CN104612722B - Tunnel gate strengthening method for starting and arriving of annular shield or annular pushing pipe - Google Patents
Tunnel gate strengthening method for starting and arriving of annular shield or annular pushing pipe Download PDFInfo
- Publication number
- CN104612722B CN104612722B CN201510006724.1A CN201510006724A CN104612722B CN 104612722 B CN104612722 B CN 104612722B CN 201510006724 A CN201510006724 A CN 201510006724A CN 104612722 B CN104612722 B CN 104612722B
- Authority
- CN
- China
- Prior art keywords
- annular
- portal
- steel ring
- push pipe
- enclosure wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000000034 method Methods 0.000 title abstract description 13
- 238000005728 strengthening Methods 0.000 title abstract 5
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 32
- 239000010959 steel Substances 0.000 claims abstract description 32
- 239000002689 soil Substances 0.000 claims abstract description 19
- 230000003014 reinforcing effect Effects 0.000 claims description 26
- 238000007789 sealing Methods 0.000 claims description 26
- 230000002787 reinforcement Effects 0.000 claims description 14
- 238000001556 precipitation Methods 0.000 claims description 4
- 238000007796 conventional method Methods 0.000 claims description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 7
- 238000009412 basement excavation Methods 0.000 abstract description 3
- 238000010276 construction Methods 0.000 description 6
- 238000010586 diagram Methods 0.000 description 6
- 230000000694 effects Effects 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 4
- 238000007569 slipcasting Methods 0.000 description 2
- 230000005641 tunneling Effects 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000007596 consolidation process Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000001419 dependent effect Effects 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 230000008676 import Effects 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 230000009974 thixotropic effect Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/38—Waterproofing; Heat insulating; Soundproofing; Electric insulating
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/06—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
- E21D9/0607—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Civil Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
The invention relates to a tunnel gate strengthening method for a starting and an arriving of an annular shield or an annular pushing pipe. The method comprises the steps that tunnel gate water stop steel ring is arranged on an enclosure wall; horizontal strengthening anchor rods are arranged in the tunnel gate of the enclosure wall; a concrete cover in two layers of the tunnel gate water stop steel ring is judged whether a rebar exists or not, if the rebar exists, the tunnel gate water stop steel ring is rearranged, if the rebar do not exist, an annular shield machine or an annular pipe pushing machine is used to explode the enclosure wall in sequence, the starting operation is completed, and a lining is formed; after a tunnel holing-through is conducted, the enclosure wall of an outer portion of the water stop steel ring is chiseled and removed, drainage for a soil body in a tunnel is conducted, the horizontal strengthening rods are removed, and an excavation of the rest soil body is conducted. Compared with the prior art, the tunnel gate strengthening method for the starting and the arriving of the annular shield or the annular pushing pipe has the advantages that the method is simple and easy, safe and reliable and the like.
Description
Technical field
The present invention relates to a kind of Tunnel Engineering technical field, especially relate to a kind of annular shield or annular push pipe originate and
The portal reinforcement means reaching.
Background technology
Gradually improving and saturation along with urban ground space development, the Chinese government is building resource-conserving, environment
Under the background of friendly society, more and more the starting point is put in the exploitation of the underground space.Due to the underground space
Exploitation there is high cost, excessive risk and irreversibility, how reasonably right with construction equipment with advanced science and technology
The underground space develops and utilizes becomes the key point solving this problem.
Annular shield or annular pipe-jacking technology be a kind of differ from conventional shield or the construction technology of push bench process, it is mainly constructed
Feature is the soil body first excavating in once lining place annular section, and applies once lining, treats after tunnel holing through again to one
The secondary lined internal soil body carries out overall excavation, and applies secondary lining.Its major advantage is tunnel-shaped and size in theory
Upper unrestricted.
