CN108486976A - Mountain highway, which is filled out, digs intersection road structure and its construction method - Google Patents

Mountain highway, which is filled out, digs intersection road structure and its construction method Download PDF

Info

Publication number
CN108486976A
CN108486976A CN201810406200.5A CN201810406200A CN108486976A CN 108486976 A CN108486976 A CN 108486976A CN 201810406200 A CN201810406200 A CN 201810406200A CN 108486976 A CN108486976 A CN 108486976A
Authority
CN
China
Prior art keywords
drainage
filling
junction
excavation
transition section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810406200.5A
Other languages
Chinese (zh)
Other versions
CN108486976B (en
Inventor
钱申春
彭申凯
孙学军
杜海峰
刘要武
任杰
刘晓晗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Construction Engineering Highway And Bridge Construction Group Co ltd
Original Assignee
Anhui Road and Bridge Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Road and Bridge Engineering Co Ltd filed Critical Anhui Road and Bridge Engineering Co Ltd
Priority to CN201810406200.5A priority Critical patent/CN108486976B/en
Publication of CN108486976A publication Critical patent/CN108486976A/en
Application granted granted Critical
Publication of CN108486976B publication Critical patent/CN108486976B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00—Foundations for pavings
    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00—Details of pavings
    • E01C11/22—Gutters; Kerbs ; Surface drainage of streets, roads or like traffic areas
    • E01C11/224—Surface drainage of streets
    • E01C11/227—Gutters; Channels ; Roof drainage discharge ducts set in sidewalks
    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00—Foundations for pavings
    • E01C3/04—Foundations produced by soil stabilisation
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00—Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12—Consolidating by placing solidifying or pore-filling substances in the soil
    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C2201/00—Paving elements
    • E01C2201/20—Drainage details
    • Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00—Adapting or protecting infrastructure or their operation
    • Y02A30/60—Planning or developing urban green infrastructure

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Architecture (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Road Paving Structures (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The present invention relates to a kind of mountain highways to fill out digging intersection road structure and its construction method, the road structure includes embankment section, excavation section and fill out dig intersection changeover portion, embankment section is equipped with changeover portion step and open drain, fill out dig intersection changeover portion be equipped with fill out dig intersection drainage system, it includes replaceable displacement hull assembled transverse drainage french drain to fill out and dig intersection drainage system, it longitudinally through weeper drain and fills out digging intersection is permeable combines changeover portion with water barrier, it fills out to dig in intersection drainage system and changeover portion step and is equipped with combined type draining ductule, it fills out the combined type draining ductule bottom dug on intersection drainage system and connects longitudinally through weeper drain, longitudinally through weeper drain is communicated with replaceable displacement hull assembled transverse drainage french drain.The present invention can in time be monitored soil body level of ground water in slope surface by the peephole of setting, effectively controls the leaning angle and size of cubic meter of stone section changeover portion step, accelerates speed of application, improve the overall stability of roadbed.

Description

山区公路填挖交界处路基结构及其施工方法Subgrade structure and its construction method at the junction of filling and excavation in mountainous highways

技术领域technical field

本发明涉及一种新型山区公路路基结构,特别涉及一种山区公路填挖交界处的路基结构及其施工方法。The invention relates to a novel subgrade structure of mountain roads, in particular to a subgrade structure at the junction of filling and excavation of mountain roads and a construction method thereof.

背景技术Background technique

随着我国高速公路的大建设到来,尤其是“县县通高速”理念提出后,高速公路施工将向山区转移,山区高速路基基本上为高填方路基,且填挖交错。高填方路基由于受自重大、工期紧、山区雨季长,以及施工的不规范,使得路基极容易发生沉降,尤其是在横纵向填挖交界处,沉降明显,导致路面开裂、沉陷等问题,对交通安全造成了极大的影响。山区高速填挖交界处路基填筑已是目前面临的突出难题。With the advent of the large-scale construction of expressways in our country, especially after the concept of "county-county expressways" is put forward, the construction of expressways will be transferred to mountainous areas. Due to the heavy weight, tight construction period, long rainy season in mountainous areas, and irregular construction, the high-fill subgrade is prone to subsidence, especially at the intersection of horizontal and vertical filling and excavation, where the subsidence is obvious, resulting in cracking and subsidence of the road surface. It has a great impact on traffic safety. Subgrade filling at the intersection of high-speed filling and excavation in mountainous areas has become a prominent problem at present.

传统的填挖交界处施工处理分为纵向填挖交界和横向填挖交界两种处理方式。前者主要是在挖方路段进行超挖回填,填方路段进行台阶开挖,该施工模式主要的缺陷在于,填方路段的台阶碾压不够充分,容易导致后期沉降过大,此外,填挖交界处过渡段由于新老路基结合不充分,若不进行加固处理,会严重影响路基结构的稳定性;后者即在公路的一侧进行开挖,与此同时,公路的另一侧进行回填工作,该施工模式十分依赖于公路的横向坡度,坡度不同,施工方式改变很大,故适用性相对较差,且在路基上要铺设土工格室,对土工格室的强度,搭接要求都较高,施工难度大。The traditional construction treatment of filling and excavation junction is divided into two methods: longitudinal filling and excavation junction and horizontal filling and excavation junction. The former is mainly to carry out over-excavation and backfill in the excavation section, and step excavation in the filling section. The main defect of this construction mode is that the step rolling in the filling section is not sufficient, which may easily lead to excessive settlement in the later stage. In addition, the junction of filling and excavation Due to the insufficient combination of old and new subgrades in the transition section, if no reinforcement treatment is carried out, the stability of the subgrade structure will be seriously affected; the latter means excavation on one side of the road, and at the same time, backfilling work on the other side of the road. This construction mode is very dependent on the lateral slope of the road. The construction method changes greatly with different slopes, so the applicability is relatively poor, and geocells need to be laid on the roadbed, which requires high strength and overlapping of geocells. , The construction is difficult.

综上所述,目前急需寻找到一种填挖交界处路基结构稳定、强度承载性能好、碾压充分、沉降小的新型山区公路填挖交界处路基及其施工方法。To sum up, there is an urgent need to find a new type of subgrade and construction method for filling and excavating junctions of mountainous highways with stable structure, good strength and bearing capacity, sufficient rolling and small settlement.

发明内容Contents of the invention

针对现有技术中存在的上述问题,本发明的目的在于提供一种山区公路填挖交界处路基结构及其施工方法。In view of the above-mentioned problems existing in the prior art, the object of the present invention is to provide a subgrade structure and construction method of a mountain road filling and excavation junction.

所述的山区公路填挖交界处路基结构,其特征在于:包括填方路段、挖方路段及填挖交界处过渡段,填方路段上设有过渡段台阶和排水明沟,填挖交界处过渡段设有填挖交界处排水体系,填挖交界处排水体系包括可更换排水体装配式横向排水盲沟、纵向贯通排水盲沟及填挖交界处透水与隔水层组合过渡段,填挖交界处透水与隔水层组合过渡段和过渡段台阶内均设有复合式排水小导管,填挖交界处透水与隔水层组合过渡段上的复合式排水小导管底部连接纵向贯通排水盲沟,纵向贯通排水盲沟与可更换排水体装配式横向排水盲沟相通,可更换排水体装配式横向排水盲沟的高度为挖方路段高度的1/3高度,且设置在挖方路段底部。The subgrade structure at the junction of filling and excavation of the mountainous highway is characterized in that it includes a filling road section, an excavation road section and a transition section at the junction of filling and excavation. There is a drainage system at the junction of filling and excavation. The drainage system at the junction of filling and excavation includes a replaceable drainage body assembled horizontal drainage blind ditch, a vertical through drainage blind ditch, and a transition section of the combination of permeable and water-resistant layers at the junction of filling and excavation. The transition section of the combination of permeable and water-resistant layers and the steps of the transition section are equipped with composite small drainage conduits. The bottom of the composite small drainage conduits on the transition section of the combination of permeable and water-resistant layers at the junction of filling and excavation is connected vertically through the blind drainage ditch. The through drainage blind ditch communicates with the replaceable drainage body assembled horizontal drainage blind ditch. The height of the replaceable drainage body assembled horizontal drainage blind ditch is 1/3 of the height of the excavated road section and is set at the bottom of the excavated road section.

