CN106906747A CN201710082481.9A CN201710082481A CN106906747A CN 106906747 A CN106906747 A CN 106906747A CN 201710082481 A CN201710082481 A CN 201710082481A CN 106906747 A CN106906747 A CN 106906747A
Authority
CN
China
Prior art keywords
column
bent cap
metal bellows
splicing
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710082481.9A
Other languages
Chinese (zh)
Inventor
沈维芳
冀振龙
崔晨
卢永成
刘经熠
朱世峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai City Road Investment (group) Co Ltd
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai City Road Investment (group) Co Ltd
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai City Road Investment (group) Co Ltd, Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai City Road Investment (group) Co Ltd
Publication of CN106906747A publication Critical patent/CN106906747A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to a kind of column and bent cap splicing structure, for the splicing of column and bent cap, the bottom of the column is fixed on cushion cap, and some reinforcing bars are stretched out at the top of the column;Pre-buried some metal bellows in the bent cap, the bottom of the metal bellows flushes with the bottom surface of the bent cap;The position of the metal bellows is corresponding with the position of the reinforcing bar;Splicing seams between the column and the bent cap are connect using high-strength mortar or epoxy piece splicing;Mud jacking passage is provided with the bent cap, the every two ends of the metal bellows are connected by the mud jacking passage with pulp inlet and grout outlet respectively.The present invention changes traditional bridge construction mode, and job site, without template, substantially reduces the live duration without support, alleviates labor strength, reduces the requirement to construction site;Eliminate live bracket basis treatment and set up the operation of rack template, good economy performance;The negative effect to surrounding environment is reduced simultaneously.

