CN102505945B - Construction method for enabling rectangular pipe jacking machine to enter into tunnel in existing building - Google Patents

Construction method for enabling rectangular pipe jacking machine to enter into tunnel in existing building Download PDF

Info

Publication number
CN102505945B
CN102505945B CN201110448926.3A CN201110448926A CN102505945B CN 102505945 B CN102505945 B CN 102505945B CN 201110448926 A CN201110448926 A CN 201110448926A CN 102505945 B CN102505945 B CN 102505945B
Authority
CN
China
Prior art keywords
hole
push
bench
cutterhead
pipe jacking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201110448926.3A
Other languages
Chinese (zh)
Other versions
CN102505945A (en
Inventor
朱晓刚
计保林
孙经经
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Mechanized Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Group Co Ltd filed Critical Shanghai Mechanized Construction Group Co Ltd
Priority to CN201110448926.3A priority Critical patent/CN102505945B/en
Publication of CN102505945A publication Critical patent/CN102505945A/en
Application granted granted Critical
Publication of CN102505945B publication Critical patent/CN102505945B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention relates to a construction method for enabling a rectangular pipe jacking machine to enter into a tunnel in an existing building. The construction method is characterized by comprising the following steps: (1) setting up a tunnel-entering receiving buffer platform in the existing building at the tunnel-entering position; (2) setting a hanging point for a cutter head of the pipe jacking machine in the existing building at the tunnel-entering position; (3) chiseling off a portal before the pipe jacking machine enters into the tunnel; (4) adjusting all parameters and enabling the pipe jacking machine to enter into the tunnel; (5) plugging the portal after the rectangular pipe jacking machine enters into the tunnel; (6) detaching the cutter head, a chest plate and internal equipment of the pipe jacking machine, and transporting the cutter, the chest plate and the internal equipment of the pipe jacking machine out of a channel; and (7) leaving a housing of the pipe jacking machine in the channel. The construction method disclosed by the invention has the advantages of smoothly taking an inner core part of the pipe jacking machine out of the existing building and saving investment in construction of a tunnel.

