CN108590680A - A kind of construction method that launching shaft foundation pit vertical section pours - Google Patents

A kind of construction method that launching shaft foundation pit vertical section pours Download PDF

Info

Publication number
CN108590680A
CN108590680A CN201810420487.7A CN201810420487A CN108590680A CN 108590680 A CN108590680 A CN 108590680A CN 201810420487 A CN201810420487 A CN 201810420487A CN 108590680 A CN108590680 A CN 108590680A
Authority
CN
China
Prior art keywords
pours
construction
side wall
foundation pit
bracing members
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810420487.7A
Other languages
Chinese (zh)
Inventor
蔡志勇
杨祥亮
郭玉海
张亮
薛春苗
李海峰
王涛
杨海健
王牧月
张晟源
陈雪峰
李星晨
吕金彪
张涛
王英波
苏世宗
石文正
王越
张建珍
李文新
庞梦月
姜宁宁
李丹丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Municipal Construction Co Ltd
Original Assignee
Beijing Municipal Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Construction Co Ltd filed Critical Beijing Municipal Construction Co Ltd
Priority to CN201810420487.7A priority Critical patent/CN108590680A/en
Publication of CN108590680A publication Critical patent/CN108590680A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of construction method that launching shaft foundation pit vertical section pours, the construction of this foundation pit structure is divided into vertical 7 times and constructs, and steps are as follows for Specific construction:The first step, bottom slab concreting;Second step, side wall pour;Third walks, and the 5th bracing members are removed and side wall pours;4th step, the 4th bracing members are removed and side wall pours;5th step, third road bracing members are removed and side wall pours;6th step, second bracing members are removed and side wall pours;7th step removes first of steel construction and completes structure construction;The present invention is poured in launching shaft foundation pit using vertical section, it ensure that the construction of shield launching well construction is smoothed out, the construction of this foundation pit structure is divided into vertical 7 times and constructs, be gradually completing to bottom plate, side wall pour and five bracing members are removed, and complete structure construction.

