CN109057255A - The auxiliary mould and its construction method of indoor distribution box construction - Google Patents

The auxiliary mould and its construction method of indoor distribution box construction Download PDF

Info

Publication number
CN109057255A
CN109057255A CN201811104909.6A CN201811104909A CN109057255A CN 109057255 A CN109057255 A CN 109057255A CN 201811104909 A CN201811104909 A CN 201811104909A CN 109057255 A CN109057255 A CN 109057255A
Authority
CN
China
Prior art keywords
distribution box
steel pipe
adjusting sleeve
indoor
sleeve pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811104909.6A
Other languages
Chinese (zh)
Inventor
王涛
廖晓涛
谭彪
陈浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN201811104909.6A priority Critical patent/CN109057255A/en
Publication of CN109057255A publication Critical patent/CN109057255A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Sewage (AREA)

Abstract

The present invention relates to indoor construction technical field, the auxiliary mould and method of open indoor distribution box construction, comprising: steel pipe, adjusting sleeve pipe and installation frame, jacking mechanism include threaded rod and tapped adjustment seat;Threaded rod injects steel pipe bottom, and adjustment seat top surface contacts support with steel pipe bottom end, and ground base supports threaded rod bottom, and steel pipe top is for holding out against indoor top;Steel pipe vertical position can be adjusted by adjustment seat;Adjusting sleeve pipe is sleeved on steel pipe and has threaded hole, and adjusting sleeve pipe can adjust its height along length of steel pipe, and be fixed on steel pipe by lock-screw, and installation frame is installed on adjusting sleeve pipe and for being fixedly mounted with distribution box.Distribution box easily can be supported in design height position, adjusting sleeve pipe vertical adjustment range is big, adapt to the variation of distribution box mounting height, installation process is not influenced by other professions, the operating space that spool is connect with fitting case is big, gap is small between distribution box surrounding and masonry panel, without largely filling up work.

