CN109024129A - The compacted construction method of high-fill roadbed - Google Patents

The compacted construction method of high-fill roadbed Download PDF

Info

Publication number
CN109024129A
CN109024129A CN201810953031.7A CN201810953031A CN109024129A CN 109024129 A CN109024129 A CN 109024129A CN 201810953031 A CN201810953031 A CN 201810953031A CN 109024129 A CN109024129 A CN 109024129A
Authority
CN
China
Prior art keywords
backfill
construction method
fill
compacted
compacting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810953031.7A
Other languages
Chinese (zh)
Inventor
杜金明
潘龙海
张鑫
李颖凡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guo Cheng Group Co., Ltd
Original Assignee
East China Construction Engineering Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by East China Construction Engineering Group Ltd filed Critical East China Construction Engineering Group Ltd
Priority to CN201810953031.7A priority Critical patent/CN109024129A/en
Publication of CN109024129A publication Critical patent/CN109024129A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation

Abstract

The invention discloses a kind of compacted construction methods of high-fill roadbed, comprising the following steps: (1) prepares backfill material;(2) backfill region is cleared up, then carries out the unwrapping wire of backfill layer;(3) backfill material is backfilled according to unwrapping wire, backfill carries out compacting point setting-out with pulverized limestone afterwards in place, and each compacting point is rammed 3-4 times;(4) it is whole to backfill material once rammed after, expect that pit caused by ramming mend using identical backfill and fill out, benefit is layouted again after tamping reality, carry out it is secondary rams, secondary ram needs all to ram once time filler surface;(5) (2) to the step (4) that repeats the above steps successively is backfilled, until designed elevation.The present invention uses the compacted technique of strong rammer, shortens the backfill duration, and roadbed backfill is high-quality, reduces construction risk, solves the problems, such as that backfill must could be completed using large-scale compacting equipment, has high economic benefit.

Description

The compacted construction method of high-fill roadbed
Technical field
The invention belongs to highway construction technology fields, and in particular to a kind of compacted construction method of high-fill roadbed.
Background technique
In today of highway in China construction high speed development, high embankment embankment is still in addition to building a bridge across cheuch One of main means.Guarantee marching into the arena for heavy compacting equipment since the backfill (the especially construction backfill of early period) of high embankment is extremely difficult Operation can only successively be backfilled using middle-size and small-size compacting equipment, be occurred since compactness deficiency will cause the road after completion Biggish sedimentation and deformation.Disease is run to reduce later period road, is usually taken postpones pavement construction by the soil body in gravity in the past Natural consolidation under effect settles or reserves the mode of secondary repairing to guarantee the running quality after engineering is formally handed over.But it is existing Construction period shortening and postrun heavy traffic pressure, it is secondary perfect to carry out to have extended the duration, because This, is badly in need of a kind of quick tamping road bed method of energy.
Summary of the invention
The technical problems to be solved by the invention are in view of the above shortcomings of the prior art, to provide a kind of high-fill roadbed Compacted construction method, it can be quickly tamping road bed using middle-size and small-size equipment, reduces the probability of subgrade deformation.
The technical scheme adopted by the invention is that: a kind of compacted construction method of high-fill roadbed, comprising the following steps:
(1) prepare backfill material, cannot be native containing fertile soil, house refuse in the backfill material of selection, it cannot contain in mud It is weeds, several;
(2) backfill region is cleared up, then carries out the unwrapping wire of backfill layer;
(3) backfill material is backfilled according to unwrapping wire, backfill carries out compacting point setting-out, each compacting with pulverized limestone afterwards in place Point is rammed 3-4 times;
(4) after once being rammed to backfill material entirety, expect that pit caused by ramming is mended using identical backfill It fills out, benefit is layouted again after tamping reality, and progress is secondary to be rammed, and secondary needs of ramming all ram once time filler surface;
(5) (2) to the step (4) that repeats the above steps successively is backfilled, until designed elevation.
Preferably, the spacing in length and breadth of adjacent compacting point is 5m in step (3).
Preferably, the work of ramming in step (3) is carried out from road both lateral sides edge to road-center.
Preferably, the height of every layer of backfill layer is 3m-4m.
Preferably, being equipped with articulamentum between adjacent two layers backfill layer, the articulamentum includes the coagulation of 70%-80% Soil, the rubble of 10%-15%, surplus are pitch.
The present invention uses the compacted technique of strong rammer, shortens the backfill duration, and roadbed backfill is high-quality, reduces construction wind Danger solves the problems, such as that backfill must could be completed using large-scale compacting equipment, has high economic benefit.
Specific embodiment
Below in conjunction with specific embodiment, invention is further described in detail.
Embodiment
The compacted construction method of high-fill roadbed provided in this embodiment, comprising the following steps:
(1) prepare backfill material, cannot be native containing fertile soil, house refuse in the backfill material of selection, it cannot contain in mud It is weeds, several;
(2) backfill region is cleared up, then carries out the unwrapping wire of backfill layer;
(3) backfill material is backfilled according to unwrapping wire, backfill carries out compacting point setting-out, adjacent compacting with pulverized limestone afterwards in place The spacing in length and breadth of point, with dipstick metering lifting rope length, slings weight according to the sling height being calculated using ramming for 5m, then Release makes weight fall naturally, and each compacting point needs to ram 3-4 times, to guarantee to ram dense effect, while ramming work It is carried out from road both lateral sides edge to road-center;
It needs to measure original ground absolute altitude before ramming, often rams and once record the elevation after this is rammed, calculate differential settlement, when Ramming times should be increased for the third time or when ramming submergence depth for the 4th time greater than specified value;
(4) after once being rammed to backfill material entirety, expect that pit caused by ramming is mended using identical backfill It fills out, benefit is layouted again after tamping reality, and progress is secondary to be rammed, and secondary needs of ramming all ram once time filler surface;
(5) (2) to the step (4) that repeats the above steps successively is backfilled, until designed elevation, the height of every layer of backfill layer For 3m-4m, and articulamentum is equipped between adjacent two layers backfill layer, the articulamentum include 70%-80% concrete, The rubble of 10%-15%, surplus are pitch.
The above is only the preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto, any The transformation and replacement carried out based on technical solution provided by the present invention and inventive concept should all be covered in protection model of the invention In enclosing.

