CN109057385A - Engineering method is repaired in the fixed pin part slip casting of inlet of a kind of hollowing inner-outer wall ceramic tile, stone material - Google Patents

Engineering method is repaired in the fixed pin part slip casting of inlet of a kind of hollowing inner-outer wall ceramic tile, stone material Download PDF

Info

Publication number
CN109057385A
CN109057385A CN201810524496.0A CN201810524496A CN109057385A CN 109057385 A CN109057385 A CN 109057385A CN 201810524496 A CN201810524496 A CN 201810524496A CN 109057385 A CN109057385 A CN 109057385A
Authority
CN
China
Prior art keywords
fixed pin
inlet
hollowing
inlet fixed
slip casting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810524496.0A
Other languages
Chinese (zh)
Other versions
CN109057385B (en
Inventor
杨雨奕
缪德忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Tianbu Technology Co.,Ltd.
Original Assignee
Shanghai State Mstar Technology Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai State Mstar Technology Ltd filed Critical Shanghai State Mstar Technology Ltd
Priority to CN201810524496.0A priority Critical patent/CN109057385B/en
Publication of CN109057385A publication Critical patent/CN109057385A/en
Application granted granted Critical
Publication of CN109057385B publication Critical patent/CN109057385B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0203Arrangements for filling cracks or cavities in building constructions
    • E04G23/0207Arrangements for filling cracks or cavities in building constructions in hollow structures, e.g. cavity walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0203Arrangements for filling cracks or cavities in building constructions
    • E04G23/0211Arrangements for filling cracks or cavities in building constructions using injection
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/24Structural elements or technologies for improving thermal insulation
    • Y02A30/244Structural elements or technologies for improving thermal insulation using natural or recycled building materials, e.g. straw, wool, clay or used tires

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Finishing Walls (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

Engineering method is repaired in a kind of fixed pin part slip casting of the inlet of hollowing outdoor tile disclosed by the invention, includes the following steps: (1) hollowing checking step;(2) inlet fixed pin length selectes step;(3) inlet fixed pin number configuration diagram determines step;(4) drill process;(5) inlet fixed pin installation steps;(6) inlet fixed pin slip casting step;(7) slip casting curing step;(8) sealing treatment step;(9) checking step is injected.The present invention is compared with existing ceramic tile, stone material hollowing repair engineering method, make ceramic tile, stone material hollowing be converted into cladding compound bar planting and hollowing layer bonding remake, with safe and reliable, the advantages that repairerment process is simple, at low cost, and short time limit, rubbish are few, no longer occurring falling hidden danger after repairerment has that repair process simple, it is at low cost, the advantages that short time limit, rubbish are few, no longer occur falling hidden danger after repairerment.

