CN109024129A - The compacted construction method of high-fill roadbed - Google Patents
The compacted construction method of high-fill roadbed Download PDFInfo
- Publication number
- CN109024129A CN109024129A CN201810953031.7A CN201810953031A CN109024129A CN 109024129 A CN109024129 A CN 109024129A CN 201810953031 A CN201810953031 A CN 201810953031A CN 109024129 A CN109024129 A CN 109024129A
- Authority
- CN
- China
- Prior art keywords
- backfill
- construction method
- fill
- compacted
- compacting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C3/00—Foundations for pavings
- E01C3/04—Foundations produced by soil stabilisation
Abstract
The invention discloses a kind of compacted construction methods of high-fill roadbed, comprising the following steps: (1) prepares backfill material;(2) backfill region is cleared up, then carries out the unwrapping wire of backfill layer;(3) backfill material is backfilled according to unwrapping wire, backfill carries out compacting point setting-out with pulverized limestone afterwards in place, and each compacting point is rammed 3-4 times;(4) it is whole to backfill material once rammed after, expect that pit caused by ramming mend using identical backfill and fill out, benefit is layouted again after tamping reality, carry out it is secondary rams, secondary ram needs all to ram once time filler surface;(5) (2) to the step (4) that repeats the above steps successively is backfilled, until designed elevation.The present invention uses the compacted technique of strong rammer, shortens the backfill duration, and roadbed backfill is high-quality, reduces construction risk, solves the problems, such as that backfill must could be completed using large-scale compacting equipment, has high economic benefit.
Description
Technical field
The invention belongs to highway construction technology fields, and in particular to a kind of compacted construction method of high-fill roadbed.
Background technique
In today of highway in China construction high speed development, high embankment embankment is still in addition to building a bridge across cheuch
One of main means.Guarantee marching into the arena for heavy compacting equipment since the backfill (the especially construction backfill of early period) of high embankment is extremely difficult
Operation can only successively be backfilled using middle-size and small-size compacting equipment, be occurred since compactness deficiency will cause the road after completion
Biggish sedimentation and deformation.Disease is run to reduce later period road, is usually taken postpones pavement construction by the soil body in gravity in the past
Natural consolidation under effect settles or reserves the mode of secondary repairing to guarantee the running quality after engineering is formally handed over.But it is existing
Construction period shortening and postrun heavy traffic pressure, it is secondary perfect to carry out to have extended the duration, because
This, is badly in need of a kind of quick tamping road bed method of energy.
Summary of the invention
The technical problems to be solved by the invention are in view of the above shortcomings of the prior art, to provide a kind of high-fill roadbed
Compacted construction method, it can be quickly tamping road bed using middle-size and small-size equipment, reduces the probability of subgrade deformation.
The technical scheme adopted by the invention is that: a kind of compacted construction method of high-fill roadbed, comprising the following steps:
(1) prepare backfill material, cannot be native containing fertile soil, house refuse in the backfill material of selection, it cannot contain in mud
It is weeds, several;
(2) backfill region is cleared up, then carries out the unwrapping wire of backfill layer;
(3) backfill material is backfilled according to unwrapping wire, backfill carries out compacting point setting-out, each compacting with pulverized limestone afterwards in place
Point is rammed 3-4 times;
(4) after once being rammed to backfill material entirety, expect that pit caused by ramming is mended using identical backfill
It fills out, benefit is layouted again after tamping reality, and progress is secondary to be rammed, and secondary needs of ramming all ram once time filler surface;
(5) (2) to the step (4) that repeats the above steps successively is backfilled, until designed elevation.
Preferably, the spacing in length and breadth of adjacent compacting point is 5m in step (3).
Preferably, the work of ramming in step (3) is carried out from road both lateral sides edge to road-center.
Preferably, the height of every layer of backfill layer is 3m-4m.
Preferably, being equipped with articulamentum between adjacent two layers backfill layer, the articulamentum includes the coagulation of 70%-80%
Soil, the rubble of 10%-15%, surplus are pitch.
The present invention uses the compacted technique of strong rammer, shortens the backfill duration, and roadbed backfill is high-quality, reduces construction wind
Danger solves the problems, such as that backfill must could be completed using large-scale compacting equipment, has high economic benefit.
Specific embodiment
Below in conjunction with specific embodiment, invention is further described in detail.