Description

The auxiliary mould and its construction method of indoor distribution box construction
Technical field
The present invention relates to indoor construction technical fields, the in particular to auxiliary mould and its construction party of indoor distribution box construction Method.
Background technique
Indoors when construction, the installation of cubicle switch and its spool is often related to, there are two types of conventional modes:
The first is first to complete wall construction, and the hole of installation distribution box has been reserved on wall, has then been opened up on wall The tube seat of spool and plastering are installed, then electrician installs spool, and by spool and distribution box abutting joint, due to hole and distribution Adjustment gap very little between case, causes spool and docking for distribution box very inconvenient, meanwhile, spool and distribution box are installed Afterwards, it also needs brickwork further to plaster, and the gap between distribution box and hole is poured and is filled up, be related to two work posts Cross-operation, it is very complicated;
It is for second while embedded spool during wall construction, needs brickwork and electrician to cooperate at the scene simultaneously at this time and apply Work is buried always to the position for needing reserved opening, and work progress is very complicated, after the completion of wall construction, then installs distribution Case is also required at this time by distribution box and spool abutting joint, to reserved opening also due to the adjustment between hole and distribution box Gap very little causes spool and docking for distribution box very inconvenient, meanwhile, after distribution box is installed, also need brickwork further Gap between distribution box and hole is poured and is filled up, the cross-operation of two work posts is also related to, it is very complicated.
In conclusion above two mode has the following problems: 1, installing distribution box in reserved opening and be easy to appear peace Phenomena such as dress skew, cabinet recess, levelness is poor, and later period adjustment difficulty is larger;2, distribution box and spool attended operation space It is limited, it installs inconvenient;3, the later period between reserved opening and distribution box, which pours, fills up heavy workload, increases distribution carton deformed With hollowing risk;4, electrician and brickwork cross-operation are frequent, and work progress is cumbersome.
Therefore, the application proposes the auxiliary mould and its construction method of a kind of indoor distribution box construction.
Summary of the invention
The technical problems to be solved by the present invention are: in view of the above problems, provides a kind of indoor distribution box and apply The auxiliary mould and its construction method of work, installation, adjusting and fixation procedure are convenient and efficient, can be convenient and effectively by distribution box It is fixedly supported to design height position, the vertical adjustment range of adjusting sleeve pipe is big, can effectively adapt to various mounting height distribution The installation of case increases adaptability, and installation process is not influenced by other professions, and installation effectiveness is higher, more flexible, spool and accessory The operating space of case connection is big, and spool can arrange neat smooth, and the gap between distribution box surrounding and subsequent masonry panel is small, no Need largely to fill up work, distribution box is unlikely to deform, and levelness can guarantee well.
The technical solution adopted by the invention is as follows: the auxiliary mould of indoor distribution box construction, including vertical steel pipe, is adjusted Casing, jacking mechanism and installation frame, the jacking mechanism include threaded rod and tapped adjustment seat, the adjustment seat It is threadedly coupled with the threaded rod;
The threaded rod is injected from the steel pipe bottom, and the top surface of the adjustment seat contacts and supports, ground with the steel pipe bottom end Face basis forms support to the bottom of the threaded rod, and the steel pipe top is for holding out against indoor top;
The steel pipe is held out against between indoor ground base and indoor top by jacking mechanism, can be adjusted by the adjustment seat The vertical position of the steel pipe, the steel pipe can be relative to the threaded rod vertical motions;
The adjusting sleeve pipe is set in the outer surface of steel tube, and the adjusting sleeve pipe internal diameter is adapted with the outer diameter of steel pipes, institute It states and offers threaded hole on adjusting sleeve pipe, lock-screw is connected in the threaded hole, the adjusting sleeve pipe can be along the steel pipe Length direction adjusts its mounting height, and realizes that adjusting sleeve pipe is locked on the steel pipe by lock-screw, the peace The frame that frames up is fixedly installed on the adjusting sleeve pipe, and the installation frame is for being fixedly mounted distribution box.
So set, steel pipe easily and effectively can be fixedly supported to indoor ground base and indoor top by jacking mechanism Between portion, can conveniently and efficiently adjust vertical fixed position of the adjusting sleeve pipe on steel pipe, so by distribution box positioning support in The height and position of design, installation process are not influenced by other professions, and installation effectiveness is higher, more flexible, and spool is connect with fitting case Operating space it is big, spool can arrange neat smooth, and the gap formed between distribution box surrounding and subsequent masonry panel is small, is not required to Work is largely filled up, distribution box is unlikely to deform, and levelness can guarantee well, meanwhile, steel can be changed by adjusting adjustment seat The vertical height of pipe, and then the high scene of different layers is adapted to, the variation of spacing between ground base and indoor top can be adapted to.
