CN108316288A - Half casing guncreting pile construction equipment and construction method - Google Patents

Half casing guncreting pile construction equipment and construction method Download PDF

Info

Publication number
CN108316288A
CN108316288A CN201810152537.8A CN201810152537A CN108316288A CN 108316288 A CN108316288 A CN 108316288A CN 201810152537 A CN201810152537 A CN 201810152537A CN 108316288 A CN108316288 A CN 108316288A
Authority
CN
China
Prior art keywords
casing
pile
original state
guncreting
reinforcement cage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810152537.8A
Other languages
Chinese (zh)
Inventor
潘春宇
陆志荣
施智亮
熊玎玮
张丽骏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 5 Group Co Ltd
Original Assignee
Shanghai Construction No 5 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 5 Group Co Ltd filed Critical Shanghai Construction No 5 Group Co Ltd
Priority to CN201810152537.8A priority Critical patent/CN108316288A/en
Publication of CN108316288A publication Critical patent/CN108316288A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/385Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to a kind of half casing guncreting pile construction equipment and construction methods, belong to pile foundation technology field, are easy to cause collapse hole, slag inclusion, pile quality poor in current bored pile construction for solving the problems, such as.The construction equipment mainly fetches earth drilling machine including spiral original state, and original state fetches earth guncreting pile frame, crawler crane, digging machine, concrete pump and casing, and the length of casing is the half of guncreting pile pile body height, and casing top is also equipped with hydraulic pressure vibration hammer.The construction method is fetched earth using the double dynamical original state of helical blade built in half casing bores cutting soil under drilling machine and forms stake holes, while soil body original state in casing being taken out, and steel reinforcement cage is inserted into after guncreting, reinforced concrete pile is formed after extraction casing.The construction method is generated without mud, not collapse hole, and vertical precision is high, and pile quality is good;Soil disturbance is small, and work progress influences surrounding enviroment small;Construction efficiency is high, at low cost.