所述的山区公路填挖交界处路基结构,其特征在于:可更换排水体装配式横向排水盲沟包括抽拉式导杆带端板更换排水体和预制装配式钢筋混凝土盲沟,预制装配式钢筋混凝土盲沟中部设有竖向钢板,将其为两个格室结构,预制装配式钢筋混凝土盲沟上部铺钢筋网片,每个格室底面各铺设有两条轨道,抽拉式导杆带端板更换排水体设置在预制装配式钢筋混凝土盲沟的格室中,抽拉式导杆带端板更换排水体底部安装有滚轮,滚轮与轨道匹配,并能在轨道滑动,使抽拉式导杆带端板更换排水体能自由滑入预制装配式钢筋混凝土盲沟。The subgrade structure at the junction of filling and excavation of mountainous roads is characterized in that: the replaceable drainage body assembled horizontal drainage blind ditch includes a pull-out guide bar with end plates to replace the drainage body and a prefabricated assembled reinforced concrete blind ditch, the prefabricated assembled type There is a vertical steel plate in the middle of the reinforced concrete blind ditch, which is divided into two cell structures. The upper part of the prefabricated reinforced concrete blind ditch is covered with steel mesh, and the bottom of each cell is laid with two tracks. Replacement drainage body with end plate is set in the cell of prefabricated reinforced concrete blind ditch, pull-type guide rod with end plate replacement drainage body is equipped with rollers at the bottom, the rollers match with the track, and can slide on the track, making pulling Type guide rod with end plate to replace the drainage body can freely slide into the prefabricated reinforced concrete blind ditch.

所述的山区公路填挖交界处路基结构,其特征在于:填挖交界处过渡段位于填方路段与挖方路段之间,长度范围不小于10m,填挖交界处过渡段的坡度为4%。The subgrade structure of the filling-cutting junction of the mountainous road is characterized in that: the transition section of the filling-cutting junction is located between the filling road section and the excavation road section, the length range is not less than 10m, and the slope of the filling-cutting junction transition section is 4%.

所述的山区公路填挖交界处路基结构,其特征在于:填挖交界处过渡段下方设置过渡段台阶,内倾角度控制在4°以内,且由于台阶处碾压断面小,故采用环形压缩,有效消除压实盲区,提高土体密实度和整体稳定性。The subgrade structure of the filling-excavation junction of the mountainous road is characterized in that: a transition section step is set below the transition section of the filling-excavation junction, the inclination angle is controlled within 4°, and because the rolling section at the step is small, ring compression is adopted, Effectively eliminate compaction blind spots, improve soil compactness and overall stability.

所述的山区公路填挖交界处路基结构,其特征在于:在填方路段内和填挖交界处透水与隔水层组合过渡段上分别设置复合式排水小导管,复合式排水小导管包括密目网、土工布袋、锥形桩头、注浆导管及扩大端板,注浆导管上从里到外依次设有密目网和土工布袋,密目网与注浆导管之间填充有碎石;注浆导管底部连接锥形桩头,顶部连接扩大端板,锥形桩头上设有圆锥开瓣,扩大端板下表面设有观测孔,复合式排水小导管后期做注浆管用。The subgrade structure at the junction of filling and excavation of the mountainous road is characterized in that: a composite small drainage conduit is respectively arranged in the filling section and on the combined transition section of the permeable and water-resistant layer at the junction of filling and excavation, and the composite small drainage conduit includes dense Mesh net, geotextile bag, tapered pile head, grouting conduit and enlarged end plate, dense mesh and geotextile bag are arranged on the grouting conduit from the inside to the outside, and gravel is filled between the dense mesh and the grouting conduit The bottom of the grouting conduit is connected to the conical pile head, and the top is connected to the enlarged end plate. The conical pile head is provided with a conical opening, and the lower surface of the enlarged end plate is provided with an observation hole. The composite drainage small conduit is used as a grouting pipe later.

所述的山区公路填挖交界处路基结构,其特征在于:过渡段台阶通过静态爆破的方法施工得到:先在填方路段内钻设L形静态爆破孔,L形静态爆破孔内填装静态爆破剂,同时安装水平带封口板整体式压水补水管和侧向带封口板整体式压水补水管,水平带封口板整体式压水补水管和侧向带封口板整体式压水补水管的外端端头分别通过端部锚固件固定在坡面上,利用水化反应把岩石胀破,得到过渡段台阶。The subgrade structure at the junction of filling and excavation of the mountainous road is characterized in that: the steps of the transition section are constructed by static blasting: firstly, an L-shaped static blast hole is drilled in the filling road section, and static blast holes are filled in the L-shaped static blast hole. Blasting agent, install horizontal integrated water supply pipe with sealing plate and lateral integral pressure water supply pipe with sealing plate, horizontal integral pressure water supply pipe with sealing plate and lateral integral pressure water supply pipe with sealing plate The outer ends of the rockers are respectively fixed on the slope surface through the end anchors, and the rocks are burst through the hydration reaction to obtain the steps in the transition section.

所述的山区公路填挖交界处路基结构的施工方法,其特征在于包括以下的步骤:The construction method of the subgrade structure at the junction of filling and excavation of the mountainous highway is characterized in that it comprises the following steps:

第一步是对原坡面的基底层进行清理与压实,具体包括开挖纵向临时水沟,纵向沟挖出土方培在沟外侧作沟埂,以免路基外侧地表水排入路基基底;路基用地范围内的树木、灌木丛等均在施工前砍伐挖根,并将地表土予以清除,路堤基底清理、平整、晒干后再整平压实,填方地段清除表土200mm,压实度不小于90%;在路堤底部填以砂、砂砾、碎石等材料进行加固,使其形成水稳性好稳定层;The first step is to clean and compact the base layer of the original slope, which specifically includes excavating a longitudinal temporary ditch, excavating the earth from the longitudinal ditch and making a ridge on the outside of the ditch, so as to prevent the surface water from the outside of the roadbed from draining into the base of the roadbed; Trees and shrubs within the scope of land use shall be cut down and rooted before construction, and the surface soil shall be removed. Less than 90%; fill the bottom of the embankment with sand, gravel, gravel and other materials for reinforcement to form a stable layer with good water stability;

第二步是在填方路段上进行填挖交界处过渡段的位置开挖过渡段台阶,并进行环形压实;The second step is to excavate the steps of the transition section at the position of the transition section of the fill-excavation junction on the filling road section, and carry out ring compaction;

第三步是在交界处过渡段开挖可更换排水体装配式横向排水盲沟,可更换排水体装配式横向排水盲沟的高度为挖方路段的1/3高度,开挖完成后,在可更换排水体装配式横向排水盲沟上安装预制装配式钢筋混凝土盲沟,预制装配式钢筋混凝土盲沟中部安装竖向钢板,将其为两个格室结构,预制装配式钢筋混凝土盲沟上部铺钢筋网片,每个格室底面各铺设有两条轨道;抽拉式导杆带端板更换排水体设置在预制装配式钢筋混凝土盲沟的格室中,抽拉式导杆带端板更换排水体底部安装有滚轮,滚轮与轨道匹配,并能在轨道滑动,使抽拉式导杆带端板更换排水体能自由滑入预制装配式钢筋混凝土盲沟,完成可更换排水体装配式横向排水盲沟的施工安装;The third step is to excavate the replaceable drainage body assembled horizontal drainage blind ditch in the transition section at the junction. The height of the replaceable drainage body assembled horizontal drainage blind ditch is 1/3 of the height of the excavated section. Install the prefabricated reinforced concrete blind ditch on the assembled horizontal drainage blind ditch of the drainage body, install a vertical steel plate in the middle of the prefabricated reinforced concrete blind ditch, and make it a two-cell structure, and pave the upper part of the prefabricated reinforced concrete blind ditch Reinforced mesh, two rails are laid on the bottom of each cell; pull-out guide rod with end plate replacement drainage body is set in the cell of prefabricated reinforced concrete blind ditch, pull-type guide rod with end plate replacement There are rollers installed at the bottom of the drainage body, which match the track and can slide on the track, so that the replacement drainage body can freely slide into the prefabricated reinforced concrete blind ditch with the pull-out guide rod and end plate, and complete the assembled horizontal drainage of the replaceable drainage body Construction and installation of blind ditch;

