle length The length of hangs muscle is controlled to adjust snap ring.Simultaneously to prevent steel reinforcement cage from breaking off relations, in bottom end, hook mouth welds 2 M16 nuts, applies Working hour uses and is inserted in 2 nuts with the isometric HPB300 φ 10mm round steel bolt of hangs muscle.
Step 3: steel reinforcement cage installation: when steel reinforcement cage is transferred, first according to casing top and stake top absolute altitude, adjusting circulation hangs muscle Length, the hook that 2 recycle hangs muscles is symmetrically hooked to the reinforcement stirrup (HRB400 φ 20) on top on the inside of steel reinforcement cage, is finally used In isometric 10 reinforcing bar bolt of the HPB300 φ insertion screw cap hole of hangs muscle.When steel reinforcement cage positions, guarantee vertically, to remove so that pile crown is hung. After the completion of drilled pile perfusion, snap ring is unclamped, extracts bolt, circulation hangs muscle can be taken out.
Step 4: the horizontal ring cutting processing of pile crown: after drilled pile construction completes excavation of foundation pit, in pile crown elevation location using small Type cutting machine carries out ring cutting one week.Pile crown absolute altitude symmetric position bore two diameters be 40mm, the hole that depth is 400mm, use It is cleaved in pile crown.
Step 5: pile crown splitting: 2 hydraulic splitting machines being symmetrically inserted into the hole that pile crown has been drilled and are cleaved, and keeps pile crown de- From.
Step 6: pile crown, which is hung, to be removed: after the completion of pile crown splitting, being carried out disposable whole hang with 25t crane and is removed.
Step 7: crotch processing at the top of steel reinforcement cage: finally carrying out crotch to pile crown reinforcing bar using Portable steel bar bending machine, Complete Stake head handling.
The foregoing is merely better embodiment of the invention, protection scope of the present invention is not with above embodiment Limit, as long as those of ordinary skill in the art's equivalent modification or variation made by disclosure according to the present invention, should all be included in power In the protection scope recorded in benefit requirement.
Although the present invention has been disclosed as a preferred embodiment, however, it is not to limit the invention.Skill belonging to the present invention Has usually intellectual in art field, without departing from the spirit and scope of the present invention, when can be used for a variety of modifications and variations.Cause This, the scope of protection of the present invention is defined by those of the claims.

Claims (1)

1. a kind of method that cast-in-situ bored pile pile crown is abolished, it is characterised in that: the following steps are included:
Step 1: main reinforcement being protected: main reinforcement being protected using plastic tube, is isolated between steel reinforcement cage and pile crown concrete Bonding, plastic tube is protruded into cushion cap and entangles main reinforcement completely, and bottom end is blocked with adhesive tape on the plastic tube, while to modeling Expects pipe bottom end is bound with tied silk;
Step 2: making circulation hangs muscle: welding round hanging ring, another end reinforced and hook weldering 1 reinforcing bar one end first It connects, reinforcing bar is connect with steel reinforcement cage to be connected using snap ring, according to the difference of hangs muscle length, adjusts snap ring to control the length of hangs muscle; 2 M16 nuts are welded at the hook mouth of bottom end, and nut is inserted into using the round steel bolt isometric with hangs muscle;
Step 3: steel reinforcement cage installation: when steel reinforcement cage is transferred, according to casing top and stake top absolute altitude, adjusting the length of circulation hangs muscle, The hook that 2 recycle hangs muscle is hooked to the reinforcement stirrup on top on the inside of steel reinforcement cage, is finally inserted with the reinforcing bar bolt isometric with hangs muscle Enter in screw cap hole;When steel reinforcement cage positions, guarantee vertically, after the completion of drilled pile perfusion, snap ring to be unclamped, bolt is extracted, takes out Recycle hangs muscle;
Step 4: the horizontal ring cutting processing of pile crown: after the completion of drilled pile construction, being carried out in pile crown elevation location using minitype cutting machine Ring cutting one week, and in pile crown absolute altitude symmetric position drill two holes hole;
Step 5: carrying out pile crown splitting: being cleaved using the hole that hydraulic splitting machine has been drilled insertion pile crown;
Step 6: progress pile crown, which is hung, to be removed: hang removing to the pile crown that step 5 has cleaved using crane;
Step 7: to progress crotch processing at the top of steel reinforcement cage: carrying out knee using reinforcing bar of the Portable steel bar bending machine to pile crown Reason.
CN201811043854.2A 2018-09-07 2018-09-07 A kind of method that cast-in-situ bored pile pile crown is abolished Withdrawn CN109267573A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811043854.2A CN109267573A (en) 2018-09-07 2018-09-07 A kind of method that cast-in-situ bored pile pile crown is abolished

