CN109083125A - Temporary drainage ditch construction method under the conditions of a kind of subgrade - Google Patents

Temporary drainage ditch construction method under the conditions of a kind of subgrade Download PDF

Info

Publication number
CN109083125A
CN109083125A CN201810789746.3A CN201810789746A CN109083125A CN 109083125 A CN109083125 A CN 109083125A CN 201810789746 A CN201810789746 A CN 201810789746A CN 109083125 A CN109083125 A CN 109083125A
Authority
CN
China
Prior art keywords
prefabricated
side plate
conditions
construction method
method under
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810789746.3A
Other languages
Chinese (zh)
Inventor
唐益辉
柳建国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201810789746.3A priority Critical patent/CN109083125A/en
Publication of CN109083125A publication Critical patent/CN109083125A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains

Abstract

Temporary drainage ditch construction method under the conditions of a kind of subgrade.Temporary drainage ditch construction method under the conditions of a kind of subgrade, comprising: A, the prefabricated panel and prefabricated side plate for making temporary drain respectively, the prefabricated panel and the prefabricated side plate are respectively equipped with hoisting ring;B, temporary drain, hoisting prefabricated bottom plate and prefabricated side plate are excavated;C, attachment beam is installed, which connect with the prefabricated side plate top of prefabricated panel two sides respectively, and prefabricated side plate top has connection ring corresponding with the attachment beam;D, using cement mortar sealing prefabricated panel and the junction of prefabricated side plate, the junction of prefabricated panel and prefabricated panel, prefabricated side plate and prefabricated side plate junction.In the present invention, serial pre-fabrication or factory prefabricated panel and the prefabricated side plate with hoisting ring can be manufactured at the scene, on-site assembly prefabricated panel and the prefabricated side plate after excavating temporary drain, interval conserves without plastering.

