CN109056716A - Rubber bag tank (chamber) Post Grouting Technique is installed at manually digging hole and full-sleeve engineering method bored concrete pile bottom - Google Patents
Rubber bag tank (chamber) Post Grouting Technique is installed at manually digging hole and full-sleeve engineering method bored concrete pile bottom Download PDFInfo
- Publication number
- CN109056716A CN109056716A CN201810868749.6A CN201810868749A CN109056716A CN 109056716 A CN109056716 A CN 109056716A CN 201810868749 A CN201810868749 A CN 201810868749A CN 109056716 A CN109056716 A CN 109056716A
- Authority
- CN
- China
- Prior art keywords
- rubber bag
- bag tank
- steel plate
- hole
- pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/62—Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/04—Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Manually digging hole and full-sleeve engineering method bored concrete pile bottom installation rubber bag tank (chamber) Post Grouting Technique are suitable for foundation and underground space field of engineering technology, background technique is to use the drilling of mud off at present, steel reinforcement cage bottom such as installation steel plate capsule, it be easy to cause borehole wall to collapse, keep bottom hole sediment exceeded, it is also easy to accumulate the silt to get off that collapses from hole wall above steel plate, influences the quality of cast-in-situ bored pile.The most prominent feature of the present invention is to have found a restrictive condition and applicable elements for the bottom installation closed slip casting of slip casting container, to the effect that pouring pile hole utilizes manually digging hole or full-sleeve engineering method, pore forming process does not use mud off, Grouting Pipe is bound on steel reinforcement cage, steel reinforcement cage bottom is installed by steel plate, rubber bag tank is installed in steel plate bottom surface, and Grouting Pipe passes through steel plate and is connected with rubber bag tank.After above-mentioned engineering method pore-forming, bottom hole will be arrived under steel reinforcement cage, then start concrete perfusion, after pile strength is met the requirements, by Grouting Pipe to the rubber bag tank slip casing by pressure of stake bottom.
Description
Technical field:
Ground and base basis underground space engineering technology
Background technique:
At present in foundation field, what bored concrete pile Post Grouting Technique was included in building pile foundation specification is open type slip casting, because
Relatively easy for open type slip casting implementation process, Grouting Pipe is with the process under steel reinforcement cage to bottom hole to hole wall especially before perfusion
Disturbance very little, but its slurries of open type slip casting note domain controllability is low, formation to stake end enlarged footing and to surrounding formation
The amplitude that compacted effect and bearing capacity of pile tip improve is not if any the closed slip casting of slip casting bag (chamber).Stake bottom has slip casting bag (chamber)
Although closed slip casting according to the requirement of slip casting " three fixed ", i.e. orientation, localization and quantitative aspect has more superiority, is using
During the bored pile construction of mud off, there is also apparent defects.Steel plate capsule such as is installed at steel reinforcement cage bottom
(chamber) is used as grouting behind shaft or drift lining container, and during under with steel reinforcement cage to bottom hole, the steel reinforcement cage with protection steel plate is in the borehole still
It such as piston, is easy to form vortex in slime water, makes to circle round and the mud current scour between steel plate edge and the wall of a borehole and disturb
Dynamic borehole wall, the steel plate of bottom are also easy scratch borehole wall, these factors all be easy to cause borehole wall to collapse, cause through
In slip casting container, metapore bottom sediment is again exceeded on earth for drilling after crossing borehole cleaning, while the upper surface of steel plate is also easy accumulation from drilling hole
Collapse the silt to get off on wall, influences the quality of cast-in-situ bored pile, broken pile is caused when serious, if protection steel plate diameter compares
It is small, or because of other reasons such as collapse hole is superfilled, pile grouting capsule (chamber) can also occur and wrapped up by concrete close, work cannot be played
With the phenomenon that, this is also the closing that drilled pile tail band is clearly had slip casting bag (chamber) by technical code for building pile foundation (JGJ94_2008)
The main reason for formula grouting method forecloses (see provision explanation).
