CN109137980A - A kind of underground pipe gallery pipeline arrangement and construction method - Google Patents
A kind of underground pipe gallery pipeline arrangement and construction method Download PDFInfo
- Publication number
- CN109137980A CN109137980A CN201811168327.4A CN201811168327A CN109137980A CN 109137980 A CN109137980 A CN 109137980A CN 201811168327 A CN201811168327 A CN 201811168327A CN 109137980 A CN109137980 A CN 109137980A
- Authority
- CN
- China
- Prior art keywords
- pipeline
- cabin
- pipe gallery
- underground pipe
- upper layer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 15
- 239000010865 sewage Substances 0.000 claims abstract description 35
- VNWKTOKETHGBQD-UHFFFAOYSA-N methane Chemical compound C VNWKTOKETHGBQD-UHFFFAOYSA-N 0.000 claims description 28
- 239000003345 natural gas Substances 0.000 claims description 15
- 238000004891 communication Methods 0.000 claims description 11
- 238000009423 ventilation Methods 0.000 claims description 9
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 4
- 238000005516 engineering process Methods 0.000 abstract description 3
- 239000010410 layer Substances 0.000 description 35
- 230000005484 gravity Effects 0.000 description 8
- 238000010586 diagram Methods 0.000 description 4
- 230000002452 interceptive effect Effects 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 230000007613 environmental effect Effects 0.000 description 2
- 239000011229 interlayer Substances 0.000 description 2
- 230000001737 promoting effect Effects 0.000 description 2
- 230000002411 adverse Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000002356 single layer Substances 0.000 description 1
- 238000003786 synthesis reaction Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/10—Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
Abstract
The present invention provides a kind of underground pipe gallery pipeline arrangement and construction methods, belong to city integrated piping lane field of engineering technology, for the problem that underground pipe gallery rain, bilge tank and other cabins are arranged in juxtaposition, rain, sewage collecting branch pipe interfere other municipal pipelines when accessing piping lane.The pipeline arrangement is set on pipe gallery ontology, it is characterized in that, the pipeline arrangement includes the upper and lower folded cabin of upper layer cabin and lower layer's cabin composition, rainwater pipeline and sewage pipeline are arranged in juxtaposition in the upper layer cabin, other municipal pipelines are laid in lower layer's cabin, wherein, piping lane node is arranged on the left of the cabin of upper layer.The construction method of underground pipe gallery pipeline arrangement of the invention is easy to operate, not only solve the access problem that branch pipe is collected after being included in rainwater pipeline, sewage pipeline, again pipe gallery special joint can be arranged in conjunction with the upper space in folded cabin, construction cost is reduced, and intensive the underground space is utilized.
Description
Technical field
The present invention relates to city integrated piping lane field of engineering technology, in particular to a kind of underground pipe gallery pipeline arrangement knot
Structure and construction method.
Background technique
Pipe gallery is to be built in Urban Underground for accommodating the structures of two classes and the above municipal engineering pipeline and attached setting
It applies.For the intensive utilization underground space, usually require that all municipal pipelines under road including rainfall and sewage pipes line are included in pipe
In corridor, pipe gallery pipeline arrangement mode such as Fig. 1 common in the art, in figure: 10- rainwater pipeline, 20- sewage pipeline,
30- natural gas line, 40- power pipeline, 50- communication line, 60- water-supply line.As it can be seen that common pipe gallery pipeline is arranged
Structure is single layer arrangement form arranged side by side, is generally used for the pressure lines such as storage electric power, communication and water supply, by using on piping lane
Portion earthing space carries out the access of branch line and picks out, and does not influence other pipelines in lower layer's corridor body.However, being included in when in piping lane
After the rainfall and sewage pipes line of gravity stream form, the access for collecting branch pipe must satisfy the absolute altitude requirement of supervisor, therefore can be to other
The indoor pipeline in cabin generates interference, has an adverse effect.
Therefore, pipe gallery pipeline arrangement mode common in the art exists following insufficient: first is that rain, bilge tank with
Other cabins are arranged in juxtaposition, and are unfavorable for the access of side rain, sewage collecting pipeline;Second is that meet rain, sewage gravity stream pipeline
Absolute altitude requirement, piping lane buried depth is sometimes shallower, is unfavorable for the arrangement of piping lane node.
Summary of the invention
It is arranged in juxtaposition for underground pipe gallery rain, bilge tank and other cabins, when rain, sewage collecting branch pipe access piping lane
The problem of interfering to other municipal pipelines, the present invention provide a kind of underground pipe gallery pipeline arrangement and construction party
Method not only can solve the access problem for collecting branch pipe after being included in rainfall and sewage pipes line, but also can arrange synthesis in conjunction with the upper space in folded cabin
Piping lane special joint, the simultaneously intensive utilization underground space of reducining the construction costs, embodies the theory of environmental protection and energy saving.
The technical solution adopted by the present invention to solve the technical problems is:
A kind of underground pipe gallery pipeline arrangement, the pipeline arrangement are set on pipe gallery ontology, institute
The upper and lower folded cabin that pipeline arrangement includes upper layer cabin and lower layer's cabin composition is stated, is arranged in juxtaposition rainwater in the upper layer cabin
Pipeline and sewage pipeline lay other municipal pipelines in lower layer's cabin, wherein piping lane node is arranged on the left of the cabin of upper layer.
Further, other described municipal pipelines include power pipeline, communication line, natural gas line and feed pipe
Line.
Further the piping lane node includes ventilation opening and bifurcations.
Further the natural gas line is set on the left of lower layer's cabin.
Further the sewage pipeline connects branch sewer, and the absolute altitude of the branch sewer is greater than the sewage pipeline
Absolute altitude.
It further further include feeding port, the feeding port is set to upper layer cabin bottom.
The present invention also provides a kind of construction method of underground pipe gallery pipeline arrangement, which includes such as
Lower step:
Step 1: construct the underground pipe gallery ontology when, construct respectively upper layer cabin and lower layer's cabin, in upperdeck
Rainwater pipeline and sewage pipeline are arranged in juxtaposition in body, in lower layer's cabin arrange power pipeline, communication line, natural gas line with
And water-supply line;
Step 2: piping lane node is arranged on the left of the cabin of upper layer.
Further, the sewage pipeline connects branch sewer., the absolute altitude of the branch sewer is greater than the sewage pipeline
Absolute altitude.
Compared with prior art, the beneficial effects of the present invention are:
Underground pipe gallery pipeline arrangement provided by the invention include upper layer cabin and lower layer's cabin composition up and down
Folded cabin, wherein rainwater pipeline and sewage pipeline with gravity stream pipeline mark high request etc. are arranged in juxtaposition in the cabin of upper layer, electricity
Solenoid line, communication line, natural gas line and water-supply line etc. are set in lower layer's cabin, the ventilation opening of pipe gallery and point
The piping lanes node such as branch mouth is also disposed in the cabin of upper layer, to realize gravity stream using adjusting of the pipeline in cabin altitude range
Requirement of the pipeline to absolute altitude, while solving when rainfall and sewage pipes line collects branch pipe access underground pipe gallery and other municipal administrations are managed
The interference of line reduces interfering with each other between pipeline and influences, moreover, using upperdeck interlayer body the underground space reasonably
It arranges the piping lanes nodes such as ventilation opening, feeding port and the bifurcations of pipe gallery, reduces complicated design of node, saved work
Cheng Chengben has preferably promotional value.
Detailed description of the invention
Fig. 1 is underground pipe gallery pipeline arrangement schematic diagram in the prior art;
Fig. 2 is the underground pipe gallery pipeline arrangement schematic diagram in one embodiment of the invention;
Fig. 3 is the schematic diagram that branch sewer accesses underground pipe gallery;
Fig. 4 is the schematic diagram of the underground pipe gallery feeding port in one embodiment of the invention.
In figure: 10- rainwater pipeline;20- sewage pipeline;30- natural gas line;40- power pipeline;50- communication line;
60- water-supply line;70- feeding port.
Specific embodiment
Below in conjunction with the drawings and specific embodiments to a kind of underground pipe gallery pipeline arrangement proposed by the present invention and
Construction method is described in further detail.According to following explanation, advantages and features of the invention will be become apparent from.It below will be by institute
The embodiment combination attached drawing enumerated, the technology contents and feature that the present invention will be described in detail.Need in addition it illustrate, attached drawing is all made of
Very simplified form and use non-accurate ratio, only to it is convenient, lucidly aid in illustrating the mesh of the embodiment of the present invention
's.For sake of convenience, "upper" described below, "lower" are consistent with the upper and lower direction of attached drawing, but this can't be the present invention
The limitation of technical solution.
Below with reference to Fig. 1 to Fig. 4, the composition for the underground pipe gallery pipeline arrangement that the present invention will be described in detail.
Embodiment one
Underground pipe gallery pipeline arrangement is placed in pipe gallery ontology in the embodiment of the present invention referring to FIG. 1 to FIG. 4,
On, pipeline arrangement includes the upper and lower folded cabin of upper layer cabin (not shown) and lower layer's cabin composition (not shown), upper layer cabin
In be arranged in juxtaposition rainwater pipeline 10 and sewage pipeline 20, power pipeline 40, communication line 50, natural gas tube are laid in lower layer's cabin
Other municipal pipelines such as line 30 and water-supply line 50, wherein arrange pipe gallery ventilation opening (not shown) on the left of the cabin of upper layer
With the piping lanes node such as bifurcations (not shown).
Specifically, the embodiment of the present invention is by the characteristics of reasonably arranging, making full use of various pipelines, using folded up and down
The underground pipe gallery pipeline arrangement in cabin come solve the problems, such as rainwater pipeline 10, sewage pipeline 20 access pipe gallery, will
Rainwater pipeline 10, sewage pipeline 20 are arranged in parallel at upper layer, will not interfere and influence the row of other municipal pipelines pipe gallery Nei
Cloth, and requirement of the gravity stream pipeline to absolute altitude is realized using adjusting of the pipeline in cabin altitude range.And utilize left side cabin
The piping lanes nodes such as space layout ventilation opening, feeding port and bifurcations above body (being natural gas line 30 in the present embodiment),
Reduce complicated design of node, saves construction investment.Therefore, underground pipe gallery pipeline arrangement of the invention, no
The access problem that branch pipe is collected after being included in rainwater pipeline, sewage pipeline is addressed only, and can be in conjunction with the upper space arrangement in folded cabin
Pipe gallery special joint, reduce construction cost and it is intensive the underground space is utilized, embody the theory of environmental protection and energy saving.
Preferably, with continued reference to FIG. 3, in order to meet absolute altitude requirement of the sewage pipeline 20 as gravity stream pipeline, it will be dirty
For water branch pipe 21 smoothly in access underground pipe gallery, sewage pipeline 20 connects branch sewer 21, and the absolute altitude of branch sewer 21 is greater than
The absolute altitude of sewage pipeline 20.
Preferably, with continued reference to FIG. 4, in order to reduce the influence caused by various municipal pipelines as far as possible, underground is comprehensive
Piping lane feeding port 70 is set to upper layer cabin bottom.
Embodiment two
Please continue to refer to Fig. 1 to Fig. 4, present embodiment discloses a kind of applying for underground pipe gallery pipeline arrangement
Work method, includes the following steps:
When step S1 construction underground pipe gallery ontology, construct respectively upper layer cabin and lower layer's cabin, in the cabin of upper layer
It is arranged in juxtaposition rainwater pipeline 10 and sewage pipeline 20, power pipeline 40, communication line 50, natural gas tube are arranged in lower layer's cabin
Line 30 and water-supply line 60, wherein natural gas line 30 is independent arranges, and natural gas line 30 is arranged on the left of lower layer's cabin.
Step S2 arranges the piping lanes nodes such as ventilation opening, bifurcations on the left of the cabin of upper layer.
In conclusion underground pipe gallery pipeline arrangement provided by the invention includes upper layer cabin and lower layer's cabin group
At upper and lower folded cabin, wherein rainwater pipeline and sewage pipeline etc. with gravity stream pipeline mark high request are arranged in juxtaposition in upper layer
In cabin, power pipeline, communication line, natural gas line and water-supply line etc. are set in lower layer's cabin, pipe gallery
The piping lanes node such as ventilation opening and bifurcations is also disposed in the cabin of upper layer, thus the adjusting using pipeline in cabin altitude range
It realizes requirement of the gravity stream pipeline to absolute altitude, while solving when rainfall and sewage pipes line collects branch pipe access underground pipe gallery pair
The interference of other municipal pipelines reduces interfering with each other between pipeline and influences, moreover, utilizing the underground of upperdeck interlayer body
The piping lanes node such as ventilation opening, feeding port and bifurcations of pipe gallery is reasonably arranged in space, reduces complicated design of node,
Engineering cost has been saved, there is preferably promotional value.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this hair
Any change, the modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to the protection of claims
Range.
Claims (8)
1. a kind of underground pipe gallery pipeline arrangement, the pipeline arrangement is set on pipe gallery ontology, special
Sign is, the pipeline arrangement includes the upper and lower folded cabin of upper layer cabin and lower layer's cabin composition, in the upper layer cabin simultaneously
Column arrange rainwater pipeline and sewage pipeline, lay other municipal pipelines in lower layer's cabin, wherein arrangement on the left of the cabin of upper layer
Piping lane node.
2. underground pipe gallery pipeline arrangement according to claim 1, which is characterized in that other described municipal pipelines
Including power pipeline, communication line, natural gas line and water-supply line.
3. underground pipe gallery pipeline arrangement according to claim 1, which is characterized in that the piping lane node includes
Ventilation opening and bifurcations.
4. underground pipe gallery pipeline arrangement according to claim 1, which is characterized in that the natural gas line is set
It is placed on the left of lower layer's cabin.
5. underground pipe gallery pipeline arrangement according to claim 1, which is characterized in that the sewage pipeline connection
Branch sewer, the absolute altitude of the branch sewer are greater than the absolute altitude of the sewage pipeline.
6. underground pipe gallery pipeline arrangement according to claim 3, which is characterized in that it further include feeding port, institute
It states feeding port and is set to upper layer cabin bottom.
7. a kind of construction method of underground pipe gallery pipeline arrangement according to claim 1 to 6,
It is characterized in that, includes the following steps:
Step 1: construct the underground pipe gallery ontology when, construct respectively upper layer cabin and lower layer's cabin, in the cabin of upper layer
It is arranged in juxtaposition rainwater pipeline and sewage pipeline, power pipeline, communication line, natural gas line are arranged in lower layer's cabin and is given
Water pipeline;
Step 2: piping lane node is arranged on the left of the cabin of upper layer.
8. construction method according to claim 7, which is characterized in that the sewage pipeline connects branch sewer, the dirt
The absolute altitude of water branch pipe is greater than the absolute altitude of the sewage pipeline.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811168327.4A CN109137980A (en) | 2018-10-08 | 2018-10-08 | A kind of underground pipe gallery pipeline arrangement and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811168327.4A CN109137980A (en) | 2018-10-08 | 2018-10-08 | A kind of underground pipe gallery pipeline arrangement and construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109137980A true CN109137980A (en) | 2019-01-04 |
Family
ID=64810486
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811168327.4A Pending CN109137980A (en) | 2018-10-08 | 2018-10-08 | A kind of underground pipe gallery pipeline arrangement and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109137980A (en) |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20120163919A1 (en) * | 2009-05-08 | 2012-06-28 | Ilja Irmscher | Method for erecting an underground construction |
CN105113543A (en) * | 2015-09-22 | 2015-12-02 | 赵洪志 | Assembled and combined cabin concrete structure of shallow-buried 0815-type underground comprehensive pipe gallery |
CN206467688U (en) * | 2017-02-17 | 2017-09-05 | 上海市城市建设设计研究总院(集团)有限公司 | Include the pipe gallery of sewage pipe and rain pipe |
-
2018
- 2018-10-08 CN CN201811168327.4A patent/CN109137980A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20120163919A1 (en) * | 2009-05-08 | 2012-06-28 | Ilja Irmscher | Method for erecting an underground construction |
CN105113543A (en) * | 2015-09-22 | 2015-12-02 | 赵洪志 | Assembled and combined cabin concrete structure of shallow-buried 0815-type underground comprehensive pipe gallery |
CN206467688U (en) * | 2017-02-17 | 2017-09-05 | 上海市城市建设设计研究总院(集团)有限公司 | Include the pipe gallery of sewage pipe and rain pipe |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206189462U (en) | Double -cabin utility tunnel structure of corridor is gone into to gas and run by gravity sewer line | |
CN202247950U (en) | Quadrate culvert member | |
CN206143899U (en) | Crossover node structure suitable for sewer line incorporates utility tunnel in | |
CN205839797U (en) | There is the underground pipe gallery of water storage function | |
CN106978820A (en) | A kind of pipe gallery reveals water utilization system | |
CN208309634U (en) | A kind of fuel gas conduit is in the pipe gallery of top level structure | |
CN205024802U (en) | Energy -saving rainwater recycling system | |
CN205296347U (en) | Arrangement structure that utility tunnel internal drain pipe said | |
CN206319337U (en) | Large-scale square tube type Urban Underground comprehensive tunnel | |
CN109137980A (en) | A kind of underground pipe gallery pipeline arrangement and construction method | |
CN206752575U (en) | A kind of municipal water supply part flow arrangement | |
CN105484291A (en) | Unilaterally-expanded comprehensive pipe gallery joint structure | |
CN201162227Y (en) | Underground pipe canal | |
CN207582572U (en) | A kind of convenient buried fire plant | |
CN205894090U (en) | Job site fire water cyclic utilization device | |
CN206844150U (en) | A kind of shallow embedding formula pipe gallery | |
CN205296221U (en) | Many function synthesis piping lane | |
CN209482352U (en) | Upper straddle type pipe gallery flowing line confluence node structure | |
CN211816399U (en) | Prefabricated assembled city utility tunnel | |
CN212613999U (en) | Reduce interior equipment tuber pipe of underground garage layer height and lay structure | |
CN206467688U (en) | Include the pipe gallery of sewage pipe and rain pipe | |
CN208518017U (en) | Two-way water system for clean operating room in hospital | |
CN206233332U (en) | A kind of drought and waterlogging racing equipment based on sponge city | |
CN207469298U (en) | Double Circle underground traffic and pipe gallery combined system | |
CN206888134U (en) | Sewage pipe picks out the underground pipe gallery structure outside corridor in corridor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190104 |
|
RJ01 | Rejection of invention patent application after publication |