CN109057254A CN201811104642.0A CN201811104642A CN109057254A CN 109057254 A CN109057254 A CN 109057254A CN 201811104642 A CN201811104642 A CN 201811104642A CN 109057254 A CN109057254 A CN 109057254A
Authority
CN
China
Prior art keywords
distribution box
steel pipe
indoor
hole
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811104642.0A
Other languages
Chinese (zh)
Inventor
王涛
廖晓涛
谭彪
陈浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN201811104642.0A priority Critical patent/CN109057254A/en
Publication of CN109057254A publication Critical patent/CN109057254A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Sewage (AREA)

Abstract

本发明涉及室内施工技术领域,公开用于户内配电箱施工的固定装置及方法,包括:钢管、调节套管和安装框架,顶托机构包括螺纹杆和带内螺纹的调节座;螺纹杆插进钢管底部,调节座与钢管底端接触支撑,地面基础对螺纹杆支撑,钢管用于顶紧户内顶部,钢管竖向可调;调节套管套装在钢管上、且具有螺纹孔,调节套管可沿钢管长度调节其高度,并通过锁紧螺钉固定于钢管上;调节套管上下部焊接水平横梁,水平横梁具有条形孔,安装框架上下部焊接角钢,角钢具有通孔,螺栓穿过通孔和条形孔实现安装框架与水平横梁固接,安装框架固装配电箱。能便捷地将配电箱支撑于设计高度,安装过程不受其他专业影响,线管与配件箱连接的操作空间大,无需大量填补工作。

The invention relates to the technical field of indoor construction, and discloses a fixing device and method for the construction of an indoor distribution box, including: a steel pipe, an adjusting sleeve and an installation frame, a jacking mechanism including a threaded rod and an adjusting seat with an internal thread; the threaded rod Inserted into the bottom of the steel pipe, the adjustment seat is in contact with the bottom of the steel pipe for support, the ground foundation is supported by the threaded rod, the steel pipe is used to tighten the indoor roof, and the steel pipe is vertically adjustable; the adjustment sleeve is set on the steel pipe and has a threaded hole. The height of the casing can be adjusted along the length of the steel pipe, and it is fixed on the steel pipe by locking screws; the upper and lower parts of the adjustment casing are welded with horizontal beams, which have strip holes, and the upper and lower parts of the installation frame are welded with angle steel, which has through holes for bolts to pass through. The installation frame is fixed to the horizontal beam through the through hole and the strip hole, and the installation frame is fixed to the electrical box. It can conveniently support the distribution box at the design height, and the installation process will not be affected by other specialties. There is a large operating space for the connection between the wire pipe and the accessory box, and there is no need for a lot of filling work.

