CN109163877A - The large scale field test simulator of sub-bottom changes piping dangerous situation - Google Patents
The large scale field test simulator of sub-bottom changes piping dangerous situation Download PDFInfo
- Publication number
- CN109163877A CN109163877A CN201810761341.9A CN201810761341A CN109163877A CN 109163877 A CN109163877 A CN 109163877A CN 201810761341 A CN201810761341 A CN 201810761341A CN 109163877 A CN109163877 A CN 109163877A
- Authority
- CN
- China
- Prior art keywords
- dangerous situation
- sub
- large scale
- main pipeline
- field test
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01M—TESTING STATIC OR DYNAMIC BALANCE OF MACHINES OR STRUCTURES; TESTING OF STRUCTURES OR APPARATUS, NOT OTHERWISE PROVIDED FOR
- G01M10/00—Hydrodynamic testing; Arrangements in or on ship-testing tanks or water tunnels
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01N—INVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
- G01N33/00—Investigating or analysing materials by specific methods not covered by groups G01N1/00 - G01N31/00
- G01N33/24—Earth materials
Landscapes
- Physics & Mathematics (AREA)
- Life Sciences & Earth Sciences (AREA)
- Health & Medical Sciences (AREA)
- Engineering & Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Chemical & Material Sciences (AREA)
- Food Science & Technology (AREA)
- Remote Sensing (AREA)
- Geology (AREA)
- Medicinal Chemistry (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Analytical Chemistry (AREA)
- Biochemistry (AREA)
- General Health & Medical Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- Immunology (AREA)
- Pathology (AREA)
- Fluid Mechanics (AREA)
- Revetment (AREA)
Abstract
The large scale field test simulator of sub-bottom changes piping dangerous situation, it is arranged on dykes and dams, it is characterized in for dykes and dams being divided into water blocking part and dangerous situation analog portion, with the separation of L shape armored concrete board wall between water blocking part and dangerous situation analog portion, the piping dangerous situation of simulation is located in board wall;Pressure tank is equipped at the top of dykes and dams, the pressure tank lower part is equipped with main pipeline, the main pipeline soil body that dangerous situation position occurs is extended to along L shape armored concrete board wall in the following, and in the end of the main pipeline, several branch pipes are set, the branch pipe is equipped with aperture, constitutes aperture floral tube;Flat water tank is equipped in dike dam back;The flat water tank is equipped with outlet pipe and is connected to the main pipeline;The main pipeline is equipped with control valve.Scene large scale of the invention simulates piping dangerous situation, and effect is true to nature;Water blocking position and dangerous situation happening part separate, dam configuration safety;Dangerous situation time of origin is controllable;Practicality is strong;Dangerous situation rehearsal section restorability is good, and rehearsal can be repeated several times.
Description
Technical field
The present invention relates to a kind of large scale field test simulator of sub-bottom changes piping dangerous situation, belong to hydraulic engineering and
It prevents and reduces natural disasters technical field, realizes the large scale field test of sub-bottom changes piping dangerous situation, can be used for sub-bottom changes piping machine
Large scale experiment research is managed, and carries out combat exercise for emergency flood fighting professional contingent and is used.
Background technique
China is vast in territory, and rivers and lakes are numerous, and bloods and droughts is frequent.In recent years, the Yangtze river basin, Pearl River Delta, Taihu Lake
Over-level flood all has occurred in basin, Second Songhua River Basin and Haihe basin including northeast in succession, and there is 2/3 territory face in the whole nation
Product and 1/2 population are threatened by flood to some extent, and flood-fighting, to prevent and reduce natural disasters be relationship people's life's wealth always
Produce the major issue of safety and national stability.
Built 24.4 ten thousand kilometers of the above river dike of Pyatyi of China, reservoir dam 9.8 ten thousand, wherein 95% the above are soil
Masonry dam.Dykes and dams are the barriers for resisting flood, but the dangerous situations such as dam leakage, piping happen occasionally, if rescuing and protecting not in time, will be led
It causes dykes and dams to burst, causes great life and property loss and ecological environment disaster.According to statistics, in native bank of stone dam dam break event, piping
The main reason for dam break ratio is up to 29%, is native bank of stone dam dam break.
Currently, the research of sub-bottom changes piping mechanism test carries out in laboratory mostly, scale is small, head is low, test knot
Fruit does not often meet engineering practice, cannot really reflect sub-bottom changes piping mechanism.Therefore, research and development can realistic simulation soil property dike
The Large scale experiment device of dam piping dangerous situation, it is horizontal to sub-bottom changes piping mechanism study is obviously improved, and effectively improve anti-
Flood emergency personnel all has significance to the identification of piping dangerous situation and the ability of rescuing and protecting.