Summary of the invention:
The present invention " rubber bag tank (chamber) Post Grouting Technique is installed at manually digging hole and full-sleeve engineering method bored concrete pile bottom " is a kind of pass
The new technical solution after the improvement of pile foundation technical method, the most prominent feature of the present invention are to have found that bottom installation slip casting is held
The restrictive condition and applicable elements of the closed slip casting of device, this technical solution are bottom installation rubber bag tank (chamber) Post Grouting Techniques and fill
Infuse the most reasonable assembled scheme of stake drilling construction method, can solve it is above-mentioned there are problems, the technical solution is simple, practical, makes
Bored concrete pile Post Grouting Technique is more reached perfection.To the effect that pouring pile hole utilizes manually digging hole or full-sleeve engineering method, pore-forming
Process does not use mud off, and Grouting Pipe is bound on steel reinforcement cage, and steel plate is installed in steel reinforcement cage bottom, and rubber bag tank is installed in steel plate bottom surface,
Grouting Pipe passes through steel plate and is connected with rubber bag tank, and steel plate main function is protection capsule.Using manually digging hole or full-sleeve engineering method
After pore-forming, bottom is equipped with to the steel reinforcement cage of steel plate rubber bag tank, it is lower to arrive bottom hole, then start concrete perfusion and forms bored concrete pile,
After pile strength is met the requirements, built-in slip casting pipe is begun through to the rubber bag tank slip casing by pressure of stake bottom, to the stratum of bored concrete pile bottom
It is compacted to carry out densification, final result is to effectively eliminate a bottom sedimentation, increases substantially ultimate bearing capacity of pile tip, reduces engineering and make
Valence.
Specific embodiment:
1, do not made first, in accordance with design requirement using manually digging hole or full-sleeve engineering method pore-forming, pore forming process in building-site
With mud off, Grouting Pipe is bound when making steel reinforcement cage, steel plate is installed in steel reinforcement cage bottom, and rubber bag tank, note are installed in steel plate bottom surface
Slurry pipe is connected across steel plate with rubber bag tank, and steel plate main function is protection capsule.
2, after using manually digging hole or full-sleeve engineering method pore-forming, bottom is equipped with to the steel reinforcement cage of steel plate rubber bag tank, under arrive
Then bottom hole starts concrete perfusion and forms bored concrete pile, after pile strength is met the requirements, begins through built-in slip casting pipe to stake bottom
Rubber bag tank slip casing by pressure, compacted to the stratum progress densification of bored concrete pile bottom, final result is to effectively eliminate a bottom sedimentation, substantially
Degree improves ultimate bearing capacity of pile tip, reduces project cost.
3, the present invention " rubber bag tank (chamber) Post Grouting Technique is installed at manually digging hole and full-sleeve engineering method bored concrete pile bottom " is suitable for
Cohesive soil, silt, husky class soil, rubble class soil and rock weathering layer.
Claims (2)
1. invention " rubber bag tank (chamber) Post Grouting Technique is installed at manually digging hole and full-sleeve engineering method bored concrete pile bottom " is one kind about stake
Base application technology method technical solution new after improving is that pouring pile hole utilizes manually digging hole or full-sleeve engineering method, pore-forming mistake
Journey does not use mud off, and Grouting Pipe is bound on steel reinforcement cage, and steel plate is installed in steel reinforcement cage bottom, and rubber bag tank, note are installed in steel plate bottom surface
Slurry pipe is connected across steel plate with rubber bag tank, and after manually digging hole or full-sleeve engineering method pore-forming, bottom is equipped with steel plate rubber
The steel reinforcement cage of capsule, it is lower to arrive bottom hole, then start concrete perfusion and form bored concrete pile, after pile strength is met the requirements, begins through
It is compacted that built-in slip casting pipe to the rubber bag tank slip casing by pressure of stake bottom, to the stratum of bored concrete pile bottom carries out densification, finally effectively eliminates stake
Bottom sedimentation, increases substantially the construction method and technical solution of ultimate bearing capacity of pile tip.
2. according to claim 1, " rubber bag tank (chamber) grouting behind shaft or drift lining is installed at manually digging hole and full-sleeve engineering method bored concrete pile bottom for the invention
For technology " it is characterized in that pouring pile hole utilizes manually digging hole or full-sleeve engineering method, pore forming process does not use mud off, steel reinforcement cage
Steel plate is installed in upper binding Grouting Pipe, steel reinforcement cage bottom, and rubber bag tank is installed in steel plate bottom surface, and Grouting Pipe passes through steel plate and is connected with rubber bag tank
It is logical, after pore-forming, bottom is equipped with to the steel reinforcement cage of steel plate rubber bag tank, it is lower to arrive bottom hole, then start concrete perfusion and forms perfusion
Stake, after pile strength is met the requirements, begins through built-in slip casting pipe to the rubber bag tank slip casing by pressure of stake bottom, to the ground of bored concrete pile bottom
It is compacted that layer carries out densification, and forms an end enlarged footing.