Description

Fixation device and its construction method for indoor distribution box construction
Technical field
The present invention relates to indoor construction technical fields, in particular to are used for the fixation device of indoor distribution box construction and its apply Work method.
Background technique
Indoors when construction, the installation of cubicle switch and its spool is often related to, there are two types of conventional modes:
The first is first to complete wall construction, and the hole of installation distribution box has been reserved on wall, has then been opened up on wall The tube seat of spool and plastering are installed, then electrician installs spool, and by spool and distribution box abutting joint, due to hole and distribution Adjustment gap very little between case, causes spool and docking for distribution box very inconvenient, meanwhile, spool and distribution box are installed Afterwards, it also needs brickwork further to plaster, and the gap between distribution box and hole is poured and is filled up, be related to two work posts Cross-operation, it is very complicated;
It is for second while embedded spool during wall construction, needs brickwork and electrician to cooperate at the scene simultaneously at this time and apply Work is buried always to the position for needing reserved opening, and work progress is very complicated, after the completion of wall construction, then installs distribution Case is also required at this time by distribution box and spool abutting joint, to reserved opening also due to the adjustment between hole and distribution box Gap very little causes spool and docking for distribution box very inconvenient, meanwhile, after distribution box is installed, also need brickwork further Gap between distribution box and hole is poured and is filled up, the cross-operation of two work posts is also related to, it is very complicated.
In conclusion above two mode has the following problems: 1, installing distribution box in reserved opening and be easy to appear peace Phenomena such as dress skew, cabinet recess, levelness is poor, and later period adjustment difficulty is larger;2, distribution box and spool attended operation space It is limited, it installs inconvenient;3, the later period between reserved opening and distribution box, which pours, fills up heavy workload, increases distribution carton deformed With hollowing risk;4, electrician and brickwork cross-operation are frequent, and work progress is cumbersome.
Therefore, the application proposes a kind of fixation device and its construction method for indoor distribution box construction.
Summary of the invention
The technical problems to be solved by the present invention are: in view of the above problems, providing a kind of for indoor distribution The fixation device and its construction method of case construction, installation are adjusted and fixation procedure is convenient and efficient, can be convenient and will effectively be matched Electronic box is fixedly supported to design height position, the vertical adjustment range of adjusting sleeve pipe is big, installation frame can transverse shifting adjust, energy Enough in the vertical and lateral design installation site for effectively adapting to each distribution box, guarantees positioning and the installation quality of distribution box, increase Adaptability, installation process are not influenced by other professions, and installation effectiveness is higher, more flexible, the operation that spool is connect with fitting case Space is big, and spool can arrange neat smooth, and the gap between distribution box surrounding and subsequent masonry panel is small, does not need largely to fill up Work, distribution box are unlikely to deform, and levelness can guarantee well.
The technical solution adopted by the invention is as follows: for indoor distribution box construction fixation device, including vertical steel pipe, Adjusting sleeve pipe, jacking mechanism and installation frame, the jacking mechanism include threaded rod and tapped adjustment seat, the tune Section seat is threadedly coupled with the threaded rod;
The threaded rod is injected from the steel pipe bottom, and the top surface of the adjustment seat contacts and supports, ground with the steel pipe bottom end Face basis forms the threaded rod bottom and supports, and the steel pipe top is for holding out against indoor top;
The steel pipe is held out against between indoor ground base and indoor top by jacking mechanism, can be adjusted by the adjustment seat The vertical position of the steel pipe, the steel pipe can be relative to the threaded rod vertical motions;
The adjusting sleeve pipe is set in the outer surface of steel tube, and threaded hole, the adjusting sleeve pipe are offered on the adjusting sleeve pipe Its mounting height can be adjusted along the length of steel pipe direction, and adjusting sleeve pipe lock is realized by threaded hole described in lock-screw precession It is tightly fixed on the steel pipe;
The adjusting sleeve pipe top and the bottom are welded with horizontal gird, and strip-shaped hole, the peace are offered on the horizontal gird The frame up top and the bottom of frame are welded with horizontal angle steel, offer through-hole on the angle steel of the level, pass through institute by bolt It states through-hole and strip-shaped hole realizes that the installation frame is fixedly connected with the horizontal gird, the installation frame is for being fixedly mounted Distribution box.