Description

A kind of in built construction thing rectangular pipe jacking machine enter the construction method in hole
Technical field
The present invention relates to a kind of in built construction thing rectangular pipe jacking machine enter the construction method in hole.
Background technology
Along with the development of urbanization process, be more and more tending towards frequent for the exploitation of urban underground space.The appearance of the technical field of rectangular top pipe, compares circular push pipe and more can improve the utilization rate in space.Rectangular pipe jacking machine, in the time of operation, hangs at beginning well, through starting well to the tunnel piercing between received well, then enters hole from received well, and reclaim on handling subsequently to ground.But along with the increase of Urban Underground construction, some places are subject to the restriction of existing building in the time of construction, push-bench completes after tunnel piercing, received well cannot be set, therefore must in built construction thing, enter hole reclaims, because push-bench is bulky, therefore greatly increase the difficult point of construction.Urgently develop can be in existing building rectangular pipe jacking machine enter the construction method in hole, cannot in existing building, enter to solve the existing rectangular pipe jacking machine of prior art the problem that reclaim in hole.
Summary of the invention
The object of this invention is to provide a kind of push-bench and enter the construction method that reclaim in hole in existing building.The present invention design a kind of in built construction thing rectangular pipe jacking machine enter the construction method in hole, it is characterized in that being formed by the following step: (1) receives buffer platform entering to set up in hole place built construction thing into hole, (2) entering push-bench cutterhead suspension centre is set in hole place built construction thing, (3) before entering hole, push pipe cuts portal, (4) adjust parameters, push-bench enters hole, (5) rectangular pipe jacking machine enters hole, shutoff portal, (6) push-bench cutterhead, plastron and internal unit are dismantled and are transported in passage, and (7) are stayed push-bench housing in passage.It is characterized in that: described step (1) is for having set up in building and receive buffer platform into hole entering hole, to alleviate push-bench soil body impact force producing of caving in while entering hole, this buffer platform is set up with I20b i iron, platform surface is laid a 2cm steel plate, and steel plate and shaped steel frame are linked to be entirety with welding.It is characterized in that: described step (2) is for entering push-bench cutterhead suspension centre is set in hole place built construction thing, push-bench in built construction thing enters above hole place portal, on floor, 4 holes for hoist is set, on the floor of hole for hoist position, open four oval-shaped holes, paving 3.5m*2.5m*0.02m steel plate, on steel plate, keep flat three i iron, steel wire penetrating hole is hung on i iron, to be used for, the push-bench cutterhead entering behind hole is lifted to dismounting.It is characterized in that: described step (3) for the ground that enters portal place, Qian Duijin hole, hole at push-bench within the walls reinforcing bar carry out from top to bottom, cut from inside to outside.And for preventing that compacted soil from pouring in the necessary interception measure that basement is taked.It is characterized in that: described step (4) is adjusted parameters for surveying, push-bench enters in the progradation of hole, moment is observed the variation of top power, enter behind stabilization zone, start to stop the mud jacking of head, and mud jacking position is moved gradually afterwards, entering after reinforcing area, move speed general control 1 ~ 2mm/min left and right, cutterhead and periphery cutter can be cut completely to cement-soil, can add proper amount of clear water or antifriction slurries to soften and the lubricated soil body, control fltting speed at 1 ~ 2 mm/min, earth balance pressure power is that 0.12MPa, the amount of being unearthed are controlled at every joint 44m 3left and right, cutterhead moment of torsion are controlled within 30%.It is characterized in that: described step (5) enter hole, shutoff portal is that rectangular pipe jacking machine enters behind hole, push-bench housing stops jacking when entering Chu Gang hole, hole circle inner edge same plane place, stop location, in the time that push-bench enters hole propelling, push-bench cutterhead has entered in built construction thing,, stop at once advancing when at the Yu Gang hole, housing forward position circle inner edge same plane place of push-bench body, housing and steel hole lap welding are connected into entirety with steel plate, carry out.And the gap of enclosing with hydraulicity slurries filling housing and hole, reduce soil erosion.It is characterized in that: described step (6) for push-bench stable after, remove 2, rear portion conveying worm, after overall pulling down, be pulled to and start in well with the interior flat car of passage, hang foundation ditch; With the Chain block suspension centre that sets in advance, large cutterhead wire rope is pinioned again fasteningly, shed the anterior cap mouth of large cutterhead, prop up plastron with jack, slowly large cutterhead is pushed in buffer platform, after slowly falling, carry in midair; After large cutterhead suspention is firm, remove 4 little cutterheads of residue in batches, 4 little cutterheads are lain against to buffer platform; Gear-box and the motor of removing cutterhead rear portion, be pulled to and started in well by flat car in passage, winches to ground and place; Remove hinged oil cylinder, disengaging oil cylinder, electric driving force cabinet and correction Hydraulic Station, be pulled to and start in well by flat car in passage, winch to ground and place; The push-bench cutterhead and the internal unit that disassemble transport in passage, finally cut off plastron, large and small cutterhead is transported to starting well in order and hangs out.It is characterized in that: described step (7) for by cast-in-place to the empty capsid of push-bench steel concrete and passage become overall.Advantage of the present invention is the core component of push-bench can be taken out smoothly from built building, has saved the investment of tunnel construction.
Brief description of the drawings
Fig. 1 is shelves cob wall construction plan of the present invention, the side schematic view that Fig. 2 is Fig. 1.Fig. 3 is that suspension centre is arranged schematic diagram.Fig. 4 is that rectangular pipe jacking machine enters hole schematic diagram, Fig. 5 ~ Fig. 9 is push-bench cutterhead, plastron and internal unit dismounting schematic diagram.
Below in conjunction with accompanying drawing and construction embodiment, the present invention is made to detailed operation instruction.
Detailed description of the invention
