CN109139109A - A kind of method on the artificial water storage stratum of solid filling coal-mining technique - Google Patents

A kind of method on the artificial water storage stratum of solid filling coal-mining technique Download PDF

Info

Publication number
CN109139109A
CN109139109A CN201810869745.XA CN201810869745A CN109139109A CN 109139109 A CN109139109 A CN 109139109A CN 201810869745 A CN201810869745 A CN 201810869745A CN 109139109 A CN109139109 A CN 109139109A
Authority
CN
China
Prior art keywords
water storage
band
mining
coal
storage stratum
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810869745.XA
Other languages
Chinese (zh)
Inventor
缪协兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810869745.XA priority Critical patent/CN109139109A/en
Publication of CN109139109A publication Critical patent/CN109139109A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/16Modification of mine passages or chambers for storage purposes, especially for liquids or gases
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings

Abstract

A kind of method on the artificial water storage stratum of solid filling coal-mining technique, includes the following steps: to implement the goaf filling that non-sold stowing band and sold stowing band alternate to mining area coal column and periphery coal seam, forms artificial water storage stratum in the goaf of non-sold stowing band;And surface precipitation is introduced into artificial water storage stratum by mining induced fissure seepage channel and two kinds of artificial recharge channel approach.The present invention can not only safe and efficient coal pillar recovery press coal, and can make full use of and handle mining area solid waste, construct water storage stratum, that is, form groundwater reservoir, solve the problems, such as storage and the Sustainable use of water shortage mine water resource.This method is simple, and securely and reliably, it is convenient to promote and apply, and has good economic, society and environmental benefit.