Description

A kind of column and bent cap splicing structure
Technical field
The present invention relates to bridge structure construction field, more particularly to a kind of column and bent cap splicing structure.
Background technology
At present, bridge coping is cast-in-place generally using Support Method with the connection of column, that is, support and template are set up, on cushion cap Colligation column reinforcing bar, after completing the cast of column concrete and maintenance, rotary ligating cover beam steel, then the cast of bent cap concrete is carried out, A general construction period is at least 2~3 weeks.
Its drawback is long construction period, and field procedure is more, high to site requirements, and strutting system is high to fundamental importance, peace Full property is poor, seriously polluted, big on surrounding enviroment influence.
The content of the invention
The present invention provides a kind of column and bent cap splicing structure, to solve above-mentioned technical problem.
In order to solve the above technical problems, the present invention provides a kind of column and bent cap splicing structure, for column and bent cap Splicing, the bottom of the column is fixed on cushion cap, and some reinforcing bars are stretched out at the top of the column;It is pre-buried some in the bent cap Metal bellows, the bottom of the metal bellows flushes with the bottom surface of the bent cap;The position of the metal bellows and institute State the position correspondence of reinforcing bar;Splicing seams between the column and the bent cap are connect using high-strength mortar or epoxy piece splicing; Be provided with mud jacking passage in the bent cap, every two ends of the metal bellows respectively by the mud jacking passage and pulp inlet and Grout outlet is connected.
It is preferred that the reinforcing bar with diameter greater than equal to 22mm.
It is preferred that a diameter of 22mm, 25mm, 28mm, 32mm, 36mm, 40mm of the reinforcing bar or more.
It is preferred that the length that the reinforcing bar stretches out the part of the column is 20~50 times of the diameter of the reinforcing bar.
It is preferred that the wall thickness of the metal bellows is 0.4~2mm, rib 3.1~5mm high, embedded depth is the reinforcing bar 20~50 times of diameter, the big 20~40mm of diameter of the internal diameter reinforcing bar.
It is preferred that slurry check ring is equipped with the every reinforcing bar, the diameter metal bellows of the slurry check ring The big 1cm of nozzle diameter.
It is preferred that the splicing seams between the column and the bent cap are highly 20~30mm, the top surface four of the column Rubber cushion blocks are respectively equipped with angle, the section of the rubber cushion blocks is the square of 100 × 100mm, the thickness of the rubber cushion blocks It is 20~31mm to spend, and the top edge of the column is enclosed and is provided with block pulp template, and the high-strength sand is laid in the block pulp template Slurry, paving slurry thickness is higher by more than the rubber cushion blocks 5mm.
It is preferred that the splicing seams between the column and the bent cap are highly 2~5mm, the top surface corner of the column Place is respectively equipped with pad, and the section of the pad is the square of 100 × 100mm, and the thickness of the pad is 2~5mm, described The top edge of column is enclosed and is provided with block pulp template, and the epoxy piece glue is laid in the block pulp template, and paving glue thickness is higher by More than the pad 2mm.
It is preferred that the bottom of the metal bellows connects with the pulp inlet, the top of the metal bellows and institute State grout outlet connection.
Compared with prior art, the column that the present invention is provided has the following advantages that with bent cap splicing structure:
1. the present invention changes traditional bridge construction mode, job site without support, without template, a large amount of field cast-in-place quantities Switch to prefabricated completion in factory, thus be substantially shorter the live duration, reduce construction site;Eliminate live bracket basis treatment With the operation for setting up rack template, overall economics are good;
2. work on the spot amount is reduced, the labour intensity of field worker is alleviated, it is ensured that the safety work of workmen;
3. metal bellows and bar connecting are used, and material price is cheap, it is possible to decrease construction costs;
4. the factor such as noise, dust, light, sewage is to surrounding enviroment when can reduce construction, and traffic is produced it is negative Influence.
5., due to being that plant produced makes, component quality is good, it is advantageously ensured that the quality and dimensional accuracy of component, and to the greatest extent may be used Use mechanized construction more than energy;By after element precast due to deposit a period of time, therefore existing certain age when mounted, Concrete shrinkage can be reduced, the deformation for causing of creeping.