(1) receive buffer platform into hole entering to set up in hole place built construction thing, (2) entering push-bench cutterhead suspension centre is set in hole place built construction thing, (3) before entering hole, push pipe cuts portal, (4) adjust parameters, push-bench enters hole, and (5) rectangular pipe jacking machine enters hole, shutoff portal, (6) push-bench cutterhead, plastron and internal unit are dismantled and are transported in passage, and (7) are stayed push-bench housing in passage.It is characterized in that: described step (1) is for having set up in building and receive buffer platform into hole entering hole, to alleviate push-bench soil body impact force producing of caving in while entering hole, this buffer platform is set up with I20b i iron, platform surface is laid a 2cm steel plate, and steel plate and shaped steel frame are linked to be entirety with welding.It is characterized in that: described step (2) is for entering push-bench cutterhead suspension centre is set in hole place built construction thing, push-bench in built construction thing enters above hole place portal, on floor, 4 holes for hoist is set, on the floor of hole for hoist position, open four oval-shaped holes, paving 3.5m*2.5m*0.02m steel plate, on steel plate, keep flat three i iron, steel wire penetrating hole is hung on i iron, to be used for, the push-bench cutterhead entering behind hole is lifted to dismounting.It is characterized in that: described step (3) for the ground that enters portal place, Qian Duijin hole, hole at push-bench within the walls reinforcing bar carry out cutting from top to bottom.It is characterized in that: described step (4) is adjusted parameters for surveying, push-bench enters in the progradation of hole, moment is observed the variation of top power, enter behind stabilization zone, start to stop the mud jacking of head, and mud jacking position is moved gradually afterwards, entering after reinforcing area, move speed general control 1 ~ 2mm/min left and right, cutterhead and periphery cutter can be cut completely to cement-soil, can add proper amount of clear water or antifriction slurries to soften and the lubricated soil body, control fltting speed at 1 ~ 2 mm/min, earth balance pressure power is that 0.12MPa, the amount of being unearthed are controlled at every joint 44m 3left and right, cutterhead moment of torsion are controlled within 30%.It is characterized in that: described step (5) enter hole, shutoff portal is that rectangular pipe jacking machine enters behind hole, push-bench housing stops jacking when entering Chu Gang hole, hole circle inner edge same plane place, stop location, in the time that push-bench enters hole propelling, push-bench cutterhead has entered in built construction thing,, stop at once advancing when at the Yu Gang hole, housing forward position circle inner edge same plane place of push-bench body, housing and steel hole lap welding are connected into entirety with steel plate, carry out.And the gap of enclosing with hydraulicity slurries filling housing and hole, reduce soil erosion.It is characterized in that: described step (6) for push-bench stable after, remove 2, rear portion conveying worm, after overall pulling down, be pulled to and start in well with the interior flat car of passage, hang foundation ditch; With the Chain block suspension centre that sets in advance, large cutterhead wire rope is pinioned again fasteningly, shed the anterior cap mouth of large cutterhead, prop up plastron with jack, slowly large cutterhead is pushed in buffer platform, after slowly falling, carry in midair; After large cutterhead suspention is firm, remove 4 little cutterheads of residue in batches, 4 little cutterheads are lain against to buffer platform; Gear-box and the motor of removing cutterhead rear portion, be pulled to and started in well by flat car in passage, winches to ground and place; Remove hinged oil cylinder, disengaging oil cylinder, electric driving force cabinet and correction Hydraulic Station, be pulled to and start in well by flat car in passage, winch to ground and place; The push-bench cutterhead and the internal unit that disassemble transport in passage, finally cut off plastron, large and small cutterhead is transported to starting well in order and hangs out.It is characterized in that: described step (7) for by cast-in-place to the empty capsid of push-bench steel concrete and passage become overall.
Wherein be noted that especially:
1, the control of move speed and the amount of being unearthed
Enter the received well soil body at push-bench otch and enter behind stabilization zone, hole, should adjust immediately head attitude, it is paralleled with jacking axis, as far as possible the gaping of joints occurring between push-bench and rear portion tube coupling is kept to minimum.The move speed that simultaneously suitably slows down, strengthens the amount of being unearthed, and reduces gradually earth balance pressure power, to ensure hole place Stability Analysis of Structures and push-bench Plant in good condition.
2, rectangular pipe jacking machine is located after entering hole
Push-bench machete dise knife point is pushed into apart from diaphragm wall 10CM place, stop jacking, and at auspicious bright reception place hole circle external-open peep hole, confirm all right after, continue jacking push-bench, be pushed into circle inner edge same plane place, Yu Gang hole, casing limit and stop jacking, immediately steel plate is welded into an entirety with it, and the gap of enclosing with hydraulicity slurries filling tube coupling and hole, reduce soil erosion.
3, this engineering push-bench, entering behind hole to take " escaping unnoticed " technique, is stayed in passage by push-bench housing, and push-bench cutterhead and internal unit dismounting transport.
(1) after push-bench is stable, remove 2, rear portion conveying worm, after overall pulling down, be pulled to and start in well with flat car in passage, hang foundation ditch.
(2) auspicious bright enter steel concrete frame back portion of hole place four shaped steel of encorbelmenting are set.To encorbelmenting to such an extent that hang Chain block on shaped steel, large cutterhead is pinioned fastening with wire rope, shed the anterior cap mouth of large cutterhead, prop up plastron with jack, slowly large cutterhead is pushed into receiving platform, after slowly falling, carry in midair.Prepare next procedure.
(3) after large cutterhead suspention is firm, remove 4 little cutterheads of residue, dismounting order according to the situation, lies against receiving platform by 4 little cutterheads, prepares next procedure in batches.
(4) gear-box and the motor at dismounting cutterhead rear portion, be pulled to and started in well by flat car in passage, winches to ground and place.
(5) remove hinged oil cylinder, disengaging oil cylinder, electric driving force cabinet and correction Hydraulic Station, be pulled to and start in well by flat car in passage, winch to ground and place.
(6) cut off plastron, large and small cutterhead is transported to starting well in order and hangs out.
(7) remove receiving platform.
(8) equipment conveying such as cutterhead, screw machine of dismounting is left the theatre.