So set, steel pipe easily and effectively can be fixedly supported to indoor ground base and indoor top by jacking mechanism Between portion, can conveniently and efficiently adjust vertical fixed position of the adjusting sleeve pipe on steel pipe, so by distribution box positioning support in The height and position of design can conveniently and efficiently adjust lateral peace of the installation frame on horizontal gird in strip-shaped hole length range Holding position, and then distribution box is finely tuned to the position that is transversely mounted of design, installation process is not influenced by other professions, installation effectiveness Higher, more flexible, the operating space that spool is connect with fitting case is big, spool can arrange it is neat smooth, distribution box surrounding with it is subsequent The gap formed between masonry panel is small, does not need largely to fill up work, and distribution box is unlikely to deform, and levelness can protect well Card, meanwhile, the vertical height of steel pipe can be changed by adjusting adjustment seat, and then adapt to the high scene of different layers, ground can be adapted to The variation of spacing between basic and indoor top.
Fixation device of the present invention for indoor distribution box construction, the top of the steel pipe is fixedly installed with channel steel Seat, the notch of the channel steel seat is upward, and chock block is fixedly installed in the notch, and the chock block contacts branch with indoor top Support;The bottom end of the threaded rod is also fixedly installed with channel steel seat, and the notch of the channel steel seat is downward, also fixed in the notch to pacify Equipped with chock block, the chock block contacts support with ground base.
So set, chock block further ensures present apparatus upper and lower side respectively between ground base and indoor top Stability of strutting system and reliability, channel steel seat provide reliable and stable installation site for chock block.
Fixation device of the present invention for indoor distribution box construction, there are two adjust ear for the adjustment seat tool.
So set, operator can easily rotate operation adjustment seat by adjusting ear, so that the vertical adjustment of steel pipe Process is more smooth.
Fixation device of the present invention for indoor distribution box construction, the adjustment seat top surface have annular groove, steel Pipe lower end is located in the annular groove.
So set, annular groove can play positioning action to steel pipe, prevent steel pipe from moving horizontally relative to adjustment seat, guarantees The horizontal position accurate positioning of distribution box.
Fixation device of the present invention for indoor distribution box construction, installation frame top and the bottom two are horizontal Angle steel is located at the left and right sides of the adjusting sleeve pipe.
So set, ensure that the reliability that installation frame is fixedly connected with adjusting sleeve pipe.
Fixation device of the present invention for indoor distribution box construction, the installation frame include four angle steel groups At forming a rectangular frame, two horizontal angle steel are welded and fixed with the top angle steel of rectangular frame and lower part angle steel respectively.
So set, installation frame is made of angle steel, material has been saved, the discarded angle steel system of construction site can be selected Make, it is convenient and efficient, it reduces costs.
Fixation device of the present invention for indoor distribution box construction, the company of offering on the angle steel of the installation frame Connect hole, the position of mounting hole Corresponding matching on the connection hole site and the distribution box, by screw pass through the through-hole and Mounting hole realizes being fixedly connected for the distribution box and installation frame.
So set, make the installation of distribution box and installation frame fixed more rationally, reliable, the later period is between the two to be torn open It unloads also more convenient, and distribution box will not be damaged.
The construction method of fixation device of the present invention for indoor distribution box construction, first distribution box is fixedly mounted In on installation frame, the projected position of distribution box is determined in ground base further according to the specific installation site of distribution box, will be pacified Dress auxiliary device is moved to projected position and is adjusted, so that distribution box is located at right above projected position, then adjusts Seat, until steel pipe top holds out against indoor top, is then pacified according to the design of distribution box so that steel pipe is vertically raised and keeps vertical It fills vertical installation site of the height adjustment adjusting sleeve pipe on steel pipe and guarantees that distribution box end face is flushed with metope, until adjusting It to the design mounting height of distribution box, tightens lock-screw and fixes, then spool is correspondingly connected to the knock-off hole on distribution box, until The positioning of this distribution box is completed, and the building construction of wall can be carried out, and carries out building construction according to already installed distribution box It is tamped with the small gap of reserved lintel, distribution box surrounding with mortar.