Brief description of the drawings
Fig. 1 is structural representation of one embodiment of the invention central post with bent cap after assembled;
Fig. 2 is the structural representation at one embodiment of the invention central post and bent cap splicing seams;
Fig. 3 is the sectional view at 1-1 in Fig. 2;
Fig. 4 is the structural representation of one embodiment of the invention central post;
Fig. 5 a to Fig. 5 c are followed successively by the construction procedure schematic diagram of one embodiment of the invention central post and bent cap splicing structure.
In figure:10- columns, 11- reinforcing bars, 20- bent caps, 21- metal bellows, 22- mud jacking passage, 23- pulp inlets, 24- Grout outlet, 30- cushion caps, 40- splicing seams, 41- rubber cushion blocks or pad, 42- slurry check rings, 43- block pulp templates.
Specific embodiment
To enable the above objects, features and advantages of the present invention more obvious understandable, below in conjunction with the accompanying drawings to the present invention Specific embodiment be described in detail.It should be noted that, accompanying drawing of the present invention is in the form of simplification and using non-essence Accurate ratio, is only used to conveniently, lucidly aid in illustrating the purpose of the embodiment of the present invention.
The column that the present invention is provided and bent cap splicing structure, as shown in Fig. 1 to Fig. 5 c, for the spelling of column 10 and bent cap 20 Connect, the bottom of the column 10 is fixed on cushion cap 30, some reinforcing bars 11 are stretched out at the top of the column 10;In the bent cap 20 Pre-buried some metal bellows 21, the bottom of the metal bellows 21 flushes with the bottom surface of the bent cap 20;The metal wave The position of line pipe 21 is corresponding with the position of the reinforcing bar 11;Splicing seams 40 between the column 10 and the bent cap 20 are using high Strength mortar or epoxy piece splicing connect;Mud jacking passage 22, the every two ends of the metal bellows 21 are provided with the bent cap 20 It is connected with pulp inlet 23 and grout outlet 24 by the mud jacking passage 22 respectively.The present invention proposes a kind of and traditional pouring procedure Entirely different construction, can shorten construction period, and can reduce the influence to surrounding enviroment, and can preferably control to mix Solidifying soil casting quality, and the relatively low construction technology of cost, in all many-sides such as applicability, economy, crudy, construction period There is promotional value higher.
It is preferred that asking emphasis to refer to Fig. 3 and Fig. 4, the column 10 in the present invention can be using prefabrication also using cast-in-place Construction, the section of column 10 can be any form, depending on bar diameter ds is calculated according to design, typically according to design requirements Not less than 22mm, generally can be using 22mm, 25mm, 28mm, 32mm, 36mm, 40mm or more;Reinforcing bar 11 can using HRB500 and HRB400;The length that the reinforcing bar 11 stretches out the part of the column 10 is 20~50 times of the bar diameter ds, i.e., described The length that reinforcing bar 11 stretches out the part of the column 10 is 20ds~50ds.
It is preferred that the bent cap 20 in the present invention uses prefabrication, can be any form, the gold according to design needs The wall thickness for belonging to bellows 21 is 0.4~2mm, and rib 3.1~5mm high, embedded depth is 20~50 times of the diameter of the reinforcing bar 11, I.e. embedded depth is 50ds~20ds, and the big 20~40mm of diameter of the internal diameter reinforcing bar 11, i.e. internal diameter are that the reinforcing bar of column 10 is straight Footpath ds+20mm~40mm.
It is preferred that asking emphasis to refer to Fig. 4, slurry check ring 42 is equipped with the every reinforcing bar 11, the slurry check ring 42 is arranged In on the reinforcing bar 11, and fitted with the Mosaic face of the column 10, the diameter metal bellows of the slurry check ring 42 The 21 big 1cm of nozzle diameter, to prevent during to irrigating high-strength mortar in metal bellows 21, high-strength mortar flows out from the mouth of pipe.
It is preferred that in the present invention corresponding paver can be chosen, and choose correspondence by the height of required splicing seams 40 Rubber cushion blocks or pad 41, specifically, the height of splicing seams 40 between the column 10 and the bent cap 20 is 20~30mm, Rubber cushion blocks are respectively equipped with the top surface corner of the column 10, the section of the rubber cushion blocks is the pros of 100 × 100mm Shape, or other sizes and shape, the thickness of the rubber cushion blocks is 20~31mm, and the top edge of the column 10 is enclosed and set There is block pulp template 43, the laying high-strength mortar label should be higher than that 20 liang of the column 10 and bent cap in the block pulp template 43 It is more than one grade of person's label high level, paving slurry thickness is higher by more than the rubber cushion blocks 5mm.