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810868749.6A CN109056716A (en) | 2018-08-03 | 2018-08-03 | Rubber bag tank (chamber) Post Grouting Technique is installed at manually digging hole and full-sleeve engineering method bored concrete pile bottom |
PCT/CN2019/093556 WO2020024740A1 (en) | 2018-08-03 | 2019-06-28 | Pile bottom grouting cavity and use method, and poured pile body and construction method of poured pile body |
CN201980000960.9A CN110896645B (en) | 2018-08-03 | 2019-06-28 | Pile bottom grouting device, using method thereof, cast-in-place pile body and construction method of cast-in-place pile body |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810868749.6A CN109056716A (en) | 2018-08-03 | 2018-08-03 | Rubber bag tank (chamber) Post Grouting Technique is installed at manually digging hole and full-sleeve engineering method bored concrete pile bottom |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109056716A true CN109056716A (en) | 2018-12-21 |
Family
ID=64832681
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810868749.6A Withdrawn CN109056716A (en) | 2018-08-03 | 2018-08-03 | Rubber bag tank (chamber) Post Grouting Technique is installed at manually digging hole and full-sleeve engineering method bored concrete pile bottom |
CN201980000960.9A Active CN110896645B (en) | 2018-08-03 | 2019-06-28 | Pile bottom grouting device, using method thereof, cast-in-place pile body and construction method of cast-in-place pile body |
Family Applications After (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201980000960.9A Active CN110896645B (en) | 2018-08-03 | 2019-06-28 | Pile bottom grouting device, using method thereof, cast-in-place pile body and construction method of cast-in-place pile body |
Country Status (2)
Country | Link |
---|---|
CN (2) | CN109056716A (en) |
WO (1) | WO2020024740A1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2020024740A1 (en) * | 2018-08-03 | 2020-02-06 | 高永光 | Pile bottom grouting cavity and use method, and poured pile body and construction method of poured pile body |
WO2020133992A1 (en) * | 2018-12-25 | 2020-07-02 | 高永光 | Pile-bottom grouting cavity and method for using same, and cast-in-place pile body and method for constructing same |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113309074B (en) * | 2021-05-12 | 2022-11-25 | 海南省农垦设计院有限公司 | A foundation ditch fender pile for building energy-saving engineering |
CN113699978B (en) * | 2021-08-26 | 2022-08-16 | 北京市市政一建设工程有限责任公司 | Anti-settling grouting process |
CN113718752A (en) * | 2021-09-10 | 2021-11-30 | 中国电建集团成都勘测设计研究院有限公司 | Ground diaphragm wall composite grouting method and grouting structure |
Family Cites Families (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09144000A (en) * | 1995-11-21 | 1997-06-03 | Toudentsuu:Kk | Method and device for retaining earth |
JP3688546B2 (en) * | 2000-02-02 | 2005-08-31 | 東日本旅客鉄道株式会社 | Cast-in-place concrete pile construction method and cast-in-place concrete pile bottom ground preloading device |
JP3669577B2 (en) * | 2001-12-04 | 2005-07-06 | 東日本旅客鉄道株式会社 | Construction method of cast-in-place piles |
JP2003213673A (en) * | 2002-01-22 | 2003-07-30 | Jr Higashi Nippon Consultants Kk | Injection control device for cast-in-place concrete pile bottom ground preloading device and construction method of cast-in-place concrete pile |
CN203514303U (en) * | 2013-10-30 | 2014-04-02 | 南京工业大学 | Post-grouting enlarged-toe uplift micropile |
CN103741683B (en) * | 2013-12-23 | 2015-11-18 | 浙江天润建设有限公司 | A kind of pouch expands end rigid-flexible mechanical arm and construction method |
CN106320728A (en) * | 2016-01-29 | 2017-01-11 | 中天建设集团有限公司 | Double-fluid grouting bag type rapid hole sealing device |
CN106836179B (en) * | 2016-12-07 | 2018-12-14 | 浙江大学城市学院 | The construction method of vertical strengthening ribs enhanced bellows grouting pile |
CN108411920A (en) * | 2018-01-25 | 2018-08-17 | 天津大学 | A kind of the multiple spot bellows grouting device and its method of control soil deformation |
CN109056716A (en) * | 2018-08-03 | 2018-12-21 | 高永光 | Rubber bag tank (chamber) Post Grouting Technique is installed at manually digging hole and full-sleeve engineering method bored concrete pile bottom |
-
2018
- 2018-08-03 CN CN201810868749.6A patent/CN109056716A/en not_active Withdrawn
-
2019
- 2019-06-28 WO PCT/CN2019/093556 patent/WO2020024740A1/en active Application Filing
- 2019-06-28 CN CN201980000960.9A patent/CN110896645B/en active Active