Conventional shield or push pipe originate and the portal reinforcement means that reaches is mainly to soil body certain limit after portal at present
Inside carry out slip casting or fender post formula is reinforced it is intended to strengthen soil strength to ensure that during export & import, excavation face is stable and plays sealing
Effect.But due to being that annular section excavates when annular shield or annular jacking construction, not full face tunneling, therefore the problems referred to above can
To obtain reasonable solution, but the portal within annular hole door holder water steel ring goes along with sb. to guard him wall construction due to lacking surrounding supporting, tunnel
The internal soil body in road lacks support, all there is the overall danger caved in into active well, this will be a problem demanding prompt solution.
Content of the invention
The purpose of the present invention is exactly to overcome the defect of above-mentioned prior art presence to provide a kind of simple, safety
The portal reinforcement means that reliably annular shield or annular push pipe originate and reach.
The purpose of the present invention can be achieved through the following technical solutions:
The portal reinforcement means that a kind of annular shield or annular push pipe originate and reach, comprises the following steps:
1) apply portal sealing steel ring on starting well, received well portal enclosure wall, this portal sealing steel ring is provided with two-layer,
Its set location corresponds to inside and outside annular shield machine or annular push pipe casing body;
2) apply horizontal reinforcing anchor pole in the range of the portal sealing steel ring of inner side, and be connected with enclosure wall;
3), before annular shield or annular push pipe originate, whether judge in the concrete cover between two-layer portal sealing steel ring
There is reinforcing bar, if so, then return to step 1), again apply portal sealing steel ring, if it is not, then execution step 4);
4), when annular shield or annular push pipe originate, annular shield machine or annular push-bench are advanced into cutterhead and are gone along with sb. to guard him with portal
Wall contacts, and cutterhead is abolished the concrete in annular region, completed to originate operation;
5) annular shield machine or annular push-bench tunnel to received well, and enclosure wall abolished by cutterhead, forms once lining;
6), after tunnel holing through, cut the enclosure wall outside portal sealing steel ring, precipitation is carried out to the soil body in tunnel, pulls out water
Flat reinforcing anchor pole, excavates the remaining soil body.
Described horizontal reinforcing anchor pole setting is multiple, and multiple horizontal reinforcing anchor poles be arranged in parallel.
The method also includes:
For short distance underpass driving, the horizontal reinforcing anchor pole in starting well and received well can be carried out to the company of drawing
Connect, improve the binding effect to portal for the anchor pole.
Horizontal reinforcing anchor pole can be applied, received well portal adopts routine side in the range of a portal sealing steel ring in starting well
Method is reinforced.
Compared with prior art, the method have the advantages that
(1) present invention utilizes this reinforcing mode of anchor pole to substitute the portal reinforcement means of traditional slip casting or fender post formula,
Waterproof and soil mass consolidation effect can be played, the connectivity of the soil body and portal building enclosure can be increased, it is to avoid portal goes along with sb. to guard him knot again
Structure causes entirety to topple due to lacking constraint, is easy to pull out simultaneously, solves annular shield or annular this new construction of push pipe
The new problem that technique is brought.
(2) this method is simple to operation, cheap, and anchor pole can be reused, have higher economy and
Promotional value.
Brief description
Fig. 1 is portal reinforcement means generalized section
Fig. 2 is annular shield or annular push-bench originates pushing tow to schematic diagram during building enclosure;
Fig. 3 is annular shield or the schematic diagram that portal originates propulsion abolished by annular push-bench;
Fig. 4 is annular shield or annular push-bench reaches pushing tow to schematic diagram during received well enclosed structure;
Fig. 5 is annular shield or annular push-bench is abolished portal and reached received well schematic diagram;
Fig. 6 progressively cuts portal for after tunnel holing through, the internal soil body is carried out with precipitation and pulls out anchor pole schematic diagram.
In figure: 1- cutterhead, 2- housing, 3- annular lining cutting, 4- injected hole, the pre- tunneling of 5-, 6- horizontal reinforcing anchor pole, 7-
Enclosure wall, 8- portal sealing steel ring, 9- originates or receives bracket, 10- active well base plate, 11- received well base plate.