Claims (7)

  1. One kind in built construction thing rectangular pipe jacking machine enter the construction method in hole, it is characterized in that being formed by the following step: (1) receives buffer platform entering to set up in hole place built construction thing into hole, (2) entering push-bench cutterhead suspension centre is set in hole place built construction thing, (3) before entering hole, push pipe cuts portal, (4) adjust parameters, push-bench enters hole, (5) rectangular pipe jacking machine enters hole, shutoff portal, described step (5) enter hole, shutoff portal is that rectangular pipe jacking machine enters behind hole, in push-bench cutterhead has entered built construction thing, Yu Gang hole, the housing forward position circle inner edge of push-bench body stops at once advancing in the time of same plane place, housing and steel hole lap welding are connected into entirety with steel plate, and the gap of enclosing with hydraulicity slurries filling housing and hole, reduce soil erosion, (6) push-bench cutterhead, plastron and internal unit dismounting also transport in passage, (7) push-bench housing is stayed in passage.
  2. By claimed in claim 1 a kind of in built construction thing rectangular pipe jacking machine enter the construction method in hole, it is characterized in that: described step (1) is for receiving buffer platform entering to set up in hole place built construction thing into hole, to alleviate push-bench soil body impact force producing of caving in while entering hole, this buffer platform is set up with I20b i iron, platform surface is laid a 2cm steel plate, and steel plate and shaped steel frame are linked to be entirety with welding.
  3. By claimed in claim 1 a kind of in built construction thing rectangular pipe jacking machine enter the construction method in hole, it is characterized in that: described step (2) is for entering push-bench cutterhead suspension centre is set in hole place built construction thing, push-bench in built construction thing enters above hole place portal, on floor, 4 holes for hoist is set, on the floor of hole for hoist position, open four oval-shaped holes, paving 3.5m*2.5m*0.02m steel plate, on steel plate, keep flat three i iron, steel wire penetrating hole is hung on i iron, to be used for, the push-bench cutterhead entering behind hole is lifted to dismounting.
  4. By claimed in claim 1 a kind of in built construction thing rectangular pipe jacking machine enter the construction method in hole, it is characterized in that: described step (3) for the ground that enters portal place, Qian Duijin hole, hole at push-bench within the walls reinforcing bar carry out from inside to outside simultaneously cutting top to bottm, and for preventing that compacted soil from pouring in the necessary interception measure that basement is taked.
  5. By claimed in claim 1 a kind of in built construction thing rectangular pipe jacking machine enter the construction method in hole, it is characterized in that: described step (4) is for adjusting parameters, push-bench enters in the progradation of hole, moment is observed the variation of top power, enter behind stabilization zone, progressively stop the mud jacking of head, and mud jacking position is moved gradually afterwards, entering after reinforcing area, cutterhead and periphery cutter can be cut completely to cement-soil, and add proper amount of clear water or antifriction slurries to soften and the lubricated soil body, control fltting speed at 1~2mm/min, earth balance pressure power is 0.12MPa, unearthed amount is controlled at every joint 44m 3left and right, cutterhead moment of torsion is controlled within 30%.
  6. By claimed in claim 1 a kind of in built construction thing rectangular pipe jacking machine enter the construction method in hole, it is characterized in that: described step (6) for push-bench stable after, remove 2, rear portion conveying worm, after overall pulling down, be pulled to and start in well with flat car in passage, hang foundation ditch; With the Chain block suspension centre that sets in advance, large cutterhead wire rope is pinioned again fasteningly, shed the anterior cap mouth of large cutterhead, prop up plastron with jack, slowly large cutterhead is pushed in buffer platform, after slowly falling, carry in midair; After large cutterhead suspention is firm, remove 4 little cutterheads of residue in batches, 4 little cutterheads are lain against to buffer platform; Gear-box and the motor of removing cutterhead rear portion, be pulled to and started in well by flat car in passage, winches to ground and place; Remove hinged oil cylinder, disengaging oil cylinder, electric driving force cabinet and correction Hydraulic Station, be pulled to and start in well by flat car in passage, winch to ground and place; Finally cut off plastron, large and small cutterhead is transported to starting well in order and hangs out.
  7. By claimed in claim 1 a kind of in built construction thing rectangular pipe jacking machine enter the construction method in hole, it is characterized in that: described step (7) for by cast-in-place to the empty capsid of push-bench steel concrete and passage become overall.
CN201110448926.3A 2011-12-29 2011-12-29 Construction method for enabling rectangular pipe jacking machine to enter into tunnel in existing building Expired - Fee Related CN102505945B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110448926.3A CN102505945B (en) 2011-12-29 2011-12-29 Construction method for enabling rectangular pipe jacking machine to enter into tunnel in existing building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110448926.3A CN102505945B (en) 2011-12-29 2011-12-29 Construction method for enabling rectangular pipe jacking machine to enter into tunnel in existing building