Claims (5)

1. a kind of compacted construction method of high-fill roadbed, it is characterised in that: the following steps are included:
(1) prepare backfill material, in the backfill material of selection cannot containing fertile soil, house refuse soil, in mud cannot containing weeds, It is several;
(2) backfill region is cleared up, then carries out the unwrapping wire of backfill layer;
(3) backfill material is backfilled according to unwrapping wire, backfill carries out compacting point setting-out with pulverized limestone afterwards in place, and each compacting point rams It hits 3-4 times;
(4) after once being rammed to backfill material entirety, expect that pit caused by ramming mend using identical backfill and fill out, mend It layouts again after tamping reality, progress is secondary to be rammed, and secondary needs of ramming all ram once time filler surface;
(5) (2) to the step (4) that repeats the above steps successively is backfilled, until designed elevation.
2. the compacted construction method of high-fill roadbed according to claim 1, it is characterised in that: adjacent compacting in step (3) The spacing in length and breadth of point is 5m.
3. the compacted construction method of high-fill roadbed according to claim 1, it is characterised in that: ram work in step (3) Make to be carried out from road both lateral sides edge to road-center.
4. the compacted construction method of high-fill roadbed according to claim 1, it is characterised in that: every layer backfill layer height be 3m-4m。
5. the compacted construction method of high-fill roadbed according to claim 1, it is characterised in that: adjacent two layers backfill between layer It is equipped with articulamentum, it is pitch that the articulamentum, which includes the concrete of 70%-80%, the rubble of 10%-15%, surplus,.
CN201810953031.7A 2018-08-21 2018-08-21 The compacted construction method of high-fill roadbed Pending CN109024129A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810953031.7A CN109024129A (en) 2018-08-21 2018-08-21 The compacted construction method of high-fill roadbed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810953031.7A CN109024129A (en) 2018-08-21 2018-08-21 The compacted construction method of high-fill roadbed

Publications (1)

Publication Number Publication Date
CN109024129A true CN109024129A (en) 2018-12-18

Family

ID=64626664

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810953031.7A Pending CN109024129A (en) 2018-08-21 2018-08-21 The compacted construction method of high-fill roadbed

Country Status (1)

Country Link
CN (1) CN109024129A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110172980A (en) * 2019-06-19 2019-08-27 贵州正业工程技术投资有限公司 A kind of coarse grain block stone superelevation fill foundation ruggedized construction and its construction method
CN111910613A (en) * 2020-08-06 2020-11-10 佛山市佳尚居建筑装饰有限公司 Construction method of green energy-saving building