Summary of the invention
The object of the present invention is to provide a kind of large scale field test simulator of sub-bottom changes piping dangerous situation, the devices
It is capable of the piping dangerous situation of large scale realistic simulation sub-bottom changes at the scene, dangerous situation should safely, controllably.Team member speedily carry out rescue work in training of speedily carrying out rescue work
When can accomplish submersible, emergency flood fighting personnel's warfighting capabilities can be effectively improved, may be repeated the rehearsal of piping dangerous situation.
The technical solution for completing foregoing invention task is as follows: a kind of large scale field test mould of sub-bottom changes piping dangerous situation
Quasi- device, is arranged on dykes and dams (also referred to as water blocking dykes and dams), which is characterized in that dykes and dams are divided into water blocking part and dangerous situation simulation part
Point, with L shape armored concrete board wall (abbreviation L shape board wall) separation, mould between the water blocking part and dangerous situation analog portion
Quasi- piping dangerous situation is located at L shape armoured concrete slab within the walls;Pressure tank, the pressure tank lower part are equipped at the top of dykes and dams
Equipped with main pipeline, which extends to the soil body that dangerous situation position occurs in the following, and at this along L shape armored concrete board wall
Several branch pipes are arranged in the end of main pipeline, and the branch pipe is equipped with aperture, constitute floral tube;Par is equipped in dike dam back
Case;The flat water tank is equipped with outlet pipe and is connected to the main pipeline;The main pipeline is equipped with control valve.
In other words, structure of the invention design is: the large scale field test simulator of sub-bottom changes piping dangerous situation is shown in
Attached drawing, by water blocking dykes and dams, L shape armored concrete board wall, pressure tank, flat water tank, supervisor, floral tube, control valve group at.
Water blocking dykes and dams are sub-bottom changes, are filled by code requirement;Sub-bottom changes are divided into two by L shape armored concrete board wall
Part is water blocking part before wall, stablizes safety and meets code requirement, is dangerous situation analog portion after wall;Pressure tank is set to dike
On top, water pump is inside set;Flat water tank is placed by wall;Control valve is manual and electric double-purpose butterfly valve;Predominant tube diameter 10cm;Aperture floral tube diameter
5cm。
Key technology content
(1) testing ground sets the pond of soil property water blocking dykes and dams formation, and dykes and dams height is not less than 3m, and the depth of water is not less than 2.5m;
(2) it is the safety for guaranteeing sub-bottom changes, dykes and dams is divided into water blocking part and dangerous situation analog portion, therebetween with " L " board wall point
Every the piping dangerous situation of simulation is located in board wall;
(3) to make the control of piping dangerous situation time of origin within 15 minutes, aperture floral tube top thickness of earth covering is less than 40cm, the soil body
Infiltration coefficient require be greater than 10-3cm/s;
(4) it is the time improved head difference, shorten the generation of piping dangerous situation, pressure tank is set on dykes and dams, and tank height is big
In 1m;
(5) to form piping group, there is position in piping and arrange more floral tubes, aperture floral tube diameter 5cm, aperture 1cm, spacing
5cm, floral tube end set plug;
(6) to ensure that piping dangerous situation occurs and effect is true to nature, the aperture floral tube top earthing powder low using impermeabilisation deformability
The earth materials such as soil, Extra-fine sand;
(7) it can be carried out band water for the team member that makes to speedily carry out rescue work to speedily carry out rescue work training, enhance practicality, during speedily carrying out rescue work, piping dangerous situation is always existed,
Dangerous situation disappears after the completion of speedily carrying out rescue work, success of rescuing and protecting;
(8) after training, all control valves are closed, remove equipment of speedily carrying out rescue work, restore to destroy the soil body, in case next time trains.
The utility model has the advantages that the large scale field test simulator of sub-bottom changes piping dangerous situation of the invention has following spy
Point:
(1) live large scale simulates piping dangerous situation, and effect is true to nature;
(2) piping dangerous situation is arranged on the sub-bottom changes of practical water blocking, and water blocking position and dangerous situation happening part separate, dykes and dams knot
Structure safety;
(3) dangerous situation time of origin is controllable;
(4) team member that speedily carries out rescue work can be carried out band water and speedily carry out rescue work training with large-scale synthesis rehearsal, and practicality is strong;
(5) dangerous situation rehearsal section restorability is good, and rehearsal can be repeated several times.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the invention patent model.