Publications (2)

Publication Number Publication Date
CN102505945A CN102505945A (en) 2012-06-20
CN102505945B true CN102505945B (en) 2014-07-30

Family

ID=46218073

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110448926.3A Expired - Fee Related CN102505945B (en) 2011-12-29 2011-12-29 Construction method for enabling rectangular pipe jacking machine to enter into tunnel in existing building

Country Status (1)

Country Link
CN (1) CN102505945B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035730A (en) * 2017-11-10 2018-05-15 煤科集团沈阳研究院有限公司 A kind of long range coal mine roadway push pipe driving method

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103075162B (en) * 2012-12-29 2015-04-22 上海市机械施工集团有限公司 Tunnel portal earth retaining device as well as underground pedestrian passageway construction system and method
CN105839643B (en) * 2016-05-23 2017-10-10 浙江省交通规划设计研究院 A kind of tunnel construction method of use pattern foundation pit supporting structure
CN105863673B (en) * 2016-05-24 2019-03-26 长江勘测规划设计研究有限责任公司 Pusher fuselage can return to formula pipe jacking construction method and constructing structure
CN107143346B (en) * 2017-07-10 2018-04-27 中铁工程装备集团有限公司 Rectangular curve pipe curtain construction method for super large underground space construction
CN108979642A (en) * 2018-08-10 2018-12-11 江苏锐成机械有限公司 Miniature underground no-dig technique device
CN109356604A (en) * 2018-10-22 2019-02-19 中国建筑第六工程局有限公司 Subway station uses the vertical shaft method of reseptance of rectangular pipe jacking machine construction exit and entrance
CN110173272B (en) * 2019-05-26 2021-05-28 中国建筑第六工程局有限公司 Method for receiving subway station access channel in rectangular pipe jacking machine construction operation
CN110439590A (en) * 2019-08-06 2019-11-12 中铁十四局集团有限公司 Method for tunnel construction
CN111075474B (en) * 2020-01-08 2021-02-02 中铁十一局集团城市轨道工程有限公司 Rectangular pipe jacking construction method for subway station access and exit channel
CN112610233B (en) * 2020-11-27 2023-06-13 中铁十五局集团有限公司 Rectangular jacking pipe receiving construction method of' golden cicada shelling

