CN109235187A - A kind of porous pavement method for paving being easy to construct and have landscape effect - Google Patents
A kind of porous pavement method for paving being easy to construct and have landscape effect Download PDFInfo
- Publication number
- CN109235187A CN109235187A CN201811136187.2A CN201811136187A CN109235187A CN 109235187 A CN109235187 A CN 109235187A CN 201811136187 A CN201811136187 A CN 201811136187A CN 109235187 A CN109235187 A CN 109235187A
- Authority
- CN
- China
- Prior art keywords
- construct
- layer
- easy
- paving
- laid
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C15/00—Pavings specially adapted for footpaths, sidewalks or cycle tracks
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C5/00—Pavings made of prefabricated single units
- E01C5/04—Pavings made of prefabricated single units made of bricks
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
The present invention relates to pervious surface technical fields, and disclose a kind of porous pavement method for paving for being easy to construct and have landscape effect, including pervious bed and stone layer, the pervious bed includes coarse sands layer, pervious concrete base and permeable screed-coat, it is described to be easy to construct and have the porous pavement method for paving of landscape effect the following steps are included: 1) roadbed to be compacted to ground to be onstructed tamping machine or road roller, original subgrade layer is formed, one layer of coarse sand is laid in dirt road base;2) mat formation since the edge for the dirt road base for laying coarse sand, mated formation with equidistant in corresponding position with masonry, water-permeable brick or engineering leftover pieces, constitute the pavement of one or more transverse and longitudinal intersection;3) it is laid with pervious concrete base on laying work area, re-lays permeable screed-coat, one layer of miscellaneous bed of material of rubble is laid on permeable screed-coat.This is easy to construct and the porous pavement method for paving with landscape effect, is easy to construct, and can take into account functional and landscape.
Description
Technical field
The present invention relates to pervious surface technical field, specially a kind of porous pavement for being easy to construct and have landscape effect
Method for paving.
Background technique
It is traditional it is non-permeable mat formation put undue emphasis on the waterproof, seepage control performance of hardened ground, such ground pavement is by natural drop
For rain completely with its underpart soil layer and underground water blocking, rainfall have to be discharged into the earth's surfaces such as rivers,lakes and seas by sewerage system pipe network
In water source, this results in Urban Underground water level and is difficult to timely be supplemented, and the effective use of rainwater is seriously affected, in addition, not
Permeable pavement rainy day surface area water, " drift is slided ", " splashing " and " dazzle " phenomenon that when autos only generates also will increase city
The security risk of traffic.
According to a kind of porous brickwalk laying method of 1644799 B of Chinese patent CN, water-permeable and air permeable performance is good, rain when raining
Water energy permeates the ground in time, is conducive to the rise of Urban Underground water level, and the aqueous vapor of fine day underground can be by the road surface of laying to sky
It is distributed in gas, is adjustable the humidity of urban air, be conducive to the improvement of ecological environment, pervious concrete pavement has permeable
Property, the seeping phenomenon on road and square can be comparatively fast eliminated when rainy, prevent river inundation and water pollution, but be laid with now
Ecological permeable ground often only focuses in terms of the water permeability on ground, is not concerned with the landscape effect of laying, mostly uses slabstone
Modes, the corny such as road and laying water-permeable brick also do not have aesthetic feeling, and landscape effect is poor.
Summary of the invention
(1) the technical issues of solving
In view of the deficiencies of the prior art, the present invention provides a kind of porous pavement pavings for being easy to construct and have landscape effect
Dress method has and is easy to construct, and the advantages that can take into account functional and landscape, solves the water permeability only focused in ground
Aspect is not concerned with the landscape effect of laying, does not have aesthetic feeling, the poor problem of landscape effect.
(2) technical solution
To achieve the above object, the present invention provides a kind of porous pavement sides of mating formation for being easy to construct and with landscape effect
Method, including pervious bed and the miscellaneous bed of material of rubble, the pervious bed include coarse sands layer, pervious concrete base and permeable screed-coat, institute
State be easy to construct and with landscape effect porous pavement method for paving the following steps are included:
1) roadbed is compacted by ground to be onstructed tamping machine or road roller, original subgrade layer is formed, in dirt road base
One layer of coarse sand is laid on layer.
2) mat formation since the edge for the dirt road base for laying coarse sand, with masonry, water-permeable brick or engineering leftover pieces with
It is equidistant to mat formation in corresponding position, constitute the pavement of one or more transverse and longitudinal intersection.
