CN101864844A - Method for repairing sloughing of exterior wall - Google Patents

Method for repairing sloughing of exterior wall Download PDF

Info

Publication number
CN101864844A
CN101864844A CN200910049289A CN200910049289A CN101864844A CN 101864844 A CN101864844 A CN 101864844A CN 200910049289 A CN200910049289 A CN 200910049289A CN 200910049289 A CN200910049289 A CN 200910049289A CN 101864844 A CN101864844 A CN 101864844A
Authority
CN
China
Prior art keywords
exterior wall
sloughing
restorative procedure
anchor bolts
chemical anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN200910049289A
Other languages
Chinese (zh)
Inventor
仇鸿胜
袁亦琦
葛宏亮
周吉
刘枫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI HENGSHENG TRADE DEVELOPMENT Co Ltd
Shanghai No 7 Construction Co Ltd
Original Assignee
SHANGHAI HENGSHENG TRADE DEVELOPMENT Co Ltd
Shanghai No 7 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI HENGSHENG TRADE DEVELOPMENT Co Ltd, Shanghai No 7 Construction Co Ltd filed Critical SHANGHAI HENGSHENG TRADE DEVELOPMENT Co Ltd
Priority to CN200910049289A priority Critical patent/CN101864844A/en
Publication of CN101864844A publication Critical patent/CN101864844A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Finishing Walls (AREA)

Abstract

The invention provides a method for repairing the sloughing of an exterior wall, and relates to a method for repairing the sloughing of the exterior wall by adopting chemical anchor bolts. The method at least comprises the following steps of: determining a construction range; determining a plurality of hole positions of the chemical anchor bolts; drilling a plurality of anchor bolt embedding holes; cleaning the anchor bolt embedding holes; putting chemical anchor bolt rubber tubes in the anchor bolt embedding holes; putting anchor bolt screws in the chemical anchor bolt rubber tubes; and finally, performing surface tamping treatment by using latex-doped mortar. The method for repairing the sloughing of the exterior wall has the advantages of convenient construction, project budget cost conservation and quality guarantee after the repair, and is particularly suitable for reinforcing the exterior walls of historic preservation buildings; in addition, the sloughing of facing tiles of the exterior walls can be smoothly repaired under the condition that epoxy grouting reinforcement method cannot be carried out.