Description

A kind of construction method that launching shaft foundation pit vertical section pours
Technical field
The present invention relates to subway work technical fields, more specifically, it relates to which a kind of launching shaft foundation pit vertically divides The construction method that section pours.
Background technology
Shield launching is very important link in subway work, needs manually or mechanically to cut hole in originating well construction Door glass fiber bar stake cuts, portal poor flatness longer with clearance time, and the soil body caves in and soil erosion when originating Risk is higher, and the waste of portal plugging material is serious.
In previous tunneling shield engineering, launching shaft generally uses shield machine bracket to support shield machine barrel, leads to Crossing reaction frame offer thrust makes shield driving, the pre-buried ring flat-plate of portal, folding shape pressing plate and rubber curtain plate collectively constitute portal sealing Device prevents shield machine barrel from gushing sand into the gap water burst between cylinder and portal when hole, plays the effect of sealing.But due to portal Its own can bear limited pressure with sealing device, and in foundation pit compared with depth and the higher place of level of ground water, Water And Earth Pressures are very big, especially It is in the pouring construction of launching shaft foundation pit, and the easy presence of mode pours and dismantling operation can not be successfully for conventional pouring The problem of progress, influences the construction that foundation pit pours and is smoothed out.
Invention content
In view of the deficiencies of the prior art, the present invention intends to provide a kind of launching shaft foundation pit vertical section The construction method poured, to solve the problems mentioned in the above background technology.
To achieve the above object, the present invention provides the following technical solutions:
A kind of construction method that launching shaft foundation pit vertical section pours, this foundation pit structure construction be divided into vertical 7 times into Row construction, steps are as follows for Specific construction:
The first step, bottom slab concreting:It is that shield well southern side portal HL2 top marks are high to pour height, and setting-up of construction joint position is bottom Plate top 1.25m;
Second step, side wall pour:After the completion of bottom slab concreting, first step support system is set up, binds side wall reinforcing bar, formwork pours Concrete is built, height 1.2m is poured;
Third walks, and the 5th bracing members are removed and side wall pours:The 5th bracing members are removed, basal plane is handled, sets up second Support system is walked, side wall is bound and north and south side ring beam steel, formwork casting concrete pours height 3.59m;
4th step, the 4th bracing members are removed and side wall pours:The 4th bracing members are removed, basal plane is handled, sets up third Support system is walked, side wall is bound and north and south side ring camber portion reinforcing bar, formwork casting concrete pours height 5.76m;
5th step, third road bracing members are removed and side wall pours:Third road bracing members are removed, basal plane is handled, sets up the 4th Support system is walked, side wall reinforcing bar is bound, formwork casting concrete pours height 6.1m;
6th step, second bracing members are removed and side wall pours:Second bracing members are removed, basal plane is handled, sets up the 5th Support system is walked, side wall reinforcing bar is bound, formwork casting concrete pours height 6.1m;
7th step removes first of steel construction and completes structure construction:It removes first of bracing members, handles basal plane, set up the Six step support systems bind side wall reinforcing bar, and formwork casting concrete pours height 4.05m, completes construction.
Further, the first segment which pours is bottom plate and leads wall and pour, construction joint Reserved location 45cm above bottom plate, it is 1.25m, construction period 5d to pour height.
Further, the second segment which pours is south and north flanks ring beam and sleeper, thing Side wall pours, and for construction joint reserved location below the 5th bracing members at 1.35m, it is 1.2m to pour height, and construction period is 7d。
Further, the third section which pours is that south and north flanks sleeper and southern side portal are horizontal Beam, thing side wall pour, and for construction joint reserved location below the 4th bracing members at 1.76m, it is 3.59m to pour height, is applied The work period is 7d.
Further, pour the 4th section of the launching shaft foundation pit vertical section has poured for south and north flanks ring beam and HL3 At, construction joint reserved location below the third road bracing members at 0.9m, it is 5.76m, construction period 7d to pour height.
Further, pour the 5th section of the launching shaft foundation pit vertical section pours for side wall, construction joint reserved place It sets below the second bracing members at 1.4m, it is 6.1m, construction period 7d to pour height.
Further, pour the 6th section of the launching shaft foundation pit vertical section pours for side wall, construction joint reserved place It sets below first of bracing members at 3.3m, it is 6.1m, construction period 7d to pour height.
Further, pour the 7th section of the launching shaft foundation pit vertical section pours for remaining wall, pours height For 4.05m, construction period 6d.
In conclusion the present invention has the advantages that compared with prior art:
The present invention is poured in launching shaft foundation pit using vertical section, ensure that the construction of shield launching well construction is smooth It carries out, top bracing members can be removed reaching 85% or more for lower part concrete strength, in conjunction with the position of bracing members, and south, The construction of this foundation pit structure is divided into vertical 7 times and constructed by northern both sides hole ring beam position and lapped length of steel bar requirement, Be gradually completing to bottom plate, side wall pour and five bracing members are removed, and complete structure construction.
More clearly to illustrate the structure feature and effect of the present invention, come below in conjunction with the accompanying drawings to this hair with specific embodiment It is bright to be described in detail.
Description of the drawings
Fig. 1 is the structural schematic diagram that bottom plate of the present invention pours.
Fig. 2 is the structural schematic diagram that side wall pours in the present invention.
Fig. 3 is the structural schematic diagram that the 5th bracing members are removed in the present invention and side wall pours.
Fig. 4 is the structural schematic diagram that the 4th bracing members are removed in the present invention and side wall pours.
Fig. 5 is the structural schematic diagram that third road bracing members are removed in the present invention and side wall pours.
Fig. 6 is the structural schematic diagram that second bracing members are removed in the present invention and side wall pours.
Fig. 7 is the structural schematic diagram removed first of steel construction in the present invention and complete structure construction.
Specific implementation mode
The following further describes the technical solution of the present invention in the following with reference to the drawings and specific embodiments.
A kind of construction method that launching shaft foundation pit vertical section pours should be in launching shaft according to design principle Foundation pit reaches 85% or more for lower part concrete strength can remove top bracing members, in conjunction with the position of bracing members, He Nan, north two The construction of this foundation pit structure is divided into vertical 7 times and constructed, specifically by side hole ring beam position and lapped length of steel bar requirement Construction procedure is as follows:
The first step, bottom slab concreting:It is that shield well southern side portal HL2 top marks are high to pour height, and setting-up of construction joint position is bottom Plate top 1.25m;As shown in Figure 1.
Second step, side wall pour:After the completion of bottom slab concreting, first step support system is set up, binds side wall reinforcing bar, formwork pours Concrete is built, height 1.2m is poured;As shown in Figure 2.
Third walks, and the 5th bracing members are removed and side wall pours:The 5th bracing members are removed, basal plane is handled, sets up second Support system is walked, side wall is bound and north and south side ring beam steel, formwork casting concrete pours height 3.59m;As shown in Figure 3.
4th step, the 4th bracing members are removed and side wall pours:The 4th bracing members are removed, basal plane is handled, sets up third Support system is walked, side wall is bound and north and south side ring camber portion reinforcing bar, formwork casting concrete pours height 5.76m;Such as Fig. 4 institutes Show.
5th step, third road bracing members are removed and side wall pours:Third road bracing members are removed, basal plane is handled, sets up the 4th Support system is walked, side wall reinforcing bar is bound, formwork casting concrete pours height 6.1m;As shown in Figure 5.
6th step, second bracing members are removed and side wall pours:Second bracing members are removed, basal plane is handled, sets up the 5th Support system is walked, side wall reinforcing bar is bound, formwork casting concrete pours height 6.1m;As shown in Figure 6.
7th step removes first of steel construction and completes structure construction:It removes first of bracing members, handles basal plane, set up the Six step support systems bind side wall reinforcing bar, and formwork casting concrete pours height 4.05m, completes construction;As shown in Figure 7.
In conclusion the construction way figure that the launching shaft foundation pit vertical section of the present invention pours is as shown in the table:
The technical principle that the present invention is described above in association with specific embodiment, is only the preferred embodiment of the present invention.This The protection domain of invention is not limited merely to above-described embodiment, and all technical solutions belonged under thinking of the present invention belong to the present invention Protection domain.Those skilled in the art would not require any inventive effort the other specific realities that can associate the present invention Mode is applied, these modes are fallen within protection scope of the present invention.