Using this construction method, there is no the cross-operation of different majors, so that left and right process is more orderly, it is cumbersome, Flowing water section can be divided to construct, improve it is whole make operating efficiency, improve the installation quality of distribution box.
The construction method of indoor distribution box of the present invention, after steel pipe top holds out against indoor top, if the non-position of distribution box Right above the projected position, can in strip-shaped hole length range lateral adjustments installation frame lateral position, and then adjust distribution The lateral position of case makes distribution box be located at the surface of projected position;It, can be according to the perpendicular of distribution box bottom spool when spool is installed To corresponding specific location, the lateral position of lateral adjustments installation frame in strip-shaped hole length range, and then adjust distribution box Lateral position so that knock-off hole on distribution box is directed at spool.
Compared with prior art, having the beneficial effect that using auxiliary device and peace of the invention by adopting the above technical scheme Dress method, installation are adjusted and fixation procedure is convenient and efficient, can be convenient and distribution box be effectively fixedly supported to design height Position, the vertical adjustment range of adjusting sleeve pipe is big, installation frame can transverse shifting adjust, can be vertical and laterally effectively adapt to The design installation site of each distribution box guarantees positioning and the installation quality of distribution box, increases adaptability, installation process is not by it He influences profession, and installation effectiveness is higher, more flexible, and the operating space that spool is connect with fitting case is big, and spool can arrange neat suitable Freely, the gap between distribution box surrounding and subsequent masonry panel is small, does not need largely to fill up work, distribution box is unlikely to deform, water Pingdu can guarantee well.
Detailed description of the invention
Fig. 1 is scheme of installation of the invention;
Fig. 2 is enlarged drawing at A in Fig. 1;
Fig. 3 is enlarged drawing at B in Fig. 1;
Fig. 4 is enlarged drawing at C in Fig. 1;
Fig. 5 is the side view of installation frame and adjusting sleeve pipe cooperation in the present invention;
Fig. 6 is the top view of horizontal gird in the present invention;
Fig. 7 is the top view of adjustment seat in the present invention;
Fig. 8 is the top view of installation frame and the cooperation of horizontal angle steel in the present invention.
Appended drawing reference: 1 is steel pipe, and 2 be adjusting sleeve pipe, and 3 be installation frame, and 4 be threaded rod, and 5 be adjustment seat, and 6 be ground Basis, 7 be indoor top, and 8 be threaded hole, and 9 be horizontal gird, and 10 be strip-shaped hole, and 11 be horizontal angle steel, and 12 be through-hole, 13 It is chock block for channel steel seat, 14,15 is adjust ear, and 16 be annular groove, and 17 be connecting hole.
Specific embodiment
The present invention is described further with reference to the accompanying drawing.
Embodiment 1
As shown in Fig. 1 to 6,8, for the fixation device of indoor distribution box construction, including vertical steel pipe 1, adjusting sleeve pipe 2, top Support mechanism and installation frame 3, jacking mechanism include threaded rod 4 and tapped adjustment seat 5, adjustment seat 5 and 4 spiral shell of threaded rod Line connection;
Threaded rod 4 is injected from 1 bottom of steel pipe, and the top surface of adjustment seat 5 contacts and supports with 1 bottom end of steel pipe, and ground base 6 is to screw thread Support is formed on 4 bottom of bar, is used to hold out against indoor top 7 at the top of steel pipe 1, steel pipe 1 is held out against by jacking mechanism in indoor ground base Between plinth 6 and indoor top 7, the vertical position of steel pipe 1 can be adjusted by adjustment seat 5, during vertical adjustment, steel pipe 1 can Relative to 4 vertical motion of threaded rod;
Adjusting sleeve pipe 2 is set in 1 outer surface of steel pipe, and 2 internal diameter of adjusting sleeve pipe is adapted with 1 outer diameter of steel pipe, opens up on adjusting sleeve pipe 2 There is threaded hole 8, specifically open up three threaded holes 8 along 2 length direction of adjusting sleeve pipe, adjusting sleeve pipe 2 can be along 1 length direction tune of steel pipe Its mounting height is saved, and realizes that adjusting sleeve pipe 2 is locked in steel pipe by lock-screw (not shown) precession threaded hole 8 On 1, lock-screw holds out against 1 outer surface of steel pipe;