Description

A kind of fixed pin part slip casting repairerment of inlet of hollowing inner-outer wall ceramic tile, stone material Engineering method
Technical field
The present invention relates to building inside and outside wall ceramic tile, stone material hollowing recovery technique field, in particular to a kind of hollowing inner-outer walls Engineering method is repaired in the fixed pin part slip casting of inlet of ceramic tile, stone material.
Background technique
Inside and outside wall facing pastes the materials category rigid materials such as ceramic tile, stone material, mosaic, the material of two kinds of different attributes it is swollen The technical performance indexs difference such as swollen coefficient is larger.Especially traditional handicraft pastes the ceramic tile brickwork joint of cement element ash, summer temperature When reaching 35 DEG C, insulating layer of external wall temperature may be up to 70 DEG C -- and 80 DEG C, prominent rainfall moment temperature of meeting can be reduced to 10 DEG C -- and 20 DEG C, temperature Poor 50 DEG C -- 60 DEG C.The biggish two kinds of materials of two kinds of coefficient of expansion difference are bonded together, when and long be bound to cause cement element The ceramic tile of ash stitches cracking.Winter ceramic tile hollowing will certainly just occur, fall off, cause in rainwater infiltration crack when snowing after freeze thawing The safety accident for killing people, injuring people by a crashing object.The serious safety for threatening living environment.
Traditional ceramic tile, stone material hollowing restorative procedure mainly include the following types:
(1) ceramic tile, stone material are all rooted out.Ceramic tile stone material is all rooted out with air compressor machine impact drill, it is not low with every square metre After the cement mortar of 30kg fills up levelling, then carry out the construction of facing ornament materials.It is time-consuming, take material, be at high cost, and leave A large amount of building waste.
(2) ceramic tile, stone material fall off part sectional repair.After rooting out to obvious hollowing, loose or dislocation part, cement mortar is used Or anticracking grout fills up levelling reparation.Not patched next year falls off again, then studies for a second time courses one has flunked.Many building images of present big and medium-sized cities Patch is the same, one piece shallow one piece deep, seriously affects the beautification and the unsafe hidden danger of living environment of urban construction.
(3) fall off after the repairing of position to ceramic tile, with traditional putty batch scrape it is levelling after, direct spraying finishing material.Smooth Ceramic tile basal plane on do not do special reinforcement processing, directly construct finishing material in ceramic tile basal plane, caused by consequence be after 2,3 years Falling off again is formed again.So that the building for spending huge fund decoration is changed so much that one loses one's identity, not only influences urban environment beautification, and And increase secondary, coating expense again three times.
For this reason, Chinese invention patent publication number CN107338967A discloses a kind of aging blocks outdoor tile facing renewal and reform New process and new material, new process, the new material of renewal and reform TY-686 flexibility face brick-imitation directly on smooth ceramic tile face, Its construction technology and the feature of new material are as follows: root out hollowing, ceramic tile-anticracking grout for loosening, falling off fill up it is levelling-apply and seep The high-strength ceramic tile bonding mucilage-batch compound alkali-resistant glass fiber mesh-anchor studs of ceramic tile cementing mortar of reinforcement liquid-spray are fixed on outer thoroughly Wall cement basic layer-batch background color filleting rubber cement is levelling-and it applies infiltration and reinforces ground coat enamel-painting flexibility face brick-imitation slurry.The patent of invention is deposited In reparative processes complexity, the big technical problem of project amount.
Summary of the invention
Aiming at the problem that technical problem to be solved by the present invention lies in the presence of ceramic tile, stone material hollowing repair process and Engineering method is repaired in the fixed pin part slip casting of inlet for providing a kind of hollowing outdoor tile.
The technical problems to be solved by the invention can be achieved through the following technical solutions:
Engineering method is repaired in the fixed pin part slip casting of inlet of a kind of hollowing inner-outer wall ceramic tile, stone material, is included the following steps:
(1) hollowing checking step
In the step, is hammered into shape to tap with hollowing and determine hollowing range and draw continuous hollowing area with marking pen and be greater than 0.25m2
(2) inlet fixed pin length selectes step
It is greater than this three's thickness according to the tile thickness of inner-outer wall, adhesive thickness, the selection of inorganic heat preservation system layer thickness The sum of the length of 25mm inlet fixed pin;
(3) inlet fixed pin number configuration diagram determines step
With (250-330mm × 250-330mm determines the quantity of inlet fixed pin configuration inlet fixed pin in the step Inlet fixed pin number configuration diagram is formed with position;
(4) drill process
Inlet fixed pin number configuration diagram according to step (3) beats inlet with drilling machine and fixes pin jack, wherein infusing The punching depth of the fixed pin jack of entrance is 5mm longer than the length of inlet fixed pin, clears up inlet with cleaner after punching Ash is floated in fixed pin jack;
(5) inlet fixed pin installation steps
In the step, in the fixed pin jack insertion inlet fixed pin of each inlet and the inlet fixed pin that pounds with a hammer In interior nail, be fixedly connected with the outer tube spreading in inlet fixed pin with structure sheaf;
(6) inlet fixed pin slip casting step
In the step, after mixing by epoxy resin or polymer cement mortar, fixed with slip casting machine injection inlet Pin is interior and passes through in the slurry outlet injection hollowing on the outer tube tube wall of inlet fixed pin until design requirement region;Check note Enter the hollowing situation of slurry surrounding, confirmation meets design requirement;
(7) slip casting curing step
It is conserved according to the maintenance situation of epoxy resin or polymer cement mortar;
(8) sealing treatment step
With paste epoxy resin to inlet fixed pin and inlet fixed pin socket surfaces deformity Seal treatment;Or installation Special inlet fixed pin cap head, appearance landscaping treatment.
(9) checking step is injected
Injection is completed to check again for hollowing situation after epoxy resin or polymer cement mortar solidification, such as there are also hollowing, It should be according to above-mentioned steps perforations adding slip casting.
Due to using technical solution as above, the present invention makes porcelain compared with existing ceramic tile, stone material hollowing repair engineering method Brick, stone material hollowing are converted into cladding compound bar planting and hollowing layer bonding remakes, and have securely and reliably, repairerment process is simple, cost It is low, the advantages that short time limit, rubbish are few, no longer occur falling hidden danger after repairerment.
Detailed description of the invention
Fig. 1 is that the inlet of engineering method is repaired in the fixed pin part slip casting of inlet of hollowing inner-outer wall ceramic tile of the present invention, stone material Fixed pin number configuration schematic diagram.
Fig. 2 is hollowing inner-outer wall ceramic tile of the present invention, after the repairerment of the fixed pin part slip casting repairerment engineering method of the inlet of stone material Inner-outer wall structural schematic diagram.
Specific embodiment
Engineering method is repaired in the fixed pin part slip casting of inlet of a kind of hollowing inner-outer wall ceramic tile, stone material, is included the following steps:
(1) hollowing checking step
In the step, is hammered into shape to tap with hollowing and determine hollowing range and draw continuous hollowing area with marking pen and be greater than 0.25m2
(2) inlet fixed pin length selectes step
It is greater than this three according to the ceramic tile of inner-outer wall, stone material thickness, adhesive thickness, the selection of inorganic heat preservation system layer thickness The inlet fixed pin of the length of the sum of thickness 25mm;
(3) inlet fixed pin number configuration diagram determines step
The quantity of inlet fixed pin configuration inlet fixed pin is determined in the step with 250-330mm × 250-330mm Inlet fixed pin number configuration diagram is formed with position, referring specifically to Fig. 1, stain is inlet fixed pin 10, disk area in Fig. 1 Domain is slurry diffusion zone 20;
(4) drill process
Inlet fixed pin number configuration diagram according to step (3) beats inlet with drilling machine and fixes pin jack, wherein infusing The punching depth of the fixed pin jack of entrance is 5mm longer than the length of inlet fixed pin, clears up inlet with cleaner after punching Ash is floated in fixed pin jack;
(5) inlet fixed pin installation steps
In the step, in the fixed pin jack insertion inlet fixed pin of each inlet and the inlet fixed pin that pounds with a hammer In interior nail, be fixedly connected with the outer tube spreading in inlet fixed pin with structure sheaf;
(6) inlet fixed pin slip casting step
In the step, after mixing by epoxy resin or polymer cement mortar, fixed with slip casting machine injection inlet Pin is interior and passes through in the slurry outlet injection hollowing on the outer tube tube wall of inlet fixed pin until until design requirement region;Inspection The hollowing situation of injection slurry surrounding is looked into, confirmation meets design requirement;
(7) slip casting curing step
It is conserved according to the maintenance situation of epoxy resin or polymer cement mortar;
(8) sealing treatment step
With paste epoxy resin to inlet fixed pin and inlet fixed pin socket surfaces deformity Seal treatment;Or installation Special inlet fixed pin cap head, appearance landscaping treatment.
(9) checking step is injected
Injection is completed to check again for hollowing situation after epoxy resin or polymer cement mortar solidification, such as there are also hollowing, It should be according to above-mentioned steps perforations adding slip casting.
External wall structure is referring to fig. 2 after repairerment.