The auxiliary mould of indoor distribution box construction of the present invention, the top of the steel pipe are fixedly installed with channel steel seat, The notch of the channel steel seat is upward, and chock block is fixedly installed in the notch, and the chock block contacts support with indoor top; The bottom end of the threaded rod is also fixedly installed with channel steel seat, and the notch of the channel steel seat is downward, is also fixedly mounted in the notch There is chock block, the chock block contacts support with ground base.
So set, chock block further ensures this tooling upper and lower side respectively between ground base and indoor top Stability of strutting system and reliability, channel steel seat provide reliable and stable installation site for chock block.
The auxiliary mould of indoor distribution box construction of the present invention, there are two adjust ear for the adjustment seat tool.
So set, operator can easily rotate operation adjustment seat by adjusting ear, so that the vertical adjustment of steel pipe Process is more smooth.
The auxiliary mould of indoor distribution box construction of the present invention, the installation frame include four angle steel compositions, shape At a rectangular frame, the installation frame is welded and fixed by other two horizontal angle steel with the adjusting sleeve pipe.
So set, installation frame is made of angle steel, installation frame is fixed by two horizontal angle steel with steel-pipe welding, Material has been saved, the discarded angle steel that construction site can be selected is made, and it is convenient and efficient, it reduces costs.
The auxiliary mould of indoor distribution box construction of the present invention, two horizontal angle steel are located at the adjusting set The left and right sides of pipe.
So set, ensure that the reliability that installation frame is fixedly connected with adjusting sleeve pipe.
The auxiliary mould of indoor distribution box of the present invention construction offers through-hole on the angle steel of the installation frame, Position of mounting hole Corresponding matching on the lead to the hole site and the distribution box passes through the through-hole by screw and mounting hole is real The existing distribution box is fixedly connected with installation frame.
So set, make the installation of distribution box and installation frame fixed more rationally, reliable, the later period is between the two to be torn open It unloads also more convenient, and distribution box will not be damaged.
The construction method of the auxiliary mould of indoor distribution box construction of the present invention, is first fixedly installed in peace for distribution box It frames up on frame, determines the projected position of distribution box in ground base further according to the specific installation site of distribution box, will install auxiliary It helps device to be moved to projected position and is adjusted, so that distribution box is located at right above projected position, then adjust adjustment seat, So that steel pipe is vertically raised and keeps vertical, until steel pipe top holds out against indoor top, then installed according to the design of distribution box Vertical installation site of the height adjustment adjusting sleeve pipe on steel pipe simultaneously guarantees that distribution box end face is flushed with metope, until being adjusted to The design mounting height of distribution box, tightens lock-screw and fixes, then spool is correspondingly connected to the knock-off hole on distribution box, so far The positioning of distribution box is completed, and the building construction of wall can be carried out, according to already installed distribution box carry out building construction and Reserved lintel, the small gap of distribution box surrounding are tamped with mortar.
Using this construction method, there is no the cross-operation of different majors, so that left and right process is more orderly, it is cumbersome, Flowing water section can be divided to construct, improve it is whole make operating efficiency, improve the installation quality of distribution box.
Compared with prior art, having the beneficial effect that using auxiliary device and peace of the invention by adopting the above technical scheme Dress method, installation are adjusted and fixation procedure is convenient and efficient, can be convenient and distribution box be effectively fixedly supported to design height The vertical adjustment range of position, adjusting sleeve pipe is big, can effectively adapt to the installation of various mounting height distribution boxs, increase adaptation Property, installation process are not influenced by other professions, and installation effectiveness is higher, more flexible, and the operating space that spool is connect with fitting case is big, Spool can arrange neat smooth, and the gap between distribution box surrounding and subsequent masonry panel is small, does not need largely to fill up work, match Electronic box is unlikely to deform, and levelness can guarantee well.
Detailed description of the invention
Fig. 1 is scheme of installation of the invention;
Fig. 2 is enlarged drawing at A in Fig. 1;
Fig. 3 is enlarged drawing at B in Fig. 1;
Fig. 4 is enlarged drawing at C in Fig. 1;
Fig. 5 is the side view of installation frame and adjusting sleeve pipe cooperation in the present invention;
Fig. 6 is the top view of adjustment seat in the present invention.