Description

Temporary drainage ditch construction method under the conditions of a kind of subgrade
Technical field
The present invention relates to temporary drainage ditch construction methods under the conditions of temporary drain field more particularly to a kind of subgrade.
Background technique
Under the conditions of subgrade, because of the low-intensity of weak soil, high-moisture percentage, high-compressibility, settling amount is big and differential settlement Speed is big, and duration of settlement is long, so being unable to satisfy site operation requirement using direct ditching draining or conventional brick gutter, opens Shoveling body sidewall can not support oneself, and substrate is easily settled, and gutter easily avalanche plug becomes silted up.
Under the conditions of subgrade, traditional masonry cement brick or shale brick gutter can not be used because substrate is too soft, and build Building gutter and will lead to brick can not recycle, and waste mortar;It needs to plaster after the completion of building, conserve, the technology intermission time It is long.
Summary of the invention
The technical problem to be solved in the present invention provides one kind and is suitable under the conditions of subgrade, in place, foundation trench and foundation pit Bright water carry out the method that concrete prefabricated element composable, reusable when Artesian Drainage carries out temporary drain construction.
In order to solve the above technical problems, the present invention is the following technical schemes are provided: temporary drain under the conditions of a kind of subgrade Construction method, comprising: A, the prefabricated panel and prefabricated side plate for making temporary drain respectively, the prefabricated panel and the prefabricated side plate It is respectively equipped with hoisting ring;B, temporary drain, hoisting prefabricated bottom plate and prefabricated side plate are excavated;C, attachment beam, the attachment beam are installed Both ends are connect with the prefabricated side plate top of prefabricated panel two sides respectively, and prefabricated side plate top has connection corresponding with the attachment beam Ring;D, using cement mortar sealing prefabricated panel and the junction of prefabricated side plate, the junction, pre- of prefabricated panel and prefabricated panel The junction of side plate processed and prefabricated side plate.
As a further improvement of the present invention, the method also includes after the step D: E, cutting cement bonded sand Starch, release the connection of the attachment beam Yu the connection ring;F, prefabricated panel and prefabricated side plate are removed in lifting.
As a further improvement of the present invention, the length of the prefabricated panel or prefabricated side plate is between 1.0m~1.5m.
As a further improvement of the present invention, the width of the prefabricated panel or prefabricated side plate is between 0.6m~1.0m.
As a further improvement of the present invention, the prefabricated panel or prefabricated side plate with a thickness of between 35mm~45mm.
As a further improvement of the present invention, the prefabricated panel or the interior of prefabricated side plate are equipped with single-layer bidirectional steel mesh.
As a further improvement of the present invention, the single-layer bidirectional steel mesh by spacing 150mm diameter 8mm reinforcing bar in length and breadth Rearrange,
As a further improvement of the present invention, the connection ring and the hoisting ring and the single-layer bidirectional steel mesh weld It is fixed.
As a further improvement of the present invention, the prefabricated panel or prefabricated side plate are made of pea gravel concreten.
As a further improvement of the present invention, the step B includes: between adjacent prefabricated panel and prefabricated panel or adjacent Prefabricated side plate and prefabricated side sheet room have the lap of splice.
In the present invention, serial pre-fabrication or factory prefabricated panel and the prefabricated side with hoisting ring can be manufactured at the scene Plate, on-site assembly prefabricated panel and the prefabricated side plate after excavating temporary drain, without plastering, interval is conserved, speed of application Fastly, prefabricated panel and the prefabricated side plate be not by software impact.
The present invention has light weight, thickness thin, and intensity height etc. a little, when not needing gutter, can directly pass through lifting Ring 3 is hung, and is reused.More save material in gutter more brick than tradition.
Detailed description of the invention
Attached drawing 1 is the structural schematic diagram of the temporary drain of first embodiment of the invention.
Attached drawing 2 is the structural schematic diagram of the prefabricated components of the temporary drain of Fig. 1.
Attached drawing 3 is the steel bar arrangement figure of the prefabricated components of Fig. 2.
Attached drawing 4 is the structure chart of the prefabricated components of Fig. 2.
Specific embodiment
It is of the invention to reach the technical means and efficacy that predetermined goal of the invention is taken further to illustrate, below in conjunction with Attached drawing and preferred embodiment, to specific embodiment, structure, feature and its effect is proposed according to the present invention, detailed description is as follows.
Referring to Figure 1 to Fig. 4, temporary drainage ditch construction method under the conditions of the subgrade of first embodiment of the invention, comprising:
A, according to live gutter design section size or digging machine bucket excavation width, 1 length and width dimensions of prefabricated components are determined. Prefabricated components 1 include prefabricated panel 1a and prefabricated side plate 1b, prefabricated panel 1a and prefabricated side plate 1b can in-situ precast or factory batch It measures prefabricated, makes the prefabricated panel 1a and prefabricated side plate 1b, prefabricated panel 1a and the prefabricated side plate 1b of temporary drain respectively It is respectively equipped with hoisting ring 3;Hoisting ring 3 moves back 100mm in prefabricated panel 1a and the prefabricated every side edge of side plate 1b, and hoisting ring 3 is adopted It is bent with the hoisting ring 3 of 8mm diameter.