Description

A kind of method on the artificial water storage stratum of solid filling coal-mining technique
Technical field
The present invention relates to a kind of methods on the artificial water storage stratum of solid filling coal-mining technique, are particularly suitable for water shortage mining area coal The water-retaining production of layer or protection coal pillar.
Background technique
14, China Large-scale Coal base, in addition to Yunnan-Guizhou, the two Hua Areas and the base Meng Dong, 11 coal bases all seriously lack Water, especially the Northwest account for the coal resources in the whole nation 75%, and water resource is only the whole nation 20% or so, and precipitation is mostly along ground Table runoff is lost quickly, and surface water drain evaporation is serious.Modernization mining area mostly uses greatly longwell to be caving formula exploitation, and goaf is quickly The overlying strata compacting being caving, and effective water-bearing layer is not present in water shortage mining area mostly in the overlying strata of coal seam, can not form water space, Mining area surface precipitation loss after exploitation is even more serious, and mining area water shortage problem can be protruded more.On the other hand, general mining area all can It can not be recycled containing a large amount of protection coal pillars, while can also discharge the solid waste such as a large amount of spoils.
Summary of the invention
In order to overcome existing above-mentioned deficiency, the present invention provides a kind of side on artificial water storage stratum of solid filling coal-mining technique Method, can not only safe and efficient coal pillar recovery press coal, and can make full use of and handle mining area solid waste, construction water storage Layer, that is, form groundwater reservoir, solve the problems, such as storage and the Sustainable use of water shortage mine water resource.
The technical solution used to solve the technical problems of the present invention is that: include the following steps: to mining area coal column and periphery coal Layer implements the goaf filling that non-sold stowing band and sold stowing band alternate, and forms people in the goaf of non-sold stowing band Make water storage stratum;And surface precipitation is introduced by artificial water storage by mining induced fissure seepage channel and two kinds of artificial recharge channel approach In stratum.
Wherein, the forming process in the artificial recharge channel is: building nature drop compared with low-lying district on above goaf ground Water collecting-tank is connected to from bottom of pond to artificial water storage earth-boring.
Further, the volume V on the artificial water storage stratum are as follows:
In formula, l is the tendency length of non-sold stowing band;D is the strike length of single non-sold stowing band;H is work Face mining height;For the pack completeness of non-sold stowing band;A is the amount of crushing of non-sold stowing band;N is non-sold stowing band Quantity.
Preferably, the solids for filling the material selection mining area developing spoil, drift-sand or the loess that use.
Further, the ratio between the width of the sold stowing band and height of coal mining are defined as the ratio of width to height, ratio is The foundation of γ, setting γ parameter value are to ensure that the long-time stability of sold stowing band, and form permanent goaf hole.Meanwhile Meet strata movement and surface subsidence control index request.γ can pass through the strata movement of mining rock and subsidence control Theory analysis processed provides.
In view of the convenience of construction, it is preferable that the non-sold stowing band is of same size with sold stowing band.
It further, can also be in non-sold stowing band in order to guarantee the pack completeness in sold stowing band and its stability Barricade is isolated in arrangement between sold stowing band.
Compared with prior art, the method on the artificial water storage stratum of a kind of solid filling coal-mining technique of the invention, by mine The goaf filling that non-sold stowing band and sold stowing band alternate is implemented in area's coal column and periphery coal seam, and control mining overburden is non- It is sufficiently caving, to form stable permanent hole in the goaf of non-sold stowing band, becomes artificial water storage stratum.As it can be seen that This method can not only safe and efficient coal pillar recovery press coal, and can make full use of and handle mining area solid waste, construct water storage Stratum forms groundwater reservoir, and to artificial water storage by the two kinds of approach in artificial recharge channel and mining induced fissure seepage channel Layer water storage, realizes the protection of water shortage mine water resource, and water resource solves water shortage mining area water money for mining area utilization after purification The storage and Sustainable use problem in source.This method technical method is simple, and securely and reliably, it is convenient to promote and apply, and has good warp Ji, society and environmental benefit.
Detailed description of the invention
Present invention will be further explained below with reference to the attached drawings and examples.
Fig. 1 is the schematic illustration on the artificial water storage stratum of one embodiment of the invention, and arrow instruction is working face in figure Direction of propulsion.
In figure: 1, natural precipitation collecting-tank, 2, mining induced fissure seepage channel, 3, artificial recharge channel, 4, coal seam, 5, non-close Real packwall, 6, sold stowing band, 7, isolation barricade, 8, filling coal mining hydraulic support, 9, filling coal mining working face, 10, artificial Water storage stratum.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is A part of the embodiments of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill people Member's every other embodiment obtained without making creative work, belongs to protection scope of the present invention.
Fig. 1 shows the structural schematic diagram of a preferred embodiment of the invention, be by taking certain mine CT3210 working face as an example, A kind of method on the artificial water storage stratum of solid filling coal-mining technique of the invention is specifically described:
A. CT3210 filling coal mining working face 9 is arranged by solid filling in the mine boundary protection coal column region of the mine, The tendency length l of the filling coal mining working face 9 is 150m, and advance of the face length is 1800m, and mining height h is 3m.It is adopted using filling Coal hydraulic bracket 8 supports face roof, mines and is compacted solid filling object (material with filling parallel operations, the rear part rammer compacter Material), realize sold stowing.
B. according to exploiting field sand coated iron mold and strata movement law-analysing, and in view of mining and filling process requirement, setting The ratio of width to height γ is 2, i.e. the width d of sold stowing band 6 and non-sold stowing band 5 is 6m, and the quantity n of non-sold stowing band is 150.Since coal column region mining induced stress is more concentrated, it is sufficiently caving state to guarantee that controlroof is in non-, is determined non-closely knit The pack completeness of fill areaIt is 0.55.
C. low-lying district builds the natural precipitation collecting-tank 1 on ground above exploiting field, and natural collecting-tank bottom is by double drillings and filling Goaf communicates, as the artificial channel for collecting surface precipitation.
D. condition is amounted to according to the solid filling object of the mine, the material using mining area developing spoil as filling, due to this A little materials are naturally pollution-free, reasonably handled mining area hillock problem in this way.
E. it observes obtaining with subsidence according to strata movement, the amount of the crushing a of non-sold stowing band 5 is 0.9m, then The groundwater reservoir formed after the exploitation of CT3210 working face solid filling can be obtained by the volume calculations formula on artificial water storage stratum 10 Volume V be 6.075 × 104m3
Advantage of the invention is as follows:
(1) solid filling coal-mining technique liberation " under three " (under building, under road, under water body) pressure coal resource is taken, it can It realizes safe working, improves coal recovery rate;And alternated by the non-sold stowing band 5 of implementation and sold stowing band 6 Goaf filling forms stable permanent hole in the goaf of non-sold stowing band 5, becomes artificial water storage stratum 10.
(2) by the 2 two kinds of approach in artificial recharge channel 3 and mining induced fissure seepage channel to artificial 10 water storage of water storage stratum, The protection for realizing water shortage mine water resource, water resource is after purification for mining area utilization.
(3) mining area solid waste is rationally utilized, solves the problems, such as mining area hillock, and this attal is naturally without dirt Dye, not will cause secondary pollution.
The above is only presently preferred embodiments of the present invention, not does limitation in any form to the present invention, it is all according to According to technical spirit of the invention, any simple modification and same variation are made to above embodiments, each fall within guarantor of the invention Within the scope of shield.

