CN109235437A - One kind abolishing pile crown method - Google Patents

One kind abolishing pile crown method Download PDF

Info

Publication number
CN109235437A
CN109235437A CN201811274367.7A CN201811274367A CN109235437A CN 109235437 A CN109235437 A CN 109235437A CN 201811274367 A CN201811274367 A CN 201811274367A CN 109235437 A CN109235437 A CN 109235437A
Authority
CN
China
Prior art keywords
mold
reinforcing bar
pile crown
concrete
recessed portion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811274367.7A
Other languages
Chinese (zh)
Inventor
闫慧清
唐玉明
李江舵
朱涵
相朋林
魏誓轩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Beijing Engineering Group Co Ltd
Original Assignee
China Railway Beijing Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Beijing Engineering Group Co Ltd filed Critical China Railway Beijing Engineering Group Co Ltd
Priority to CN201811274367.7A priority Critical patent/CN109235437A/en
Publication of CN109235437A publication Critical patent/CN109235437A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

Abolishing pile crown method the present invention provides one kind includes: the first molding process of installation, installs the first mold in grouting region, and enter and install mold additional;Reinforcing bar step is installed, the first reinforcing bar is installed in the first mold;Second molding process is installed, the second mold is installed in the first mold exterior, the lower part of the second mold has a recessed portion, and the position that recessed portion needs guiding through the first reinforcing bar is provided with aperture, and tapping is provided with rubber stopper, and ensuring will not spillage between the first mold and the second mold;Casing step is installed, is arranged with casing in the reinforcing bar being located in the second mold;Grouting step, to the first mold and the second mold penetration concrete;Step of removal after concrete completes solidification, removes the first mold and the second mold;Pile crown step is abolished, the concrete section of recess is crushed;Pile crown step is removed, concrete at pile crown is hung.With human cost is reduced, difficulty of construction is reduced, improves the technical effects such as construction efficiency.