B, excavate temporary drain, stay set drainage grade as required, and clear up substrate and side wall, hoisting prefabricated bottom plate 1a and Prefabricated side plate 1b,;
C, attachment beam 5 is installed, which connect with the top prefabricated side plate 1b of the two sides prefabricated panel 1a respectively, The top prefabricated side plate 1b has connection ring 4 corresponding with the attachment beam 5, and connection ring 4 can also be used as lifting and use;
D, using junction, prefabricated panel 1a and the prefabricated panel of cement mortar sealing prefabricated panel 1a and prefabricated side plate 1b The junction of 1a, prefabricated side plate 1b and prefabricated side plate 1b junction.
Preferred method further includes after step D:
E, the connection for cutting cement mortar, releasing attachment beam 5 and connection ring 4;
F, prefabricated panel 1a and prefabricated side plate 1b is removed in lifting.
It is preferred that step B include: between adjacent prefabricated panel 1a and prefabricated panel 1a or adjacent prefabricated side plate 1b and pre- There is the lap of splice between side plate 1b processed.
The length of prefabricated panel 1a or prefabricated side plate 1b are between 1.0m~1.5m, and width is between 0.6m~1.0m, in advance Bottom plate 1a processed or prefabricated side plate 1b with a thickness of between 35mm~45mm, preferred thickness uses 40mm.
The interior of prefabricated panel 1a or prefabricated side plate 1b is equipped with single-layer bidirectional steel mesh 2.Single-layer bidirectional steel mesh 2 is by spacing The reinforcing bar of 150mm diameter 8mm rearranges in length and breadth.Single-layer bidirectional steel mesh 2 is preferably rearranged using grade III steel in length and breadth.
Connection ring 4 and hoisting ring 3 are welded and fixed with single-layer bidirectional steel mesh 2.Prefabricated panel 1a or prefabricated side plate 1b are by thin Stone concrete is made.It is preferred that using C20 or more pea gravel concreten.In the present invention, it serial pre-fabrication or factory can manufacture at the scene Prefabricated panel 1a with the hoisting ring 3 and prefabricated side plate 1b, after excavating temporary drain on-site assembly prefabricated panel 1a with The prefabricated side plate 1b, without plastering, interval is conserved, and speed of application is fast, and prefabricated panel 1a and the prefabricated side plate 1b be not by software shadow It rings.
Prefabricated panel 1a of the invention and prefabricated side plate 1b has light weight, thickness thin, and intensity height etc. a little, is not needing When gutter, it can directly be hung, be reused by hoisting ring 3.More save material in gutter more brick than tradition.
Under the conditions of subgrade, southern summer, rainy season can Quick drainage using the present invention.The present invention is in settlement of foundation Afterwards, ditch body deforms, and passes through hoisting prefabricated bottom plate 1a and prefabricated side plate 1b;Temporary drain can be repaired, maintenance cost is low.
Under the conditions of subgrade, after gutter is excavated, it is laid with bottom and side wall with this component in time, bottom plate and side plate use Cement mortar sits slurry connection, prevents wall deformation from caving in, and substrate is soaked to wait adverse effect.Bottom plate is identical as component used in side wall, Adjacent panels overlap 100mm when laying, guarantee that, when gutter bottom or side wall deform, ditch body is still able to maintain completely.Side The soil body tilts 10~20 degree to plate outward, then fixed with attachment beam 5.
This component uses C20 or more concrete grade, interior to match 8@of φ, 150 single-layer bidirectional reinforcing bar, and 100mm setting is moved back in edge Two 8 reinforcing bar hoisting rings 3 of φ, intensity and rigidity of above design based on 1, guarantee material, because of the moisture absorption of GRC concrete Property, so the present invention is prefabricated using normal concrete;2,100mm setting hoisting ring 3 is moved back in edge, and for a, sedimentation and deformation occurs When needing to modify gutter, convenient in carrying;B, it is used as inner support positioning and fixing;C, it is positioned when as side plate with bottom plate assembly And it is fixed use, do not allow in side plate and move or sidesway;D, in the case where no outside soil body can be with fixed side panel, hoisting ring 3 can be made For binding and fixing use, fixed point is beaten in draining furrow rim, with iron wire and 3 drawknot of hoisting ring, 3 drawknot of opposite hoisting ring of inside two. 3, bottom plate and side plate are sat slurry using cement mortar and are connected, and can guarantee the overall stiffness in gutter, and guarantee that gutter is water-tight.
More than, it is only presently preferred embodiments of the present invention, is not intended to limit the present invention in any form, although this Invention has been disclosed in a preferred embodiment above, and however, it is not intended to limit the invention, any person skilled in the art, It does not depart within the scope of technical solution of the present invention, when the technology contents using the disclosure above make a little change or are modified to equivalent The equivalent embodiment of variation, but without departing from the technical solutions of the present invention, according to the technical essence of the invention to the above reality Any simple modification, equivalent variations and modification made by example are applied, all of which are still within the scope of the technical scheme of the invention.