Embodiment
The compacted construction method of high-fill roadbed provided in this embodiment, comprising the following steps:
(1) prepare backfill material, cannot be native containing fertile soil, house refuse in the backfill material of selection, it cannot contain in mud
It is weeds, several;
(2) backfill region is cleared up, then carries out the unwrapping wire of backfill layer;
(3) backfill material is backfilled according to unwrapping wire, backfill carries out compacting point setting-out, adjacent compacting with pulverized limestone afterwards in place
The spacing in length and breadth of point, with dipstick metering lifting rope length, slings weight according to the sling height being calculated using ramming for 5m, then
Release makes weight fall naturally, and each compacting point needs to ram 3-4 times, to guarantee to ram dense effect, while ramming work
It is carried out from road both lateral sides edge to road-center;
It needs to measure original ground absolute altitude before ramming, often rams and once record the elevation after this is rammed, calculate differential settlement, when
Ramming times should be increased for the third time or when ramming submergence depth for the 4th time greater than specified value;
(4) after once being rammed to backfill material entirety, expect that pit caused by ramming is mended using identical backfill
It fills out, benefit is layouted again after tamping reality, and progress is secondary to be rammed, and secondary needs of ramming all ram once time filler surface;
(5) (2) to the step (4) that repeats the above steps successively is backfilled, until designed elevation, the height of every layer of backfill layer
For 3m-4m, and articulamentum is equipped between adjacent two layers backfill layer, the articulamentum include 70%-80% concrete,
The rubble of 10%-15%, surplus are pitch.
The above is only the preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto, any
The transformation and replacement carried out based on technical solution provided by the present invention and inventive concept should all be covered in protection model of the invention
In enclosing.
Claims (5)
1. a kind of compacted construction method of high-fill roadbed, it is characterised in that: the following steps are included:
(1) prepare backfill material, in the backfill material of selection cannot containing fertile soil, house refuse soil, in mud cannot containing weeds,
It is several;
(2) backfill region is cleared up, then carries out the unwrapping wire of backfill layer;
(3) backfill material is backfilled according to unwrapping wire, backfill carries out compacting point setting-out with pulverized limestone afterwards in place, and each compacting point rams
It hits 3-4 times;
(4) after once being rammed to backfill material entirety, expect that pit caused by ramming mend using identical backfill and fill out, mend
It layouts again after tamping reality, progress is secondary to be rammed, and secondary needs of ramming all ram once time filler surface;
(5) (2) to the step (4) that repeats the above steps successively is backfilled, until designed elevation.
2. the compacted construction method of high-fill roadbed according to claim 1, it is characterised in that: adjacent compacting in step (3)
The spacing in length and breadth of point is 5m.
3. the compacted construction method of high-fill roadbed according to claim 1, it is characterised in that: ram work in step (3)
Make to be carried out from road both lateral sides edge to road-center.
4. the compacted construction method of high-fill roadbed according to claim 1, it is characterised in that: every layer backfill layer height be
3m-4m。
5. the compacted construction method of high-fill roadbed according to claim 1, it is characterised in that: adjacent two layers backfill between layer
It is equipped with articulamentum, it is pitch that the articulamentum, which includes the concrete of 70%-80%, the rubble of 10%-15%, surplus,.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810953031.7A CN109024129A (en) | 2018-08-21 | 2018-08-21 | The compacted construction method of high-fill roadbed |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810953031.7A CN109024129A (en) | 2018-08-21 | 2018-08-21 | The compacted construction method of high-fill roadbed |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109024129A true CN109024129A (en) | 2018-12-18 |
Family
ID=64626664
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810953031.7A Pending CN109024129A (en) | 2018-08-21 | 2018-08-21 | The compacted construction method of high-fill roadbed |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109024129A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110172980A (en) * | 2019-06-19 | 2019-08-27 | 贵州正业工程技术投资有限公司 | A kind of coarse grain block stone superelevation fill foundation ruggedized construction and its construction method |