Description

Half casing guncreting pile construction equipment and construction method
Technical field
The present invention relates to pile foundation technology field, more particularly to a kind of half casing guncreting pile construction equipment and construction method.
Background technology
Mud off and discharge mud are needed in traditional bored pile construction, not only mud influence environment, but also Mud off quality control is difficult, therefore in the construction process once occur collapsing problem, can to the construction progress of entire engineering with And quality causes tremendous influence, economic loss big.
Accordingly, it is desirable to provide a kind of hidden danger of quality that can be eliminated before pile, it is ensured that Construction Quality for Bore Filling Pile is applied The technical issues of construction equipment and construction method are those skilled in the art's urgent need to resolve.
Invention content
The purpose of the present invention is to provide a kind of half casing guncreting pile construction equipment and construction methods, are bored at present for solving It is easy to cause collapse hole, the problem of slag inclusion, pile quality difference in hole pouring pile construction.The construction method uses spiral shell built in half casing The double dynamical original state of vane piece, which fetches earth, bores cutting soil under drilling machine and forms stake holes, while soil body original state in casing being taken out, pressure filling It is inserted into steel reinforcement cage after concrete, reinforced concrete pile is formed after extracting casing.
In order to solve the above technical problems, technical scheme is as follows:
A kind of construction method of half casing guncreting pile, includes the following steps:
Step 1: passing through measurement markers stake position;
Step 2: providing half casing guncreting pile construction equipment, casing is buried in drilling, built-in helical blade it is double dynamical Original state, which fetches earth, bores cutting soil under drilling machine and forms stake holes, while soil body original state in casing being taken out;
Step 3: after shield-tube embedment in place after, casing power head and upper section cylinder are detached from, and holding casing is motionless, drilling rod after Continuous drilling is until stake bottom designed elevation;
Step 4: after drilling machine to stake bottom designed elevation, pump concrete carries out carrying brill after reaching 1m height, is pumped in Ti Zuan Concrete, until stake top absolute altitude;;
Step 5: steel reinforcement cage is hung in above the stake holes using crawler crane and is directed at limit;Then steel reinforcement cage relies on Dead weight be inserted into concrete, with the constantly sinking of steel reinforcement cage, its suffered resistance gradually increases, wait for steel reinforcement cage can not rely on dead weight after Continuous sinking starts the vibrator that steel reinforcement cage delivers bar top so that the steel reinforcement cage body vibration sinks down into a bottom.
Further, the step 5 includes:After steel reinforcement cage is inserted in place and pulls out delivery bar completely, concrete two is carried out It is secondary to pour.
Further, the step 5 further includes:When casing starts to pull out, pulled out again in rotation after 5S should be rotated in place Go out.
The present invention also provides a kind of half casing guncreting pile construction equipment, the half casing guncreting pile construction equipment includes original Shape fetch earth drilling machine, original state fetch earth guncreting pile frame, crawler crane, digging machine, concrete pump and casing, and the original state fetches earth in drilling machine Helical blade is set, the casing top is equipped with hydraulic pressure vibration hammer, and the crawler crane is for lifting steel reinforcement cage, the digging The transhipment original state that machine is used to assist fetches earth the soil body of drilling machine taking-up, the length of the casing for guncreting pile pile body height half.
Further, the original state fetches earth drilling machine as double dynamical drilling machine.
Further, the casing includes power head and cylinder, and the cylinder is the standard knot steel pile casting that length is 12m.
Further, the depth that the casing is inserted into the soil body is the half of the guncreting pile pile body height, the casing Top is higher 1m than the guncreting pile stake top.
Compared with prior art, the present invention is beneficial has technical effect that:
1, the construction equipment of half casing guncreting pile provided by the invention, main to fetch earth drilling machine including long spire original state, original state Fetch earth guncreting pile frame, crawler crane, digging machine, concrete pump and casing, and original state fetches earth helical blade built in drilling machine and top And height concordant with guncreting pile pile body top to be onstructed is only the casing of guncreting pile pile body mid-height, certainly, casing top Also it is equipped with hydraulic pressure vibration hammer.The construction equipment is drawn materials simply, conveniently, and noise is small, and integrated construction cost is relatively low.
2, the construction method of half casing guncreting pile provided by the invention, the retaining wall in long auger guncreting pile work progress Cement mortar and mud need not be used, to effectively reduce in work progress to being polluted caused by surrounding enviroment, it is ensured that The neat and tidy of construction site, and retaining wall need not be carried out using cement mortar or mud, also effectively save construction Master Cost makes construction cost be controlled effectively.
3, the construction method of half casing guncreting pile provided by the invention solves the problems, such as that thick sand bed, hard stratum penetrate hardly possible, And undergauge will not be caused, hole and the surface uplift of collapsing phenomena such as.
4, the construction method of half casing guncreting pile provided by the invention, can significantly improve speed of application, and pile is efficient, greatly It shortens the construction period greatly, stable quality.
Description of the drawings
Fig. 1 is the schematic diagram of the half casing guncreting pile of one embodiment of the invention.
In figure:
1- casings;2- hydraulic pressure vibration hammers;3- triaxial cement mixing piles.
Specific implementation mode
Below in conjunction with the drawings and specific embodiments to half casing guncreting pile construction equipment proposed by the present invention and construction method It is described in further detail.According to following explanation and claims, advantages and features of the invention will become apparent from.It should be noted That attached drawing is all made of very simplified form and uses non-accurate ratio, only to it is convenient, lucidly aid in illustrating this hair The purpose of bright embodiment.For sake of convenience, "upper" described below, "lower" are consistent with the upper and lower direction of attached drawing, but this is not The limitation of technical solution of the present invention can be become.