第四步在可更换排水体装配式横向排水盲沟上方安装纵向贯通排水盲沟,再在纵向贯通排水盲沟上方进行填挖交界处透水与隔水层组合过渡段施工,并进行增强补压,所述填挖交界处透水与隔水层组合过渡段长度不小于 10m,填挖交界处透水与隔水层组合过渡段采用液压夯和落锤式强夯机进行组合施工,压实度不小于96%,坡度为4%;The fourth step is to install a longitudinal through-drainage blind ditch above the horizontal drainage blind ditch assembled with replaceable drainage bodies, and then carry out the construction of the transition section of the combination of permeable and water-resistant layers at the junction of filling and excavation above the vertical through-drainage blind ditch, and carry out enhanced pressure supplementation , the length of the transition section between the permeable and water-resisting layers at the junction of filling and excavation shall not be less than 10m, and the transition section of the combination of permeable and water-resisting layers at the junction of filling and excavation shall be constructed in combination with a hydraulic rammer and a falling hammer dynamic compaction machine, and the degree of compaction shall not be less than 10m. Less than 96%, the slope is 4%;

第五步是在过渡段台阶上设置复合式排水小导管,复合式排水小导管由密目网和土工布袋缠绕在注浆导管外部形成,密目网和注浆导管之间填充有碎石,复合式排水小导管,下端部设有锥形桩头,扩大端板内含观测孔,锥形桩头下端部设有圆锥瓣膜,与注浆导管直接相连;各复合式排水小导管之间设置有坡面斜管导引,通过坡面斜管导引串联,坡内水体可经复合式排水小导管,再经坡面斜管导引排出;The fifth step is to install a small composite drainage conduit on the steps of the transition section. The small composite drainage conduit is formed by winding a dense mesh and a geotextile bag outside the grouting conduit, and gravel is filled between the dense mesh and the grouting conduit. Composite small drainage conduit, the lower end is provided with a conical pile head, and the enlarged end plate contains an observation hole. The lower end of the conical pile head is provided with a conical valve, which is directly connected with the grouting conduit; There are inclined pipes on the slope for guidance, through which the inclined pipes on the slope are guided in series, and the water body in the slope can be discharged through the composite small drainage pipe, and then guided by the inclined pipe on the slope;

第六步对填方路段进行坡面施工,并在填方路段底部设置排水明沟等,再对挖方路段进行施工。The sixth step is to carry out slope construction on the filled road section, and set drainage ditches at the bottom of the filled road section, and then carry out construction on the excavated road section.

所述的山区公路填挖交界处路基结构的施工方法,其特征在于步骤二中开挖过渡段台阶具体过程如下:利用钻具先在坡面从上至下依次钻设若干L形静态爆破孔,L形静态爆破孔的宽度不小于2.0m,高度不大于1.0m,内径为50mm,横向每隔0.3m布置一个;紧接着将提前配置好的静态爆破剂放入L形静态爆破孔的孔道内,本发明实施例中,根据L形静态爆破孔的大小,大约需要2.5kg,再在L形静态爆破孔上安装水平带封口板整体式压水补水管和侧向带封口板整体式压水补水管,两个补水管分别利用端部锚固件固定安装在坡面36上,通过补水管向L形静态爆破孔内补水,与静态爆破剂发生水化反应,放出热量,将岩石体胀破开裂,该施工过程一般需要3个小时,裂缝为3公分为宜,静态爆破之后将破损的岩体利用人工镐凿除,控制台阶坡度在4%以内。尽可能的在基底清除完毕后立即开始由上至下的一次性修筑成型,若不能从上至下一次修筑的,在每层填筑土以上至少保留3个台阶,再进行分层填筑。The construction method of the subgrade structure at the junction of filling and excavation of mountainous roads is characterized in that the specific process of excavating the transition section steps in step 2 is as follows: using a drilling tool to drill a number of L-shaped static blast holes sequentially from top to bottom on the slope surface , the width of the L-shaped static blasting hole is not less than 2.0m, the height is not more than 1.0m, the inner diameter is 50mm, and one is arranged every 0.3m in the horizontal direction; then the static blasting agent configured in advance is put into the hole of the L-shaped static blasting hole Inside the tunnel, according to the size of the L-shaped static blasting hole, about 2.5kg is needed in the embodiment of the present invention, and then a horizontal integral pressure water supply pipe with a sealing plate and a lateral integral pressure water supply pipe with a sealing plate are installed on the L-shaped static blasting hole. Water supply pipes, two water supply pipes are respectively fixed and installed on the slope 36 by using end anchors, supply water to the L-shaped static blasting hole through the water supply pipes, hydration reaction occurs with the static blasting agent, release heat, and expand the rock mass. To break the cracks, the construction process generally takes 3 hours, and the cracks are preferably 3 cm. After the static blasting, the damaged rock mass is chiseled with a pickaxe, and the slope of the console steps is within 4%. Try to start one-time construction from top to bottom immediately after the base is cleared. If it is impossible to build from top to bottom, keep at least 3 steps above each layer of filling soil, and then fill in layers.

所述的山区公路填挖交界处路基结构的施工方法,其特征在于压实方法采用环形压实,再结合液压式碾压设备,有利于冲击点的满布、均匀,增强整体效果,有效消除压实盲区。The construction method of the subgrade structure at the junction of filling and excavation of mountainous roads is characterized in that the compaction method adopts ring compaction, combined with hydraulic rolling equipment, which is conducive to the full distribution and uniformity of impact points, enhances the overall effect, and effectively eliminates Compact blind spots.

通过采用上述技术,与现有技术相比,本发明具有如下特点和有益效果:By adopting the above-mentioned technology, compared with the prior art, the present invention has the following characteristics and beneficial effects:

1)本发明采用环形碾压的方式,可以消除开挖台阶处碾压不充分的缺陷;1) The present invention adopts the circular rolling method, which can eliminate the defect of insufficient rolling at the excavation steps;

2)本发明通过在填挖交界处设置填挖交界处透水与隔水层组合过渡段,并与纵向贯通排水盲沟以及可更换排水体装配式横向排水盲沟连接在一起,既可防水又能及时排水,保证了填挖交界处的承载性能,从而保证了整个路基结构的稳定性;2) The present invention sets the transition section of the combination of permeable and water-resistant layers at the junction of filling and excavation, and connects it with the longitudinal blind drainage ditch and the assembled horizontal drainage blind ditch of the replaceable drainage body, which can be waterproof and It can drain water in time to ensure the load-bearing performance at the junction of filling and excavation, thereby ensuring the stability of the entire subgrade structure;

3)本发明在过渡段台阶处埋设了复合式排水小导管,且配合坡面斜管导引,可随时监测路基内部的水位与渗水问题,及时排出路基内积水,降低水位,以此避免滑坡等地质灾害的发生,且复合式排水小导管后期可用做注浆管;3) In the present invention, a composite drainage small conduit is buried at the step of the transition section, and with the guide of the inclined pipe on the slope surface, the water level and seepage inside the roadbed can be monitored at any time, and the accumulated water in the roadbed can be discharged in time to reduce the water level, so as to avoid The occurrence of geological disasters such as landslides, and the composite drainage small conduit can be used as a grouting pipe in the later stage;

4)本发明中的抽拉式导杆带端板更换排水体与预制装配式钢筋混凝土盲沟组合,可以及时更换出现损坏的排水体;4) The combination of the pull-type guide rod with end plate replacement drainage body and the prefabricated assembled reinforced concrete blind ditch in the present invention can replace the damaged drainage body in time;

5)本发明中采用的静态爆破施工方法,可有效控制石方路段过渡段台阶的内倾角及尺寸,加快了施工速度。5) The static blasting construction method adopted in the present invention can effectively control the inclination angle and size of the steps in the transition section of the masonry road section, and accelerate the construction speed.