Claims (7)

1. a kind of method on the artificial water storage stratum of solid filling coal-mining technique, characterized in that include the following steps: to mining area coal column And the goaf filling that periphery coal seam (4) implement non-sold stowing band (5) and sold stowing band (6) alternates, it closely knit is filled non- The goaf for filling out band (5) forms artificial water storage stratum (10);And pass through mining induced fissure seepage channel (2) and artificial recharge channel Surface precipitation is introduced into artificial water storage stratum (10) by (3) two kinds of approach.
2. the method on the artificial water storage stratum of a kind of solid filling coal-mining technique according to claim 1, it is characterized in that: described The volume V of artificial water storage stratum (10) are as follows:
In formula, l is the tendency length of non-sold stowing band (5);D is the strike length of single non-sold stowing band (5);H is work Make face mining height;For the pack completeness of non-sold stowing band (5);A is the amount of crushing of non-sold stowing band (5);N is non-closely knit The quantity of packwall (5).
3. a kind of method on the artificial water storage stratum of solid filling coal-mining technique according to claim 1 or 2, it is characterized in that: The forming process of the artificial recharge channel (3) is: building natural precipitation collecting-tank compared with low-lying district on above goaf ground (1), it drills and is connected to from bottom of pond to artificial water storage stratum (10).
4. a kind of method on the artificial water storage stratum of solid filling coal-mining technique according to claim 1 or 2, it is characterized in that: The solids for filling the material selection mining area developing spoil, drift-sand or the loess that use.
5. a kind of method on the artificial water storage stratum of solid filling coal-mining technique according to claim 1 or 2, it is characterized in that: The ratio between the width of the sold stowing band (6) and height of coal mining are defined as the ratio of width to height, ratio γ passes through mining rock Strata movement is provided with surface subsidence control theory analysis.
6. the method on the artificial water storage stratum of a kind of solid filling coal-mining technique according to claim 5, it is characterized in that: described Non- sold stowing band (5) is of same size with sold stowing band (6).
7. a kind of method on the artificial water storage stratum of solid filling coal-mining technique according to claim 1 or 2, it is characterized in that: Barricade (7) are isolated in arrangement between non-sold stowing band (5) and sold stowing band (6).
CN201810869745.XA 2018-08-02 2018-08-02 A kind of method on the artificial water storage stratum of solid filling coal-mining technique Pending CN109139109A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810869745.XA CN109139109A (en) 2018-08-02 2018-08-02 A kind of method on the artificial water storage stratum of solid filling coal-mining technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810869745.XA CN109139109A (en) 2018-08-02 2018-08-02 A kind of method on the artificial water storage stratum of solid filling coal-mining technique

Publications (1)

Publication Number Publication Date
CN109139109A true CN109139109A (en) 2019-01-04

Family

ID=64799478

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810869745.XA Pending CN109139109A (en) 2018-08-02 2018-08-02 A kind of method on the artificial water storage stratum of solid filling coal-mining technique

Country Status (1)

Country Link
CN (1) CN109139109A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109973095A (en) * 2019-05-14 2019-07-05 中国矿业大学 A kind of method of coal mine solid filling exploitation reconstruction groundwater storage space
CN110344877A (en) * 2019-08-02 2019-10-18 新疆大学 The method of carbon dioxide gas is stored in the goaf of porous media filling
CN111577280A (en) * 2020-05-19 2020-08-25 中国矿业大学 Mining area multi-layer water resource collaborative protective mining method
CN113638769A (en) * 2021-08-27 2021-11-12 烟台杰瑞石油装备技术有限公司 Goaf filling method
CN114017108A (en) * 2021-11-04 2022-02-08 河南理工大学 Gangue functional type partially-filled coal mine underground reservoir
CN114575847A (en) * 2022-03-15 2022-06-03 中国矿业大学(北京) Method for integrating water-retaining mining of shallow coal seam and construction of underground reservoir
CN115853583A (en) * 2022-09-02 2023-03-28 中国矿业大学 Method for reforming and utilizing abandoned mine roadway

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110272402A1 (en) * 2010-05-07 2011-11-10 Robert Garwood Lamond Container for forming a barrier in an enclosed environment
CN102913282A (en) * 2012-11-20 2013-02-06 中国神华能源股份有限公司 Open pit coal mine underground reservoir
CN104074541A (en) * 2014-06-25 2014-10-01 中国矿业大学 Solid filling mining design method under water body
CN107013215A (en) * 2017-05-15 2017-08-04 太原理工大学 A kind of subregion domain construction filling mining is to reduce the method for safety pillar under wa ter bodies size
CN107194615A (en) * 2017-06-28 2017-09-22 中国神华能源股份有限公司 The evaluation method of coal mine underground reservoir construction applicability