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2635799A1 (en) * 1988-08-26 1990-03-02 Montcocol Method and device for positioning underground ducts.
RU2209978C1 (en) * 2002-11-15 2003-08-10 Общество с ограниченной ответственностью "Трансстройтоннель-99" Method of tunnel construction and device for method embodiment
CN101749021A (en) * 2008-12-18 2010-06-23 上海市机械施工有限公司 The oblique method of reseptance that enters in the narrow receiving well of push-bench during a kind of underground jacking construction

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100538398B1 (en) * 2002-11-29 2005-12-22 건양씨엔이 (주) The method of construction (KY-5 Pipejacking and propulsion method) and apparatus for propulsion based on soft and weak layer soil
KR20030045695A (en) * 2003-03-20 2003-06-11 성 봉 위 Method for Digging a Tunnel
JP3978746B2 (en) * 2003-03-31 2007-09-19 堤 郁夫 Tube installation method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2635799A1 (en) * 1988-08-26 1990-03-02 Montcocol Method and device for positioning underground ducts.
RU2209978C1 (en) * 2002-11-15 2003-08-10 Общество с ограниченной ответственностью "Трансстройтоннель-99" Method of tunnel construction and device for method embodiment
CN101749021A (en) * 2008-12-18 2010-06-23 上海市机械施工有限公司 The oblique method of reseptance that enters in the narrow receiving well of push-bench during a kind of underground jacking construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035730A (en) * 2017-11-10 2018-05-15 煤科集团沈阳研究院有限公司 A kind of long range coal mine roadway push pipe driving method
CN108035730B (en) * 2017-11-10 2020-04-28 煤科集团沈阳研究院有限公司 Long-distance coal mine roadway pipe jacking tunneling method

Also Published As

Publication number Publication date
CN102505945A (en) 2012-06-20

Similar Documents

Publication Publication Date Title
CN102505945B (en) Construction method for enabling rectangular pipe jacking machine to enter into tunnel in existing building
CN108691550B (en) Vertical shaft shield machine for underground upward construction and construction method thereof
CN106437737B (en) Pipe jacking type coal mine small-section roadway tunneling method
CN107035376B (en) One kind common law in huge thick bedrock aquifer digs shaft construction method
CN106285693A (en) A kind of shield steel bushing airtight reception construction method
CN105041322A (en) Method and system for reinforcing hole for push bench to go in and out
CN103821523A (en) Excavating method for extending existing single-hole two-driveway tunnel into four-driveway tunnel
CN105442532A (en) Construction method for pile-head-expanded bored pile
CN108662284A (en) The construction method of small-bore push pipe
CN103510572A (en) Construction method of water getting vertical shaft under complex geological condition
CN113494295A (en) Underground butt joint construction method for long and large shield tunnel
CN104612722B (en) Tunnel gate strengthening method for starting and arriving of annular shield or annular pushing pipe
CN208441848U (en) Freezing Method for Cross-passage Construction class rectangle push-bench
CN104453915B (en) Big cross section vertical shaft pre-pouring grout reinforces Rapid Excavation method
CN103643673A (en) Self-advancing recyclable steel pipe pile and construction method
CN110656952A (en) Shield tunneling machine cutter head access hole and construction method thereof
CN204040042U (en) A kind of super large ultra-deep support with manually dug piles structure
CN110566217A (en) shallow-earth-covered shield construction method
CN102635365B (en) Construction method for holing of shield machine
CN103334433B (en) A kind of construction method of pile pulling
CN104847373A (en) Gravel clay stratum shield departure and reception construction process
CN104989409A (en) Full-face excavation method after vertical shaft small-face pore forming
CN114754194A (en) Storage tank top pipe installation device and construction method thereof
CN107975027A (en) The construction method that shield launching is reinforced with reaching end soil body
CN108005083A (en) Anchor cable processing method in the range of a kind of foundation pit enclosure structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 201802 Jiading District Shunda Road, Shanghai, No. 615

Applicant after: SHANGHAI MECHANIZED CONSTRUCTION GROUP Co.,Ltd.

Address before: 201802 Jiading District Shunda Road, Shanghai, No. 615

Applicant before: SHANGHAI MECHANIZED CONSTRUCTION Co.,Ltd.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: SHANGHAI CITY MACHINERY CONSTRUCTION CO., LTD. TO: SHANGHAI MECHANIZED CONSTRUCTION CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140730

CF01 Termination of patent right due to non-payment of annual fee