Appended drawing reference: 1 is steel pipe, and 2 be adjusting sleeve pipe, and 3 be installation frame, and 4 be threaded rod, and 5 be adjustment seat, and 6 be ground Basis, 7 be indoor top, and 8 be threaded hole, and 9 be channel steel seat, and 10 be chock block, and 11 is adjust ear, and 12 be horizontal angle steel, 13 For through-hole.
Specific embodiment
The present invention is described further with reference to the accompanying drawing.
Embodiment 1
As shown in Fig. 1 to 4,6, the auxiliary mould of indoor distribution box construction, including vertical steel pipe 1, adjusting sleeve pipe 2, jacking machine Structure and installation frame 3, jacking mechanism include threaded rod 4 and tapped adjustment seat 5, and adjustment seat 5 and 4 screw thread of threaded rod connect It connects, there are two adjust ear 11 for the tool of adjustment seat 5;
Threaded rod 4 is injected from 1 bottom of steel pipe, and the top surface of adjustment seat 5 contacts and supports with 1 bottom end of steel pipe, and ground base 6 is to screw thread Support is formed on the bottom of bar 4, is used to hold out against indoor top 7 at the top of steel pipe 1, steel pipe 1 is held out against by jacking mechanism in indoor ground Between basis 6 and indoor top 7, the vertical position of steel pipe 1, during vertical adjustment, steel pipe 1 can be adjusted by adjustment seat 5 It can be relative to 4 vertical motion of threaded rod;
Adjusting sleeve pipe 2 is set in 1 outer surface of steel pipe, and 2 internal diameter of adjusting sleeve pipe is adapted with 1 outer diameter of steel pipe, opens up on adjusting sleeve pipe 2 There is threaded hole 8, specifically opens up three threaded holes 8 along 2 length direction of adjusting sleeve pipe, be connected with lock-screw (in figure in threaded hole 8 It is not shown), adjusting sleeve pipe 2 can adjust its mounting height along 1 length direction of steel pipe, and realize adjusting sleeve pipe 2 by lock-screw It is locked on steel pipe 1, lock-screw holds out against 1 outer surface of steel pipe, and installation frame 3 is installed on adjusting sleeve pipe by being welded and fixed On 2, installation frame 3 is for being fixedly mounted distribution box (not shown).
Further, the top of steel pipe 1 is equipped with channel steel seat 9 by being welded and fixed, and the notch of channel steel seat 9 is upward, notch It is inside fixedly installed with chock block 10, the top surface of chock block 10 is higher by 9 top of channel steel seat, and chock block 10 contacts branch with indoor top 7 Support;The bottom end of threaded rod 4 is equipped with channel steel seat 9 also by being welded and fixed, and the notch of channel steel seat 9 is downward, also fixed peace in notch Equipped with chock block 10, the bottom surface of chock block 10 is lower than 9 bottom of channel steel seat, and chock block 10 contacts support with ground base 6.
Embodiment 2
As shown in Figures 3 and 5, on the basis of embodiment 1, installation frame 3 includes four angle steel compositions, and four angle steel weld to be formed One rectangular frame, installation frame 3 are welded and fixed by other two horizontal angle steel 12 with adjusting sleeve pipe 2, and two horizontal Angle steel 12 is located at the left and right sides of adjusting sleeve pipe 2, two horizontal angle steel 12 respectively with the top angle steel of rectangular frame and under Portion's angle steel is welded and fixed.
Embodiment 3
As shown in figure 3, on the basis of embodiment 2, offer through-hole 13 on the angle steel of installation frame 3,13 position of through-hole with match Mounting hole (not shown) position Corresponding matching on electronic box, the quantity of through-hole 13 and position are according to distribution box upper installing hole Quantity and specific location are specifically set, and pass through through-hole 13 by screw (not shown) and mounting hole realizes distribution box and installation Frame 3 is fixedly connected.
The construction method of the auxiliary mould of above-mentioned indoor distribution box construction, is first fixedly installed in installation frame for distribution box On 3, the projected position of distribution box is determined in ground base 6 further according to the specific installation site of distribution box, by installation auxiliary dress It sets and is moved to projected position and is adjusted, so that distribution box is located at right above projected position, then adjust adjustment seat 5, so that Steel pipe 1 is vertically raised and keeps vertical, until holding out against indoor top 7 at the top of steel pipe 1, is then installed according to the design of distribution box high It spends the vertical installation site adjusted adjusting sleeve pipe 2 on steel pipe 1 and guarantees that distribution box end face is flushed with metope, until being adjusted to The design mounting height of distribution box, tightens lock-screw and fixes, then spool is correspondingly connected to the knock-off hole on distribution box, so far The positioning of distribution box is completed, and the building construction of wall can be carried out, according to already installed distribution box carry out building construction and Reserved lintel, the small gap of distribution box surrounding are tamped with mortar.
The invention is not limited to specific embodiments above-mentioned.The present invention, which expands to, any in the present specification to be disclosed New feature or any new combination, and disclose any new method or process the step of or any new combination.If this Field technical staff is altered or modified not departing from the unsubstantiality that spirit of the invention is done, should belong to power of the present invention The claimed range of benefit.