Claims (10)

1. temporary drainage ditch construction method under the conditions of a kind of subgrade characterized by comprising
A, the prefabricated panel and prefabricated side plate of temporary drain are made respectively, and the prefabricated panel and the prefabricated side plate, which are respectively equipped with, to be hung Fill ring;
B, temporary drain, hoisting prefabricated bottom plate and prefabricated side plate are excavated;
C, attachment beam is installed, which connect with the prefabricated side plate top of prefabricated panel two sides respectively, on prefabricated side plate Portion has connection ring corresponding with the attachment beam;
D, using cement mortar sealing prefabricated panel and the junction of prefabricated side plate, prefabricated panel and prefabricated panel junction, The junction of prefabricated side plate and prefabricated side plate.
2. temporary drainage ditch construction method under the conditions of subgrade according to claim 1, which is characterized in that the method is also Including after the step D:
E, the connection for cutting cement mortar, releasing the attachment beam and the connection ring;
F, prefabricated panel and prefabricated side plate are removed in lifting.
3. temporary drainage ditch construction method under the conditions of subgrade according to claim 1, which is characterized in that the prefabricated bottom The length of plate or prefabricated side plate is between 1.0m~1.5m.
4. temporary drainage ditch construction method under the conditions of subgrade according to claim 1, which is characterized in that the prefabricated bottom The width of plate or prefabricated side plate is between 0.6m~1.0m.
5. temporary drainage ditch construction method under the conditions of subgrade according to claim 1, which is characterized in that the prefabricated bottom Plate or prefabricated side plate with a thickness of between 35mm~45mm.
6. temporary drainage ditch construction method under the conditions of subgrade according to claim 1, which is characterized in that the prefabricated bottom Plate or the interior of prefabricated side plate are equipped with single-layer bidirectional steel mesh.
7. temporary drainage ditch construction method under the conditions of subgrade according to claim 6, which is characterized in that the single layer is double It is rearranged in length and breadth to steel mesh by the reinforcing bar of spacing 150mm diameter 8mm.
8. temporary drainage ditch construction method under the conditions of subgrade according to claim 6, which is characterized in that the connection ring It is welded and fixed with the hoisting ring and the single-layer bidirectional steel mesh.
9. temporary drainage ditch construction method under the conditions of subgrade according to claim 1, which is characterized in that the prefabricated bottom Plate or prefabricated side plate are made of pea gravel concreten.
10. temporary drainage ditch construction method under the conditions of subgrade according to claim 1, which is characterized in that the step B It include: between adjacent prefabricated panel and prefabricated panel or adjacent prefabricated side plate and prefabricated side sheet room have the lap of splice.
CN201810789746.3A 2018-07-18 2018-07-18 Temporary drainage ditch construction method under the conditions of a kind of subgrade Pending CN109083125A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810789746.3A CN109083125A (en) 2018-07-18 2018-07-18 Temporary drainage ditch construction method under the conditions of a kind of subgrade

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810789746.3A CN109083125A (en) 2018-07-18 2018-07-18 Temporary drainage ditch construction method under the conditions of a kind of subgrade

Publications (1)

Publication Number Publication Date
CN109083125A true CN109083125A (en) 2018-12-25

Family

ID=64837735

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810789746.3A Pending CN109083125A (en) 2018-07-18 2018-07-18 Temporary drainage ditch construction method under the conditions of a kind of subgrade

Country Status (1)

Country Link
CN (1) CN109083125A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109944133A (en) * 2019-03-06 2019-06-28 中国建筑西北设计研究院有限公司 A kind of prefabricated assembled component of mountainous region photovoltaic project road draining device