2 top and the bottom of adjusting sleeve pipe are welded with horizontal gird 9, and horizontal gird 9 is specially angle steel, two horizontal girds 9 difference Positioned at the left and right sides of adjusting sleeve pipe 2, lateral strip-shaped hole 10, the top and the bottom weldering of installation frame 3 are offered on two horizontal girds 9 It connects and is fixed with two horizontal angle steel 11, two horizontal angle steel 11 are located at the left and right sides of adjusting sleeve pipe 2, and two horizontal Angle steel 11 is correspondingly connected with 2 left and right sides of adjusting sleeve pipe, two horizontal gird 9 respectively, offers through-hole 12 on horizontal angle steel 11, is led to It crosses bolt (not shown) and realizes that installation frame 3 is fixedly connected with horizontal gird 9 across through-hole 12 and strip-shaped hole 10, it can be in item Installation frame 3 is adjusted in the length range in shape hole 10 and is transversely mounted position on horizontal gird 9, and installation frame 3 is for fixing Distribution box (not shown) is installed.
Further, the top of steel pipe 1 is equipped with channel steel seat 13 by being welded and fixed, and the notch of channel steel seat 13 is upward, slot Chock block 14 is fixedly installed in mouthful, the top surface of chock block 14 is higher by 13 top of channel steel seat, and chock block 14 is contacted with indoor top 7 Support;The bottom end of threaded rod 4 is equipped with channel steel seat 13 also by being welded and fixed, and the notch of channel steel seat 13 is downward, also solid in notch Dingan County is equipped with chock block 14, and the bottom surface of chock block 14 is lower than 13 bottom of channel steel seat, and chock block 14 contacts support with ground base 6.
Embodiment 2
As shown in fig. 7, on the basis of embodiment 1, the tool of adjustment seat 5 has annular groove there are two ear 15,5 top surface of adjustment seat is adjusted 16,1 lower end of steel pipe is located in annular groove 16 with being adapted.
Embodiment 3
As shown in Figures 3 and 5, on the basis of embodiment 2, installation frame 3 includes four angle steel compositions, and four angle steel weld to be formed One rectangular frame, two horizontal angle steel 11 are welded and fixed with the top angle steel of rectangular frame and lower part angle steel respectively, and two Horizontal angle steel 11 is welded and fixed with the top angle steel of rectangular frame and lower part angle steel respectively.
Embodiment 4
As shown in figure 3, offering connecting hole 17,17 position of connecting hole on the angle steel of installation frame 3 on the basis of embodiment 3 With the mounting hole (not shown) position Corresponding matching on distribution box, the quantity of connecting hole 17 and position are pacified according on distribution box The quantity and specific location for filling hole are specifically set, and pass through through-hole 12 by screw (not shown) and mounting hole realizes distribution box With being fixedly connected for installation frame 3.
The construction method of the above-mentioned fixation device for indoor distribution box construction, is first fixedly installed in installation for distribution box On frame 3, the projected position of distribution box is determined in ground base 6 further according to the specific installation site of distribution box, will be installed auxiliary It helps device to be moved to projected position and is adjusted, so that distribution box is located at right above projected position, then adjust adjustment seat 5, So that steel pipe 1 is vertically raised and keeps vertical, until holding out against indoor top 7 at the top of steel pipe 1, then pacified according to the design of distribution box It fills vertical installation site of the height adjustment adjusting sleeve pipe 2 on steel pipe 1 and guarantees that distribution box end face is flushed with metope, until tune It saves to the design mounting height of distribution box, tightens lock-screw and fix, then spool is correspondingly connected to the knock-off hole on distribution box, So far the positioning of distribution box is completed, and can carry out the building construction of wall, build according to already installed distribution box and be applied Work and reserved lintel, the small gap of distribution box surrounding are tamped with mortar.
In above-mentioned construction method, further, after indoor top 7 is held out against at the top of steel pipe 1, if distribution box is not located at throwing Right above shadow position, can in 10 length range of strip-shaped hole lateral adjustments installation frame 3 lateral position, and then adjust distribution box Lateral position, so that distribution box is located at the surface of projected position;It, can be according to the vertical of distribution box bottom spool when spool is installed Corresponding specific location, the lateral position of lateral adjustments installation frame 3 in 10 length range of strip-shaped hole, and then adjust distribution box Lateral position so that knock-off hole on distribution box is directed at spool.
The invention is not limited to specific embodiments above-mentioned.The present invention, which expands to, any in the present specification to be disclosed New feature or any new combination, and disclose any new method or process the step of or any new combination.If this Field technical staff is altered or modified not departing from the unsubstantiality that spirit of the invention is done, should belong to power of the present invention The claimed range of benefit.