Claims (8)

1. a kind of construction method that launching shaft foundation pit vertical section pours, which is characterized in that the construction of this foundation pit structure is divided into It constructs for vertical 7 times, steps are as follows for Specific construction:
The first step, bottom slab concreting:It is that shield well southern side portal HL2 top marks are high to pour height, and setting-up of construction joint position is on bottom plate Portion 1.25m;
Second step, side wall pour:After the completion of bottom slab concreting, first step support system is set up, binds side wall reinforcing bar, formwork pours mixed Solidifying soil, pours height 1.2m;
Third walks, and the 5th bracing members are removed and side wall pours:The 5th bracing members are removed, basal plane is handled, sets up second step branch Support body system, binds side wall and north and south side ring beam steel, formwork casting concrete pour height 3.59m;
4th step, the 4th bracing members are removed and side wall pours:The 4th bracing members are removed, basal plane is handled, set up third step branch Support body system, binds side wall and north and south side ring camber portion reinforcing bar, formwork casting concrete pour height 5.76m;
5th step, third road bracing members are removed and side wall pours:Third road bracing members are removed, basal plane is handled, sets up the 4th step branch Support body system, binds side wall reinforcing bar, and formwork casting concrete pours height 6.1m;
6th step, second bracing members are removed and side wall pours:Second bracing members are removed, basal plane is handled, sets up the 5th step branch Support body system, binds side wall reinforcing bar, and formwork casting concrete pours height 6.1m;
7th step removes first of steel construction and completes structure construction:First of bracing members is removed, basal plane is handled, sets up the 6th step Support system binds side wall reinforcing bar, and formwork casting concrete pours height 4.05m, completes construction.
2. the construction method that a kind of launching shaft foundation pit vertical section according to claim 1 pours, which is characterized in that The first segment that the launching shaft foundation pit vertical section pours is bottom plate and leads wall and pour, and construction joint reserved location is on bottom plate Square 45cm, it is 1.25m, construction period 5d to pour height.
3. the construction method that a kind of launching shaft foundation pit vertical section according to claim 1 pours, which is characterized in that The second segment that the launching shaft foundation pit vertical section pours is that south and north flanks ring beam and sleeper, thing side wall pour, and is constructed Reserved location places 1.35m below the 5th bracing members are stitched, pour height as 1.2m, construction period 7d.
4. the construction method that a kind of launching shaft foundation pit vertical section according to claim 1 pours, which is characterized in that The third section that the launching shaft foundation pit vertical section pours is that south and north flanks sleeper and southern side portal crossbeam, thing side wall pour It builds, for construction joint reserved location below the 4th bracing members at 1.76m, it is 3.59m, construction period 7d to pour height.
5. the construction method that a kind of launching shaft foundation pit vertical section according to claim 1 pours, which is characterized in that Pour the 4th section of the launching shaft foundation pit vertical section pours completions for south and north flanks ring beam and HL3, and construction joint is reserved Below the third road bracing members at 0.9m, it is 5.76m, construction period 7d to pour height for position.
6. the construction method that a kind of launching shaft foundation pit vertical section according to claim 1 pours, which is characterized in that Pour the 5th section of the launching shaft foundation pit vertical section pours for side wall, and construction joint reserved location is in second bracing members At the 1.4m of lower section, it is 6.1m, construction period 7d to pour height.
7. the construction method that a kind of launching shaft foundation pit vertical section according to claim 1 pours, which is characterized in that Pour the 6th section of the launching shaft foundation pit vertical section pours for side wall, and construction joint reserved location is in first of bracing members At the 3.3m of lower section, it is 6.1m, construction period 7d to pour height.
8. the construction method that a kind of launching shaft foundation pit vertical section according to claim 1 pours, which is characterized in that Pour the 7th section of the launching shaft foundation pit vertical section pours for remaining wall, and it is 4.05m, construction period to pour height For 6d.
CN201810420487.7A 2018-05-04 2018-05-04 A kind of construction method that launching shaft foundation pit vertical section pours Pending CN108590680A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810420487.7A CN108590680A (en) 2018-05-04 2018-05-04 A kind of construction method that launching shaft foundation pit vertical section pours

