Summary of the invention
The deficiency existed for prior art, it is an object of the invention to provide a kind of building pile foundation construction method, passes through
The pile foundation with relatively large bearing capacity is set bottom pile foundation, is irrigated a technique the most again, thus is greatly improved filling
The bearing capacity of note stake.
For achieving the above object, the technical scheme is that a kind of building pile foundation construction method, its feature exists
In, comprise the following steps: prepare before P1, boring: smooth location, measuring stake holes position, mud pit, mud circulation groove be set,
According to building shape base plane position and the drilling sequences upper bore operation stand laid for supporting rig on construction ground;
P2, boring: use percussive drill and Spiral digging machine to combine boring, according to position, hole geological condition, select percussive drill, churning driven
The drilling sequences of machine;
P3, expansion ground datum hole: wait digging to the required degree of depth, overturn by the convertible drill bit being arranged on rig, expand
Hole, reaming aperture now is D1;
P4, expansion supported hole: boring is upwards regained, and then carries out a reaming at interval of one section, and aperture is followed successively by D2, D3, D4...Dn
(n >=2);
P5, bury casing underground: bar connecting is passed through in place corresponding with ground datum hole and supported hole on the barrel of casing, then will
In casing embedment hole;
P6, pile: take percussive drill or crane lifting to transfer installation steel reinforcement cage, use catheterized reperfusion underwater concrete.
By using technique scheme, because in prior art when being irrigated technique, because of not foot bottom it
Enough supports thus cause bearing capacity to be told somebody what one's real intentions are, existing employing drills through ground datum hole and supported hole in advance, is then carrying out concrete filling
Note, so that building pile foundation can have enough supports in the part of below ground, thus improves its bearing capacity, also simultaneously
Strengthen the structural strength of building pile foundation, thus from performance, the most preferably improve its bearing capacity.
Further, wherein D1, D2, D3...Dn are equal in magnitude.
By using technique scheme, the aperture of ground datum hole and supported hole is set to unanimously, so when molding
Ensure whole building pile foundation entirety uniformity.
Further, wherein D1, D2, D3...Dn taper into.
By using technique scheme, the aperture of ground datum hole and supported hole is tapered into from lower to upper, so that
It is more firm to obtain bottom building pile foundation, and foundation consolidates, and saves material simultaneously.
Further, wherein D1, D2, D3...Dn become larger.
By using technique scheme, the aperture of ground datum hole and supported hole is become larger from lower to upper, so may be used
To ensure the forming stability of building pile foundation, the part near ground is not easy to be inclined by deformation, and perpendicularity is high, can reach simultaneously
To facilitating the purpose of molding, the time period of curing molding, the duration shortens.
Further, the spacing in adjacent supports hole about 2 ~ 3m.
By using technique scheme, the distance between adjacent supports hole is set to 2 and is to ensure that building to 3m
Pile foundation reaches to save material, the purpose of reduction of erection time on the basis of having enough bearing capacities simultaneously, and long too short meeting causes building
Build the cost performance step-down of construction.
Further, in P6 pile-formation process, during pouring underwater concrete, first pour molding ground datum hole, treat that ground datum hole coagulates
Gu carry out overall perfusion concrete formation after Gu Hua again.
By using technique scheme, when molding pile foundation, first molding ground datum hole, make the concrete in ground datum hole first solid
Determine molding, pour building pile foundation the most again, be so to ensure that and make building pile foundation conflict in the portion of the ground datum hole having cured
Point, thus realize the raising of the bearing capacity of building pile foundation.
Further, described ground datum hole is reserved with the preformed hole of circular platform type when pouring molding.
By using technique scheme, the hole reserving truncated cone-shaped when ground datum hole pours molding is in order at building pile foundation
Can be combined with ground bore portion more firm during molding, be further ensured that the bearing capacity of building pile foundation.
Further, described supported hole and Water table stagger setting.
By using technique scheme, supported hole and Water table are staggered and is to ensure that building pile foundation is when molding
Will not be affected by subsoil water.
Further, at the bottom of the hole of described ground datum hole with the hole base thickness degree of preformed hole more than 10cm.
By using technique scheme, the spacing at the bottom of the hole of ground datum hole and at the bottom of the hole of preformed hole is arranged more than 10cm
It is to ensure that apparatus for building has enough supports when conflicting in ground datum hole, if less than 10cm, then easily by ground datum hole
The concrete extrusion of part produces slight crack and affects its bearing capacity.
Further, described casing thickness >=5mm.
By using technique scheme, the thickness of casing is set greater than being to ensure that concrete is becoming equal to 5mm
Will not deform because casing arm is relatively thin during type, certainly can not arrange blocked up, should be less than equal to 10mm, therefore protect under this technique
Cylinder non-dismountable, arrange blocked up, cause cost to increase.