Claims (7)

1. the auxiliary mould of indoor distribution box construction, it is characterised in that: including vertical steel pipe (1), adjusting sleeve pipe (2), jacking Mechanism and installation frame (3), the jacking mechanism include threaded rod (4) and tapped adjustment seat (5), the adjustment seat (5) it is threadedly coupled with the threaded rod (4);
The threaded rod (4) is injected from the steel pipe (1) bottom, and top surface and the steel pipe (1) bottom end of the adjustment seat (5) connect It touches and supports, ground base (6) forms support to the bottom of the threaded rod (4), is used to hold out against at the top of the steel pipe (1) indoor Top (7);
The steel pipe (1) is held out against between indoor ground base (6) and indoor top (7) by jacking mechanism, can be by described Adjustment seat (5) adjusts the vertical position of the steel pipe (1), and the steel pipe (1) can be relative to the threaded rod (4) vertical motion;
The adjusting sleeve pipe (2) is set in the steel pipe (1) outer surface, and adjusting sleeve pipe (2) internal diameter and the steel pipe (1) are outside Diameter is adapted, and is offered threaded hole (8) on the adjusting sleeve pipe (2), is connected with lock-screw in the threaded hole (8), described Adjusting sleeve pipe (2) can adjust its mounting height along the steel pipe (1) length direction, and realize adjusting sleeve pipe by lock-screw (2) it is locked on the steel pipe (1), the installation frame (3) is fixedly installed on the adjusting sleeve pipe (2), the peace Frame (3) are framed up for distribution box to be fixedly mounted.
2. the auxiliary mould of indoor distribution box construction according to claim 1, it is characterised in that: the top of the steel pipe (1) End is fixedly installed with channel steel seat (9), and the notch of the channel steel seat (9) is upward, and chock block (10) are fixedly installed in the notch, The chock block (10) contacts support with indoor top (7);The bottom end of the threaded rod (4) is also fixedly installed with channel steel seat (9), The notch of the channel steel seat (9) is downward, is also fixedly installed in the notch chock block (10), the chock block (10) and ground Basic (6) contact support.
3. the auxiliary mould of indoor distribution box construction according to claim 1, it is characterised in that: adjustment seat (5) tool There are two adjust ear (11).
4. the auxiliary mould of indoor distribution box construction according to claim 1, it is characterised in that: the installation frame (3) Formed including four angle steel, form a rectangular frame, the installation frame (3) by other two horizontal angle steel (12) with The adjusting sleeve pipe (2) is welded and fixed.
5. the auxiliary mould of indoor distribution box construction according to claim 4, it is characterised in that: two horizontal angle steel (12) it is located at the left and right sides of the adjusting sleeve pipe (2).
6. the auxiliary mould of indoor distribution box construction according to claim 4, it is characterised in that: the installation frame (3) Angle steel on offer through-hole (13), the position of mounting hole Corresponding matching on through-hole (13) position and the distribution box leads to Cross screw being fixedly connected across the through-hole (13) and the mounting hole realization distribution box and installation frame (3).
7. the construction method of the auxiliary mould using the construction of indoor distribution box described in claim 1 to 6, it is characterised in that: first Distribution box is fixedly installed on installation frame (3), is determined on ground base (6) further according to the specific installation site of distribution box Installation auxiliary device is moved to projected position and is adjusted by the projected position of distribution box, so that distribution box is located at projection position Right above setting, adjustment seat (5) then are adjusted, so that steel pipe (1) is vertically raised and keeps vertical, until holding out against at the top of steel pipe (1) Indoor top (7) then adjusts the vertical installation of adjusting sleeve pipe (2) on steel pipe (1) according to the design mounting height of distribution box Position simultaneously guarantees that distribution box end face is flushed with metope, until being adjusted to the design mounting height of distribution box, it is solid to tighten lock-screw It is fixed, then spool is correspondingly connected to the knock-off hole on distribution box, so far the positioning of distribution box is completed, and can carry out the masonry of wall Construction carries out building construction according to already installed distribution box and reserved lintel, the small gap of distribution box surrounding is filled out with mortar Reality.
CN201811104909.6A 2018-09-21 2018-09-21 The auxiliary mould and its construction method of indoor distribution box construction Pending CN109057255A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811104909.6A CN109057255A (en) 2018-09-21 2018-09-21 The auxiliary mould and its construction method of indoor distribution box construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811104909.6A CN109057255A (en) 2018-09-21 2018-09-21 The auxiliary mould and its construction method of indoor distribution box construction