附图说明Description of drawings

图1是高填深挖横断面示意图;Fig. 1 is a schematic diagram of a cross-section of high filling and deep excavation;

图2是山区公路填挖交界处路基结构示意图;Fig. 2 is a schematic diagram of the subgrade structure at the junction of filling and excavation of mountainous highways;

图3是复合式排水小导管结构示意图;Fig. 3 is a structural schematic diagram of a composite drainage small conduit;

图4是可更换排水体装配式横向排水盲沟断面图;Fig. 4 is a cross-sectional view of a replaceable drainage body assembled horizontal drainage blind ditch;

图5是静态爆破施工示意图;Figure 5 is a schematic diagram of static blasting construction;

图6是图2中A处放大图。Fig. 6 is an enlarged view of A in Fig. 2 .

其中:1-填方路段;2-挖方路段;3-填挖交界处过渡段;4-过渡段台阶;5-透水层;6-水泥钉;7-土工格栅;8-可更换排水体装配式横向排水盲沟;9-排水明沟;10-复合式排水小导管;11-密目网;12-土工布袋;13-锥形桩头;14-碎石;15-注浆导管;16-扩大端板;17-圆锥开瓣;18-填挖交界处排水体系;19-坡面斜管导引;20-纵向贯通排水盲沟;21-填挖交界处透水与隔水层组合过渡段;22-隔水层;23-竖向小导管嵌入头层;24-加筋泡沫混凝土调节层;25-钢筋网片;26-竖向钢板;27-预制装配式钢筋混凝土盲沟;28-轨道;29-滚轮;30-抽拉式导杆带端板更换排水体;31-观测孔;32-L形静态爆破孔;33-水平带封口板整体式压水补水管;34-侧向带封口板整体式压水补水管;35-端部锚固件;36-坡面;37-原坡面。Among them: 1- filling road section; 2- excavation road section; 3- transition section at the junction of filling and excavation; 4- transition section steps; 5- permeable layer; 6- cement nails; 7- geogrid; 8- replaceable drainage body Assembled horizontal drainage blind ditch; 9-drainage open ditch; 10-compound drainage small conduit; 11-dense mesh; 12-geotextile bag; 13-conical pile head; 14-gravel; 15-grouting conduit; 16 -enlarged end plate; 17-cone opening; 18-drainage system at the junction of filling and excavation; 19-incline pipe guidance on the slope; 20-blind ditch for vertical drainage; Section; 22- water-repelling layer; 23- vertical small conduit embedded in the head layer; 24- reinforced foam concrete adjustment layer; 25- steel mesh; 26- vertical steel plate; 27- prefabricated reinforced concrete blind ditch; 28 -Rail; 29-Roller; 30-Pullable guide rod with end plate to replace drainage body; 31-Observation hole; 32-L-shaped static blasting hole; 33-Horizontal integrated water supply pipe with sealing plate; 34-Side Integral pressure water supply pipe with sealing plate; 35-end anchor; 36-slope; 37-original slope.

具体实施方式Detailed ways

以下结合说明书附图对本发明作进一步的描述,但本发明的保护范围并不仅限于此:The present invention will be further described below in conjunction with accompanying drawing of description, but protection scope of the present invention is not limited thereto:

如图1-6所示,本发明的山区公路填挖交界处路基结构,包括填方路段1、挖方路段2及填挖交界处过渡段3,填方路段1上设有过渡段台阶4和排水明沟9,填挖交界处过渡段3设有填挖交界处排水体系18,填挖交界处排水体系18包括可更换排水体装配式横向排水盲沟8、纵向贯通排水盲沟20及填挖交界处透水与隔水层组合过渡段21,填挖交界处透水与隔水层组合过渡段21和过渡段台阶4内均设有复合式排水小导管10,填挖交界处透水与隔水层组合过渡段21上的复合式排水小导管10底部连接纵向贯通排水盲沟20,纵向贯通排水盲沟20与可更换排水体装配式横向排水盲沟8相通,可更换排水体装配式横向排水盲沟8的高度为挖方路段2高度的1/3高度,且设置在挖方路段2底部。As shown in Figure 1-6, the subgrade structure at the junction of filling and excavation of mountainous highways of the present invention comprises a filling section 1, an excavation section 2 and a transition section 3 at the junction of filling and excavation, and the filling section 1 is provided with a transition section step 4 and Drainage ditch 9, the transition section 3 at the junction of filling and excavation is provided with a drainage system 18 at the junction of filling and excavation, and the drainage system 18 at the junction of filling and excavation includes a replaceable drainage body assembled horizontal drainage blind ditch 8, a vertical through drainage blind ditch 20 and a filling and excavation The combined transition section 21 of the permeable and water-resistant layer at the junction, the combined transition section 21 of the permeable and water-resistant layer at the junction of filling and excavation, and the steps 4 of the transition section are all equipped with composite drainage small conduits 10, and the permeable and water-resistant layer at the junction of filling and excavation The bottom of the combined small drainage conduit 10 on the combined transition section 21 is connected to the vertically penetrating blind drainage ditch 20, and the longitudinally penetrating blind drainage ditch 20 communicates with the replaceable drainage body-assembled horizontal drainage blind ditch 8, and the replaceable drainage body-assembled horizontal drainage blind ditch The height of the ditch 8 is 1/3 of the height of the excavated road section 2, and is arranged at the bottom of the excavated road section 2.

如图4所示,所述可更换排水体装配式横向排水盲沟8包括抽拉式导杆带端板更换排水体30和预制装配式钢筋混凝土盲沟27,预制装配式钢筋混凝土盲沟27中部设有竖向钢板26,将其为两个格室结构,预制装配式钢筋混凝土盲沟27上部铺钢筋网片25,每个格室底面各铺设有两条轨道28,抽拉式导杆带端板更换排水体30设置在预制装配式钢筋混凝土盲沟27的格室中,抽拉式导杆带端板更换排水体30底部安装有滚轮29,滚轮29与轨道28匹配,并能在轨道28滑动,使抽拉式导杆带端板更换排水体30能自由滑入预制装配式钢筋混凝土盲沟27。As shown in Figure 4, the replaceable drainage body assembled horizontal drainage blind ditch 8 includes a pull-out guide rod with an end plate to replace the drainage body 30 and a prefabricated assembled reinforced concrete blind ditch 27, a prefabricated assembled reinforced concrete blind ditch 27 There is a vertical steel plate 26 in the middle, which is divided into two cell structures. The upper part of the prefabricated reinforced concrete blind ditch 27 is covered with steel mesh 25, and the bottom surface of each cell is respectively laid with two rails 28. Pull-type guide rods Replacement drainage body 30 with end plate is arranged in the cell of prefabricated reinforced concrete blind ditch 27, pull-type guide bar with end plate replacement drainage body 30 bottom is installed with roller 29, and roller 29 matches with track 28, and can The track 28 slides so that the pull-type guide bar band end plate replaces the drainage body 30 and can freely slide into the prefabricated assembled reinforced concrete blind ditch 27.

填挖交界处过渡段3位于填方路段1与挖方路段2之间,长度范围不小于10m,填挖交界处过渡段3的坡度为4%;填挖交界处过渡段3下方设置过渡段台阶4,内倾角度控制在4°以内,且由于台阶处碾压断面小,故采用环形压缩,有效消除压实盲区,提高土体密实度和整体稳定性。The transition section 3 of the fill-cut junction is located between the fill section 1 and the excavation section 2, and the length range is not less than 10m. The slope of the fill-cut transition section 3 is 4%; a transition section step is set below the fill-cut transition section 3 4. The inclination angle is controlled within 4°, and because the rolling section at the steps is small, ring compression is adopted to effectively eliminate compaction blind spots and improve soil compactness and overall stability.