It is preferred that the height of splicing seams 40 between the column 10 and the bent cap 20 is 2~5mm, the column 10 It is respectively equipped with pad at top surface corner, the section of the pad is the square of 100 × 100mm, or other sizes and shape Shape, the thickness of the pad is 2~5mm, and the top edge of the column 10 is enclosed and is provided with block pulp template 43, in the block pulp template The laying epoxy piece glue in 43, paving glue thickness is higher by more than the pad 2mm.
It is preferred that the bottom of the metal bellows 21 connects with the pulp inlet 23, the top of the metal bellows 21 Portion connects with the grout outlet 24, high-strength mortar is flowed from bottom to top using pressure, improves mud jacking intensity.
Please emphasis refer to Fig. 5 a to 5c, the construction method of column 10 and the splicing structure of bent cap 20 that the present invention is provided is included such as Lower step:
S1:The prefabricated column 10, as shown in Figure 5 a, and the pre-buried reinforcing bar 11 in the column 10, in the steel Slurry check ring 42 is installed on muscle 11;The prefabricated bent cap 20, and (the metal wave of the metal bellows 21 is reserved in the bent cap 20 Line pipe 21 inserts provisions for grouting), while setting the mud jacking passage 22 in the bent cap 20;Clean and measure the column 10 and institute State the Mosaic face of bent cap 20, it is ensured that the flatness of the top surface of column 10 and the bottom surface of bent cap 20;
S2:Preassembling, is directed at the duct of the metal bellows 21 reinforcing bar 11 and is inserted in, as shown in Figure 5 b, utilizes The perpendicularity and absolute altitude of rubber cushion blocks or pad 41 the regulation bent cap 20 on the column 10, specifically, using to the rubber The thickness of the regulating guarantee splicing seams 40 of rubber cushion block or pad 41 simultaneously adjusts the positional precision of bent cap 20, after the completion of regulation, lifting The bent cap 20, carries out the construction of splicing seams 40;
S3:The column 10 is laid using seat slurry processes (correspondence rubber cushion blocks) or epoxy piece gemel connection method (correspondence pad) With the splicing seams 40 between the bent cap 20, after the completion of paving slurry/paving glue, the bent cap 20 is dropped down onto the rubber cushion blocks that regulate or On pad 41, after the material at the splicing seams 40 reaches intensity requirement, the high-strength of M80 is not less than to the press-in of the pulp inlet 23 Mortar, until the pulp of the grout outlet 24, after all the mud jacking of metal bellows 21 terminates, assembling construction is completed.
Above-mentioned construction method is convenient and swift, substantially reduces construction period, and assembled process several hours can complete;Save Live bracket basis treatment and the operation of rack template is set up, overall economics are good;Work on the spot amount is reduced, is alleviated existing The labour intensity of field workman, it is ensured that the safety work of workmen.
In sum, the present invention is provided column and bent cap splicing structure, it is described for the splicing of column 10 and bent cap 20 The bottom of column 10 is fixed on cushion cap 30, and some reinforcing bars 11 are stretched out at the top of the column 10;If pre-buried in the bent cap 20 Dry metal bellows 21, the bottom of the metal bellows 21 flushes with the bottom surface of the bent cap 20;The metal bellows 21 Position it is corresponding with the position of the reinforcing bar 11;Splicing seams 40 between the column 10 and the bent cap 20 use high-strength mortar Or epoxy piece splicing connects;Mud jacking passage 22 is provided with the bent cap 20, the two ends of the every metal bellows 21 lead to respectively The mud jacking passage 22 is crossed to be connected with pulp inlet 23 and grout outlet 24.The present invention changes traditional bridge construction mode, and construction is existing Field, without template, substantially reduces the live duration without support, alleviates labor strength, reduces the requirement to construction site; Eliminate live bracket basis treatment and set up the operation of rack template, good economy performance;Reduce simultaneously and surrounding environment is born Face rings.
In addition, the splicing structure that the present invention is provided is applicable not only to prefabricated stand column 10 and is also applied for cast-in-place column 10.
Obviously, those skilled in the art can carry out various changes and modification without deviating from spirit of the invention to invention And scope.So, if these modifications of the invention and modification belong to the claims in the present invention and its equivalent technologies scope it Interior, then the present invention is also intended to including including these changes and modification.