Description

A kind of restorative procedure of sloughing of exterior wall
Technical field
The present invention relates to a kind of restorative procedure of building furring brick sloughing of exterior wall, particularly a kind of chemical anchor bolts that adopt carry out the method that sloughing of exterior wall is repaired.
Background technology
Building in use for some time, exterior wall is by erosion by wind and rain, hollowing, to flake be common phenomenon, way commonly used in the prior art is to cut off again at the position of generally flaking to whitewash, and then the paving exterior wall tile, renovates.Yet, for the historical relic's protection building, can't find the exterior wall finish material that has same hue with original exterior wall tile at all, therefore, it is infeasible adopting the mode of whitewashing tile work again to restore relics and protecting building.
In addition, the job practices of utilizing epoxy grouting to reinforce in addition, but because the restriction of actual environment, the epoxy grouting reinforcing method often can't be constructed.
In view of this; how can under the prerequisite that keeps former facing tile, effectively repair the sloughing of exterior wall phenomenon of historical relic's protection building, can realize under the situation that the epoxy grouting reinforcing method can't be constructed that again the reparation of sloughing of exterior wall has become the technical problem that industry needs to be resolved hurrily.
Summary of the invention
Main purpose of the present invention is the reinforcing at the historical relic's protection building exterior wall face, and the wall face hollowing phenomenon that can't adopt the epoxy grouting reinforcing method to repair, and a kind of sloughing of exterior wall restorative procedure that utilizes chemical anchor bolts is provided.
For achieving the above object, the present invention has adopted following technical scheme:
A kind of restorative procedure of sloughing of exterior wall, it comprises the following steps: at first, adopts hammering method or infrared analysis method and original construction note to determine described boundary of works area; Then, determine a plurality of chemical anchors keyholes position, the density of described chemical anchors keyhole position is 10 to 15 every square metre, selects furring brick T-joining intersection as chemical anchors keyhole position usually, and described chemical anchors keyhole position is on the porthole that the plum blossom shape is distributed in described building furring brick exterior wall; Then, on chemical anchors keyhole position, with Churn drill with 15 ° ± 3 ° angular bit holes, hole depth 30mm at least to the basal plane of building; Subsequently, adopt rubber to blow or compressed air blows described to the greatest extent a plurality of crab-bolts and buries broken gravel in the hole underground, bury the hole underground to clean described crab-bolt; Bury underground in the hole in described crab-bolt and place the chemical anchor bolts sebific duct, wherein said chemical anchor bolts sebific duct is the sebific duct with supporting brand of chemical anchor bolts and model; At last, with electric drill chemical anchor bolts are pressed to revolve to be installed in the described chemical anchor bolts sebific duct, and mounted chemical anchor bolts are lower than building furring brick exterior wall 8~12mm.
The restorative procedure of metope hollowing of the present invention, utilize chemical anchor bolts with floated coat " nail " plinth course outside the building firmly, influence to the floated coat of periphery is less, and position, cementation hole is all in exterior wall tile T-joining intersection, can not produce and destroy facing tile, and mounted crab-bolt is lower than the decoration of exterior wall layer, can not destroy outer facade effect.
Description of drawings
To the description of one embodiment of the invention, can further understand purpose, specific structural features and the advantage of its invention by following in conjunction with its accompanying drawing.Wherein, accompanying drawing is:
Fig. 1 carries out the structural representation that sloughing of exterior wall is repaired for the present invention adopts chemical anchor bolts;
Fig. 2 is that the chemical anchor bolts hollowing of a preferred embodiment of the present invention is repaired the distribution schematic diagram of position, hole.
The specific embodiment
Below with reference to embodiment the restorative procedure of sloughing of exterior wall of the present invention is described in further detail.
Seeing also Fig. 1 and Fig. 2, is that the employing chemical anchor bolts of a preferred embodiment carry out the structural representation that sloughing of exterior wall is repaired as shown in the figure.Chemical anchor bolts hollowing restorative procedure of the present invention; be applied to repair building; especially the furring brick sloughing of exterior wall phenomenon of historical relic's protection building; and described building furring brick exterior wall hierarchical structure from inside to outside is followed successively by barnacle layer 1 (being basal plane), leveling layer 2 (promptly drawing together rough layer) and decorative layer 3 (being face brick).
Chemical anchor bolts hollowing restorative procedure provided by the present invention, its basic step is as follows:
S1. with hammering method or infrared analysis method, find the hollowing of skin, the position of flaking to determine boundary of works area in conjunction with original construction note;
S2. on decorative layer 3, determine the position in (marking) a plurality of chemical anchor bolts hollowings reparation hole 20, these density of repairing hole 20 can be 10 to 15 every square metre, usually select furring brick T-joining intersection as repairing hole 20 (see figure 2)s, and these are repaired holes 20 and are on the exterior wall that the plum blossom shape is distributed in building furring brick 3, concrete arrangement mode as shown in Figure 2, adopt many rows to repair hole 20, be equidistant arrangement between a plurality of holes of each row, column alignment is pressed in the reparation hole 20 of odd-numbered line each other, column alignment is also pressed in the reparation hole of even number line, the half pitch but stagger in the reparation hole of even number line and odd-numbered line.
S3. repair the position (being the T-joining intersection) in hole 20 at the chemical anchor bolts hollowing that is marked, with downward 15 ° ± 3 ° angular bit holes of Churn drill (shown in ∠ a among the figure), the aperture can be 8mm, is deep to basal plane 1 with interior 30mm at least, and promptly the distance b that marks among Fig. 1 is at least 30mm.
S4. blow with rubber or compressed air blows most chemical anchor bolts hollowing and repairs broken gravel in the hole 20.
S5. place chemical anchor bolts sebific ducts (not shown) in repairing hole 20, this chemical anchor bolts sebific duct can be the sebific duct with supporting brand of chemical anchor bolts and model.
S6. with electric drill chemical anchor bolts 30 are pressed to revolve and be installed in the chemical anchor bolts sebific duct, can tightly link to each other with basic unit after sebific duct breaks and play fixation, mounted crab-bolt 30 should be lower than the decoration of exterior wall layer, for example, can be lower than decoration of exterior wall layer 8~12mm, as mark among Fig. 1 apart from shown in the d.
S7. adopt the mortar that is mixed with latex to carry out the surface and tamp processing.
Owing to adopted technique scheme, compare generally flake the position cut off again whitewash, the technology of paving exterior wall tile, chemical anchor bolts hollowing restorative procedure of the present invention has following characteristics and advantage:
1, utilize chemical anchor bolts with floated coat " nail " plinth course outside firmly, less to the influence of the floated coat of periphery;
2, position, cementation hole is all in exterior wall tile T-joining intersection, can not produce facing tile and destroy, and mounted crab-bolt is lower than the decoration of exterior wall layer, can not destroy outer facade effect;
3, convenient and quick construction can not influence the duration.
Of particular note, the restorative procedure of a kind of metope hollowing of the present invention is not limited to structure and step execution sequence defined in the foregoing description, although the present invention is had been described in detail with reference to preferred embodiment, those of ordinary skill in the art is to be understood that, can make amendment or be equal to replacement the present invention, and not breaking away from the spirit and scope of the present invention, it all should be encompassed in the middle of the claim scope of the present invention.