Claims (9)

1.用于户内配电箱施工的固定装置,其特征在于:包括竖直的钢管(1)、调节套管(2)、顶托机构和安装框架(3),所述顶托机构均包括螺纹杆(4)和带内螺纹的调节座(5),所述调节座(5)与所述螺纹杆(4)螺纹连接;1. A fixing device for indoor distribution box construction, characterized in that it includes a vertical steel pipe (1), an adjusting sleeve (2), a jacking mechanism and an installation frame (3), and the jacking mechanism is It includes a threaded rod (4) and an adjustment seat (5) with internal threads, and the adjustment seat (5) is threadedly connected with the threaded rod (4); 所述螺纹杆(4)从所述钢管(1)底部插进,所述调节座(5)的顶面与所述钢管(1)底端接触并支撑,地面基础(6)对所述螺纹杆(4)底部形成支撑,所述钢管(1)顶部用于顶紧户内顶部(7);The threaded rod (4) is inserted from the bottom of the steel pipe (1), the top surface of the adjustment seat (5) contacts and supports the bottom end of the steel pipe (1), and the ground foundation (6) supports the thread The bottom of the rod (4) forms a support, and the top of the steel pipe (1) is used to tighten the indoor roof (7); 所述钢管(1)通过顶托机构顶紧于户内地面基础(6)和户内顶部(7)之间,可通过所述调节座(5)调节所述钢管(1)的竖向位置,所述钢管(1)可相对于所述螺纹杆(4)竖向运动;The steel pipe (1) is tightened between the indoor ground foundation (6) and the indoor roof (7) through the jacking mechanism, and the vertical position of the steel pipe (1) can be adjusted through the adjustment seat (5) , the steel pipe (1) can move vertically relative to the threaded rod (4); 所述调节套管(2)套装于所述钢管(1)外表面,所述调节套管(2)上开设有螺纹孔(8),所述调节套管(2)可沿所述钢管(1)长度方向调节其安装高度,并通过锁紧螺钉旋进所述螺纹孔(8)实现调节套管(2)锁紧固定于所述钢管(1)上;The adjusting sleeve (2) is set on the outer surface of the steel pipe (1), and a threaded hole (8) is opened on the adjusting sleeve (2), and the adjusting sleeve (2) can be moved along the steel pipe ( 1) Adjust the installation height in the length direction, and screw the locking screw into the threaded hole (8) to lock and fix the adjusting sleeve (2) on the steel pipe (1); 所述调节套管(2)上下部均焊接固定有水平横梁(9),所述水平横梁(9)上开设有条形孔(10),所述安装框架(3)的上下部焊接固定有水平的角钢(11),所述水平的角钢(11)上开设有通孔(12),通过螺栓穿过所述通孔(12)和条形孔(10)实现所述安装框架(3)与所述水平横梁(9)固定连接,所述安装框架(3)用于固定安装配电箱。The upper and lower parts of the adjusting sleeve (2) are welded and fixed with horizontal beams (9), the horizontal beams (9) are provided with strip holes (10), and the upper and lower parts of the installation frame (3) are welded and fixed with Horizontal angle steel (11), the horizontal angle steel (11) is provided with a through hole (12), and the installation frame (3) is realized by passing through the through hole (12) and the strip hole (10) by bolts Fixedly connected with the horizontal beam (9), the installation frame (3) is used for fixed installation of the distribution box. 2.根据权利要求1所述的用于户内配电箱施工的固定装置,其特征在于:所述钢管(1)的顶端固定安装有槽钢座(13),所述槽钢座(13)的槽口向上,所述槽口内固定安装有垫木块(14),所述垫木块(14)与户内顶部(7)接触支撑;所述螺纹杆(4)的底端也固定安装有槽钢座(13),所述槽钢座(13)的槽口向下,所述槽口内也固定安装有垫木块(14),所述垫木块(14)与地面基础(6)接触支撑。2. The fixing device for indoor distribution box construction according to claim 1, characterized in that: a channel steel seat (13) is fixedly installed on the top of the steel pipe (1), and the channel steel seat (13) ) upwards, and a wooden block (14) is fixedly installed in the notch, and the wooden block (14) is in contact with the indoor top (7) for support; the bottom end of the threaded rod (4) is also fixed A channel steel seat (13) is installed, and the notch of the channel steel seat (13) is downward, and a wooden block (14) is also fixedly installed in the notch, and the wooden block (14) is connected with the ground foundation ( 6) Contact support. 3.根据权利要求1所述的用于户内配电箱施工的固定装置,其特征在于:所述调节座(5)具有两个调节耳(15)。3. The fixing device for indoor distribution box construction according to claim 1, characterized in that: the adjustment seat (5) has two adjustment ears (15). 4.根据权利要求1所述的用于户内配电箱施工的固定装置,其特征在于:所述调节座(5)顶面具有圆环槽(16),钢管(1)下端位于所述圆环槽(16)内。4. The fixing device for indoor distribution box construction according to claim 1, characterized in that: the top surface of the adjustment seat (5) has a circular groove (16), and the lower end of the steel pipe (1) is located at the In the ring groove (16). 5.根据权利要求1所述的用于户内配电箱施工的固定装置,其特征在于:所述安装框架(3)上下部两根水平的角钢(11)分别位于所述调节套管(2)的左右侧。5. The fixing device for indoor distribution box construction according to claim 1, characterized in that: two horizontal angle steels (11) on the upper and lower parts of the installation frame (3) are respectively located in the adjustment sleeve ( 2) Left and right sides. 6.根据权利要求1所述的用于户内配电箱施工的固定装置,其特征在于:所述安装框架(3)包括四根角钢组成,形成一个矩形框架,两根水平的角钢(11)分别与矩形框架的上部角钢和下部角钢焊接固定。