Description

One kind abolishing pile crown method
Technical field
The present invention relates to technical field of concrete construction, and in particular to one kind abolishes pile crown method.
Background technique
When pouring, coarse aggregate can sink pile foundation concrete, while cement mortar can float, and then make at the top of pile foundation Concrete gravel content is accordingly less, is also easy to produce pine top phenomenon, and concrete strength also accordingly reduces, to guarantee pile foundation pouring quality And intensity abolishes extra pile crown often in the concrete of the superfilled 0.5m-0.8m in top, and after concrete curing.
Summary of the invention
The object of the present invention is to provide one kind to abolish pile crown method, can efficiently abolish the superfilled concrete pile head in top, subtract Few human cost, reduces difficulty of construction, improves construction efficiency.
To solve the above problems, abolishing pile crown method the present invention provides one kind includes: the first molding process of installation, filling It starches region and the first mold is installed, and enter and install mold additional;Reinforcing bar step is installed, the first reinforcing bar is installed in first mold; Second molding process is installed, the second mold is installed in first mold exterior, the lower part of second mold is recessed with one Concave portion, the position that the recessed portion needs guiding through first reinforcing bar is provided with aperture, and the tapping is provided with rubber stopper, And ensure will not spillage between first mold and second mold;Casing step is installed, second mold is being located at Interior reinforcing bar is arranged with casing;Grouting step, to first mold and the second mold penetration concrete;Step of removal, After concrete completes solidification, first mold and second mold are removed;Pile crown step is abolished, the recess is crushed Concrete section;Pile crown step is removed, concrete at pile crown is hung.
After receiving in recessed portion, so that the first reinforcing bar is exposed herein, after concrete grouting, the first mold and second is removed Mold, and the concrete at the second mold indentions portion is abolished, simultaneously because the reinforcing bar in the second mold is arranged with casing, so this Place can hang top pile crown concrete.
Further, above-mentioned to abolish pile crown method further include: the first reinforcing bar step of adjustment is abolishing concrete at pile crown Afterwards, by first bar straightening.
It is curved due to that may touch reinforcing bar in abolishing Concrete, so by reinforcing bar again straightening.
Further, above-mentioned to abolish pile crown method further include: the second reinforcing bar step of welding is wiped out in second mold Reinforcing bar, and the second reinforcing bar is welded at first reinforcing bar place of wiping out.
If poured, effect is undesirable, and the reinforcing bar in the second mold, can be by recessed portion together with concrete bonding Concrete is wiped out, and again welded reinforcement enter in next step pour.
Further, above-mentioned to abolish recessed portion described in pile crown method with a round-corner transition.
Further, above-mentioned to abolish the first mold described in pile crown method and second mold is made of plank.
Further, it is above-mentioned abolish the first molding process is installed described in pile crown method after, further includes: pre-buried step: Second mold is laterally embedded with suspender steel pipe casing.
The present invention reduces difficulty of construction with that can reduce human cost, improves the technical effects such as construction efficiency.
Detailed description of the invention
Fig. 1 is illustrated embodiment scheme of installation according to the present invention;
Fig. 2 is the top view of the second mold in illustrated embodiment according to the present invention;
Fig. 3 is the A-A cross-sectional view in Fig. 2.
Appended drawing reference:
1: the first mold;2: the second molds;21: recessed portion;22: suspender steel pipe casing;3: the first reinforcing bars.
Specific embodiment
In order to make the objectives, technical solutions and advantages of the present invention clearer, With reference to embodiment and join According to attached drawing, the present invention is described in more detail.It should be understood that these descriptions are merely illustrative, and it is not intended to limit this hair Bright range.In addition, in the following description, descriptions of well-known structures and technologies are omitted, to avoid this is unnecessarily obscured The concept of invention.
In the description of the present invention, it should be noted that term " first ", " second ", " third " are used for description purposes only, It is not understood to indicate or imply relative importance.
With reference to Fig. 1, illustrated embodiment of the present invention includes the following steps: to install the first molding process, installs in grouting region First mold 1, and enter and install mold additional;Reinforcing bar step is installed, the first reinforcing bar 3 is installed in first mold 1;Installation second Molding process, installs the second mold 2 outside first mold 1, and the lower part of second mold 2 has a recessed portion 21, the position that the recessed portion 21 needs guiding through first reinforcing bar is provided with aperture, and the tapping is provided with rubber stopper, And ensure will not spillage between first mold 1 and second mold 2;Casing step is installed, second mould is being located at Reinforcing bar in tool 2 is arranged with casing;Grouting step, to first mold 1 and 2 penetration concrete of the second mold;Demoulding Step after concrete completes solidification, removes first mold 1 and second mold 2;Pile crown step is abolished, is crushed described The concrete section of recess 21;Pile crown step is removed, concrete at pile crown is hung.
After receiving in recessed portion, so that the first reinforcing bar is exposed herein, after concrete grouting, the first mold and the second mould are removed Tool, and the concrete at the second mold indentions portion is abolished, simultaneously because the reinforcing bar in the second mold is arranged with casing, so herein Top pile crown concrete can be hung.
Simultaneously in order to avoid the concrete being located in the second mold 2 is Nian Jie with the first reinforcing bar 3, can be wrapped in jacket exterior Foam, in this way at the top of removal when pile crown concrete, will not because the concrete in the second template 2 is Nian Jie with the first reinforcing bar 3 and Cause top pile crown concrete that can not extract, so the amount of abolishing of concrete is greatly reduced.
Specifically, method shown in the present embodiment further include: adjustment 3 step of the first reinforcing bar is being abolished at pile crown after concrete, By 3 straightening of the first reinforcing bar.
It is curved due to that may touch reinforcing bar in abolishing Concrete, so by reinforcing bar again straightening.
Specifically, method shown in the present embodiment further include: the second reinforcing bar step of welding is wiped out in second mold 2 First reinforcing bar 3, and the second reinforcing bar is welded at 3 place of wiping out of the first reinforcing bar.
If poured, effect is undesirable, and the reinforcing bar in the second mold, can be by recessed portion together with concrete bonding Concrete is wiped out, and again welded reinforcement enter in next step pour.
Specifically, the recessed portion 21 in method shown in the present embodiment has a round-corner transition.
Specifically, first mold 1 in method shown in the present embodiment and second mold 2 are made of plank.
It, can also pre-buried two suspender steel pipes casing 22, reference in the first mold after the first molding process is installed Steel wire is penetrated the through-hole formed by suspender steel pipe casing 22 in this way after completing concreting by Fig. 2 and Fig. 3, can be light Pine completes lifting operation, removes pile crown.
It should be understood that above-mentioned specific embodiment of the invention is used only for exemplary illustration or explains of the invention Principle, but not to limit the present invention.Therefore, that is done without departing from the spirit and scope of the present invention is any Modification, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.In addition, appended claims purport of the present invention Covering the whole variations fallen into attached claim scope and boundary or this range and the equivalent form on boundary and is repairing Change example.

Claims (6)

1. one kind abolishes pile crown method characterized by comprising
First molding process is installed, in grouting region installation the first mold (1), and enters installation reinforcing bar step;
Reinforcing bar step is installed, the first reinforcing bar (3) are installed in first mold (1);
Second molding process is installed, the second mold (2) are installed outside first mold (1), under second mold (2) Portion has a recessed portion (21), and the position that the recessed portion (21) needs guiding through first reinforcing bar is provided with aperture, and in institute It states tapping and is provided with rubber stopper;
Casing step is installed, is arranged with casing in the reinforcing bar being located in second mold (2);
Grouting step, to first mold (1) and second mold (2) penetration concrete;
Step of removal after concrete completes solidification, removes first mold (1) and second mold (2);
Pile crown step is abolished, the concrete section of the recess (21) is crushed;
Pile crown step is removed, concrete at pile crown is hung.
2. abolishing pile crown method according to claim 1, which is characterized in that further include:
The first reinforcing bar (3) step is adjusted, is being abolished at pile crown after concrete, by the first reinforcing bar (3) straightening.
3. according to claim 1 or claim 2 abolish pile crown method, which is characterized in that further include:
The second reinforcing bar step is welded, wipes out the first reinforcing bar (3) in second mold (2), and cut in first reinforcing bar (3) Except the second reinforcing bar is welded at place.
4. abolishing pile crown method according to claim 1, it is characterised in that:
The recessed portion (21) has a round-corner transition.
5. abolishing pile crown method according to claim 1, it is characterised in that:
First mold (1) and second mold (2) are made of plank.
6. abolishing pile crown method according to claim 1, it is characterised in that:
After the first molding process of the installation, further includes:
Pre-buried step: suspender steel pipe casing (22) is laterally embedded in second mold.
CN201811274367.7A 2018-10-30 2018-10-30 One kind abolishing pile crown method Pending CN109235437A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811274367.7A CN109235437A (en) 2018-10-30 2018-10-30 One kind abolishing pile crown method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811274367.7A CN109235437A (en) 2018-10-30 2018-10-30 One kind abolishing pile crown method