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102605698A (en) * 2012-03-09 2012-07-25 新疆北新路桥建设股份有限公司 Construction method for reinforcing and rolling soft soil subgrade by aid of impact-type road roller
CN104652180A (en) * 2015-02-11 2015-05-27 中国水利水电第四工程局有限公司 Roadbed filling construction method
CN106835884A (en) * 2017-01-02 2017-06-13 浙江泛华工程监理有限公司 A kind of permanent roadbed construction method of highly filled road
CN106869000A (en) * 2017-04-11 2017-06-20 中交第二航务工程局有限公司 A kind of device and setting out method for roadbed setting-out
CN106988323A (en) * 2017-03-14 2017-07-28 中国十七冶集团有限公司 A kind of construction method of silty clay degree of being backfilling and compacted control

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102605698A (en) * 2012-03-09 2012-07-25 新疆北新路桥建设股份有限公司 Construction method for reinforcing and rolling soft soil subgrade by aid of impact-type road roller
CN104652180A (en) * 2015-02-11 2015-05-27 中国水利水电第四工程局有限公司 Roadbed filling construction method
CN106835884A (en) * 2017-01-02 2017-06-13 浙江泛华工程监理有限公司 A kind of permanent roadbed construction method of highly filled road
CN106988323A (en) * 2017-03-14 2017-07-28 中国十七冶集团有限公司 A kind of construction method of silty clay degree of being backfilling and compacted control
CN106869000A (en) * 2017-04-11 2017-06-20 中交第二航务工程局有限公司 A kind of device and setting out method for roadbed setting-out

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
杨玉平: "《高填方路基强夯法施工技术》", 《中华建设》 *
苑举民等: "《强夯法高填方路基施工与质量控制》", 《建筑机械化》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110172980A (en) * 2019-06-19 2019-08-27 贵州正业工程技术投资有限公司 A kind of coarse grain block stone superelevation fill foundation ruggedized construction and its construction method
CN111910613A (en) * 2020-08-06 2020-11-10 佛山市佳尚居建筑装饰有限公司 Construction method of green energy-saving building

Similar Documents

Publication Publication Date Title
CN101963061B (en) Construction method for underground box culvert of existing railway line
CN106120702B (en) High roadbed artificial foundation back-filling in layers is layered strong rammer composite reinforcement method
CN104358188A (en) Filling construction method for collapsible loess subgrade
CN104695343B (en) Long-distance jacking construction method based on back wall pushing technology
CN113445521B (en) High side slope construction method for filling
CN104294769B (en) A kind of piling and the construction method increasing the built bridge abutment structure of platform cap composite reinforcement
CN202416195U (en) Pier deviation correcting and reinforcing system
CN101311418A (en) Exchange filling method for deep-foundation pit and large area equipment foundation
CN103276649B (en) Side is had to limit layering many thickness Stone Filled Embankment construction method
CN111535291A (en) Dynamic compaction treatment process for geological structure
CN104358196B (en) Highway open to traffic Embankment Subsidence disposes the construction method of structure
CN109024129A (en) The compacted construction method of high-fill roadbed
CN108486976A (en) Mountain highway, which is filled out, digs intersection road structure and its construction method
CN106522248A (en) Method for reinforcing soil slope and slope reinforcing device
CN210194361U (en) Splicing structure for widening new and old roadbeds on road
CN104947648A (en) Deep replacement dynamic compaction gravel pile foundation reinforcement method
CN103993533B (en) For the comprehensive debulking methods of Canal in Loess Area high-filled embankment
CN102296591A (en) Rapid drainage solidifying treatment method of soft soil foundation
CN104727295B (en) Preexisting hole filler displacement hammer flattener heavy-tamping method
CN204097889U (en) A kind of piling and the built bridge abutment structure of increase platform cap composite reinforcement
CN109704656A (en) A kind of bridge joint hillside fields polymer grouting strengthening method
CN109537526A (en) A kind of ecological revetment and construction method
CN206512620U (en) A kind of steel basil is buried jacking box culvert device
CN206385525U (en) A kind of timber structure for preventing the high backfill earthwork from sinking
CN102817298A (en) Construction method on permafrost

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20190528

Address after: 610000 No. 58 Tengfei Avenue, Qingyang District, Chengdu City, Sichuan Province

Applicant after: Guo Cheng Group Co., Ltd

Address before: 266071 Yanji Road 237, Shinan District, Qingdao City, Shandong Province

Applicant before: East China Construction Engineering Group Limited

WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181218