6. The fixing device for indoor distribution box construction according to claim 1, characterized in that: the installation frame (3) consists of four angle steels, forming a rectangular frame, two horizontal angle steels (11 ) are respectively welded and fixed to the upper angle steel and the lower angle steel of the rectangular frame. 7.根据权利要求6所述的用于户内配电箱施工的固定装置,其特征在于:所述安装框架(3)的角钢上开设有连接孔(17),所述连接孔(17)位置与所述配电箱上的安装孔位置对应匹配,通过螺钉穿过所述通孔(12)和安装孔实现所述配电箱与安装框架(3)的固定连接。7. The fixing device for indoor distribution box construction according to claim 6, characterized in that: the angle steel of the installation frame (3) is provided with a connection hole (17), and the connection hole (17) The position is correspondingly matched with the position of the installation hole on the distribution box, and the fixed connection between the distribution box and the installation frame (3) is realized by passing through the through hole (12) and the installation hole with screws. 8.利用权利要求1至7所述的用于户内配电箱施工的固定装置的施工方法,其特征在于:先将配电箱固定安装于安装框架(3)上,再根据配电箱具体安装位置在地面基础(6)上确定出配电箱的投影位置,将安装辅助装置移动至投影位置、并进行调整,使得配电箱位于投影位置正上方,然后调节调节座(5),使得钢管(1)竖向上升并保持竖直,直至钢管(1)顶部顶紧户内顶部(7),然后根据配电箱的设计安装高度调节调节套管(2)在钢管(1)上的竖向安装位置、并保证配电箱端面与墙面齐平,直至调节至配电箱的设计安装高度,拧紧锁紧螺钉固定,再将线管对应连接至配电箱上的敲落孔,至此配电箱的定位完成,即可进行墙体的砌筑施工,根据已经安装好的配电箱进行砌筑施工和预留过梁,配电箱四周的小缝隙用砂浆填实即可。8. The construction method using the fixing device for indoor distribution box construction according to claims 1 to 7, characterized in that: the distribution box is fixedly installed on the installation frame (3) first, and then according to the distribution box The specific installation position determines the projection position of the distribution box on the ground foundation (6), moves the installation auxiliary device to the projection position, and adjusts it so that the distribution box is located directly above the projection position, and then adjusts the adjustment seat (5), Make the steel pipe (1) rise vertically and keep it vertical until the top of the steel pipe (1) presses against the indoor top (7), and then adjust the installation height of the adjusting sleeve (2) on the steel pipe (1) according to the design of the distribution box The vertical installation position, and ensure that the end face of the distribution box is flush with the wall until it is adjusted to the designed installation height of the distribution box, tighten the locking screw to fix it, and then connect the line pipe to the knock-out hole on the distribution box At this point, the positioning of the distribution box is completed, and the masonry construction of the wall can be carried out. According to the installed distribution box, the masonry construction and the reserved lintel are carried out. The small gaps around the distribution box can be filled with mortar. . 9.根据权利要求8所述的户内配电箱的施工方法,其特征在于:钢管(1)顶部顶紧户内顶部(7)后,若配电箱未位于投影位置正上方,可在条形孔(10)长度范围内横向调节安装框架(3)的横向位置,进而调节配电箱的横向位置,使配电箱位于投影位置的正上方;安装线管时,可根据配电箱底部线管的竖向对应的具体位置,在条形孔(10)长度范围内横向调节安装框架(3)的横向位置,进而调节配电箱的横向位置,使得配电箱上的敲落孔对准线管。9. The construction method of the indoor distribution box according to claim 8, characterized in that: after the top of the steel pipe (1) is pressed against the indoor top (7), if the distribution box is not located directly above the projected position, it can be Adjust the lateral position of the installation frame (3) horizontally within the length of the strip hole (10), and then adjust the lateral position of the distribution box so that the distribution box is located directly above the projection position; For the specific position corresponding to the vertical direction of the bottom line pipe, adjust the horizontal position of the installation frame (3) horizontally within the length of the strip hole (10), and then adjust the horizontal position of the distribution box so that the knock-out hole on the distribution box Align the conduit.
CN201811104642.0A 2018-09-21 2018-09-21 Fixation device and its construction method for indoor distribution box construction Pending CN109057254A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811104642.0A CN109057254A (en) 2018-09-21 2018-09-21 Fixation device and its construction method for indoor distribution box construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811104642.0A CN109057254A (en) 2018-09-21 2018-09-21 Fixation device and its construction method for indoor distribution box construction