Fig. 2 is the plan view of the invention patent model.
Specific embodiment
Embodiment 1, the large scale field test simulator of sub-bottom changes piping dangerous situation, referring to Fig.1, Fig. 2: by dykes and dams 1
It is divided into water blocking part and dangerous situation analog portion, with L shape armoured concrete slab between the water blocking part and dangerous situation analog portion
Wall 5 separates, and the piping dangerous situation of simulation is located in L shape armored concrete board wall 5;It is equipped with pressure tank 2 at the top of dykes and dams, it should
2 lower part of pressure tank is equipped with main pipeline 3, which extends to along L shape armored concrete board wall occurs dangerous situation position
The soil body 8 in the following, and in the end of the main pipeline 3, several branch pipes are set, the branch pipe is equipped with aperture, constitutes aperture floral tube 7;?
Dike dam back is equipped with flat water tank 4;The flat water tank 4 is equipped with outlet pipe and is connected to the main pipeline 3;The main pipeline is equipped with
Control valve 6.
Claims (8)
1. a kind of large scale field test simulator of sub-bottom changes piping dangerous situation is arranged on dykes and dams, which is characterized in that will
Dykes and dams are divided into water blocking part and dangerous situation analog portion, with L shape reinforced concrete between the water blocking part and dangerous situation analog portion
Native board wall separates, and the piping dangerous situation of simulation is located at the L shape armoured concrete slab within the walls;Pressurized water is equipped at the top of dykes and dams
Case, the pressure tank lower part are equipped with main pipeline, which extends to along L shape armored concrete board wall occurs dangerous situation position
The soil body in the following, and in the end of the main pipeline, several branch pipes are set, the branch pipe is equipped with aperture, constitutes aperture floral tube;?
Dike dam back is equipped with flat water tank;The flat water tank is equipped with outlet pipe and is connected to the main pipeline;The main pipeline is equipped with control
Valve processed.
2. the large scale field test simulator of sub-bottom changes piping dangerous situation according to claim 1, which is characterized in that
The dykes and dams height is not less than 3m, and the depth of water is not less than 2.5m.
3. the large scale field test simulator of sub-bottom changes piping dangerous situation according to claim 1, which is characterized in that
Aperture floral tube top thickness of earth covering is less than 40cm, and the infiltration coefficient of the soil body requires to be greater than 10-3cm/s。
4. the large scale field test simulator of sub-bottom changes piping dangerous situation according to claim 1, which is characterized in that
The aperture floral tube top earthing silt or Extra-fine sand low using impermeabilisation deformability.
5. the large scale field test simulator of sub-bottom changes piping dangerous situation according to claim 1, which is characterized in that
Water pump is equipped with inside the pressure tank.
6. the large scale field test simulator of sub-bottom changes piping dangerous situation according to claim 1, which is characterized in that
The control valve uses manual and electric double-purpose butterfly valve.
7. the large scale field test simulator of sub-bottom changes piping dangerous situation according to claim 1, which is characterized in that
The main pipeline diameter 10cm;Aperture floral tube diameter 5cm.
8. the large scale field test simulator of sub-bottom changes piping dangerous situation described in one of -7 according to claim 1, special
Sign is, after opening the control valve on main pipeline, piping dangerous situation can occur after dike, and time of origin control is within 15 minutes.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810761341.9A CN109163877A (en) | 2018-07-12 | 2018-07-12 | The large scale field test simulator of sub-bottom changes piping dangerous situation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810761341.9A CN109163877A (en) | 2018-07-12 | 2018-07-12 | The large scale field test simulator of sub-bottom changes piping dangerous situation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109163877A true CN109163877A (en) | 2019-01-08 |
Family
ID=64897724
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810761341.9A Pending CN109163877A (en) | 2018-07-12 | 2018-07-12 | The large scale field test simulator of sub-bottom changes piping dangerous situation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109163877A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115323993A (en) * | 2022-08-15 | 2022-11-11 | 中国建筑科学研究院有限公司 | Dyke dangerous case handling training device and practical training method |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102051896A (en) * | 2009-11-02 | 2011-05-11 | 郑州优特基础工程维修有限公司 | Dam piping rescue high polymer closed grouting method |