Claims (10)

1. the restorative procedure of a sloughing of exterior wall is used to repair building furring brick sloughing of exterior wall, it is characterized in that described method comprises the following steps:
Step S1 determines boundary of works area;
Step S2 determines a plurality of chemical anchors keyholes position;
Step S3 bores a plurality of crab-bolts and buries the hole underground;
Step S4 cleans described crab-bolt and buries the hole underground;
Step S5 buries underground in described crab-bolt and places the chemical anchor bolts sebific duct in the hole;
Step S6 places the crab-bolt screw rod in described chemical anchor bolts sebific duct;
Step S7 adopts the mortar that is mixed with latex to carry out the surface and tamps processing.
2. the restorative procedure of sloughing of exterior wall according to claim 1 is characterized in that, in step S1, adopts hammering method or infrared analysis method, determines described boundary of works area according to original construction note.
3. the restorative procedure of sloughing of exterior wall according to claim 1 is characterized in that, in step S2, selects furring brick T-joining intersection as chemical anchors keyhole position, and described chemical anchors keyhole position is on the exterior wall that the plum blossom shape is distributed in described building furring brick.
4. according to the restorative procedure of claim 1 or 3 described sloughing of exterior wall, it is characterized in that the density of described chemical anchors keyhole position is 10 to 15 every square metre.
5. the restorative procedure of sloughing of exterior wall according to claim 1 is characterized in that, in step S3, on chemical anchors keyhole position, with predetermined angle boring, hole depth is to the basal plane of building with Churn drill.
6. the restorative procedure of sloughing of exterior wall according to claim 5 is characterized in that, described predetermined angle is 15 ° ± 3 °, hole depth to basal plane with interior 30mm at least.
7. the restorative procedure of sloughing of exterior wall according to claim 1 is characterized in that, in step S4, adopts rubber to blow or compressed air blows described to the greatest extent a plurality of crab-bolts and buries broken gravel in the hole underground.
8. the restorative procedure of sloughing of exterior wall according to claim 1 is characterized in that, in step S5, described chemical anchor bolts sebific duct is the sebific duct with supporting brand of chemical anchor bolts and model.
9. the restorative procedure of sloughing of exterior wall according to claim 1 is characterized in that, in step S6, with electric drill the crab-bolt screw rod is pressed to revolve to be installed in the described chemical anchor bolts sebific duct.
10. the restorative procedure of sloughing of exterior wall according to claim 9 is characterized in that, mounted chemical anchor bolts are lower than building furring brick exterior wall 8~12mm.
CN200910049289A 2009-04-14 2009-04-14 Method for repairing sloughing of exterior wall Pending CN101864844A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910049289A CN101864844A (en) 2009-04-14 2009-04-14 Method for repairing sloughing of exterior wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910049289A CN101864844A (en) 2009-04-14 2009-04-14 Method for repairing sloughing of exterior wall

Publications (1)

Publication Number Publication Date
CN101864844A true CN101864844A (en) 2010-10-20