Claims (1)

1. engineering method is repaired in a kind of fixed pin part slip casting of the inlet of hollowing outdoor tile, which comprises the steps of:
(1) hollowing checking step
In the step, is hammered into shape with hollowing and tap determining hollowing range and draw continuous hollowing area greater than 0.25m with marking pen2
(2) inlet fixed pin length selectes step
It is greater than the sum of this three's thickness according to the tile thickness of exterior wall, adhesive thickness, the selection of inorganic heat preservation system layer thickness The inlet fixed pin of length;
(3) inlet fixed pin number configuration diagram determines step
Determine that the quantity of inlet fixed pin configuration inlet fixed pin and position form note in the step with 330mm × 330mm Entrance fixed pin number configuration diagram;
(4) drill process
Inlet fixed pin number configuration diagram according to step (3) beats inlet with drilling machine and fixes pin jack, wherein inlet The punching depth of fixed pin jack is 10mm longer than the length of inlet fixed pin, is fixed after punching with cleaner cleaning inlet Ash is floated in pin jack;
(5) inlet fixed pin installation steps
In the step, in the fixed pin jack insertion inlet fixed pin of each inlet and the inlet fixed pin that pounds with a hammer Interior nail is fixedly connected with the outer tube spreading in inlet fixed pin with structure sheaf;
(6) inlet fixed pin slip casting step
In the step, after mixing by epoxy resin or polymer cement mortar, in slip casting machine injection inlet fixed pin And the slurry outlet on the outer tube tube wall for passing through inlet fixed pin injects in hollowing until design requirement region;Check injection slurry Expect the hollowing situation of surrounding, confirmation meets design requirement;
(7) slip casting curing step
It is conserved according to the maintenance situation of epoxy resin or polymer cement mortar;
(8) sealing treatment step
With paste epoxy resin to inlet fixed pin and inlet fixed pin socket surfaces deformity Seal treatment;Or installation is special Inlet fixed pin cap head, appearance landscaping treatment.
(9) checking step is injected
Injection is completed to check again for hollowing situation after epoxy resin or polymer cement mortar solidification, should be by such as there are also hollowing According to above-mentioned steps perforations adding slip casting.
CN201810524496.0A 2018-05-28 2018-05-28 Grouting repairing method for filling port fixing pin parts of ceramic tiles and stones on hollow inner and outer walls Active CN109057385B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810524496.0A CN109057385B (en) 2018-05-28 2018-05-28 Grouting repairing method for filling port fixing pin parts of ceramic tiles and stones on hollow inner and outer walls