Claims (9)

1. a kind of column and bent cap splicing structure, for the splicing of column (10) and bent cap (20), it is characterised in that the column (10) bottom is fixed on cushion cap (30), and some reinforcing bars (11) are stretched out at the top of the column (10);In the bent cap (20) Pre-buried some metal bellows (21), the bottom of the metal bellows (21) flushes with the bottom surface of the bent cap (20);It is described The position of metal bellows (21) is corresponding with the position of the reinforcing bar (11);Between the column (10) and the bent cap (20) Splicing seams (40) are connect using high-strength mortar or epoxy piece splicing;Mud jacking passage (22), every institute are provided with the bent cap (20) The two ends for stating metal bellows (21) are connected by the mud jacking passage (22) with pulp inlet (23) and grout outlet (24) respectively.
2. column as claimed in claim 1 and bent cap splicing structure, it is characterised in that the reinforcing bar (11) with diameter greater than etc. In 22mm.
3. column as claimed in claim 2 and bent cap splicing structure, it is characterised in that the reinforcing bar (11) it is a diameter of 22mm, 25mm, 28mm, 32mm, 36mm, 40mm or more.
4. column as claimed in claim 2 and bent cap splicing structure, it is characterised in that the reinforcing bar (11) stretches out the column (10) length of part is 20~50 times of the diameter of the reinforcing bar (11).
5. column as claimed in claim 1 and bent cap splicing structure, it is characterised in that the wall thickness of the metal bellows (21) It is 0.4~2mm, rib 3.1~5mm high, embedded depth is 20~50 times of the diameter of the reinforcing bar (11), the internal diameter reinforcing bar (11) the big 20~40mm of diameter.
6. column as claimed in claim 1 and bent cap splicing structure, it is characterised in that be equipped with the every reinforcing bar (11) Slurry check ring (42), the big 1cm of nozzle diameter of the diameter metal bellows (21) of the slurry check ring (42).
7. column as claimed in claim 1 and bent cap splicing structure, it is characterised in that the column (10) and the bent cap (20) splicing seams (40) between are highly 20~30mm, and rubber cushion blocks are respectively equipped with the top surface corner of the column (10), The section of the rubber cushion blocks is the square of 100 × 100mm, and the thickness of the rubber cushion blocks is 20~31mm, the column (10) top edge is enclosed and is provided with block pulp template (43), and the laying high-strength mortar in the block pulp template (43), paving slurry is thick Degree is higher by more than the rubber cushion blocks 5mm.
8. column as claimed in claim 1 and bent cap splicing structure, it is characterised in that the column (10) and the bent cap (20) splicing seams (40) between are highly 2~5mm, and pad, the pad are respectively equipped with the top surface corner of the column (10) The section of piece is the square of 100 × 100mm, and the thickness of the pad is 2~5mm, and the top edge of the column (10) is enclosed Block pulp template (43) is provided with, the laying epoxy piece glue in the block pulp template (43), paving glue thickness is higher by the pad More than 2mm.
9. column as claimed in claim 1 and bent cap splicing structure, it is characterised in that the bottom of the metal bellows (21) Connected with the pulp inlet (23), the top of the metal bellows (21) connects with the grout outlet (24).
CN201710082481.9A 2016-10-28 2017-02-16 A kind of column and bent cap splicing structure Pending CN106906747A (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN2016109705632 2016-10-28
CN201610970563 2016-10-28

Publications (1)

Publication Number Publication Date
CN106906747A true CN106906747A (en) 2017-06-30

Family

ID=59208415

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710082481.9A Pending CN106906747A (en) 2016-10-28 2017-02-16 A kind of column and bent cap splicing structure

Country Status (1)

Country Link
CN (1) CN106906747A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107338728A (en) * 2017-02-16 2017-11-10 上海市政工程设计研究总院(集团)有限公司 A kind of column and bent cap splicing structure
CN108103936A (en) * 2017-11-03 2018-06-01 上海公路桥梁(集团)有限公司 The method that prefabricated bent cap is installed on column
CN108677716A (en) * 2018-08-03 2018-10-19 同济大学 A kind of group's nail attachment device with corrugated sleeve
CN108824191A (en) * 2018-08-03 2018-11-16 同济大学 A kind of group with corrugated sleeve follows closely the construction technology of attachment device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100804125B1 (en) * 2007-02-28 2008-02-19 진성토건 주식회사 Connecting apparatus for precast concrete members, and fabricated bridge pier using the apparatus, and constructing method thereof
CN104018422A (en) * 2014-06-18 2014-09-03 上海市城市建设设计研究总院 Wet joint structure for prefabrication and splicing of joint part between bridge pier column and cover beam
CN105484157A (en) * 2015-11-19 2016-04-13 宁波交通工程建设集团有限公司 Positioning device and construction method of capping beam of prefabricated bridge
CN205576723U (en) * 2016-02-15 2016-09-14 上海应用技术学院 Adoption is excelled in prefabrication of fibre mortar and bellows joint and is assembled pier
CN206189279U (en) * 2016-10-28 2017-05-24 上海市政工程设计研究总院(集团)有限公司 Structure is assembled with bent cap to stand