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810420487.7A CN108590680A (en) 2018-05-04 2018-05-04 A kind of construction method that launching shaft foundation pit vertical section pours

Publications (1)

Publication Number Publication Date
CN108590680A true CN108590680A (en) 2018-09-28

Family

ID=63619857

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810420487.7A Pending CN108590680A (en) 2018-05-04 2018-05-04 A kind of construction method that launching shaft foundation pit vertical section pours

Country Status (1)

Country Link
CN (1) CN108590680A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109162741A (en) * 2018-10-29 2019-01-08 中铁十二局集团有限公司 The method in shield crossing piston air duct and piston air duct superstructure synchronous construction
CN109403981A (en) * 2018-12-07 2019-03-01 石家庄铁源工程咨询有限公司 The construction technology of subway shield shaft main structure
CN110159309A (en) * 2019-05-27 2019-08-23 中国水利水电第八工程局有限公司 A kind of construction method using foam concrete backfill Tunneling by mining method
CN110820756A (en) * 2019-11-05 2020-02-21 中铁二十二局集团轨道工程有限公司 Shield well and vertical shaft deep foundation pit excavation safety construction method
CN110820752A (en) * 2019-11-05 2020-02-21 中铁二十二局集团轨道工程有限公司 Bottom plate steel bar system and shield well foundation pit main structure construction method comprising same

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103334778A (en) * 2012-12-21 2013-10-02 中交一公局第三工程有限公司 Construction technology of step temporary support and partial double side walls
CN103615252A (en) * 2013-11-25 2014-03-05 中铁十八局集团有限公司 Construction process of subway shield shaft single-layer main body structure
CN103628503A (en) * 2013-11-27 2014-03-12 中铁第四勘察设计院集团有限公司 Construction method for using underground second-layer station enclosure to make underground third-layer transfer joint
CN104632227A (en) * 2014-12-22 2015-05-20 中铁十九局集团轨道交通工程有限公司 Subway station excavation technology of single-layer beam arch structure
CN104747191A (en) * 2015-02-05 2015-07-01 山东华新建筑工程集团有限责任公司 Construction method for connecting structure of shaft and shaft station
CN107476337A (en) * 2017-08-21 2017-12-15 中铁六局集团有限公司 The prefabricated side wall assembling and construction method in open cut subway assembled station
CN107664035A (en) * 2017-10-20 2018-02-06 中国建筑第八工程局有限公司 The construction method of well after shield piping lane elder generation shield