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810524496.0A CN109057385B (en) 2018-05-28 2018-05-28 Grouting repairing method for filling port fixing pin parts of ceramic tiles and stones on hollow inner and outer walls

Publications (2)

Publication Number Publication Date
CN109057385A true CN109057385A (en) 2018-12-21
CN109057385B CN109057385B (en) 2022-08-12

Family

ID=64819731

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810524496.0A Active CN109057385B (en) 2018-05-28 2018-05-28 Grouting repairing method for filling port fixing pin parts of ceramic tiles and stones on hollow inner and outer walls

Country Status (1)

Country Link
CN (1) CN109057385B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185274A (en) * 2019-04-19 2019-08-30 上海市建筑装饰工程集团有限公司 The restorative procedure that existing building exterior wall true stone paint falls off
CN110185279A (en) * 2019-04-19 2019-08-30 上海市建筑装饰工程集团有限公司 The restorative procedure of existing building sloughing of exterior wall
CN110185276A (en) * 2019-04-19 2019-08-30 上海市建筑装饰工程集团有限公司 The restorative procedure of existing building Countermeasures for Dropping of Face Bricks of Exposed Walls
CN110284727A (en) * 2019-07-03 2019-09-27 广州市第二建筑工程有限公司 A kind of post-processing approach for preventing vitrified tile hollowing from falling off
CN111042564A (en) * 2019-12-26 2020-04-21 定州康拓科技有限公司 Method and device for quickly detecting and repairing floor tile hollowing area in building
CN112962935A (en) * 2021-03-04 2021-06-15 邹海荣 Interior notes epoxy construction pretreatment device

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1074007A (en) * 1991-12-30 1993-07-07 北京市第一建筑工程公司 Repairing technology for ceramic tile
JPH11193640A (en) * 1997-11-04 1999-07-21 Ozawa Concrete Ind Co Ltd Repairing method of existing concrete structure and construction method of newly provided concrete structure
CN101864844A (en) * 2009-04-14 2010-10-20 上海恒升经贸发展有限公司 Method for repairing sloughing of exterior wall
CN107313605A (en) * 2017-07-14 2017-11-03 深圳市坤巽建筑设计顾问有限公司 A kind of hollowing restorative procedure
CN107338967A (en) * 2017-06-12 2017-11-10 张新生 A kind of new technology and new material of aging blocks outdoor tile facing renewal and reform
CN108071238A (en) * 2017-12-13 2018-05-25 李彬杰 A kind of environmental protection outdoor tile reinforcement process

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1074007A (en) * 1991-12-30 1993-07-07 北京市第一建筑工程公司 Repairing technology for ceramic tile
JPH11193640A (en) * 1997-11-04 1999-07-21 Ozawa Concrete Ind Co Ltd Repairing method of existing concrete structure and construction method of newly provided concrete structure
CN101864844A (en) * 2009-04-14 2010-10-20 上海恒升经贸发展有限公司 Method for repairing sloughing of exterior wall
CN107338967A (en) * 2017-06-12 2017-11-10 张新生 A kind of new technology and new material of aging blocks outdoor tile facing renewal and reform
CN107313605A (en) * 2017-07-14 2017-11-03 深圳市坤巽建筑设计顾问有限公司 A kind of hollowing restorative procedure
CN108071238A (en) * 2017-12-13 2018-05-25 李彬杰 A kind of environmental protection outdoor tile reinforcement process