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100804125B1 (en) * 2007-02-28 2008-02-19 진성토건 주식회사 Connecting apparatus for precast concrete members, and fabricated bridge pier using the apparatus, and constructing method thereof
CN104018422A (en) * 2014-06-18 2014-09-03 上海市城市建设设计研究总院 Wet joint structure for prefabrication and splicing of joint part between bridge pier column and cover beam
CN105484157A (en) * 2015-11-19 2016-04-13 宁波交通工程建设集团有限公司 Positioning device and construction method of capping beam of prefabricated bridge
CN205576723U (en) * 2016-02-15 2016-09-14 上海应用技术学院 Adoption is excelled in prefabrication of fibre mortar and bellows joint and is assembled pier
CN206189279U (en) * 2016-10-28 2017-05-24 上海市政工程设计研究总院(集团)有限公司 Structure is assembled with bent cap to stand

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
佚名: "预制拼装桥墩技术规程", 《HTTPS://WENKU.BAIDU.COM/VIEW/BAA8FE3289EB172DEC63B772.HTML?PN=51》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107338728A (en) * 2017-02-16 2017-11-10 上海市政工程设计研究总院(集团)有限公司 A kind of column and bent cap splicing structure
CN108103936A (en) * 2017-11-03 2018-06-01 上海公路桥梁(集团)有限公司 The method that prefabricated bent cap is installed on column
CN108677716A (en) * 2018-08-03 2018-10-19 同济大学 A kind of group's nail attachment device with corrugated sleeve
CN108824191A (en) * 2018-08-03 2018-11-16 同济大学 A kind of group with corrugated sleeve follows closely the construction technology of attachment device

Similar Documents

Publication Publication Date Title
CN106400692A (en) Construction method for stand column and cover beam assembled structure
CN106906747A (en) A kind of column and bent cap splicing structure
CN104963289B (en) A kind of abnormity pier stud mass concrete overall time pouring construction method
CN206189279U (en) Structure is assembled with bent cap to stand
CN103015719B (en) Integral casting process for reinforced concrete wastewater tank of pre-drilling engineering
CN101831875A (en) Precast assembly process of prestressed concrete cylindrical hollow pier
CN104674945A (en) Tree-shaped steel pipe column structure and construction method thereof
CN108638324A (en) A kind of construction method of prefabricated case beam
CN105350777A (en) Device and method for one-time pouring molding of ultra-high concrete column
CN105839985A (en) Hydropower station rectangular high tower hydraulic climb slip form system and construction method
CN110273359A (en) A kind of prefabricated bent cap and construction method of packaged type bridges
CN202000251U (en) Cylindrical hollow prefabricated prestressed concrete pier structure
CN106522104A (en) Construction method of curved-surface arc-shaped concrete tower
CN105926672A (en) Mined metro station steel pipe column construction method
CN203174510U (en) Movable assembly type hanging basket for bridge anti-collision guardrail construction and formwork for construction
CN110185268A (en) A kind of control method of pouring thickness of concrete floor and flatness
CN113202222A (en) Construction method for assembled type superposed beam slab
CN109750832A (en) A kind of construction method of constructional column concrete self-compaction
CN106245770A (en) Expanded letter variable cross-section annular stiff beam construction method
CN108590680A (en) A kind of construction method that launching shaft foundation pit vertical section pours
CN206245730U (en) A kind of cast-in-place pitched roof double template structure
CN104911999A (en) Construction method for deeply burying anchor
CN205296197U (en) Prefabricated cushion cap of anticorrosive industry factory building concrete rim of a cup formula
CN107338728A (en) A kind of column and bent cap splicing structure
CN106567328A (en) Half-prefabricated reinforced concrete wall-type guardrail construction process

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170630