Publications (1)

Publication Number Publication Date
CN109057254A true CN109057254A (en) 2018-12-21

Family

ID=64763357

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811104642.0A Pending CN109057254A (en) 2018-09-21 2018-09-21 Fixation device and its construction method for indoor distribution box construction

Country Status (1)

Country Link
CN (1) CN109057254A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110565952A (en) * 2019-09-12 2019-12-13 上海建工一建集团有限公司 electric box installation device and installation method
CN111677938A (en) * 2020-06-23 2020-09-18 中国五冶集团有限公司 A W-type flexible cast iron drainage pipe load-bearing structure
CN112993833A (en) * 2019-12-17 2021-06-18 柏诚工程股份有限公司 Method for centralized installation of multiple power distribution cabinets of static pressure box

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196239A (en) * 2014-08-11 2014-12-10 中建二局第三建筑工程有限公司 Method for installing concealed installation distribution box in block wall and applied fixing device
CN204597304U (en) * 2015-05-07 2015-08-26 中国新兴建设开发总公司 A kind of distributing box fixing device for installing
CN205846637U (en) * 2016-07-15 2016-12-28 中建五局第三建设有限公司 Distribution box and wire box direct-buried device in inner and outer building blocks
CN205921249U (en) * 2016-08-08 2017-02-01 广东施富电气实业有限公司 XM type lighting power distribution panel's casing
CN107171233A (en) * 2017-06-23 2017-09-15 陕西建工第三建设集团有限公司 Built a wall after building concealed distribution box one-time-reach-place installation method
CN107394648A (en) * 2017-09-11 2017-11-24 中国五冶集团有限公司 Servicing unit for strong and weak electronic box location and installation

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196239A (en) * 2014-08-11 2014-12-10 中建二局第三建筑工程有限公司 Method for installing concealed installation distribution box in block wall and applied fixing device
CN204597304U (en) * 2015-05-07 2015-08-26 中国新兴建设开发总公司 A kind of distributing box fixing device for installing
CN205846637U (en) * 2016-07-15 2016-12-28 中建五局第三建设有限公司 Distribution box and wire box direct-buried device in inner and outer building blocks
CN205921249U (en) * 2016-08-08 2017-02-01 广东施富电气实业有限公司 XM type lighting power distribution panel's casing
CN107171233A (en) * 2017-06-23 2017-09-15 陕西建工第三建设集团有限公司 Built a wall after building concealed distribution box one-time-reach-place installation method
CN107394648A (en) * 2017-09-11 2017-11-24 中国五冶集团有限公司 Servicing unit for strong and weak electronic box location and installation

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110565952A (en) * 2019-09-12 2019-12-13 上海建工一建集团有限公司 electric box installation device and installation method
CN112993833A (en) * 2019-12-17 2021-06-18 柏诚工程股份有限公司 Method for centralized installation of multiple power distribution cabinets of static pressure box
CN111677938A (en) * 2020-06-23 2020-09-18 中国五冶集团有限公司 A W-type flexible cast iron drainage pipe load-bearing structure

Similar Documents

Publication Publication Date Title
CN103498555B (en) Adjustable large-area terrace slot steel template system and construction method thereof
KR101304985B1 (en) Foundation bolt mount with height adjustment
JP2010043468A (en) Anchor bolt setting apparatus and construction method of foundation
KR20210016812A (en) Reinforcing rod fixing system for pricast concrete column
CN108539687B (en) Fine-tuning type civil building line-connecting and line-arranging box accurate pre-installation structure and construction method
JP2008267030A (en) Method and device for supporting anchor bolt for building structure
CN109057255A (en) The auxiliary mould and its construction method of indoor distribution box construction
JP2022136214A (en) Fire extinguisher stand, fire extinguisher
CN109066409A (en) The auxiliary device and its installation method of indoor distribution box installation
JP4628739B2 (en) Steel column installation jig, concrete pile and steel column joining method using this steel column installation jig, and joint structure between concrete pile and steel column
CN208608690U (en) Embedded junction box accurate-location device in a kind of masonry structure
CN210628812U (en) A connection structure for installing power distribution equipment on a masonry wall
KR100824799B1 (en) Local panel assembly device using unit panel
CN208056661U (en) A kind of pinpoint device of pre embedded bolt
KR20120106172A (en) Pipe stands
CN205791363U (en) A kind of electrical engineering positioning installation apparatus
KR200468906Y1 (en) Foundation bolt mount with height adjustment
JP2000215707A (en) Anchor frame for lighting pole
KR101955352B1 (en) Fixing apparatus of embedded-type for securing a support means and installation method of support means using the same
CN219317838U (en) Hanging rod embedded mounting structure capable of fine adjustment of position
KR200263919Y1 (en) Base for fixing support of road facilities
CN114991281B (en) Assembled pipeline supporting device and pipe laying construction method
KR101239038B1 (en) Base ground construction method for concrete waterway pipe
KR200475858Y1 (en) Connection devices for Steel skeleton
CN110424551B (en) Reinforcing device for large-size arc embedded part for silo outer wall fixation and use method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181221