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103334778A (en) * 2012-12-21 2013-10-02 中交一公局第三工程有限公司 Construction technology of step temporary support and partial double side walls
CN103615252A (en) * 2013-11-25 2014-03-05 中铁十八局集团有限公司 Construction process of subway shield shaft single-layer main body structure
CN103628503A (en) * 2013-11-27 2014-03-12 中铁第四勘察设计院集团有限公司 Construction method for using underground second-layer station enclosure to make underground third-layer transfer joint
CN104632227A (en) * 2014-12-22 2015-05-20 中铁十九局集团轨道交通工程有限公司 Subway station excavation technology of single-layer beam arch structure
CN104747191A (en) * 2015-02-05 2015-07-01 山东华新建筑工程集团有限责任公司 Construction method for connecting structure of shaft and shaft station
CN107476337A (en) * 2017-08-21 2017-12-15 中铁六局集团有限公司 The prefabricated side wall assembling and construction method in open cut subway assembled station
CN107664035A (en) * 2017-10-20 2018-02-06 中国建筑第八工程局有限公司 The construction method of well after shield piping lane elder generation shield

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109162741A (en) * 2018-10-29 2019-01-08 中铁十二局集团有限公司 The method in shield crossing piston air duct and piston air duct superstructure synchronous construction
CN109403981A (en) * 2018-12-07 2019-03-01 石家庄铁源工程咨询有限公司 The construction technology of subway shield shaft main structure
CN110159309A (en) * 2019-05-27 2019-08-23 中国水利水电第八工程局有限公司 A kind of construction method using foam concrete backfill Tunneling by mining method
CN110159309B (en) * 2019-05-27 2021-03-23 中国水利水电第八工程局有限公司 Construction method for backfilling mine method tunnel with foam concrete
CN110820756A (en) * 2019-11-05 2020-02-21 中铁二十二局集团轨道工程有限公司 Shield well and vertical shaft deep foundation pit excavation safety construction method
CN110820752A (en) * 2019-11-05 2020-02-21 中铁二十二局集团轨道工程有限公司 Bottom plate steel bar system and shield well foundation pit main structure construction method comprising same

Similar Documents

Publication Publication Date Title
CN108590680A (en) A kind of construction method that launching shaft foundation pit vertical section pours
CN106223360B (en) Using the open cut cast in place and precast construction subway station construction method of stake supporting system
CN106869172A (en) In-situ deposited prefabricated split-mounting type subway underground station construction method
CN106320377B (en) A kind of rich water soft clay area deep basal pit covered back-digging construction method
CN205742213U (en) Foundation pit supporting construction
CN107201910A (en) For shaking traffic tunnel fracture plugging and reinforcement means under bumpy weather
CN103696784B (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN1714227A (en) Structure of intermediate wall of three arch excavated tunnel and method for constructing the same
CN105951612B (en) Stake head bug repairing and reinforcement structure and its construction method under active service bridge water
CN103726503B (en) Anchor rod pile reinforcing bearing platform structure used for reinforcing deformed bridge pile and construction method thereof
CN103835217A (en) Method for prevention and treatment on damage and depression of pavement around inspection well
CN105089670B (en) Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel
CN203948108U (en) A kind of concreting moulding form of the tunnel with withe and dividing plate
CN206408655U (en) The top plate sidewall structure of covered back-digging construction
CN201943086U (en) Underground building wall body
CN208933989U (en) A kind of tower-crane foundation structure
CN1563612A (en) Construction method for underground structure through half reverse course of action of inverting connection
CN108396761A (en) The non-fully pile foundation cushion cap and production method under precipitation state inside a kind of foundation pit
CN103882883B (en) Tower crane and garage frame post share a foundation construction method
CN105862912B (en) A kind of agent on crack resistance of concrete sliding pile panelling construction method
CN208072390U (en) A kind of connection structure of the stake of bridge support and underwater binder
CN106948350B (en) The rapid constructing method of deep basal pit accessory structure
CN206071096U (en) The underpinning device of load bearing wall in brick mix structure
CN209144877U (en) A kind of basement post-pouring zone water sealing structure of easy disassembly
CN208184739U (en) A kind of launching shaft foundation pit structure of subway work

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180928

RJ01 Rejection of invention patent application after publication