The present invention is illustrated by taking certain base pit engineering as an example, about -0.500 meter of nature terrace relative elevation, foundation pit week skirt Watch box combines outside 3 water-stop curtain of triaxial cement mixing pile using guncreting pile, and uses " pile wall interaction " technology, vertically arranged Twice armored concrete horizontal supporting system.
It is pressed with reference to Fig. 1 half casing guncreting pile construction equipments that the present invention will be described in detail and using the construction equipment Fill the construction method of pile driving construction.
Embodiment one
The half casing guncreting pile construction equipment of the present embodiment, including the double dynamical original state of built-in bolt blade fetch earth drilling machine; Original state fetches earth guncreting pile frame, crawler crane, digging machine, concrete pump and casing 1, and crawler crane is for lifting steel reinforcement cage, digging machine For assisting transhipment original state to fetch earth the soil body of drilling machine taking-up, the length of casing 1 is the half of guncreting pile pile body height;One cooperation is set It is placed in the hydraulic pressure vibration hammer 2 on 1 top of casing.
Preferably, original state fetches earth, drilling machine is that the double dynamical original state of long spire fetches earth drilling machine, and pore-forming efficiency is high, and hole quality is good. Casing 1 includes power head and cylinder, and cylinder is the standard knot steel pile casting that length is 12m, to facilitate the insertion of casing 1 to construct. Good protection is played to pile using casing 1, collapse hole, slag inclusion can be avoided in constructing operation, improve guncreting pile at Quality of pile.
Preferably, the depth that casing 1 squeezes into the soil body is the half of guncreting pile pile body height, guncreting pile is compared on the top of casing 1 The high 1m in top of pile body.
Embodiment two
Correspondingly, the present embodiment additionally provides the construction method of half casing guncreting pile.Referring Figure 1, half casing pressure The construction method for filling stake, includes the following steps:
Step 1: passing through measurement markers stake position.Specifically, first according to building orientation axis, people is measured by sole duty Member presses stake bit plan accurately by the setting-out of stake position to scene, and adds lime point as stake bit identification using wooden bat is inserted.When So, in order to improve into pile verticality, smooth construction site is needed, stake machine is kept to be horizontal.
Step 2: providing aforementioned construction equipment, casing 1 is buried in drilling, the double dynamical original state of built-in helical blade takes Cutting soil is bored under earth boring auger machine and forms stake holes, while soil body original state in casing 1 being taken out, and taken out using digging machine auxiliary cleaning Soil block.
Step 3: after shield-tube embedment in place after, casing power head and upper section casing are detached from, and holding casing is motionless, drilling rod after Continuous drilling is until stake bottom designed elevation.
Step 4: after casing 1 and drill bit reach designed elevation, casing power head is detached from upper section cylinder, keeps casing 1 It is motionless, drilling rod 200mm is promoted, decentralization conduit to stake bottom position begins pumping concrete to stake top absolute altitude.Certainly, concrete pumping Should be carried out continuously, avoid caused by backstage feeding is slow it is under feeding, shut down phenomenon to be expected;Pump concrete reach 1m height after again Start to carry brill, the pump concrete in Ti Zuan, and control puies forward drilling speed rate and with pump output matches;The row of must assure that in formation of pile Air valve works normally, and prevents that plugging occurs in formation of pile;Hopper inner concrete face height is remained in pumping procedure not Less than 400mm, plugging is caused to prevent sucking air.
Step 5: steel reinforcement cage is hung in above stake holes using crawler crane and is directed at limit;Then steel reinforcement cage is by dead weight It is inserted into concrete, its suffered resistance gradually increases with the constantly sinking of steel reinforcement cage, under waiting for that steel reinforcement cage can not rely on dead weight to continue It is heavy, start the vibrator that steel reinforcement cage delivers bar top so that steel reinforcement cage body vibration sinks down into a bottom.Steel reinforcement cage integral manufacturing and At, therefore lifting construction is required relatively high.The lifting of steel reinforcement cage should use 4 points of liftings, and should ensure that straight lifting;Moreover, After steel reinforcement cage hangs ground, straight lifting is realized by pulley of the hoisting wirerope on crane ditch using centre-of gravity shift principle It is converted into vertical lifting, in order to enter hole;Finally, each lifting point should reinforce its rigidity and stress, prevent because of steel reinforcement cage itself weight Power is overweight and deforms.
Particularly, casing 1 should be pulled out after the completion of steel reinforcement cage is inserted into.In step 5, when casing 1 starts to pull out, original place is answered It is extracted again in rotation after rotation 5S.
Particularly, since steel reinforcement cage insertion is inserted into using vibrations form, steel reinforcement cage delivers the bar meeting of pulling out after being inserted in place Decline along with concrete horizontal, in step 5, progress concrete secondary is needed to pour.
In conclusion the present invention carries out the construction method of half casing guncreting pile using construction equipment, using built in half casing The double dynamical original state of helical blade, which fetches earth, bores cutting soil under drilling machine and forms stake holes, while soil body original state in casing being taken out, pressure It is inserted into steel reinforcement cage after filling concrete, reinforced concrete pile is formed after extracting casing.The construction method is generated without mud, protection ring Border;The construction method carries out guncreting pile construction not collapse hole, and vertical precision is high, and pile quality is good;The construction method carries out guncreting pile Soil disturbance of constructing is small, and work progress influences surrounding enviroment small;Construction method progress guncreting pile construction, construction efficiency height, Use cost is low.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this hair Any change, the modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to the protection of claims Range.