如图所示,本发明在填方路段1内和填挖交界处透水与隔水层组合过渡段21上分别设置复合式排水小导管10,如图3所示,所述复合式排水小导管10包括密目网11、土工布袋12、锥形桩头13、注浆导管15及扩大端板16,注浆导管15上从里到外依次设有密目网11和土工布袋12,密目网11与注浆导管15之间填充有碎石14;注浆导管15底部连接锥形桩头13,顶部连接扩大端板16,锥形桩头13上设有圆锥开瓣17,扩大端板16下表面设有观测孔31,复合式排水小导管10后期做注浆管用。As shown in the figure, the present invention sets composite small drainage conduits 10 respectively in the filling road section 1 and on the combined transition section 21 of the permeable and water-resistant layer at the junction of filling and excavation. As shown in Figure 3, the composite small drainage conduits 10 includes a dense mesh 11, a geotextile bag 12, a tapered pile head 13, a grouting conduit 15 and an enlarged end plate 16, and the grouting conduit 15 is sequentially provided with a dense mesh 11 and a geotextile bag 12 from the inside to the outside. Gravel 14 is filled between the net 11 and the grouting conduit 15; the bottom of the grouting conduit 15 is connected to the conical pile head 13, and the top is connected to the enlarged end plate 16. The lower surface of 16 is provided with an observation hole 31, and the composite drainage small conduit 10 is used as a grouting pipe in the later stage.

如图5所示,所述过渡段台阶4通过静态爆破的方法施工得到:先在填方路段1内钻设L形静态爆破孔32,L形静态爆破孔32内填装静态爆破剂,同时安装水平带封口板整体式压水补水管33和侧向带封口板整体式压水补水管34,水平带封口板整体式压水补水管33和侧向带封口板整体式压水补水管34的外端端头分别通过端部锚固件35固定在坡面36上,利用水化反应把岩石胀破,得到过渡段台阶4。As shown in Figure 5, the step 4 of the transition section is constructed by static blasting: first, an L-shaped static blast hole 32 is drilled in the filling section 1, and a static blasting agent is filled in the L-shaped static blast hole 32, and at the same time Install the integral press water supply pipe 33 with the sealing plate horizontally and the integral press water supply pipe 34 with the sealing plate laterally, the integral press water supply pipe 33 with the sealing plate horizontally and the integral press water supply pipe 34 with the sealing plate laterally The outer ends of the rockers are respectively fixed on the slope surface 36 through the end anchors 35, and the rocks are burst through the hydration reaction to obtain the steps 4 of the transition section.

如图1所示,一般的山区公路施工需要对原坡面37进行填挖施工,而在填挖交界处的路基结构施工时,由于填挖交界处的路基结构包括填方路段1、交界处过渡段3及挖方路段2,具体包括如下步骤:As shown in Figure 1, general mountain road construction needs to carry out filling and digging construction to the original slope 37, and when the subgrade structure construction of filling and digging junction, because the subgrade structure of filling and digging junction includes filling road section 1, junction The transition section 3 and the excavation section 2 specifically include the following steps:

第一步是对原坡面37的基底层进行清理与压实,具体包括开挖纵向临时水沟,纵向沟挖出土方培在沟外侧作沟埂,以免路基外侧地表水排入路基基底;路基用地范围内的树木、灌木丛等均在施工前砍伐挖根,并将地表土予以清除,路堤基底清理、平整、晒干后再整平压实,填方地段清除表土200mm,压实度不小于90%;为避免基底受地下水位影响,在路堤底部填以水稳定性优良、不易风化的砂、砂砾、碎石等材料进行加固处理,使其形成水稳性好稳定层。The first step is to clean and compact the base layer of the original slope 37, which specifically includes excavating a longitudinal temporary ditch, excavating the earth from the longitudinal ditch and making a ridge on the outside of the ditch, so as to prevent the surface water from the outside of the roadbed from draining into the roadbed base; Trees and shrubs within the scope of subgrade land shall be cut down and rooted before construction, and the surface soil shall be removed. Not less than 90%; in order to prevent the base from being affected by the groundwater level, the bottom of the embankment is reinforced with sand, gravel, gravel and other materials that have excellent water stability and are not easily weathered, so as to form a stable layer with good water stability.

第二步是在填方路段1上进行填挖交界处过渡段3的位置开挖过渡段台阶4,并进行环形压实,具体过程如下:按照设计图纸进行台阶的开挖,如图5所示,利用钻具先在坡面36从上至下依次钻设若干L形静态爆破孔32,L形静态爆破孔32的宽度不小于2.0m,高度不大于1.0m,内径为50mm,横向每隔0.3m布置一个;紧接着将提前配置好的静态爆破剂放入L形静态爆破孔32的孔道内,本发明实施例中,根据L形静态爆破孔32的大小,大约需要2.5kg,再在L形静态爆破孔32上安装水平带封口板整体式压水补水管33和侧向带封口板整体式压水补水管34,两个补水管分别利用端部锚固件35固定安装在坡面36上,通过补水管向L形静态爆破孔32内补水,与静态爆破剂发生水化反应,放出热量,将岩石体胀破开裂,该施工过程一般需要3个小时,裂缝为3公分为宜,静态爆破之后将破损的岩体利用人工镐凿除,控制台阶坡度在4%以内。尽可能的在基底清除完毕后立即开始由上至下的一次性修筑成型,若不能从上至下一次修筑的,在每层填筑土以上至少保留3个台阶,再进行分层填筑,压实方法采用环形压实,再结合液压式碾压设备,有利于冲击点的满布、均匀,增强整体效果,有效消除压实盲区。The second step is to excavate the transition section step 4 at the position of the transition section 3 at the filling-excavation junction on the filling road section 1, and carry out ring compaction. The specific process is as follows: Excavate the steps according to the design drawings, as shown in Figure 5 As shown, a number of L-shaped static blast holes 32 are drilled sequentially from top to bottom on the slope 36 by using a drilling tool. Arrange one every 0.3m; then put the static blasting agent configured in advance into the channel of the L-shaped static blasting hole 32. In the embodiment of the present invention, according to the size of the L-shaped static blasting hole 32, about 2.5kg is needed, and then On the L-shaped static blasting hole 32, a horizontal integral pressurized water supply pipe 33 with a sealing plate and a lateral integral pressurized water supply pipe 34 with a sealing plate are installed. 36, supply water to the L-shaped static blasting hole 32 through the water supply pipe, hydration reaction occurs with the static blasting agent, release heat, and the rock body is swelled and cracked. This construction process generally takes 3 hours, and the crack is preferably 3 cm. , After static blasting, the damaged rock mass was chiseled out with artificial picks, and the slope of the console steps was within 4%. Try to start one-time construction from top to bottom as soon as possible after the base is cleared. If it is impossible to build from top to bottom, at least 3 steps should be reserved above each layer of filling soil, and then layered filling will be carried out. The compaction method adopts circular compaction, combined with hydraulic rolling equipment, which is conducive to the full distribution and uniformity of the impact point, enhances the overall effect, and effectively eliminates the blind spot of compaction.

第三步是在交界处过渡段3开挖可更换排水体装配式横向排水盲沟8,可更换排水体装配式横向排水盲沟8的高度为挖方路段2的1/3高度,开挖完成后,在可更换排水体装配式横向排水盲沟8上安装预制装配式钢筋混凝土盲沟27,如图4所示,本发明实施例中的预制装配式钢筋混凝土盲沟27截面尺寸为50*30cm,预制装配式钢筋混凝土盲沟27中部设有竖向钢板26,将其为两个格室结构,预制装配式钢筋混凝土盲沟27上部铺钢筋网片25,每个格室底面各铺设有两条轨道28;抽拉式导杆带端板更换排水体30设置在预制装配式钢筋混凝土盲沟27的格室中,抽拉式导杆带端板更换排水体30截面尺寸为20*18cm,其底部安装有滚轮29,滚轮29与轨道28匹配,并能在轨道28滑动,使抽拉式导杆带端板更换排水体30能自由滑入预制装配式钢筋混凝土盲沟27,完成可更换排水体装配式横向排水盲沟8的施工安装。The third step is to excavate the replaceable drainage body assembled horizontal drainage blind ditch 8 in the transition section 3 of the junction. The height of the replaceable drainage body assembled horizontal drainage blind ditch 8 is 1/3 of the height of the excavation section 2, and the excavation is completed. Finally, install the prefabricated assembled reinforced concrete blind ditch 27 on the replaceable drainage body assembled horizontal drainage blind ditch 8, as shown in Figure 4, the cross-sectional size of the prefabricated assembled reinforced concrete blind ditch 27 in the embodiment of the present invention is 50* 30cm, the middle part of the prefabricated reinforced concrete blind ditch 27 is provided with a vertical steel plate 26, which is divided into two cell structures, the upper part of the prefabricated reinforced concrete blind ditch 27 is covered with steel mesh 25, and the bottom surface of each cell is laid with Two rails 28; the pull-type guide rod with end plate to replace the drainage body 30 is arranged in the cell of the prefabricated reinforced concrete blind ditch 27, and the cross-sectional size of the pull-type guide rod with end plate to replace the drain body 30 is 20*18cm , the bottom is equipped with a roller 29, the roller 29 is matched with the track 28, and can slide on the track 28, so that the pull-type guide bar with the end plate can freely slide into the prefabricated reinforced concrete blind ditch 27 for replacing the drainage body 30, and the completion can be completed. Replace the construction and installation of the assembled horizontal drainage blind ditch 8 of the drainage body.