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200361653Y1 (en) * 2004-06-09 2004-09-14 박영수 Structure thing for water pipe
CN2644504Y (en) * 2003-09-25 2004-09-29 范云聪 Ditch sheet material
CN2905894Y (en) * 2006-04-30 2007-05-30 范云聪 Concrete prefabricated groove
CN103620120A (en) * 2011-06-30 2014-03-05 李礼顺 Prefabricated drain structure
CN205296349U (en) * 2016-01-19 2016-06-08 中建四局第三建筑工程有限公司 Can assemble dismountable escape canal of having enough to meet need use
CN207062686U (en) * 2017-08-12 2018-03-02 常州市市政工程设计研究院有限公司 Precast assembly concrete saucer type gutter

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2644504Y (en) * 2003-09-25 2004-09-29 范云聪 Ditch sheet material
KR200361653Y1 (en) * 2004-06-09 2004-09-14 박영수 Structure thing for water pipe
CN2905894Y (en) * 2006-04-30 2007-05-30 范云聪 Concrete prefabricated groove
CN103620120A (en) * 2011-06-30 2014-03-05 李礼顺 Prefabricated drain structure
CN205296349U (en) * 2016-01-19 2016-06-08 中建四局第三建筑工程有限公司 Can assemble dismountable escape canal of having enough to meet need use
CN207062686U (en) * 2017-08-12 2018-03-02 常州市市政工程设计研究院有限公司 Precast assembly concrete saucer type gutter

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《水利水电工程施工实用手册》编委会: "《钢筋工程施工》", 31 December 2017, 中国环境出版集团 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109944133A (en) * 2019-03-06 2019-06-28 中国建筑西北设计研究院有限公司 A kind of prefabricated assembled component of mountainous region photovoltaic project road draining device

Similar Documents

Publication Publication Date Title
CN109630127B (en) Construction method of ultra-deep shield vertical shaft for water-rich weak stratum
CN105002931B (en) The two-way Precast Concrete Segmental Bridges construction method of a kind of large scale underpass
CN109026064B (en) Construction method for large-span multi-arch tunnel with semi-bright and semi-dark
CN104805866A (en) Prefabricated comprehensive pipe gallery and construction method
CN102444143B (en) Construction method for cancelling operation channel for facades of basement
CN107012871B (en) A kind of suspension type goes along with sb. to guard him the deep reversed construction method for greatly enhancing foundation pit fabricated construction
CN106759384A (en) A kind of method that use prefabricated pipeline base plate does Brace in Deep Footing Groove
CN204753627U (en) Prefabricated comprehensive piping lane
CN108035379B (en) Comprehensive pipe gallery and construction method thereof
CN110468938A (en) A kind of municipal drain pipeline construction method
CN114411756A (en) Construction method and construction device for water-rich sand layer subway station open excavation foundation pit without precipitation
CN103306497B (en) Shock prevention and strengthening construction method for existing brickwork dwelling house fabricated structure
CN109898556A (en) A kind of underground pipe gallery structure and sunk type construction method
CN111305218A (en) Construction method for foundation pit excavation
CN109083125A (en) Temporary drainage ditch construction method under the conditions of a kind of subgrade
CN110117959B (en) Construction method for foundation pit support near river
CN104846837B (en) The construction method of ultra-deep well in a kind of bright draining foundation ditch
CN207727603U (en) Big cushion cap deep basal pit formwork supporting system
CN105926665A (en) Large block assembled type prefabricated concrete drainage pipeline base and construction method thereof
CN106988337B (en) It is a kind of for reducing the reinforcement means of bar shaped shallow foundation house differential settlement
CN114922195A (en) Construction method of soft soil deep and large foundation pit adjacent to protected object
CN211421139U (en) Shield constructs well crown beam bearing structure
AU2020100004A4 (en) A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method
CN110093945B (en) Pit with elevator steel structure
CN113818482A (en) New and old pipe gallery connecting method for reducing uneven settlement

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181225