Compared with prior art the present invention has an advantage that by just getting out ground datum hole when boring, then at ground
Concrete perfusion molding in hole, so that make rocks system under the effect not having rock support by oneself, pours and builds
Build pile foundation, so that building pile foundation is conflicted in the ground datum hole of well in advance, thus improve the bearing capacity of building pile foundation, with
Time when building pile foundation molding also can contoured support hole is suitable on its sidewall concrete, thus improve the knot with ground
Close intensity and the structural strength of self, this makes it possible to be greatly improved the bearing capacity of building pile foundation.
Embodiment one: a kind of building pile foundation construction method, as it is shown in figure 1, comprise the steps:
P1: prepare before boring: first place is carried out before construction smooth, compacting, meets and lay rig place requirement for bearing capacity;Survey
Put stake holes position, mud pit, mud circulation groove are set;Go up on construction ground according to building pile foundation plan-position and drilling sequences
Lay the bore operation stand for supporting rig;Using operation platform to provide stable support for rig, pile foundation construction can not
By soil property place mud, solidifying, the rainy day etc. affect, it is ensured that pile foundation is constructed continuously, reduce construction cost, improve efficiency of construction.
P2: boring: use percussive drill and rotary drilling rig to combine boring;According to position, hole geological condition, impact is selected to bore
Machine, the drilling sequences of rotary drilling rig;5-8 platform percussive drill is typically taked to coordinate 1 rotary drilling rig operation;Dig initially with rotation
Drill hole of drilling machine, drills through artificial miscellaneous fill layer and argillic horizon, and the degree of depth, to underground 10m, supplements mud in boring in boring procedure
Starch with keep creeping into and carry in brill metapore mud liquid level higher than mud liquid level in more than 2.0m, and hole bottom casing above Ground under
More than water level elevation 1.0m, it is to avoid carry mud during brill and wash away and form negative pressure in level of ground water at the bottom of soil layer or mud face and cause
Boring collapse hole;After being drilled into pebble layer, mobile rotary drilling rig, to next position, hole, is laid percussive drill and is continued boring, percussive drilling
Begin to take on low stroke, stable after normally creep into, boring procedure throws in stake holes clay pulping, the most compacted hole wall, really
Protect pebble layer hole wall safety;Percussive drilling muck removal take circulating mud and draw quarrel cylinder draw quarrel associated form;Percussive drilling passes
After boulder bed, enter mud, continue to take percussive drilling, according to geological condition during boring, part stone can be put into, stable silt
Mud ground layer hole wall, drills through mud, enters horizon d, whole hole after reaching projected depth;
P3, expansion ground datum hole: wait digging to the required degree of depth, start the hydraulic jack being arranged on unit head top, pass through hydraulic pressure
Cylinder piston rod lower end anti-screws back rotary head and pulls steel wire rope, drives convertible drill bit to overturn, and the diameter of upset is straight beyond drilling rod
Footpath reaches after design requires height, and hydraulic jack is regained upset drill bit and stopped stirring reaming.
P4, expansion supported hole: now drill bit is upwards regained, rising 2-3m then repeats the technique of P3 and carries out expanding supported hole, and
The length of supported hole keeps consistent with the length of ground datum hole, i.e. state in Fig. 1 is looped around the support on the sidewall of building pile foundation 1
Hole 2 is identical with the aperture of the ground datum hole being positioned at bottom building pile foundation 1, and then need not carry out reaming when running into Water table,
Stagger.
P5: bury casing underground: take to change the clear quarrel of slurry and rotary drilling rig double door drill bit or percussive drill is drawn quarrel cylinder and drawn the clear hole of quarrel
Combining clear hole technique by the disintegrating slag Impurity removal in hole, then use rotary drilling rig boring to after the depth of burying, rotary drilling rig is pacified
Dress casing driver, promotes casing, is directed at position, hole, rotates armed lever and transfers installation casing;Bury rear casing end face underground to exceed than ground
300mm, periphery uses clay backfilling compacting;Described casing uses the steel plate making being less than or equal to 10mm more than or equal to 5mm, simultaneously
Casing being, the part of ground datum hole and supported hole, by default bar connecting, is used for forming cavity and arrives for Concrete Filled
In ground datum hole and supported hole.
P6: pile: after casing buries, first imports to part concrete in ground datum hole, and presets mould in ground datum hole
Tool is used for being formed cavity, at the bottom of the hole of the end of mould and ground datum hole between distance more than 10cm, simultaneously cavity be shaped as circle
Platform shape, after being positioned at the concrete formation of ground datum hole, takes out mould, then takes percussive drill or crane lifting to transfer
Installing steel reinforcement cage, after using catheterized reperfusion underwater concrete, coagulation forming gets final product pile.