Publications (1)

Publication Number Publication Date
CN109057255A true CN109057255A (en) 2018-12-21

Family

ID=64762375

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811104909.6A Pending CN109057255A (en) 2018-09-21 2018-09-21 The auxiliary mould and its construction method of indoor distribution box construction

Country Status (1)

Country Link
CN (1) CN109057255A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110565952A (en) * 2019-09-12 2019-12-13 上海建工一建集团有限公司 electric box installation device and installation method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008071827A2 (en) * 2006-12-15 2008-06-19 Sanchez Lorenzo Salvador Support means for built-in assembly of electric boxes
CN104196239A (en) * 2014-08-11 2014-12-10 中建二局第三建筑工程有限公司 Method for installing concealed installation distribution box in block wall and applied fixing device
CN205543820U (en) * 2016-02-04 2016-08-31 中国五冶集团有限公司 Novel mounting bracket
CN107171233A (en) * 2017-06-23 2017-09-15 陕西建工第三建设集团有限公司 Built a wall after building concealed distribution box one-time-reach-place installation method
CN107394648A (en) * 2017-09-11 2017-11-24 中国五冶集团有限公司 Servicing unit for strong and weak electronic box location and installation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008071827A2 (en) * 2006-12-15 2008-06-19 Sanchez Lorenzo Salvador Support means for built-in assembly of electric boxes
CN104196239A (en) * 2014-08-11 2014-12-10 中建二局第三建筑工程有限公司 Method for installing concealed installation distribution box in block wall and applied fixing device
CN205543820U (en) * 2016-02-04 2016-08-31 中国五冶集团有限公司 Novel mounting bracket
CN107171233A (en) * 2017-06-23 2017-09-15 陕西建工第三建设集团有限公司 Built a wall after building concealed distribution box one-time-reach-place installation method
CN107394648A (en) * 2017-09-11 2017-11-24 中国五冶集团有限公司 Servicing unit for strong and weak electronic box location and installation

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110565952A (en) * 2019-09-12 2019-12-13 上海建工一建集团有限公司 electric box installation device and installation method

Similar Documents

Publication Publication Date Title
CN103498555B (en) Adjustable large area terrace steel channel formwork system and construction method thereof
US20140259989A1 (en) Pivoting bracket for foundation support system
WO2019105022A1 (en) System and method applicable to automatically adjusting elevation of horizontal prefabricated component
CN104711996A (en) End steel shell mounting and positioning device and operation method
CN207283099U (en) A kind of wall pre-embedded hydroelectric line case positioning device
CN109057255A (en) The auxiliary mould and its construction method of indoor distribution box construction
CN109057254A (en) Fixation device and its construction method for indoor distribution box construction
CN105421629A (en) Fixing device and installation method for curtain wall unit
CN109066409A (en) The auxiliary device and its installation method of indoor distribution box installation
CN104452810B (en) The erecting device of pipe trench interior conduit buttress and mounting method thereof
CN110416888A (en) The connection structure and its construction method of installation breakers on a kind of masonry panel
CN210049616U (en) Vertical pre-buried device of reservation entrance to a cave
JP2002322701A (en) Structure and method for execution of piping
CN208608690U (en) Embedded junction box accurate-location device in a kind of masonry structure
CN104405233B (en) A kind of erection of doors and windows method
CN208056661U (en) A kind of pinpoint device of pre embedded bolt
CN210628812U (en) Connecting structure for installing distribution equipment on masonry wall
CN112096096B (en) Positioning device for embedded steel plate and construction method thereof
CN207878943U (en) A kind of foundation ground flatness and elevation control device
CN207812926U (en) A kind of decoration of exterior wall board mounting assembly
KR101072091B1 (en) Height control member for low and high contril of window
JPH10311045A (en) Surface table construction method and device for erecting post
CN104328981A (en) Door and window attached frame positioning and installing method
CN216378938U (en) Ballastless track plate structure seam construction fixing device and tunnel construction device
CN214008278U (en) Engineering construction is pre-buried auxiliary device of pipeline for construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181221