第四步在可更换排水体装配式横向排水盲沟8上方安装纵向贯通排水盲沟20,如图2和图6所示,纵向贯通排水盲沟20的截面为半径20cm的圆;再在纵向贯通排水盲沟20上方进行填挖交界处透水与隔水层组合过渡段21施工,并进行增强补压,所述填挖交界处透水与隔水层组合过渡段21长度不小于 10m,其压实度不小于 96%,坡度为4%,填挖交界处透水与隔水层组合过渡段21从上往下分别是5cm厚的双层土工格栅7、隔水层22、透水层5、竖向小导管嵌入头层23、隔水层22与加筋泡沫混凝土调节层24,双层土工格栅7采用水泥钉6固定在隔水层22上,铺设土工格栅时应拉直平顺,紧贴下承层,不得有褶皱。下承层应平整,严禁有坚硬凸出物,隔水层22厚度为3cm,隔水层22采用SBS改性沥青、隔水层22下填充有2cm厚的碎石,构成透水层5,透水层5下方依次设有3cm厚的竖向小导管嵌入头层23、3cm厚的隔水层22以及5cm厚的加筋泡沫混凝土调节层24。填挖交界处透水与隔水层组合过渡段21采用液压夯和落锤式强夯机进行组合效果好。对于施工断面小的区域,比如台阶处和拐角处,根据液压夯压实有效厚度,逐层夯实,对其它部位采取落锤式强夯机每4米进行补强,针对施工断面大的区域,采用液压夯和32吨高性能强夯震动压路机进行组合碾压,施工完成后的纵向贯通排水盲沟20、坡面斜管导引19以及可更换排水体装配式横向排水盲沟8组成了山区公路填挖交界处路基结构的重要排水体系18。The fourth step is to install a vertical through-drainage blind ditch 20 above the replaceable drainage body assembled horizontal drainage blind ditch 8, as shown in Figure 2 and Figure 6, the section of the longitudinal through-drainage blind ditch 20 is a circle with a radius of 20cm; Through the top of the blind drainage ditch 20, the construction of the transition section 21 of the combination of the permeable and water-resisting layer at the fill-excavation junction is carried out, and the pressure is enhanced. The solidity is not less than 96%, the slope is 4%, and the combined transition section 21 of the permeable and water-resistant layer at the junction of filling and excavation is respectively a 5cm thick double-layer geogrid 7, a water-resistant layer 22, a water-resistant layer 5, The vertical small conduit is embedded in the head layer 23, the water-repellent layer 22 and the reinforced foam concrete adjustment layer 24. The double-layer geogrid 7 is fixed on the water-repellent layer 22 with cement nails 6. When laying the geogrid, it should be straightened and smooth. Adhere to the underlying layer without wrinkles. The lower bearing layer should be flat, and hard protrusions are strictly prohibited. The water-proof layer 22 has a thickness of 3cm. The water-proof layer 22 is made of SBS modified asphalt. Below the layer 5, a 3cm-thick vertical small conduit embedded in the head layer 23, a 3cm-thick water-proof layer 22, and a 5cm-thick reinforced foam concrete regulating layer 24 are sequentially arranged. The combined transition section 21 of the permeable and water-resistant layer at the junction of filling and excavation is combined with a hydraulic rammer and a drop hammer dynamic compaction machine, and the effect is good. For areas with small construction sections, such as steps and corners, according to the effective thickness of the hydraulic tamp compaction, compaction layer by layer, and other parts are reinforced every 4 meters with a drop hammer dynamic tamping machine. For areas with large construction sections, Combined rolling with hydraulic rammer and 32-ton high-performance strong-tamping vibratory roller. After the construction is completed, the vertical drainage blind ditch 20, the slope inclined pipe guide 19 and the replaceable drainage body assembled horizontal drainage blind ditch 8 form the mountainous area. The important drainage system of the subgrade structure at the junction of highway filling and excavation18.

第五步是在过渡段台阶4上设置复合式排水小导管10,复合式排水小导管10由密目网11和土工布袋12缠绕在注浆导管15外部形成,密目网11和注浆导管15之间填充有碎石14,其结构示意图可见图3,复合式排水小导管10的直径42mm,长150mm,其上端部设有扩大端板16,下端部设有锥形桩头13,扩大端板16内含直径10mm的观测孔31,锥形桩头13下端部设有圆锥瓣膜17,与注浆导管15直接相连;各复合式排水小导管10之间设置有坡面斜管导引19,通过坡面斜管导引19将复合式排水小导管10串联起来,坡内水体可经复合式排水小导管10,再经坡面斜管导引19排出。最后对填方路段1进行坡面36施工、设置排水明沟9等,再对挖方路段2进行施工。The fifth step is to set a composite small drainage conduit 10 on the step 4 of the transition section. The composite small drainage conduit 10 is formed by winding the dense mesh 11 and the geotextile bag 12 outside the grouting conduit 15. The dense mesh 11 and the grouting conduit 15 is filled with crushed stone 14, its structural schematic diagram is shown in Fig. 3, and the diameter 42mm of compound drainage small conduit 10, long 150mm, its upper end is provided with enlarged end plate 16, and lower end is provided with conical pile head 13, expands The end plate 16 contains an observation hole 31 with a diameter of 10mm, and the lower end of the conical pile head 13 is provided with a conical valve 17, which is directly connected to the grouting conduit 15; between the small composite drainage conduits 10, there is a sloped inclined conduit guide 19. Connect the small composite drainage conduits 10 in series through the inclined pipe guide 19 on the slope surface. Finally, carry out slope 36 construction on the filling road section 1, set drainage open ditches 9, etc., and then carry out construction on the excavating road section 2.

Claims (9)