Specific embodiment
The present invention is described in detail with specific embodiment below in conjunction with the accompanying drawings.The present embodiment is with technical solution of the present invention
Premised on implemented, give detailed embodiment and specific operating process, but protection scope of the present invention be not limited to
Following embodiments.
Be present invention annular shield as shown in figs 1 to 6 or annular push pipe originate and the portal reinforcement means that reaches concrete
Schematic diagram, in Fig. 1, applies portal sealing steel ring 8 along portal position, applies horizontal reinforcing anchor pole 6 in the range of the steel ring of inner side;Figure
In 2, when annular shield or annular push pipe originate, annular shield or annular push pipe are advanced into cutterhead 1 and are contacted with portal enclosure wall 7;
In Fig. 3, the concrete in annular section abolished by cutterhead 1, and annular shield or annular push pipe complete to originate propulsion;In Fig. 4, annular shield
Structure or annular push pipe complete tunnel piercing, reach received well enclosure wall 7;In Fig. 5, the concrete in annular section abolished by cutterhead 1,
Annular shield or annular push pipe reach received well;In Fig. 6, after tunnel holing through, progressively cut the outside portal enclosure wall of sealing steel ring 8
7, precipitation is carried out to the tunnel internal soil body, pulls out horizontal reinforcing anchor pole 6, excavate the remaining soil body.
Annular shield that the present embodiment provides or annular push pipe originate and the portal reinforcement means that reaches specifically include following
Step:
1) starting well (active well), received well and corresponding enclosure wall 7 structure are applied using conventional method, enclosure wall 7 is applied
In man-hour, apply portal sealing steel ring 8 along portal position;
2) portal sealing steel ring 8 is provided with two-layer, and its set location corresponds to annular shield machine or annular push pipe casing body 2
Inside and outside;
3), after enclosure wall 7 construction terminates, inside portal sealing steel ring 8, apply horizontal reinforcing anchor pole 6 in the range of steel ring, many
Individual horizontal reinforcing anchor pole 6 be arranged in parallel, and is reliably connected with enclosure wall 7 formation, as shown in Figure 1;
Horizontal reinforcing anchor pole can apply in the range of the inner side portal sealing steel ring of starting well and received well simultaneously, and will begin
Send out the horizontal reinforcing anchor pole in well and received well to be attached, to drawing, improving the binding effect to portal for the anchor pole;Also dependent on tool
The feature of body engineering, only arranges horizontal reinforcing anchor pole in starting well, and the portal in received well can adopt existing portal reinforcing side
Method is reinforced.
4) it is respectively mounted in starting well and received well and originate or receive bracket 9, lifting annular shield machine or annular push-bench;
5), before annular shield or annular push pipe originate, whether deposit in the concrete cover between detection portal sealing steel ring 8
In reinforcing bar, if so, then return to step 1), again apply portal sealing steel ring 8, if it is not, then execution step 6);
6), when annular shield or annular push pipe originate, annular shield or annular push pipe are advanced into cutterhead 1 and portal enclosure wall 7
Contact, as shown in Figure 2;
7) concrete in annular section abolished by cutterhead 1, and annular shield or annular push pipe complete to originate propulsion, as Fig. 3 institute
Show;
8), when annular shield or annular push pipe tunnel, thixotropic slurry is from injected hole 4 note of rear annular lining cutting 3 surfaces externally and internally
Enter the gap between annular lining cutting 3 and the soil body;
9) annular shield or annular push pipe tunnel to received well enclosure wall 7, as shown in Figure 4;
10) concrete in annular section abolished by cutterhead 1, and annular shield or annular push pipe reach received well, as Fig. 5 institute
Show;
11), after tunnel holing through, progressively cut the portal enclosure wall 7 outside sealing steel ring 8, the tunnel internal soil body is dropped
Water, pulls out horizontal reinforcing anchor pole 6, excavates the remaining soil body, as shown in Figure 6.