3) it is laid with one layer of pervious concrete base on laying work area, cement and fine sand is mixed, a small amount of water is added, paving
It is located in pervious concrete base, forms permeable screed-coat, the region on permeable screed-coat and except being located at pavement
It is laid with one layer of miscellaneous bed of material of rubble, compacting of spraying water after being bulldozed on the miscellaneous material of rubble.
4) landscape object part or addition are laid with according to the theme of laying, on the miscellaneous material of rubble in laying work area has mark beauty
The article of change.
Preferably, the shape of water-permeable brick is rectangle, and the length of the water-permeable brick is not less than one meter, and the width of water-permeable brick is not
Less than 50 centimetres, the masonry includes wooden footway, marble or Concrete brick.
Preferably, the miscellaneous material of rubble includes gravel, cobble, gravel or bark, and the laying depth of the miscellaneous material of rubble is in 100-
Between 200 millimeters.
Preferably, for the laying depth of permeable screed-coat between 30-50 millimeters, the clay content of the coarse sand is percent
Five.
Preferably, when being laid with masonry or water-permeable brick, it can be made to constitute the pavement of one or more transverse and longitudinal intersection.
(3) beneficial effect
Compared with prior art, the present invention provides a kind of porous pavement sides of mating formation for being easy to construct and with landscape effect
Method, have it is following the utility model has the advantages that
This is easy to construct and the porous pavement method for paving with landscape effect, by with masonry, water-permeable brick or engineering side
Corner material is mated formation with equidistant in corresponding position, it can be made to constitute the pavement of one or more transverse and longitudinal intersection, can basis
Place flexible shapes are laid with, it is not necessary to fixed shape and lines are limited to, by being laid on the miscellaneous material of rubble in laying work area
Landscape object or addition have the article of mark beautification, can arbitrarily remove to landscape object after use, without to ground
It is destroyed and is repaired, play the role of being easy to construct and conveniently beautify road, due to being laid with one on laying work area
Cement and fine sand are mixed and a small amount of water are added, be laid in pervious concrete base, formed permeable by layer pervious concrete base
Screed-coat considerably increases the ecological function such as water-permeable and air permeable, is easy to construct to reach, and can take into account functional and scape
The purpose for the property seen.
Detailed description of the invention
Fig. 1 is the permeable ground structure schematic diagram based on landscape effect;
Wherein, 1 coarse sands layer, 2 pervious concrete bases, 3 permeable screed-coats, the miscellaneous bed of material of 4 rubbles, 5 masonries.
Specific embodiment
Below in conjunction with the embodiment of the present invention, technical solution in the embodiment of the present invention is clearly and completely retouched
It states, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Based on the present invention
In embodiment, every other implementation obtained by those of ordinary skill in the art without making creative efforts
Example, shall fall within the protection scope of the present invention.
A kind of porous pavement method for paving being easy to construct and have landscape effect, including pervious bed and stone layer, it is described
Pervious bed includes coarse sands layer, pervious concrete base and permeable screed-coat, described to be easy to construct and permeable with landscape effect
Paving method the following steps are included:
1) roadbed is compacted by ground to be onstructed tamping machine or road roller, original subgrade layer is formed, in dirt road base
One layer of coarse sand is laid on layer.
2) mat formation since the edge for the dirt road base for laying coarse sand, with masonry, water-permeable brick or engineering leftover pieces with
Equidistant to mat formation in corresponding position, the shape of water-permeable brick is rectangle, and the length of the water-permeable brick is permeable not less than one meter
The width of brick is not less than 50 centimetres, and the masonry includes wooden footway, marble or Concrete brick, it is described be laid with masonry or
When water-permeable brick, it can be made to constitute the pavement of one or more transverse and longitudinal intersection.
3) it is laid with one layer of pervious concrete base on laying work area, cement and fine sand is mixed, a small amount of water is added, paving
Be located in pervious concrete base, form permeable screed-coat, the laying depth of the permeable screed-coat between 30-50 millimeters,
The clay content of the coarse sand is 5 percent, and one layer of region laying on permeable screed-coat and except being located at pavement is broken
The miscellaneous material of stone, compacting of spraying water after being bulldozed on the miscellaneous material of rubble, the miscellaneous material of rubble includes gravel, cobble, gravel or bark, described broken
The laying depth of the miscellaneous material of stone is between 100-200 millimeters.