1.山区公路填挖交界处路基结构,其特征在于:包括填方路段(1)、挖方路段(2)及填挖交界处过渡段(3),填方路段(1)上设有过渡段台阶(4)和排水明沟(9),填挖交界处过渡段(3)设有填挖交界处排水体系(18),填挖交界处排水体系(18)包括可更换排水体装配式横向排水盲沟(8)、纵向贯通排水盲沟(20)及填挖交界处透水与隔水层组合过渡段(21),填挖交界处透水与隔水层组合过渡段(21)和过渡段台阶(4)内均设有复合式排水小导管(10),填挖交界处透水与隔水层组合过渡段(21)上的复合式排水小导管(10)底部连接纵向贯通排水盲沟(20),纵向贯通排水盲沟(20)与可更换排水体装配式横向排水盲沟(8)相通,可更换排水体装配式横向排水盲沟(8)的高度为挖方路段(2)高度的1/3高度,且设置在挖方路段(2)底部。1. Subgrade structure at the junction of filling and excavation of mountainous highways, characterized in that it includes the filling road section (1), the excavation road section (2) and the transition section (3) at the junction of filling and excavation, and there is a transition section on the filling road section (1) Steps (4) and drainage ditches (9), the transition section (3) at the junction of filling and excavation is equipped with drainage system (18) at the junction of filling and excavation, and the drainage system (18) at the junction of filling and excavation includes assembled horizontal drainage with replaceable drainage body Blind ditch (8), vertical drainage blind ditch (20) and transition section (21) of combination of permeable and water-resisting layer at the junction of filling and excavation, transition section of combination of permeable and water-resisting layer at the junction of filling and excavation (21) and transition section steps (4) There are composite small drainage conduits (10) inside, and the bottom of the composite small drainage conduits (10) on the combined transition section (21) of the permeable and water-resistant layer at the junction of filling and excavation is connected longitudinally through the blind drainage ditch (20 ), the longitudinal blind drainage ditch (20) communicates with the replaceable drainage body-assembled horizontal drainage blind ditch (8), and the height of the replaceable drainage body-assembled horizontal drainage blind ditch (8) is 1 /3 height, and set at the bottom of the excavation section (2). 2.根据权利要求1所述的山区公路填挖交界处路基结构,其特征在于:可更换排水体装配式横向排水盲沟(8)包括抽拉式导杆带端板更换排水体(30)和预制装配式钢筋混凝土盲沟(27),预制装配式钢筋混凝土盲沟(27)中部设有竖向钢板(26),将其为两个格室结构,预制装配式钢筋混凝土盲沟(27)上部铺钢筋网片(25),每个格室底面各铺设有两条轨道(28),抽拉式导杆带端板更换排水体(30)设置在预制装配式钢筋混凝土盲沟(27)的格室中,抽拉式导杆带端板更换排水体(30)底部安装有滚轮(29),滚轮(29)与轨道(28)匹配,并能在轨道(28)滑动,使抽拉式导杆带端板更换排水体(30)能自由滑入预制装配式钢筋混凝土盲沟(27)。2. The subgrade structure at the junction of filling and excavation of mountainous roads according to claim 1, characterized in that: the replaceable drainage body assembled horizontal drainage blind ditch (8) includes a pull-out guide rod with an end plate to replace the drainage body (30) and the prefabricated reinforced concrete blind ditch (27), the middle part of the prefabricated reinforced concrete blind ditch (27) is provided with a vertical steel plate (26), making it a two-cell structure, the prefabricated reinforced concrete blind ditch (27 ) on the upper part of the reinforced mesh (25), and two rails (28) are laid on the bottom of each cell. ) in the compartment, the bottom of the drain body (30) with pull-out guide rod and end plate is installed with a roller (29). The roller (29) matches the track (28) and can slide on the track (28), so that the drawer The pull-type guide rod band end plate replaces the drainage body (30) and can freely slide into the prefabricated assembled reinforced concrete blind ditch (27). 3.根据权利要求1所述的山区公路填挖交界处路基结构,其特征在于:填挖交界处过渡段(3)位于填方路段(1)与挖方路段(2)之间,长度范围不小于10m,填挖交界处过渡段(3)的坡度为4%。3. The subgrade structure of the filling-cutting junction of mountainous roads according to claim 1, characterized in that: the transition section (3) of the filling-cutting junction is located between the filling section (1) and the excavation section (2), and the length range is not If it is less than 10m, the slope of the transition section (3) at the junction of fill and excavation is 4%. 4.根据权利要求1所述的山区公路填挖交界处路基结构,其特征在于:填挖交界处过渡段(3)下方设置过渡段台阶(4),内倾角度控制在4°以内,且由于台阶处碾压断面小,故采用环形压缩,有效消除压实盲区,提高土体密实度和整体稳定性。4. The subgrade structure at the filling-cutting junction of mountainous roads according to claim 1, characterized in that: a transition section step (4) is set under the transition section (3) at the filling-cutting junction, and the inclination angle is controlled within 4°, and due to The rolling section at the steps is small, so ring compression is adopted to effectively eliminate the compaction blind area and improve the compactness and overall stability of the soil. 5.根据权利要求1所述的山区公路填挖交界处路基结构,其特征在于:在填方路段(1)内和填挖交界处透水与隔水层组合过渡段(21)上分别设置复合式排水小导管(10),复合式排水小导管(10)包括密目网(11)、土工布袋(12)、锥形桩头(13)、注浆导管(15)及扩大端板(16),注浆导管(15)上从里到外依次设有密目网(11)和土工布袋(12),密目网(11)与注浆导管(15)之间填充有碎石(14);注浆导管(15)底部连接锥形桩头(13),顶部连接扩大端板(16),锥形桩头(13)上设有圆锥开瓣(17),扩大端板(16)下表面设有观测孔(31),复合式排水小导管(10)后期做注浆管用。5. The subgrade structure at the filling-excavation junction of mountainous roads according to claim 1, characterized in that: a composite layer is respectively set in the filling road section (1) and on the combined transition section (21) of the permeable and water-resisting layer at the filling-excavation junction. small drainage conduit (10), composite small drainage conduit (10) includes dense mesh (11), geotextile bag (12), conical pile head (13), grouting conduit (15) and enlarged end plate (16 ), the grouting conduit (15) is provided with a dense mesh (11) and a geotextile bag (12) in sequence from the inside to the outside, and gravel (14) is filled between the dense mesh (11) and the grouting conduit (15) ); the bottom of the grouting conduit (15) is connected to the conical pile head (13), and the top is connected to the enlarged end plate (16). The lower surface is provided with an observation hole (31), and the composite drainage small conduit (10) is used as a grouting pipe in the later stage. 6.根据权利要求1所述的山区公路填挖交界处路基结构,其特征在于:过渡段台阶(4)通过静态爆破的方法施工得到:先在填方路段(1)内钻设L形静态爆破孔(32),L形静态爆破孔(32)内填装静态爆破剂,同时安装水平带封口板整体式压水补水管(33)和侧向带封口板整体式压水补水管(34),水平带封口板整体式压水补水管(33)和侧向带封口板整体式压水补水管(34)的外端端头分别通过端部锚固件(35)固定在坡面(36)上,利用水化反应把岩石胀破,得到过渡段台阶(4)。6. The subgrade structure at the junction of filling and excavation of mountainous roads according to claim 1, characterized in that: the steps (4) of the transition section are constructed by static blasting: firstly, L-shaped static blasting is drilled in the filling section (1). The blasting hole (32), the L-shaped static blasting hole (32) is filled with static blasting agent, and the horizontal integral pressure water supply pipe with sealing plate (33) and the lateral integral pressure water supply pipe with sealing plate (34) are installed at the same time ), the outer ends of the horizontal integral pressurized water replenishment pipe with sealing plate (33) and the lateral integral pressurized water replenishment pipe (34) with sealing plate (34) are respectively fixed on the slope surface (36 ), use the hydration reaction to burst the rock, and obtain the transitional step (4). 7.