Publications (1)

Publication Number Publication Date
CN109235437A true CN109235437A (en) 2019-01-18

Family

ID=65079184

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811274367.7A Pending CN109235437A (en) 2018-10-30 2018-10-30 One kind abolishing pile crown method

Country Status (1)

Country Link
CN (1) CN109235437A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5961253A (en) * 1994-12-05 1999-10-05 Okawa; Shogen Pile head dresser, pile head dressing method, and, placement of cast-in-place concrete piles
CN102518124A (en) * 2011-11-30 2012-06-27 中交隧道工程局有限公司 Method for chiseling away cast-in-place pile head concrete rapidly
CN106400803A (en) * 2016-10-31 2017-02-15 中国葛洲坝集团第六工程有限公司 Integral cast-in-situ bored pile head breaking process
CN107130601A (en) * 2017-05-31 2017-09-05 中建二局第二建筑工程有限公司 It is a kind of to improve device and restructuring bankrupt that pile crown abolishes efficiency
CN108385686A (en) * 2018-03-02 2018-08-10 中铁上海工程局集团有限公司 A kind of cast-in-situ bored pile exempts from stripping and exempts from ring cutting to cut pile crown technique

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5961253A (en) * 1994-12-05 1999-10-05 Okawa; Shogen Pile head dresser, pile head dressing method, and, placement of cast-in-place concrete piles
CN102518124A (en) * 2011-11-30 2012-06-27 中交隧道工程局有限公司 Method for chiseling away cast-in-place pile head concrete rapidly
CN106400803A (en) * 2016-10-31 2017-02-15 中国葛洲坝集团第六工程有限公司 Integral cast-in-situ bored pile head breaking process
CN107130601A (en) * 2017-05-31 2017-09-05 中建二局第二建筑工程有限公司 It is a kind of to improve device and restructuring bankrupt that pile crown abolishes efficiency
CN108385686A (en) * 2018-03-02 2018-08-10 中铁上海工程局集团有限公司 A kind of cast-in-situ bored pile exempts from stripping and exempts from ring cutting to cut pile crown technique

Similar Documents

Publication Publication Date Title
CN106013530B (en) The reinforcement structure of concrete shear force wall based on 3D printing
CN103276651B (en) No-cutting-seam cement concrete pavement structure and construction method thereof
CN106150523B (en) A kind of Railway Tunnel ditch cable trench integral mold plate construction
CN203729322U (en) Precast concrete pipeline foundation
CN106149878B (en) Concrete frame structure prefabricated post and the connection structure and method at beam slab node
CN106149877B (en) Concrete frame structure prefabricated post and the docking structure and method at beam slab node
CN106906747A (en) A kind of column and bent cap splicing structure
CN109235437A (en) One kind abolishing pile crown method
CN104911999A (en) Construction method for deeply burying anchor
CN205714221U (en) A kind of Tunnel Second Lining vault is owed to dig place's teeming building structure
KR101120588B1 (en) Vertical joint frame for improving monolithic concrete
CN107190781A (en) Horizontal joint waterproofing construction method is set up in large space basement roof post-cast strip
CN106223477A (en) A kind of precast reinforced concrete structure method of attachment
CN110205943A (en) The construction method of prefabricated freely-supported small box girder end floor beam
CN209227530U (en) One kind abolishing pile crown device
CN213268394U (en) Simple and easy channel-section steel hole shutoff mould
CN103161311A (en) Construction method for transverse penetration of long-diameter reinforced concrete pipeline through bridge abutment
KR102105771B1 (en) Water proofing plate installed with forms
CN103266769B (en) A kind of construction method of spherical vault lid
JP5290714B2 (en) PRECAST CONCRETE MEMBER FOR WAVE RETURN PART OF DAM WALL WALL
CN209457383U (en) The working sealing stirrup in high-low bay position
CN110778110B (en) Post-pouring method for plugging plate at hollow-out structure of hyperboloid diagonal grid concrete member
CN110258341B (en) Construction method for improving smoothness of longitudinal ribs of curved section of bridge sidewalk
CN108612126A (en) A kind of Reinforced Concrete Retaining Walls setting-up of construction joint method for determining position
CN109024852A (en) Secondary lifting installation method and device for rain grate opening

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination