CN106978820A - A kind of pipe gallery reveals water utilization system - Google Patents
A kind of pipe gallery reveals water utilization system Download PDFInfo
- Publication number
- CN106978820A CN106978820A CN201710261307.0A CN201710261307A CN106978820A CN 106978820 A CN106978820 A CN 106978820A CN 201710261307 A CN201710261307 A CN 201710261307A CN 106978820 A CN106978820 A CN 106978820A
- Authority
- CN
- China
- Prior art keywords
- water
- pipe gallery
- utilization system
- tank
- storage pond
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/12—Restraining of underground water by damming or interrupting the passage of underground water
- E02D19/20—Restraining of underground water by damming or interrupting the passage of underground water by displacing the water, e.g. by compressed air
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/10—Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- Mining & Mineral Resources (AREA)
- General Engineering & Computer Science (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Oil, Petroleum & Natural Gas (AREA)
- Chemical & Material Sciences (AREA)
- Sewage (AREA)
Abstract
The present invention relates to pipe gallery technical field, more particularly to a kind of pipe gallery leakage water utilization system.The system includes pipe gallery and storage pond, and the pipe gallery at least includes Feed Water Tank, and the Feed Water Tank bottom is provided with water leg, and the water leg is connected by drainpipe with the storage pond;Liquid level sensor and the first water pump are provided with the Feed Water Tank, the liquid level sensor is connected with the water leg, and first water pump is connected with the drainpipe.Pipe gallery of the present invention reveals water utilization system, solve and reveal shipwreck in pipe gallery Feed Water Tank to discharge, the problem of influenceing piping lane integral waterproofing performance, reduce maintainer's workload, the problem of also solving each self planning in process of construction of the city integrated piping lane with the rainwater storage in sponge city simultaneously, individually construct, pipe gallery is combined with the rainwater utilization facility of road construction, the two unified planning, design and construction, cost is reduced, the influence construction to urban road is preferably minimized.
Description
Technical field
The present invention relates to pipe gallery technical field, more particularly to a kind of pipe gallery leakage water utilization system.
Background technology
Pipe gallery is to be built in Urban Underground to accommodate two classes and above municipal pipeline in the box culvert tunnel of one.It will can give
The municipal engineering pipeline such as water, rainwater, sewage, recycled water, natural gas, heating power, electric power, communication is included, realizes planning, builds
It is unified with management three.
The processing mode of water tank ponding is to be transported to draining by conveyance conduit and connecting pipe in existing pipe gallery
Emitted in pipeline, have ignored the processing Utilizing question to piping lane internal water accumulation.On the one hand, piping lane ponding can cause ground in piping lane
Face and pipeline are soaked, and piping lane ponding is difficult to discharge, and influence piping lane waterproof, and maintainer needs manual cleaning piping lane ponding,
Maintenance and supervision to piping lane make troubles, and increase maintainer's workload;On the other hand, piping lane ponding is still in the prior art
Selection is directly discharged into sewage conduct mode and excluded, and without considering the recycling to ponding, causes the waste of resource.
The content of the invention
(1) technical problem to be solved
Water utilization system is revealed it is an object of the invention to provide a kind of pipe gallery, water tank in existing pipe gallery is solved and accumulates
Shipwreck influences piping lane waterproof, the problem of not recycled to ponding to discharge.
(2) technical scheme
In order to solve the above-mentioned technical problem, water utilization system, including synthesis are revealed the invention provides a kind of pipe gallery
Piping lane and storage pond, wherein the pipe gallery at least includes Feed Water Tank, the bottom of the Feed Water Tank is provided with water leg, the collection
Tank is connected by drainpipe with the storage pond;Liquid level sensor and the first water pump are provided with the Feed Water Tank, wherein described
Liquid level sensor is connected with the water leg, and first water pump is connected with the drainpipe.
Further, the storage pond is connected by rainwater pipeline with drip molding, and the drip molding is provided with ground rainwater mouthful.
Further, the storage pond is connected by delivery pipe with river.
Further, the bottom of the storage pond is provided with collecting-tank, and the collecting-tank is connected with the storage pond.
Specifically, the collecting-tank is connected with ground with one end of water pipe, and the other end of the ground water pipe passes through institute
Storage pond is stated to set on the ground.
Specifically, the second water pump is provided with the storage pond, second water pump is connected with the ground with water pipe.
Further, the pipe gallery also includes bilge tank, telecommunications cabin and combustion gas cabin.
Specifically, the bottom section of the bilge tank is using ellipse.
Specifically, illumination dress is respectively equipped with the Feed Water Tank, the bilge tank, the telecommunications cabin and the combustion gas cabin
Put.
Specifically, be additionally provided with controller in the Feed Water Tank, the controller respectively with the liquid level sensor, described
One water pump is connected.
(3) beneficial effect
The above-mentioned technical proposal of the present invention has the following advantages that:
Pipe gallery of the present invention reveals water utilization system, is catchmented by being set in the Feed Water Tank of pipe gallery
Groove, the ponding revealed for storing in Feed Water Tank by setting liquid level sensor and the first water pump in Feed Water Tank, and will catchment
Groove is connected by drainpipe with storage pond, is just led to ponding by the first water pump when the ponding in water leg is stored into certain altitude
Cross drainpipe conveying and be discharged into storage pond.This structure type, solves and reveals shipwreck in pipe gallery Feed Water Tank to discharge, influence
The problem of piping lane integral waterproofing performance, while reducing maintainer's workload, the integrality and water proofing property of Pipe rack are kept,
Take full advantage of the space inside piping lane.
Pipe gallery of the present invention reveals water utilization system, and the Feed Water Tank of pipe gallery is combined with storage pond,
The problem of solving each self planning in process of construction of the city integrated piping lane with the rainwater storage in sponge city, individually construct, will
Pipe gallery is combined construction with the rainwater utilization facility of road construction, is accomplished the two unified planning, design and is constructed, reduces into
Influence of this while construction to urban road is preferably minimized.
Brief description of the drawings
Fig. 1 is pipe gallery of embodiment of the present invention leakage water utilization system structure chart.
In figure:1:Feed Water Tank;2:Bilge tank;3:Telecommunications cabin;4:Combustion gas cabin;5:Ground rainwater mouthful;6:Storage pond;7:Catchment
Pond;8:Water leg;9:Liquid level sensor;10:First water pump;11:Drip molding;12:Drainpipe;13:Rainwater pipeline;14:Ground
Use water pipe;15:Lighting device.
Embodiment
To make the purpose, technical scheme and advantage of the embodiment of the present invention clearer, below in conjunction with the embodiment of the present invention
In accompanying drawing, the technical scheme in the embodiment of the present invention is clearly and completely described, it is clear that described embodiment is
A part of embodiment of the present invention, rather than whole embodiments.Based on the embodiment in the present invention, ordinary skill people
The every other embodiment that member is obtained on the premise of creative work is not made, belongs to the scope of protection of the invention.
As shown in figure 1, a kind of pipe gallery leakage water utilization system provided in an embodiment of the present invention, including pipe gallery and
Storage pond 6, wherein the pipe gallery includes separate Feed Water Tank 1, bilge tank 2, telecommunications cabin 3 and combustion gas cabin 4, wherein institute
Stating Feed Water Tank 1 is used to accommodate water-supply line, middle water line and other pipelines, and the bilge tank 2 is used to accommodate sewage or sewage pipe
Line, the telecommunications cabin 3 is used to accommodate the electric power telecommunication line being independent of each other, and the combustion gas cabin 4 is used to accommodate burning line.
Wherein, the bottom of the Feed Water Tank 1 is provided with water leg 8, and the water leg 8 is used to collect in storage Feed Water Tank 1
Water is revealed, the water leg 8 is connected by drainpipe 12 with the storage pond 6.Level sensing is additionally provided with the Feed Water Tank 1
Device 9, the first water pump 10 and controller (not shown), the liquid level sensor 9 are connected with the water leg 8, first water
Pump 10 is connected with the drainpipe 12, and the controller is connected with the liquid level sensor 9, first water pump 10 respectively.
In the present embodiment, the liquid level sensor 9 and first water pump 10 are arranged in the water leg 8, pass through the liquid level
Sensor 9 senses the height of water level of ponding in the water leg 8, by first water pump 10 by the product in the water leg 8
Water is discharged into the storage pond 6 through the drainpipe 12.
Specifically, the storage pond 6 is connected by rainwater pipeline 13 with drip molding 11, and the drip molding 11 is provided with ground
Face inlet for stom water 5, the rainwater from ground rainwater mouthful 5 is stored by the storage pond 6.
Specifically, the storage pond 6 is connected by delivery pipe (not shown) with river, when the water of storage pond 6 is full,
Then by the discharged into neighbouring river.
Specifically, the bottom of the storage pond 6 is provided with collecting-tank 7, and the collecting-tank 7 is connected with the storage pond 6.
Wherein, the collecting-tank 7 is connected with ground with one end of water pipe 14, and the other end of the ground water pipe 14 is regulated and stored through described
Pond 6 is set on the ground.The second water pump (not shown), second water pump and the ground are provided with the storage pond 6
It is connected with water pipe 14.In the presence of second water pump, the reclaimed water of storage pond 6 is promoted to ground, by described
Face the upper end linking-up road sprinkling of water pipe 14 or rainer, so as to the water of the storage pond 6 be recycled, for ground
Face pour spill with greening etc..
In addition, the bottom section of the bilge tank 2 is using ellipse, this structure is difficult silting impurity.
In addition, being respectively equipped with illumination dress in the Feed Water Tank 1, the bilge tank 2, the telecommunications cabin 3 and the combustion gas cabin 4
15 are put, easy access personnel carry out repair and maintenance in each cabin of pipe gallery.
The operation principle of pipe gallery leakage water utilization system is described in the embodiment of the present invention:
During rainfall, rainwater is flowed into drip molding 11 by the ground rainwater mouthful 5 of both sides of the road, then is flowed by rainwater pipeline 13
Enter into storage pond 6, when rainfall is small, the storage pond 6 can store whole waters, when rainfall is big, the water of storage pond 6
It is full, then rainwater is drained into river nearby by delivery pipe.
When there is leakage water in Feed Water Tank 1, it is collected by water leg 8, when the ponding in water leg 8 rises to certain height
When spending, liquid level sensor 9 is triggered, liquid level sensor 9 can send induced signal to controller, and controller controls the first water pump 10
Ponding is drained into storage pond 6 by drainpipe 12, and the water in the storage pond 6 can be with the second water pump through ground water
Pipe 14 is promoted to ground, spill and afforest for pouring etc., so as to realize the recycling that water is revealed in Feed Water Tank 1.
In summary, the pipe gallery leakage water utilization system described in the embodiment of the present invention, by easily occurring in piping lane
Water leg is set in the Feed Water Tank of water leakage phenomenon, in the case where not increasing piping lane quantities and worker workload, increased
The strong water resistance of piping lane, improves structure and the security of management.Ponding of the invention without in artificial cleaning water tank,
Laying for other pipelines is not influenceed simultaneously, by setting liquid level sensor, the first water pump of high pressure and drainpipe by water leg
Ponding be discharged into storage pond, to recycle, solve current composite piping lane and leakage shipwreck be set to discharge the disadvantage of disposal
End.
The present invention builds pipe gallery with the rainwater storage in sponge city jointly, and ponding unnecessary in Feed Water Tank is arranged
Enter storage pond, recycled together with unnecessary rainwater.Compared with the pipe gallery system of prior art, the present invention is in reduction
While cost, with good environmental benefit and economic benefit, and engineering application value well.
Pipe gallery leakage water utilization system described in the embodiment of the present invention, pipe gallery system compared with prior art and
Speech, it is more reasonable to design, and storage pond is set by ground rainwater mouthful and piping lane, ground rainwater is collected, piping lane ponding is collected and mutually tied
Close, when carrying out draining, rainwater is regulated and stored by storage pond, collect part rainwater and carry out reuse utilization, water of regulating and storing is expired
When discharge in time, so as to reduce the generation of waterlogging.
The present invention influence of reduction to environment while underground space utilization ratio is improved, reduces flood incidence,
Flood disaster risk is reduced, while having carried out reuse utilization to ponding and rainwater, load of the runoff pollution with water supply plant is reduced.
Finally it should be noted that:The above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although
The present invention is described in detail with reference to the foregoing embodiments, it will be understood by those within the art that:It still may be used
To be modified to the technical scheme described in foregoing embodiments, or equivalent substitution is carried out to which part technical characteristic;
And these modification or replace, do not make appropriate technical solution essence depart from various embodiments of the present invention technical scheme spirit and
Scope.
Claims (10)
1. a kind of pipe gallery reveals water utilization system, it is characterised in that:Including pipe gallery and storage pond, wherein the synthesis
Piping lane at least includes Feed Water Tank, and the bottom of the Feed Water Tank is provided with water leg, and the water leg is regulated and stored by drainpipe with described
Pond is connected;Liquid level sensor and the first water pump are provided with the Feed Water Tank, wherein the liquid level sensor and the water leg phase
Even, first water pump is connected with the drainpipe.
2. pipe gallery according to claim 1 reveals water utilization system, it is characterised in that:The storage pond passes through rainwater
Pipeline is connected with drip molding, and the drip molding is provided with ground rainwater mouthful.
3. pipe gallery according to claim 1 reveals water utilization system, it is characterised in that:The storage pond passes through discharge
Pipe is connected with river.
4. pipe gallery according to claim 1 reveals water utilization system, it is characterised in that:The bottom of the storage pond is set
There is collecting-tank, the collecting-tank is connected with the storage pond.
5. pipe gallery according to claim 4 reveals water utilization system, it is characterised in that:The collecting-tank is used with ground
One end of water pipe is connected, and the other end of the ground water pipe is set on the ground through the storage pond.
6. pipe gallery according to claim 5 reveals water utilization system, it is characterised in that:Provided with the in the storage pond
Two water pumps, second water pump is connected with the ground with water pipe.
7. pipe gallery according to claim 1 reveals water utilization system, it is characterised in that:The pipe gallery also includes
Bilge tank, telecommunications cabin and combustion gas cabin.
8. pipe gallery according to claim 7 reveals water utilization system, it is characterised in that:The bottom of the bilge tank is cut
Face is using ellipse.
9. pipe gallery according to claim 7 reveals water utilization system, it is characterised in that:The Feed Water Tank, the dirt
Lighting device is respectively equipped with water tank, the telecommunications cabin and the combustion gas cabin.
10. pipe gallery according to claim 1 reveals water utilization system, it is characterised in that:Also set in the Feed Water Tank
There is controller, the controller is connected with the liquid level sensor, first water pump respectively.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710261307.0A CN106978820A (en) | 2017-04-20 | 2017-04-20 | A kind of pipe gallery reveals water utilization system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710261307.0A CN106978820A (en) | 2017-04-20 | 2017-04-20 | A kind of pipe gallery reveals water utilization system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106978820A true CN106978820A (en) | 2017-07-25 |
Family
ID=59346101
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710261307.0A Pending CN106978820A (en) | 2017-04-20 | 2017-04-20 | A kind of pipe gallery reveals water utilization system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106978820A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108107236A (en) * | 2017-12-06 | 2018-06-01 | 国网宁夏电力有限公司宁东供电公司 | A kind of cable duct intelligent acquisition unit protection babinet |
CN111608228A (en) * | 2020-04-16 | 2020-09-01 | 中国一冶集团有限公司 | Sponge city and utility tunnel integration system |
CN112459111A (en) * | 2020-10-27 | 2021-03-09 | 江苏旭松建设工程有限公司 | Pipe gallery protection device based on sponge city and construction method thereof |
CN113863373A (en) * | 2021-10-29 | 2021-12-31 | 浙江华东测绘与工程安全技术有限公司 | Novel utility tunnel structure |
CN115059116A (en) * | 2022-07-05 | 2022-09-16 | 济南市市政工程设计研究院(集团)有限责任公司 | Pipe gallery drainage system capable of being rapidly transformed and drainage method |
CN116122331A (en) * | 2023-02-17 | 2023-05-16 | 北京市水利规划设计研究院 | Utility tunnel |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07133631A (en) * | 1993-11-10 | 1995-05-23 | Shigeo Morimoto | Block for common channel and side channel |
CN202117066U (en) * | 2011-06-22 | 2012-01-18 | 天津华津制药有限公司 | Automatic discharging system for underground water |
CN103953068A (en) * | 2014-05-19 | 2014-07-30 | 上海市城市建设设计研究总院 | Underground integrated pipe gallery structure |
CN204491665U (en) * | 2015-02-03 | 2015-07-22 | 张楸长 | Prestressed structure expanded type underground pipe gallery combined system |
CN205348223U (en) * | 2016-01-12 | 2016-06-29 | 上海市城市建设设计研究总院 | Node structure of being connected control center and two cabin utility tunnel |
CN105951879A (en) * | 2016-07-05 | 2016-09-21 | 宏大国源(芜湖)资源环境治理有限公司 | Comprehensive pipe rack structure |
CN205688460U (en) * | 2016-06-23 | 2016-11-16 | 上海市城市建设设计研究总院 | Pipe gallery system with sponge city function |
CN205712417U (en) * | 2016-03-01 | 2016-11-23 | 上海市政工程设计研究总院(集团)有限公司 | A kind of rainwater-collecting being applied to pipe gallery is regulated and stored device |
CN106400839A (en) * | 2016-12-02 | 2017-02-15 | 中冶京诚工程技术有限公司 | Natural gas cabin of utility tunnel |
-
2017
- 2017-04-20 CN CN201710261307.0A patent/CN106978820A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07133631A (en) * | 1993-11-10 | 1995-05-23 | Shigeo Morimoto | Block for common channel and side channel |
CN202117066U (en) * | 2011-06-22 | 2012-01-18 | 天津华津制药有限公司 | Automatic discharging system for underground water |
CN103953068A (en) * | 2014-05-19 | 2014-07-30 | 上海市城市建设设计研究总院 | Underground integrated pipe gallery structure |
CN204491665U (en) * | 2015-02-03 | 2015-07-22 | 张楸长 | Prestressed structure expanded type underground pipe gallery combined system |
CN205348223U (en) * | 2016-01-12 | 2016-06-29 | 上海市城市建设设计研究总院 | Node structure of being connected control center and two cabin utility tunnel |
CN205712417U (en) * | 2016-03-01 | 2016-11-23 | 上海市政工程设计研究总院(集团)有限公司 | A kind of rainwater-collecting being applied to pipe gallery is regulated and stored device |
CN205688460U (en) * | 2016-06-23 | 2016-11-16 | 上海市城市建设设计研究总院 | Pipe gallery system with sponge city function |
CN105951879A (en) * | 2016-07-05 | 2016-09-21 | 宏大国源(芜湖)资源环境治理有限公司 | Comprehensive pipe rack structure |
CN106400839A (en) * | 2016-12-02 | 2017-02-15 | 中冶京诚工程技术有限公司 | Natural gas cabin of utility tunnel |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108107236A (en) * | 2017-12-06 | 2018-06-01 | 国网宁夏电力有限公司宁东供电公司 | A kind of cable duct intelligent acquisition unit protection babinet |
CN111608228A (en) * | 2020-04-16 | 2020-09-01 | 中国一冶集团有限公司 | Sponge city and utility tunnel integration system |
CN112459111A (en) * | 2020-10-27 | 2021-03-09 | 江苏旭松建设工程有限公司 | Pipe gallery protection device based on sponge city and construction method thereof |
CN113863373A (en) * | 2021-10-29 | 2021-12-31 | 浙江华东测绘与工程安全技术有限公司 | Novel utility tunnel structure |
CN115059116A (en) * | 2022-07-05 | 2022-09-16 | 济南市市政工程设计研究院(集团)有限责任公司 | Pipe gallery drainage system capable of being rapidly transformed and drainage method |
CN115059116B (en) * | 2022-07-05 | 2023-11-24 | 济南市市政工程设计研究院(集团)有限责任公司 | Pipe gallery drainage system capable of being quickly modified and drainage method |
CN116122331A (en) * | 2023-02-17 | 2023-05-16 | 北京市水利规划设计研究院 | Utility tunnel |
CN116122331B (en) * | 2023-02-17 | 2023-08-11 | 北京市水利规划设计研究院 | Utility tunnel |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106978820A (en) | A kind of pipe gallery reveals water utilization system | |
CN106638681B (en) | A kind of pipe gallery | |
CN204001088U (en) | A kind of building rainwater and daily life sewage intermediate water reuse system | |
CN206143897U (en) | Multi -functional rainwater is collected and is handled recycling system | |
CN107630464A (en) | Rainwater-collecting is regulated and stored and the pipe gallery of preliminary purification function | |
CN202227456U (en) | Rainwater collection and recycling system for environment-friendly transformer station | |
CN112681375A (en) | Utility tunnel with rainwater regulation function | |
CN104790516B (en) | A kind of rainwater regulating pondage system | |
CN205024802U (en) | Energy -saving rainwater recycling system | |
CN207211190U (en) | A kind of pipe gallery | |
CN206368389U (en) | One kind backwash and sewage sucking system | |
CN103161192B (en) | A kind of Power-free rainwater collection device | |
CN101519885B (en) | Method for synthetically utilizing concrete curing water and rain water in constructional engineering | |
CN207062994U (en) | A kind of Urban Storm Flood joint utilizes system | |
CN208578071U (en) | A kind of underground pipe gallery structure that band rain sewage becomes a mandarin | |
CN115726430A (en) | Building site rainwater waste water recovery system | |
CN207597427U (en) | Rainwater-collecting is regulated and stored and the pipe gallery of preliminary purification function | |
CN209099505U (en) | A kind of rainwater utilization system based on municipal storm sewer | |
CN211685016U (en) | Foundation pit underground water utilization system | |
CN209636899U (en) | Substation's rain reclamation and treatment system | |
CN106759763A (en) | A kind of urban rainwater accumulates and utilization system naturally | |
CN205224231U (en) | Urban rainwater store up naturally with comprehensive utilization system | |
CN206233332U (en) | A kind of drought and waterlogging racing equipment based on sponge city | |
CN207988089U (en) | A kind of rain water collecting system and rainwater recycle recycle equipment | |
CN206396786U (en) | Suitable for the pipe gallery section structure of area of heavy rainfull |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170725 |
|
RJ01 | Rejection of invention patent application after publication |