4) landscape object part or addition are laid with according to the theme of laying, on the miscellaneous material of rubble in laying work area has mark beauty
The article of change.
The present invention has following technical characterstic:
1) resource is rationally utilized
Raw material sources involved in the present invention are extensive, and type is more, mat formation using engineering leftover pieces, reasonable disposition
Resource, can be improved the effect of water penetration with water-permeable brick etc..
2) save the cost
Compared to using the special ecological floor laying material such as water-permeable brick, based on utilizing works leftover pieces and the miscellaneous material of rubble
It wants material cost lower, and is laid with and does not need large-scale instrument, cost can be further saved.
3) flexibility is big
The present invention is not influenced by place shape size is laid with, and can lay out irregular outer boundary, can also be according to laying
Place theme, which flexibly changes, is laid with shape, and practicability is stronger, can facilitate and replace to landscape object.
4) functional, landscape and ecological is taken into account
Compared to conventional ground laying method, flooring mode proposed by the present invention is novel, and structure is changeable, greatly strengthens scape
Effect is seen, while the masonry being laid with is assumed responsibility for current function, mated formation using the miscellaneous material of rubble, enhanced for visitor's walking
The water permeability on ground, ensure that mat formation it is ecological.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with
A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding
And modification, the scope of the present invention is defined by the appended.
Claims (5)
1. a kind of porous pavement method for paving for being easy to construct and have landscape effect, including pervious bed and stone layer, described
Water layer includes coarse sands layer, pervious concrete base and permeable screed-coat, it is characterised in that: described to be easy to construct and have landscape effect
The porous pavement method for paving of fruit the following steps are included:
1) roadbed is compacted by ground to be onstructed tamping machine or road roller, original subgrade layer is formed, in dirt road base
It is laid with one layer of coarse sands layer;
2) mat formation since the edge for the dirt road base for laying coarse sand, with masonry, water-permeable brick or engineering leftover pieces with equidistant
Mat formation from corresponding position, constitutes the pavement of one or more transverse and longitudinal intersection;
3) it is laid with one layer of pervious concrete base on laying work area, cement and fine sand is mixed, a small amount of water is added, be laid on
In pervious concrete base, permeable screed-coat is formed, the region on permeable screed-coat and except being located at pavement is laid with
One layer of miscellaneous bed of material of rubble, compacting of spraying water after being bulldozed on the miscellaneous material of rubble;
4) landscape object part or addition are laid with according to the theme of laying, on the miscellaneous material of rubble in laying work area has mark beautification
Article.
2. a kind of porous pavement method for paving for being easy to construct and have landscape effect according to claim 1, feature
It is, the shape of the water-permeable brick is rectangle, and the length of the water-permeable brick is not less than one meter, and the width of water-permeable brick is not less than five
Ten centimetres, the masonry includes wooden footway, marble or Concrete brick.
3. a kind of porous pavement method for paving for being easy to construct and have landscape effect according to claim 1, feature
It is, the miscellaneous material of rubble includes gravel, cobble, gravel or bark, and the laying depth of the miscellaneous material of rubble is at 100-200 millimeters
Between.
4. a kind of porous pavement method for paving for being easy to construct and have landscape effect according to claim 1, feature
It is, for the laying depth of the permeable screed-coat between 30-50 millimeters, the clay content of the coarse sand is 5 percent.