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110272402A1 (en) * 2010-05-07 2011-11-10 Robert Garwood Lamond Container for forming a barrier in an enclosed environment
CN102913282A (en) * 2012-11-20 2013-02-06 中国神华能源股份有限公司 Open pit coal mine underground reservoir
CN104074541A (en) * 2014-06-25 2014-10-01 中国矿业大学 Solid filling mining design method under water body
CN107013215A (en) * 2017-05-15 2017-08-04 太原理工大学 A kind of subregion domain construction filling mining is to reduce the method for safety pillar under wa ter bodies size
CN107194615A (en) * 2017-06-28 2017-09-22 中国神华能源股份有限公司 The evaluation method of coal mine underground reservoir construction applicability

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李文平 等: "采空区储水——干旱区保水采煤新途径", 《工程地质学报》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109973095A (en) * 2019-05-14 2019-07-05 中国矿业大学 A kind of method of coal mine solid filling exploitation reconstruction groundwater storage space
CN109973095B (en) * 2019-05-14 2020-04-24 中国矿业大学 Method for reconstructing underground water storage space in coal mine solid filling mining
CN110344877A (en) * 2019-08-02 2019-10-18 新疆大学 The method of carbon dioxide gas is stored in the goaf of porous media filling
CN111577280A (en) * 2020-05-19 2020-08-25 中国矿业大学 Mining area multi-layer water resource collaborative protective mining method
CN111577280B (en) * 2020-05-19 2021-04-27 中国矿业大学 Mining area multi-layer water resource collaborative protective mining method
CN113638769A (en) * 2021-08-27 2021-11-12 烟台杰瑞石油装备技术有限公司 Goaf filling method
CN113638769B (en) * 2021-08-27 2023-12-01 烟台杰瑞石油装备技术有限公司 Goaf filling method
CN114017108A (en) * 2021-11-04 2022-02-08 河南理工大学 Gangue functional type partially-filled coal mine underground reservoir
CN114017108B (en) * 2021-11-04 2024-02-02 河南理工大学 Gangue functional type partial filling coal mine underground reservoir
CN114575847A (en) * 2022-03-15 2022-06-03 中国矿业大学(北京) Method for integrating water-retaining mining of shallow coal seam and construction of underground reservoir
CN115853583A (en) * 2022-09-02 2023-03-28 中国矿业大学 Method for reforming and utilizing abandoned mine roadway

Similar Documents

Publication Publication Date Title
CN109139109A (en) A kind of method on the artificial water storage stratum of solid filling coal-mining technique
CN108661705B (en) Strip goaf four-in-one comprehensive treatment construction method
CN102865103B (en) Distributed using method for mine underground water
CN102635392B (en) Co-extraction method for pillar-less coal and gas of advanced entry-retaining construction extraction engineering
CN103498696B (en) A kind of method from roadway in the roof grouting filling compacting goaf filling body
CN103615250B (en) The full Open stope mining afterwards filling of itemize studding works in coordination with mining codes
CN100554642C (en) A kind of method of long-wall integrated-extraction reclaiming room-type coal column mining
CN106930763B (en) A method of the filling residual mining area roadway support coal column of second mining super high seam
CN108194088A (en) A kind of soft top coal layer cuts top release gob-side entry retaining method without explosion
CN101737052A (en) Sublevel fill-mining method
CN106050234B (en) The construction technology that underground water is protected in progress of coal mining
CN106014344B (en) Environment-friendly water-holding coal and uranium coordinated mining system and application method thereof
CA2986062C (en) Fully mechanized mining-filling mixed mining working face filling section length determination method
CN107893658A (en) Big thick ore body stage open stope afterwards filling mining methods in pole under strong ground pressure ring border
CN103046955A (en) Large-range goaf group filling method
CN103147792B (en) Drift type coal mining filling method
CN110714760B (en) Mining method for coal-aluminum symbiotic layered induction collaborative mining
CN103993882A (en) Method for replacing strip coal pillars by means of grouting in collapse area
CN109538210A (en) A kind of soft extremely irregularcoal seam fully mechanized coal face gob-side entry retaining method of high methane three
CN110173238A (en) The anti-reflection extraction of high seam three-dimensional roadway layout networking explosion thick gas method entirely
CN110410076A (en) A kind of filling mining method for leaving Pillar Recovery for old pillars of a house goaf
CN103557001B (en) A kind of low section high oper cylinler shrink afterwards filling mining method
CN103114854B (en) Pillar robbing method of reconstructed artificial stud
CN106089207A (en) Super high seam work surface gob side entry driving thin coal pillar stays equipment, method
CN109162713A (en) A kind of double resource pit mining modes of coal water not changing overlying strata hydrogeologic condition

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190104

RJ01 Rejection of invention patent application after publication