Claims (7)

1. a kind of construction method of half casing guncreting pile, which is characterized in that include the following steps:
Step 1: passing through measurement markers stake position;
Step 2: providing half casing guncreting pile construction equipment, casing, the double dynamical original state of built-in helical blade are buried in drilling It fetches earth and bores cutting soil under drilling machine and form stake holes, while soil body original state in casing being taken out;
Step 3: after shield-tube embedment in place after, casing power head and upper section cylinder are detached from, and holding casing is motionless, and drilling rod continues to bore Hole is until stake bottom designed elevation;
Step 4: after drilling machine to stake bottom designed elevation, pump concrete carries out carrying brill after reaching 1m height, the pumped concrete in Ti Zuan Soil, until stake top absolute altitude;
Step 5: steel reinforcement cage is hung in above the stake holes using crawler crane and is directed at limit;Then steel reinforcement cage is by dead weight It is inserted into concrete, its suffered resistance gradually increases with the constantly sinking of steel reinforcement cage, under waiting for that steel reinforcement cage can not rely on dead weight to continue It is heavy, start the vibrator that steel reinforcement cage delivers bar top so that the steel reinforcement cage body vibration sinks down into a bottom.
2. construction method as described in claim 1, which is characterized in that the step 5 includes:Steel reinforcement cage is inserted in place and complete It pulls out entirely after delivering bar, carries out concrete secondary and pour.
3. construction method as described in claim 1, which is characterized in that the step 5 further includes:When casing starts to pull out, answer It is extracted again in rotation after rotating in place 5S.
4. half casing guncreting pile construction equipment, which is characterized in that fetch earth guncreting pile frame, crawler belt including fetch earth drilling machine, original state of original state Loop wheel machine, digging machine, concrete pump and casing, the original state fetch earth helical blade built in drilling machine, and the casing top is equipped with There is a hydraulic pressure vibration hammer, for lifting steel reinforcement cage, the digging machine fetches earth drilling machine taking-up the crawler crane for assisting transhipment original state The soil body, the length of the casing is the half of guncreting pile pile body height.
5. half casing guncreting pile construction equipment as claimed in claim 4, which is characterized in that the original state fetch earth drilling machine be it is double acting Power drilling machine.
6. half casing guncreting pile construction equipment as claimed in claim 4, which is characterized in that the casing includes power head and cylinder Body, the cylinder are the standard knot steel pile casting that length is 12m.
7. half casing guncreting pile construction equipment as claimed in claim 4, which is characterized in that the casing is inserted into the depth of the soil body Top for the half of the guncreting pile pile body height, the casing is higher 1m than the guncreting pile stake top.
CN201810152537.8A 2018-02-16 2018-02-16 Half casing guncreting pile construction equipment and construction method Withdrawn CN108316288A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810152537.8A CN108316288A (en) 2018-02-16 2018-02-16 Half casing guncreting pile construction equipment and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810152537.8A CN108316288A (en) 2018-02-16 2018-02-16 Half casing guncreting pile construction equipment and construction method