Family

ID=42956752

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910049289A Pending CN101864844A (en) 2009-04-14 2009-04-14 Method for repairing sloughing of exterior wall

Country Status (1)

Country Link
CN (1) CN101864844A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103924675A (en) * 2014-05-06 2014-07-16 宁夏煤炭基本建设有限公司 Outer wall strengthening rivet and outer wall strengthening method
CN103924792A (en) * 2014-05-06 2014-07-16 北京筑福建筑事务有限责任公司 Method of replacing mortar in mortar joint for masonry structure reinforcement
CN105421811A (en) * 2015-12-17 2016-03-23 北京筑福建筑事务有限责任公司 Quincuncial mortar joint mortar reinforced masonry structure and construction method thereof
CN108590219A (en) * 2018-05-07 2018-09-28 浙江大学 A kind of ancient seawall restorative procedure based on MICP
CN109025344A (en) * 2018-05-28 2018-12-18 上海天补材料科技有限公司 Engineering method is repaired in the comprehensive slip casting of inlet fixed pin of a kind of hollowing inner-outer wall ceramic tile, stone material
CN109057385A (en) * 2018-05-28 2018-12-21 上海天补材料科技有限公司 Engineering method is repaired in the fixed pin part slip casting of inlet of a kind of hollowing inner-outer wall ceramic tile, stone material
CN110185276A (en) * 2019-04-19 2019-08-30 上海市建筑装饰工程集团有限公司 The restorative procedure of existing building Countermeasures for Dropping of Face Bricks of Exposed Walls
CN110607881A (en) * 2018-06-15 2019-12-24 上海天补材料科技有限公司 Whitewash mortar hollowing bonding regeneration technology
CN110821198A (en) * 2019-10-23 2020-02-21 浙江勤业建工集团有限公司 High-rise building external wall thermal insulation mortar falling prevention method
CN112459526A (en) * 2020-12-03 2021-03-09 安徽墨砂工程修缮技术有限公司 Method for repairing external wall thermal insulation hollowing and dropping

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6429578A (en) * 1987-07-24 1989-01-31 Masaru Eng Kk Land-floating repair method of slate for finishing surface of building
DE4227975A1 (en) * 1991-08-28 1993-03-04 Boehl Adolf Ejot Gmbh Method of anchoring of two parallel wall panels - has hole drilled through panel and bolt located onto inner wall.
JPH08291631A (en) * 1995-04-24 1996-11-05 Nippon Tetsudo Kensetsu Kodan Reinforcing method of concrete structure with steel plate
CN1392319A (en) * 2002-07-09 2003-01-22 阚小勇 Post rubber injection method for building wet covered with steel and reinforced with crab-bolt
KR20030061951A (en) * 2002-01-14 2003-07-23 배석동 Maintenance and Reinforcement Engineering Method of Concrete Structure
CN101275432A (en) * 2008-05-23 2008-10-01 北京城建建设工程有限公司 Construction method for building postposition pre-buried wall connecting parts

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6429578A (en) * 1987-07-24 1989-01-31 Masaru Eng Kk Land-floating repair method of slate for finishing surface of building
DE4227975A1 (en) * 1991-08-28 1993-03-04 Boehl Adolf Ejot Gmbh Method of anchoring of two parallel wall panels - has hole drilled through panel and bolt located onto inner wall.
JPH08291631A (en) * 1995-04-24 1996-11-05 Nippon Tetsudo Kensetsu Kodan Reinforcing method of concrete structure with steel plate
KR20030061951A (en) * 2002-01-14 2003-07-23 배석동 Maintenance and Reinforcement Engineering Method of Concrete Structure
CN1392319A (en) * 2002-07-09 2003-01-22 阚小勇 Post rubber injection method for building wet covered with steel and reinforced with crab-bolt
CN101275432A (en) * 2008-05-23 2008-10-01 北京城建建设工程有限公司 Construction method for building postposition pre-buried wall connecting parts