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811043854.2A CN109267573A (en) 2018-09-07 2018-09-07 A kind of method that cast-in-situ bored pile pile crown is abolished

Publications (1)

Publication Number Publication Date
CN109267573A true CN109267573A (en) 2019-01-25

Family

ID=65188813

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811043854.2A Withdrawn CN109267573A (en) 2018-09-07 2018-09-07 A kind of method that cast-in-situ bored pile pile crown is abolished

Country Status (1)

Country Link
CN (1) CN109267573A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587380A (en) * 2012-02-08 2012-07-18 湖南省第二工程有限公司 Construction method for wholly removing drilling pile head
CN207739259U (en) * 2018-01-02 2018-08-17 中国水利水电第八工程局有限公司 A kind of filling pile head cuts device

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587380A (en) * 2012-02-08 2012-07-18 湖南省第二工程有限公司 Construction method for wholly removing drilling pile head
CN207739259U (en) * 2018-01-02 2018-08-17 中国水利水电第八工程局有限公司 A kind of filling pile head cuts device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
景锋: ""钻孔灌注桩桩头套管法整体破除施工技术"", 《城市建设理论研究(电子版)》 *

Similar Documents

Publication Publication Date Title
CN106400802B (en) A kind of drilled pile pile crown is pre-buried to exempt from the whole quickly lifting method of ring cutting that drills
CN100535261C (en) Pile extractor and construction method thereof
CN105569560B (en) A full set of tubular type long auger stake machine and the method for utilizing the ram machine construction
CN102505945B (en) Construction method for enabling rectangular pipe jacking machine to enter into tunnel in existing building
CN101368386A (en) Pile extractor and construction method for pile extraction
CN210562236U (en) Underwater hard rock stratum crushing and soil taking system
CN106245931A (en) The underpinning device of load bearing wall and construction method in brick mix structure
CN108612109A (en) The carrierless method for dismounting of concrete support beam
CN104631460A (en) Girdling splitting type integral pile breaking method
CN111005378A (en) Construction method for breaking pile head of cast-in-situ bored pile through static spalling
CN207739259U (en) A kind of filling pile head cuts device
CN108978661B (en) Construction method for removing cast-in-situ bored pile
CN106958242A (en) Steel pile casting is installed and method for dismounting
CN103615120A (en) Combined-type shaping building peripheral horizontal safety net
CN207057520U (en) A kind of filling pile head bar straightening instrument
CN206859222U (en) The quick structure for abolishing concrete pile head
CN109267573A (en) A kind of method that cast-in-situ bored pile pile crown is abolished
CN206110122U (en) Bridge drilled pile convenient to get rid of pile head
CN109403326B (en) Method for taking out reinforcement cage based on serious hole collapse of drilled pile
CN203022001U (en) Pile-pulling device with vibrating sleeve ring
CN216971710U (en) Vertical hoist and mount construction node of steel reinforcement cage
CN211922619U (en) Pile head breaking device
CN108316288A (en) Half casing guncreting pile construction equipment and construction method
CN207092089U (en) A kind of pile foundation pile crown auxiliary cuts device
CN108086309B (en) Mini pile reinforcement cage installation method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20190125

WW01 Invention patent application withdrawn after publication