Publications (1)

Publication Number Publication Date
CN108316288A true CN108316288A (en) 2018-07-24

Family

ID=62899862

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810152537.8A Withdrawn CN108316288A (en) 2018-02-16 2018-02-16 Half casing guncreting pile construction equipment and construction method

Country Status (1)

Country Link
CN (1) CN108316288A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112030961A (en) * 2020-08-07 2020-12-04 湖北中南岩土工程有限公司 Vibration pipe following construction process for long spiral cast-in-place pile
CN113089652A (en) * 2021-02-23 2021-07-09 中铁十九局集团第三工程有限公司 Occlusive pile construction method and reinforced structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112030961A (en) * 2020-08-07 2020-12-04 湖北中南岩土工程有限公司 Vibration pipe following construction process for long spiral cast-in-place pile
CN112030961B (en) * 2020-08-07 2021-11-02 湖北中南岩土工程有限公司 Vibration pipe following construction process for long spiral cast-in-place pile
CN113089652A (en) * 2021-02-23 2021-07-09 中铁十九局集团第三工程有限公司 Occlusive pile construction method and reinforced structure

Similar Documents

Publication Publication Date Title
CN105780763B (en) Mesoporous vibrates the construction method of casing retaining wall long auger guncreting pile
CN106761474B (en) A kind of the full-sleeve engineering method steel sleeve and its construction method of the soil that can actively muck haulage
CN102720186B (en) Underwater once pouring method for variable cross-section bored cast-in-place pile
CN203403404U (en) High-efficiency cast-in-place pile device
CN104563098A (en) Construction method of pore-forming pouring pile in dry work of super-large-diameter full-steel pipe casing
CN108457282A (en) Deep water hard rock is without back cover steel sheet pile cofferdam construction method
CN107489158A (en) A kind of spiral-digging pore stirs the construction method of water spray soil occlusion curtain pile
CN105442532A (en) Construction method for pile-head-expanded bored pile
CN106284317A (en) A kind of building pile foundation construction method
CN108086342A (en) The construction method of karst strata pile foundation
CN110273413A (en) A kind of efficient construction method of prefabricated pile
CN101608452B (en) Bottom-connected reinforced concrete sinking well water-jetting sinking construction method
CN109183790A (en) A kind of Screw Pile and its construction tool and construction method
CN104711975B (en) Construction technology for long spiral cast-in-situ bored pile
CN106677166A (en) Flow construction method for forming cast-in-place bored pile for gravel-decomposed rock stratum in double-machine combined mode
CN208088287U (en) Half casing guncreting pile construction equipment
CN111364449A (en) Construction method and structure for penetrating karst cave of precast tubular pile
CN205776216U (en) A kind of implantation equipment of rigid pile
CN102304915A (en) New method for controlling top quality of drilled pile
CN110080779A (en) Tunnel tunnel bottom karst cave treatment construction method
CN108316288A (en) Half casing guncreting pile construction equipment and construction method
CN201459749U (en) Stable structure for construction platform of deep water steel pipe pile
CN205444192U (en) Bridge stake is towards pile driving construction system
CN108625388A (en) A kind of sleeve combination formula large diameter single pile foundation and its construction method suitable for Shallow Bedrock geological conditions
CN101245597A (en) Breast wall type cast-in-situ bored pile construction method and pile machine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20180724