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103924675A (en) * 2014-05-06 2014-07-16 宁夏煤炭基本建设有限公司 Outer wall strengthening rivet and outer wall strengthening method
CN103924792A (en) * 2014-05-06 2014-07-16 北京筑福建筑事务有限责任公司 Method of replacing mortar in mortar joint for masonry structure reinforcement
CN105421811A (en) * 2015-12-17 2016-03-23 北京筑福建筑事务有限责任公司 Quincuncial mortar joint mortar reinforced masonry structure and construction method thereof
CN108590219A (en) * 2018-05-07 2018-09-28 浙江大学 A kind of ancient seawall restorative procedure based on MICP
CN109025344A (en) * 2018-05-28 2018-12-18 上海天补材料科技有限公司 Engineering method is repaired in the comprehensive slip casting of inlet fixed pin of a kind of hollowing inner-outer wall ceramic tile, stone material
CN109057385A (en) * 2018-05-28 2018-12-21 上海天补材料科技有限公司 Engineering method is repaired in the fixed pin part slip casting of inlet of a kind of hollowing inner-outer wall ceramic tile, stone material
CN110607881A (en) * 2018-06-15 2019-12-24 上海天补材料科技有限公司 Whitewash mortar hollowing bonding regeneration technology
CN110185276A (en) * 2019-04-19 2019-08-30 上海市建筑装饰工程集团有限公司 The restorative procedure of existing building Countermeasures for Dropping of Face Bricks of Exposed Walls
CN110821198A (en) * 2019-10-23 2020-02-21 浙江勤业建工集团有限公司 High-rise building external wall thermal insulation mortar falling prevention method
CN112459526A (en) * 2020-12-03 2021-03-09 安徽墨砂工程修缮技术有限公司 Method for repairing external wall thermal insulation hollowing and dropping
CN112459526B (en) * 2020-12-03 2021-12-14 安徽墨砂工程修缮技术有限公司 Method for repairing external wall thermal insulation hollowing and dropping

Similar Documents

Publication Publication Date Title
CN101864844A (en) Method for repairing sloughing of exterior wall
CN107989401B (en) Existing building outer wall reconstruction structure and construction method
CN104060704B (en) The mechanical type restorative procedure of heat preservation mortar for outer wall hollowing and structure
CN109025343A (en) A kind of hollowing displacement repairerment engineering method of hollowing outdoor tile
CN106801517A (en) A kind of schoolhouse surface consolidation of Prefabricated porous plate brick mixed structure strengthens method
Pescari et al. Rehabilitation and restauration of the main façade of historical masonry building–Romanian National Opera Timisoara
CN109025344B (en) Method for comprehensive grouting repair of filling port fixing pins of ceramic tiles and stones on hollow inner and outer walls
CN113374295A (en) Old steel-wood structure roof truss dismantling and rebuilding construction method
CN104695706B (en) AAC building block freely loads wall construction
CN108166772B (en) Reinforcing method for column steel-clad reinforced variable cross-section node
Sinyakin et al. The renovation technology of structures that has lost reliability during long-term operation in an aggressive environment
CN114575620A (en) Formwork-supporting-free reinforcement high-ductility concrete construction method for masonry reinforcement
CN203145206U (en) Mechanical repairing structure of hollowing of external wall insulation mortar
CN110714626B (en) Building wall leakage repairing method
CN112983039A (en) Construction method for integral dismantling protection of reserved vertical face of historical building
ES2641307A1 (en) Procedure for the repair and consolidation of cracked surfaces of buildings by means of reinforcing clips, and new reinforcement staple to perform this procedure (Machine-translation by Google Translate, not legally binding)
Chmielewski et al. Selected problems of protection of historic buildings against the rainwater and the groundwater
Sabbadini et al. Environmental sustainability of the retrofitting of a vernacular dwelling in the Liguria seaside
Drobiec Repair and renovation of the historic church in Ruda Śląska after many failures caused by mining exploitation
CN110670895A (en) Toughness of masonry structure enhanced by combination of vertical steel plates and angle steel and construction method thereof
CN204510524U (en) A kind of steam pressure sand aerated concrete block combination masonry panel
Niedostatkiewicz et al. Assessment of Technical Conditions in Adapting a Historic Warehouse's Space Functionality
RU2795923C1 (en) Method of repairing the facade of a brick building
Brosens et al. Cathodic Protection of the Historic Boerentoren (KBC Tower)
CN115773006B (en) Construction method of hollow stone masonry wall without constructional column

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20101020