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185274A (en) * 2019-04-19 2019-08-30 上海市建筑装饰工程集团有限公司 The restorative procedure that existing building exterior wall true stone paint falls off
CN110185279A (en) * 2019-04-19 2019-08-30 上海市建筑装饰工程集团有限公司 The restorative procedure of existing building sloughing of exterior wall
CN110185276A (en) * 2019-04-19 2019-08-30 上海市建筑装饰工程集团有限公司 The restorative procedure of existing building Countermeasures for Dropping of Face Bricks of Exposed Walls
CN110284727A (en) * 2019-07-03 2019-09-27 广州市第二建筑工程有限公司 A kind of post-processing approach for preventing vitrified tile hollowing from falling off
CN111042564A (en) * 2019-12-26 2020-04-21 定州康拓科技有限公司 Method and device for quickly detecting and repairing floor tile hollowing area in building
CN112962935A (en) * 2021-03-04 2021-06-15 邹海荣 Interior notes epoxy construction pretreatment device

Also Published As

Publication number Publication date
CN109057385B (en) 2022-08-12

Similar Documents

Publication Publication Date Title
CN109057385A (en) Engineering method is repaired in the fixed pin part slip casting of inlet of a kind of hollowing inner-outer wall ceramic tile, stone material
CN109025343A (en) A kind of hollowing displacement repairerment engineering method of hollowing outdoor tile
CN109025344A (en) Engineering method is repaired in the comprehensive slip casting of inlet fixed pin of a kind of hollowing inner-outer wall ceramic tile, stone material
CN109838065B (en) Floor tile ground paving construction method
CN104746772B (en) Ash concrete hollow partition board anti-cracking construction method
CN111042570B (en) Repairing construction method for fresh water brick wall of ancient building
CN107338967A (en) A kind of new technology and new material of aging blocks outdoor tile facing renewal and reform
Thagunna Building cracks–causes and remedies
CN106013509A (en) Dry-method construction method for high-performance autolaved aerated concrete block wall
CN104591649A (en) Modified cement mortar pavement patching material and pavement patching construction method
CN106812219A (en) Filling wall top stuff up a crack construction method
CN104032972A (en) Method for repairing cracks of thermal mortar of outer wall
CN104556877B (en) A kind of preparation method of the acrylic resin mortar of modification
CN208534084U (en) A kind of tile decorative surface point face reinforcing repairerment engineering method anchor studs
CN208534936U (en) A kind of tile decorative surface point face reinforcing repairerment engineering method modified anchor studs
CN105888084A (en) Whole outer wall internal thermal insulation system construction method by using enhanced composite thermal insulation material
CN108708563A (en) It is a kind of to keep the ceramic tile of ceramic tile original state, stone facing point face to reinforce repairing engineering method
CN110259144A (en) A kind of novel energy-saving environment-friendly ash concrete lightweight wall plate construction method
KR102256371B1 (en) Method For Repairing Cracks In Exterior Concrete Walls
CN109779287A (en) Microdilatancy water-proof emulsion construction technology
CN109537926B (en) Waterproof and leaking stoppage construction method for building area
CN102535847B (en) Method for constructing gypsum self-insulation outer wall block masonry
CN214462853U (en) Self-healing concrete micro-crack repairing structure
CN101446138A (en) Reconstructed project wall external decoration material anti-seepage construction method
CN209670134U (en) Assembled wall right angle connecting structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A grouting repair method for the fixed pin part of the injection port of hollow inner and outer wall tiles and stones

Effective date of registration: 20230331

Granted publication date: 20220812

Pledgee: The Bank of Shanghai branch Caohejing Limited by Share Ltd.

Pledgor: SHANGHAI TIANBU MATERIAL TECHNOLOGY CO.,LTD.

Registration number: Y2023310000103

PE01 Entry into force of the registration of the contract for pledge of patent right
CP01 Change in the name or title of a patent holder

Address after: Room 431, building 147, 500 Zhennan Road, Putuo District, Shanghai 200331

Patentee after: Shanghai Tianbu Technology Co.,Ltd.

Address before: Room 431, building 147, 500 Zhennan Road, Putuo District, Shanghai 200331

Patentee before: SHANGHAI TIANBU MATERIAL TECHNOLOGY CO.,LTD.

CP01 Change in the name or title of a patent holder