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2020024740A1 (en) * | 2018-08-03 | 2020-02-06 | 高永光 | Pile bottom grouting cavity and use method, and poured pile body and construction method of poured pile body |
CN110896645A (en) * | 2018-08-03 | 2020-03-20 | 高永光 | Pile bottom grouting cavity, using method thereof, cast-in-place pile body and construction method of cast-in-place pile body |
CN110896645B (en) * | 2018-08-03 | 2021-04-02 | 高永光 | Pile bottom grouting device, using method thereof, cast-in-place pile body and construction method of cast-in-place pile body |
WO2020133992A1 (en) * | 2018-12-25 | 2020-07-02 | 高永光 | Pile-bottom grouting cavity and method for using same, and cast-in-place pile body and method for constructing same |
US11401674B2 (en) | 2018-12-25 | 2022-08-02 | Yunfei Gao | Pile-bottom grouting cavity and method for using same, and cast-in-place pile body and method for constructing same |
Also Published As
Publication number | Publication date |
---|---|
CN110896645A (en) | 2020-03-20 |
WO2020024740A1 (en) | 2020-02-06 |
CN110896645B (en) | 2021-04-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109469050A (en) | Grout pile bottom is installed by hollow (hole) doughnut-shaped steel plate capsule (chamber) Post Grouting Technique | |
CN109056716A (en) | Rubber bag tank (chamber) Post Grouting Technique is installed at manually digging hole and full-sleeve engineering method bored concrete pile bottom | |
CN101532290B (en) | Granule grouting pile of ripple plastic sleeve with hole for strengthening soft soil foundation and strengthening method | |
CN1193141C (en) | Combined grouting construction process of reinforcing foundation | |
CN101638891B (en) | Construction method of all casing precessing isolation pile | |
CN104499479B (en) | It is a kind of to pass through the dug pile construction method that sand gravel backfills layer | |
CN101614020B (en) | Flexible bladder type anticorrosion device, anticorrosion pile and construction method using same | |
CN104929114A (en) | High pressure jet grouting pile waterproof curtain construction device and method | |
CN107513995A (en) | A kind of bridge struction pile post grouting construction method | |
CN105464074B (en) | A kind of artificial digging pile high polymer grouting safeguard structure and its construction method | |
CN110735600B (en) | Mechanical pore-forming pile construction process for karst geology | |
CN108867673A (en) | A kind of underwater prevention method in the foundation pit based on the curtain that draws water | |
CN103147450A (en) | Construction method for plugging partial steel pipe dewatering well by using flange plates for excavation of deep foundation pit | |
CN101481913A (en) | Construction method of rock-socketed underground continuous wall punching slot section | |
CN104074184B (en) | Pile base post-grouted expanded-base bored pile | |
CN102979087B (en) | Construction method for rotary excavation pile | |
CN110409416A (en) | A kind of processing method of collapsible soil or molten sunken property soil base | |
CN108360542A (en) | Waterproof between piles curtain combination stake side sleeve valve barrel grouting water stop construction method | |
CN102817349B (en) | Method for consolidating soft soil foundations through fine dynamic compaction replacement | |
CN102425179B (en) | Reinforced soil infiltration ditch structure supported by miniature steel pipe cast-in-place pile | |
CN201411687Y (en) | Corrugated plastic sleeve pipe granule grouting pile with hole | |
Ischy et al. | AN INTRODUCTION TO ALLUVIAL GROUTING. | |
CN106192987A (en) | A kind of construction method that stake periphery is crushed geology reinforcing | |
CN109944251A (en) | The drawing hole construction method that soft rock stratum steel sheet pile is squeezed into | |
CN212001139U (en) | Deep foundation pit supporting structure capable of preventing deformation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information | ||
CB02 | Change of applicant information |
Address after: 102600 Beijing Daxing District Kangzhuang Road No. 9 Central Railway Fifth Courtyard District B Building 703 Applicant after: Gao Yongguang Applicant after: Gao Yunfei Address before: 100012 Huayu City, Tiejian, China 9-1-302, Shuiban South Street, Chaoyang District, Beijing Applicant before: Gao Yongguang Applicant before: Gao Yunfei |
|
WW01 | Invention patent application withdrawn after publication | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20181221 |