CN111910613A (en) * | 2020-08-06 | 2020-11-10 | 佛山市佳尚居建筑装饰有限公司 | Construction method of green energy-saving building |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102605698A (en) * | 2012-03-09 | 2012-07-25 | 新疆北新路桥建设股份有限公司 | Construction method for reinforcing and rolling soft soil subgrade by aid of impact-type road roller |
CN104652180A (en) * | 2015-02-11 | 2015-05-27 | 中国水利水电第四工程局有限公司 | Roadbed filling construction method |
CN106835884A (en) * | 2017-01-02 | 2017-06-13 | 浙江泛华工程监理有限公司 | A kind of permanent roadbed construction method of highly filled road |
CN106869000A (en) * | 2017-04-11 | 2017-06-20 | 中交第二航务工程局有限公司 | A kind of device and setting out method for roadbed setting-out |
CN106988323A (en) * | 2017-03-14 | 2017-07-28 | 中国十七冶集团有限公司 | A kind of construction method of silty clay degree of being backfilling and compacted control |
-
2018
- 2018-08-21 CN CN201810953031.7A patent/CN109024129A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102605698A (en) * | 2012-03-09 | 2012-07-25 | 新疆北新路桥建设股份有限公司 | Construction method for reinforcing and rolling soft soil subgrade by aid of impact-type road roller |
CN104652180A (en) * | 2015-02-11 | 2015-05-27 | 中国水利水电第四工程局有限公司 | Roadbed filling construction method |
CN106835884A (en) * | 2017-01-02 | 2017-06-13 | 浙江泛华工程监理有限公司 | A kind of permanent roadbed construction method of highly filled road |
CN106988323A (en) * | 2017-03-14 | 2017-07-28 | 中国十七冶集团有限公司 | A kind of construction method of silty clay degree of being backfilling and compacted control |
CN106869000A (en) * | 2017-04-11 | 2017-06-20 | 中交第二航务工程局有限公司 | A kind of device and setting out method for roadbed setting-out |
Non-Patent Citations (2)
Title |
---|
杨玉平: "《高填方路基强夯法施工技术》", 《中华建设》 * |
苑举民等: "《强夯法高填方路基施工与质量控制》", 《建筑机械化》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110172980A (en) * | 2019-06-19 | 2019-08-27 | 贵州正业工程技术投资有限公司 | A kind of coarse grain block stone superelevation fill foundation ruggedized construction and its construction method |
CN111910613A (en) * | 2020-08-06 | 2020-11-10 | 佛山市佳尚居建筑装饰有限公司 | Construction method of green energy-saving building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101963061B (en) | Construction method for underground box culvert of existing railway line | |
CN106120702B (en) | High roadbed artificial foundation back-filling in layers is layered strong rammer composite reinforcement method | |
CN104358188A (en) | Filling construction method for collapsible loess subgrade | |
CN104695343B (en) | Long-distance jacking construction method based on back wall pushing technology | |
CN113445521B (en) | High side slope construction method for filling | |
CN104294769B (en) | A kind of piling and the construction method increasing the built bridge abutment structure of platform cap composite reinforcement | |
CN202416195U (en) | Pier deviation correcting and reinforcing system | |
CN101311418A (en) | Exchange filling method for deep-foundation pit and large area equipment foundation | |
CN103276649B (en) | Side is had to limit layering many thickness Stone Filled Embankment construction method | |
CN111535291A (en) | Dynamic compaction treatment process for geological structure | |
CN104358196B (en) | Highway open to traffic Embankment Subsidence disposes the construction method of structure | |
CN109024129A (en) | The compacted construction method of high-fill roadbed | |
CN108486976A (en) | Mountain highway, which is filled out, digs intersection road structure and its construction method | |
CN106522248A (en) | Method for reinforcing soil slope and slope reinforcing device | |
CN210194361U (en) | Splicing structure for widening new and old roadbeds on road | |
CN104947648A (en) | Deep replacement dynamic compaction gravel pile foundation reinforcement method | |
CN103993533B (en) | For the comprehensive debulking methods of Canal in Loess Area high-filled embankment | |
CN102296591A (en) | Rapid drainage solidifying treatment method of soft soil foundation | |
CN104727295B (en) | Preexisting hole filler displacement hammer flattener heavy-tamping method | |
CN204097889U (en) | A kind of piling and the built bridge abutment structure of increase platform cap composite reinforcement | |
CN109704656A (en) | A kind of bridge joint hillside fields polymer grouting strengthening method | |
CN109537526A (en) | A kind of ecological revetment and construction method | |
CN206512620U (en) | A kind of steel basil is buried jacking box culvert device | |
CN206385525U (en) | A kind of timber structure for preventing the high backfill earthwork from sinking | |
CN102817298A (en) | Construction method on permafrost |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20190528 Address after: 610000 No. 58 Tengfei Avenue, Qingyang District, Chengdu City, Sichuan Province Applicant after: Guo Cheng Group Co., Ltd Address before: 266071 Yanji Road 237, Shinan District, Qingdao City, Shandong Province Applicant before: East China Construction Engineering Group Limited |
|
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20181218 |