CN103114553A (en) * | 2013-03-20 | 2013-05-22 | 水利部交通运输部国家能源局南京水利科学研究院 | Earth and rockfill dam piping burst field test method |
CN203213068U (en) * | 2013-03-20 | 2013-09-25 | 水利部交通运输部国家能源局南京水利科学研究院 | Earth-rock dam for piping dam break simulating test |
CN104833579A (en) * | 2015-04-24 | 2015-08-12 | 河海大学 | Test device and test method for testing strength change of soil body after occurrence of seepage deformation of dykes and dams |
CN206346147U (en) * | 2017-01-03 | 2017-07-21 | 江克证 | Sand base Piping Occurring in Embankment experimental simulation and detection means |
CN207419382U (en) * | 2017-09-30 | 2018-05-29 | 潘文安 | Dike piping plugging device and its dike piping ball sealer |
-
2018
- 2018-07-12 CN CN201810761341.9A patent/CN109163877A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102051896A (en) * | 2009-11-02 | 2011-05-11 | 郑州优特基础工程维修有限公司 | Dam piping rescue high polymer closed grouting method |
CN103114553A (en) * | 2013-03-20 | 2013-05-22 | 水利部交通运输部国家能源局南京水利科学研究院 | Earth and rockfill dam piping burst field test method |
CN203213068U (en) * | 2013-03-20 | 2013-09-25 | 水利部交通运输部国家能源局南京水利科学研究院 | Earth-rock dam for piping dam break simulating test |
CN104833579A (en) * | 2015-04-24 | 2015-08-12 | 河海大学 | Test device and test method for testing strength change of soil body after occurrence of seepage deformation of dykes and dams |
CN206346147U (en) * | 2017-01-03 | 2017-07-21 | 江克证 | Sand base Piping Occurring in Embankment experimental simulation and detection means |
CN207419382U (en) * | 2017-09-30 | 2018-05-29 | 潘文安 | Dike piping plugging device and its dike piping ball sealer |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115323993A (en) * | 2022-08-15 | 2022-11-11 | 中国建筑科学研究院有限公司 | Dyke dangerous case handling training device and practical training method |
CN115323993B (en) * | 2022-08-15 | 2023-11-14 | 中国建筑科学研究院有限公司 | Dyke dangerous case disposal training device and practical training method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109163877A (en) | The large scale field test simulator of sub-bottom changes piping dangerous situation | |
CN108104058A (en) | A kind of dykes and dams flood crevasse plugging device and its method for blocking | |
CN109024476A (en) | Base self collapsing levee dam geotechnique's woven fabric very floodway is washed in a pan in cross flow | |
CN205475127U (en) | Dykes and dams super -standard flood flood diversion siphon pipe racks | |
CN202596258U (en) | Obstruction leakage-proof device | |
CN109235362A (en) | Cross flow confluence, which is drawn, rushes self collapsing levee dam geotechnique's plate very floodway | |
CN106436649A (en) | Flow control technology and series equipment thereof | |
Tinti et al. | Modeling a possible holocenic landslide-induced tsunami at Stromboli volcano, Italy | |
CN207714256U (en) | A kind of dykes and dams flood crevasse plugging device | |
CN109024474A (en) | Geotechnological plate cut-pff wall self collapsing levee dam flood diversion gate | |
Veale et al. | Estimation of gravity dam breach geometry | |
CN109024475A (en) | Forbidden lamella geomembrane cloth antiseepage curtain self collapsing levee dam floodway | |
CN105544455B (en) | Dykes and dams super standard flood flood diversion pipe band | |
CN210421001U (en) | Liquid/gas filling type water plugging bag | |
Ishikawa et al. | Collapse mechanism of seawall protective structure by huge tsunami | |
Hansen | Studies of a channel through Padre Island, Texas | |
Yasuhara et al. | Geosynthetics-aided adaptation against coastal instability caused by sea-level rise | |
Roehman | Flood mitigation of settlements on the sea tide with a water-filled rubber weir as an efficient innovation (a case study of flood in Semarang) | |
Fernández Arce et al. | Tsunamis and tsunami prepardness in Costa Rica, central America | |
CN202689193U (en) | Desalting plant special for earthen site | |
CN213277027U (en) | Device for simulating piping dangerous case of dike in drilling base | |
Hinwood | Design for tsunamis–coastal engineering considerations | |
Li et al. | Yangtze dyke and its strengthening | |
CN101709575B (en) | A kind of serial equipment and servicing unit and application of stoping the perils of the sea to occur of fast fighting flood and relieve victims | |
Warniyati et al. | Design of a Facility for Tsunami Run up Generation to Study Tsunami and Seawall Interaction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190108 |
|
RJ01 | Rejection of invention patent application after publication |