Claims (5)
1. a kind of annular shield or annular push pipe originate and the portal reinforcement means that reaches is it is characterised in that comprise the following steps:
1) apply portal sealing steel ring on starting well, received well portal enclosure wall, this portal sealing steel ring is provided with two-layer, and it sets
Seated position corresponds to inside and outside annular shield machine or annular push pipe casing body;
2) apply horizontal reinforcing anchor pole in the range of the portal sealing steel ring of inner side, and be connected with enclosure wall;
3), before annular shield or annular push pipe originate, judge to whether there is in the concrete cover between two-layer portal sealing steel ring
Reinforcing bar, if so, then return to step 1), again apply portal sealing steel ring, if it is not, then execution step 4);
4), when annular shield or annular push pipe originate, annular shield machine or annular push-bench are advanced into cutterhead and are connect with portal enclosure wall
Touch, the concrete in annular region abolished by cutterhead, completes to originate operation;
5) annular shield machine or annular push-bench tunnel to received well, and enclosure wall abolished by cutterhead, forms once lining;
6), after tunnel holing through, cut the enclosure wall outside portal sealing steel ring, precipitation is carried out to the soil body in tunnel, the level of pulling out adds
Gu anchor pole, excavate the remaining soil body.
2. the portal reinforcement means that annular shield according to claim 1 or annular push pipe originate and reach, its feature exists
In described horizontal reinforcing anchor pole setting is multiple, and multiple horizontal reinforcing anchor poles be arranged in parallel.
3. the portal reinforcement means that annular shield according to claim 1 or annular push pipe originate and reach, its feature exists
In applying horizontal reinforcing anchor pole in the range of the inner side portal sealing steel ring of starting well and received well simultaneously.
4. the portal reinforcement means that annular shield according to claim 3 or annular push pipe originate and reach, its feature exists
In also including:
For short distance underpass driving, the horizontal reinforcing anchor pole in starting well and received well is carried out to drawing connection.
5. the portal reinforcement means that annular shield according to claim 1 or annular push pipe originate and reach, its feature exists
In only applying horizontal reinforcing anchor pole in the range of the inner side portal sealing steel ring of starting well, received well portal adopts conventional method
Reinforce.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510006724.1A CN104612722B (en) | 2015-01-07 | 2015-01-07 | Tunnel gate strengthening method for starting and arriving of annular shield or annular pushing pipe |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510006724.1A CN104612722B (en) | 2015-01-07 | 2015-01-07 | Tunnel gate strengthening method for starting and arriving of annular shield or annular pushing pipe |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104612722A CN104612722A (en) | 2015-05-13 |
CN104612722B true CN104612722B (en) | 2017-01-25 |
Family
ID=53147347
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510006724.1A Expired - Fee Related CN104612722B (en) | 2015-01-07 | 2015-01-07 | Tunnel gate strengthening method for starting and arriving of annular shield or annular pushing pipe |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104612722B (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105863673B (en) * | 2016-05-24 | 2019-03-26 | 长江勘测规划设计研究有限责任公司 | Pusher fuselage can return to formula pipe jacking construction method and constructing structure |
CN108729469B (en) * | 2017-04-14 | 2020-10-20 | 植村技研工业株式会社 | Construction method of underground structure |
JP6933520B2 (en) * | 2017-07-25 | 2021-09-08 | 積水化学工業株式会社 | Reinforcement anchor |
JP7032143B2 (en) * | 2018-01-11 | 2022-03-08 | 積水化学工業株式会社 | Reinforcing anchor |
CN111677518B (en) * | 2020-07-08 | 2022-05-13 | 北京建工土木工程有限公司 | Shield receiving end reinforcing structure, reinforcing method and shield receiving method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1862637B1 (en) * | 2006-05-30 | 2009-07-15 | DYWIDAG Bau GmbH | Device and method for a shield driving start-up and extension |