5. a kind of porous pavement method for paving for being easy to construct and have landscape effect according to claim 1, feature
It is, it is described when being laid with masonry or water-permeable brick, it can be made to constitute the pavement of one or more transverse and longitudinal intersection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811136187.2A CN109235187A (en) | 2018-09-28 | 2018-09-28 | A kind of porous pavement method for paving being easy to construct and have landscape effect |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811136187.2A CN109235187A (en) | 2018-09-28 | 2018-09-28 | A kind of porous pavement method for paving being easy to construct and have landscape effect |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109235187A true CN109235187A (en) | 2019-01-18 |
Family
ID=65057798
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811136187.2A Pending CN109235187A (en) | 2018-09-28 | 2018-09-28 | A kind of porous pavement method for paving being easy to construct and have landscape effect |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109235187A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113605172A (en) * | 2021-08-02 | 2021-11-05 | 河南中交路通工程监理咨询有限公司 | Permeable pavement and construction method thereof |
CN113718579A (en) * | 2021-07-30 | 2021-11-30 | 中铁十九局集团有限公司 | Environment-friendly ground construction method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103669145A (en) * | 2013-12-31 | 2014-03-26 | 北京东方园林股份有限公司 | Pavement method of permeable pavement structure |
CN103696343A (en) * | 2013-12-31 | 2014-04-02 | 北京东方园林股份有限公司 | Seepy floor pavement method based on landscape effect |
CN105544338A (en) * | 2016-01-28 | 2016-05-04 | 绵阳靓固科技有限公司 | Colored water permeable integral pavement and construction technology |
CN207062672U (en) * | 2017-08-24 | 2018-03-02 | 胡云友 | A kind of permeable pavement structure |
-
2018
- 2018-09-28 CN CN201811136187.2A patent/CN109235187A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103669145A (en) * | 2013-12-31 | 2014-03-26 | 北京东方园林股份有限公司 | Pavement method of permeable pavement structure |
CN103696343A (en) * | 2013-12-31 | 2014-04-02 | 北京东方园林股份有限公司 | Seepy floor pavement method based on landscape effect |
CN105544338A (en) * | 2016-01-28 | 2016-05-04 | 绵阳靓固科技有限公司 | Colored water permeable integral pavement and construction technology |
CN207062672U (en) * | 2017-08-24 | 2018-03-02 | 胡云友 | A kind of permeable pavement structure |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113718579A (en) * | 2021-07-30 | 2021-11-30 | 中铁十九局集团有限公司 | Environment-friendly ground construction method |
CN113605172A (en) * | 2021-08-02 | 2021-11-05 | 河南中交路通工程监理咨询有限公司 | Permeable pavement and construction method thereof |
CN113605172B (en) * | 2021-08-02 | 2022-12-02 | 河南中交路通工程监理咨询有限公司 | Permeable pavement |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103669145B (en) | A kind of paving method of permeable pavement structure | |
CN204875416U (en) | Porous pavement structure | |
CN205420946U (en) | Novel ecology that prevents surface gathered water road structure of permeating water | |
CN203295913U (en) | Novel ecological permeable road structure | |
CN105887609A (en) | Method for constructing ecological infiltration pavement in sponge city | |
CN105735082A (en) | Water-permeable planting formwork frame and multifunctional water-permeable pavement structure system and pavement method thereof | |
CN102337714B (en) | Ecological environmental-friendly economical and durable pavement combination panel design and assembly technologies | |
CN103669167B (en) | A kind of permeable pavement structure | |
CN205711609U (en) | Framed and the multi-functional porous pavement structural system of permeable plantation | |
CN107237386A (en) | A kind of terrace pavement system of ecological luminous stone | |
CN207362616U (en) | Permeable brick paving structure | |
CN109235187A (en) | A kind of porous pavement method for paving being easy to construct and have landscape effect | |
CN107794822B (en) | Permeable pavement based on sponge city idea | |
CN202500072U (en) | Permeable pavement structure | |
CN105484125B (en) | A kind of step of Collection utilization rainwater | |
CN106801371A (en) | High-bearing capacity permeable ground structure and laying method | |
CN208362838U (en) | A kind of porous pavement | |
CN105803888A (en) | Sponge type road paving structure | |
CN207862717U (en) | Porous pavement with pervious concrete column | |
CN203890824U (en) | Recycled aggregate based total pervious concrete pavement structure | |
CN206090204U (en) | Height ecological road surface structure of permeating water | |
CN204982588U (en) | Basic unit on square, parking area and garden way structure of mating formation | |
CN204509940U (en) | A kind of sidewalk drainage pavement | |
CN208486146U (en) | A kind of novel filter infiltration garden road step and sunk type square laying structure | |
CN207047996U (en) | A kind of terrace pavement system of ecological luminous stone |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information |
Address after: 430000 Donghu Development Zone, Wuhan City, Hubei Province, 77 Guanggu Avenue, Financial Port Backstage Service Center Phase I, Building A3, 13 Floors Applicant after: Wuhan Huatian Garden Group Co., Ltd Address before: 430000 Donghu Development Zone, Wuhan City, Hubei Province, 77 Guanggu Avenue, Financial Port Backstage Service Center Phase I, Building A3, 13 Floors Applicant before: WUHAN CHINESESKY LANDSCAPE ART Co.,Ltd. |
|
CB02 | Change of applicant information | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190118 |
|
RJ01 | Rejection of invention patent application after publication |