CN101608551A (en) * | 2009-06-15 | 2009-12-23 | 广东华隧建设股份有限公司 | The job practices of a kind of shield machine closed origin and arrival |
CN102022118A (en) * | 2010-12-15 | 2011-04-20 | 广东华隧建设股份有限公司 | Method for realizing balanced arrival of shield machine |
CN102425423A (en) * | 2011-12-31 | 2012-04-25 | 上海市机械施工有限公司 | Constructing method for shield entering into hole while passing through pipeline |
CN103790592A (en) * | 2014-01-27 | 2014-05-14 | 中铁二十二局集团第一工程有限公司 | End soil mass reinforcement system and method |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009046959A (en) * | 2007-08-16 | 2009-03-05 | Hiroaki Fujii | Construction method for underground pipe line |
-
2015
- 2015-01-07 CN CN201510006724.1A patent/CN104612722B/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1862637B1 (en) * | 2006-05-30 | 2009-07-15 | DYWIDAG Bau GmbH | Device and method for a shield driving start-up and extension |
CN101608551A (en) * | 2009-06-15 | 2009-12-23 | 广东华隧建设股份有限公司 | The job practices of a kind of shield machine closed origin and arrival |
CN102022118A (en) * | 2010-12-15 | 2011-04-20 | 广东华隧建设股份有限公司 | Method for realizing balanced arrival of shield machine |
CN102425423A (en) * | 2011-12-31 | 2012-04-25 | 上海市机械施工有限公司 | Constructing method for shield entering into hole while passing through pipeline |
CN103790592A (en) * | 2014-01-27 | 2014-05-14 | 中铁二十二局集团第一工程有限公司 | End soil mass reinforcement system and method |
Also Published As
Publication number | Publication date |
---|---|
CN104612722A (en) | 2015-05-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104612722B (en) | Tunnel gate strengthening method for starting and arriving of annular shield or annular pushing pipe | |
CN105888703B (en) | Super Shallow Covered Metro Station construction method under lateral canopy lid is performed in micro- pilot tunnel | |
CN101775988B (en) | Construction method for inclined shaft to main tunnel of weak surrounding rock | |
CN102493822B (en) | Method for performing curtain grouting construction on tunnel by water rich fault influence zone | |
CN104278993B (en) | A kind of bias voltage Skew Tunnel enters the constructional method in hole | |
CN105240024B (en) | A kind of method of parallel shield method enlarging construction subway station | |
CN104047623B (en) | A kind of big across cavern excavation construction method | |
CN103306680B (en) | Existing single-track tunnel enlarging is the construction method of multiple track tunnel | |
CN102155234B (en) | Excavation construction method for unsymmetrical small-space tunnel | |
CN101781991B (en) | Double-well type reinforcement method of shield arrival or starting end and double-well type shield arrival method | |
CN202117686U (en) | Surrounding rock advanced support structure for railway tunnel at deep-buried watery and weak stratums | |
CN109736827B (en) | Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing | |
CN107218045B (en) | The rapid constructing method of rocky stratum tunneling subway station entrance tunneling section | |
CN103485790A (en) | Shallow tunneling method for pipe-proof-supporting structure combined system | |
CN105065009B (en) | A kind of method extending shield-tunneling construction subway station | |
CN103114857A (en) | Shield tunnel construction method | |
CN105041322A (en) | Method and system for reinforcing hole for push bench to go in and out | |
CN109209392A (en) | Loopful excavation method suitable for IV-V grade of country rock of large cross-section tunnel | |
CN104675405B (en) | Rectangular pipe jacking machine tunnel entering auxiliary structure and construction method | |
CN102817621B (en) | Comprehensive construction method applicable to controlling arch basement sedimentation for tunnel in unfavorable geological conditions | |
CN107165661A (en) | A kind of high-ground stress weak surrounding rock large deformation tunnel overlength enlarged footing anchor cable construction method | |
CN102182464A (en) | Construction structure and construction method of channel structure | |
CN106321142A (en) | Rock cross-cut coal uncovering method combining microwave-assisted extraction with grouting reinforcement | |
CN105240023B (en) | A kind of method of Curve Pipe Jacking supporting construction enlarging shield-tunneling construction subway station | |
CN109356193B (en) | Prefabricated piping lane propelling movement construction equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170125 Termination date: 20200107 |