一种基于权利要求1所述的山区公路填挖交界处路基结构的施工方法,其特征在于包括以下的步骤:7. A construction method based on the subgrade structure at the junction of filling and excavating mountain roads according to claim 1, characterized in that it comprises the following steps: 第一步是对原坡面(37)的基底层进行清理与压实,具体包括开挖纵向临时水沟,纵向沟挖出土方培在沟外侧作沟埂,以免路基外侧地表水排入路基基底;路基用地范围内的树木、灌木丛等均在施工前砍伐挖根,并将地表土予以清除,路堤基底清理、平整、晒干后再整平压实,填方地段清除表土200mm,压实度不小于90%;在路堤底部填以砂、砂砾、碎石等材料进行加固,使其形成水稳性好稳定层;The first step is to clean and compact the base layer of the original slope (37), which specifically includes excavating a longitudinal temporary ditch, excavating the soil from the longitudinal ditch and making a ridge on the outside of the ditch, so as to prevent the surface water outside the roadbed from being discharged into the roadbed Base; the trees and shrubs within the scope of subgrade land shall be cut down and dug for roots before construction, and the surface soil shall be removed. The solidity is not less than 90%; the bottom of the embankment is reinforced with sand, gravel, gravel and other materials to form a stable layer with good water stability; 第二步是在填方路段(1)上进行填挖交界处过渡段(3)的位置开挖过渡段台阶(4),并进行环形压实;The second step is to excavate the transition section step (4) at the position of the transition section (3) at the filling-excavation junction on the filling road section (1), and carry out ring compaction; 第三步是在交界处过渡段(3)开挖可更换排水体装配式横向排水盲沟(8),可更换排水体装配式横向排水盲沟(8)的高度为挖方路段(2)的1/3高度,开挖完成后,在可更换排水体装配式横向排水盲沟(8)上安装预制装配式钢筋混凝土盲沟(27),预制装配式钢筋混凝土盲沟(27)中部安装竖向钢板(26),将其为两个格室结构,预制装配式钢筋混凝土盲沟(27)上部铺钢筋网片(25),每个格室底面各铺设有两条轨道(28);抽拉式导杆带端板更换排水体(30)设置在预制装配式钢筋混凝土盲沟(27)的格室中,抽拉式导杆带端板更换排水体(30)底部安装有滚轮(29),滚轮(29)与轨道(28)匹配,并能在轨道(28)滑动,使抽拉式导杆带端板更换排水体(30)能自由滑入预制装配式钢筋混凝土盲沟(27),完成可更换排水体装配式横向排水盲沟(8)的施工安装;The third step is to excavate the replaceable drainage body-assembled horizontal drainage blind ditch (8) in the transition section (3) at the junction. The height of the replaceable drainage body-assembled horizontal drainage blind ditch (8) is 2 1/3 height, after the excavation is completed, install the prefabricated reinforced concrete blind ditch (27) on the replaceable drainage body assembled horizontal drainage blind ditch (8), and install the vertical To the steel plate (26), it is a two-cell structure, the upper part of the prefabricated reinforced concrete blind ditch (27) is laid with steel mesh (25), and the bottom surface of each cell is laid with two tracks (28); The pull-type guide rod with end plate to replace the drainage body (30) is set in the cell of the prefabricated reinforced concrete blind ditch (27), and the bottom of the pull-type guide rod with end plate to replace the drain body (30) is installed with rollers (29 ), the rollers (29) are matched with the track (28), and can slide on the track (28), so that the pull-out guide bar with end plate to replace the drainage body (30) can freely slide into the prefabricated reinforced concrete blind ditch (27 ), complete the construction and installation of the replaceable drainage body assembled horizontal drainage blind ditch (8); 第四步在可更换排水体装配式横向排水盲沟(8)上方安装纵向贯通排水盲沟(20),再在纵向贯通排水盲沟(20)上方进行填挖交界处透水与隔水层组合过渡段(21)施工,并进行增强补压,所述填挖交界处透水与隔水层组合过渡段(21)长度不小于 10m,填挖交界处透水与隔水层组合过渡段(21)采用液压夯和落锤式强夯机进行组合施工,压实度不小于96%,坡度为4%;The fourth step is to install the vertical through drainage blind ditch (20) above the replaceable drainage body assembled horizontal drainage blind ditch (8), and then carry out the combination of the permeable and water-resistant layer at the junction of filling and excavation above the longitudinal through drainage blind ditch (20) Construction of the transition section (21) and enhanced pressure supplementation, the length of the transition section (21) of the combination of the permeable and water-resisting layer at the fill-excavation interface (21) is not less than 10m, and the transition section (21) of the combination of the permeable and water-resisting layer Combined construction with hydraulic rammer and drop hammer dynamic compaction machine, the compaction degree is not less than 96%, and the slope is 4%; 第五步是在过渡段台阶(4)上设置复合式排水小导管(10),复合式排水小导管(10)由密目网(11)和土工布袋(12)缠绕在注浆导管(15)外部形成,密目网(11)和注浆导管(15)之间填充有碎石(14),复合式排水小导管(10上端部设有扩大端板(16),下端部设有锥形桩头(13),扩大端板(16)内含观测孔(31),锥形桩头(13)下端部设有圆锥瓣膜(17),与注浆导管(15)直接相连;各复合式排水小导管(10)之间设置有坡面斜管导引(19),通过坡面斜管导引(19)串联,坡内水体可经复合式排水小导管(10),再经坡面斜管导引(19)排出;The fifth step is to set the composite small drainage conduit (10) on the transition section step (4). The composite small drainage conduit (10) is wound on the grouting conduit (15) by dense mesh (11) and geotextile bag (12). ) is externally formed, gravel (14) is filled between the dense mesh (11) and the grouting conduit (15), the composite drainage small conduit (10 is provided with an enlarged end plate (16) at the upper end, and a cone is provided at the lower end shaped pile head (13), the enlarged end plate (16) contains observation holes (31), and the lower end of the conical pile head (13) is provided with a conical valve (17), which is directly connected with the grouting catheter (15); There is a slope inclined pipe guide (19) between the small drainage conduits (10) on the slope surface, through which the slope surface inclined pipe guidance (19) is connected in series, the water body in the slope can pass through the composite small drainage conduit (10), and then pass through the slope The inclined pipe guide (19) is discharged; 第六步对填方路段(1)进行坡面(36)施工,并在填方路段(1)底部设置排水明沟(9)等,再对挖方路段(2)进行施工。The sixth step is to carry out slope (36) construction on the filling road section (1), and set drainage ditches (9) etc. at the bottom of the filling road section (1), and then carry out construction on the excavating road section (2). 8.根据权利要求7所述的山区公路填挖交界处路基结构的施工方法,其特征在于步骤二中开挖过渡段台阶(4)具体过程如下:利用钻具先在坡面(36)从上至下依次钻设若干L形静态爆破孔(32);紧接着将提前配置好的静态爆破剂放入L形静态爆破孔(32)的孔道内,再在L形静态爆破孔(32)上安装水平带封口板整体式压水补水管(33)和侧向带封口板整体式压水补水管(34),两个补水管分别利用端部锚固件(35)固定安装在坡面(36)上,通过补水管向L形静态爆破孔(32)内补水,与静态爆破剂发生水化反应,放出热量,将岩石体胀破开裂,静态爆破之后将破损的岩体利用人工镐凿除,控制台阶坡度在4%以内;在基底清除完毕后立即开始由上至下的一次性修筑成型,若不能从上至下一次修筑的,在每层填筑土以上至少保留3个台阶,再进行分层填筑。8. The construction method of the subgrade structure at the junction of filling and excavating mountain roads according to claim 7, characterized in that in step 2, the specific process of excavating the steps (4) in the transition section is as follows: use the drilling tool to first dig from the slope (36) Drill several L-shaped static blasting holes (32) sequentially from top to bottom; then put the pre-configured static blasting agent into the channel of the L-shaped static blasting hole (32), and then drill the L-shaped static blasting hole (32) Install the horizontal integral pressurized water supply pipe (33) with sealing plate and the lateral integral pressurized water supply pipe (34) with sealing plate on the top, and the two water supply pipes are respectively fixed and installed on the slope ( 36), supply water to the L-shaped static blasting hole (32) through the water supply pipe, hydration reaction with the static blasting agent, release heat, and expand and crack the rock mass. In addition, the slope of the console steps shall be within 4%; immediately after the base clearing is completed, the one-time construction from top to bottom shall be started. If it cannot be built from top to bottom, at least 3 steps shall be reserved above each layer of filling soil. Then fill in layers. 9.根据权利要求8所述的山区公路填挖交界处路基结构的施工方法,其特征在于压实方法采用环形压实,再结合液压式碾压设备。9. The construction method of the subgrade structure at the junction of filling and excavation of mountainous roads according to claim 8, characterized in that the compaction method adopts ring compaction, combined with hydraulic rolling equipment.
CN201810406200.5A 2018-04-30 2018-04-30 Roadbed structure at mountain highway filling and digging junction and construction method thereof Active CN108486976B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810406200.5A CN108486976B (en) 2018-04-30 2018-04-30 Roadbed structure at mountain highway filling and digging junction and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810406200.5A CN108486976B (en) 2018-04-30 2018-04-30 Roadbed structure at mountain highway filling and digging junction and construction method thereof

Publications (2)

Publication Number Publication Date
CN108486976A true CN108486976A (en) 2018-09-04
CN108486976B CN108486976B (en) 2023-06-27

Family

ID=63313386

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810406200.5A Active CN108486976B (en) 2018-04-30 2018-04-30 Roadbed structure at mountain highway filling and digging junction and construction method thereof

Country Status (1)

Country Link
CN (1) CN108486976B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610435A (en) * 2019-01-29 2019-04-12 中国机械设备工程股份有限公司 A kind of loess high roadbed cheuch ground discharge structure and its laying method
CN110055831A (en) * 2019-04-28 2019-07-26 中铁二院工程集团有限责任公司 A kind of abrupt slope high-speed railway concrete rigid short circuit based structures and construction method
CN110172884A (en) * 2019-06-04 2019-08-27 中信国安建工集团有限公司 A kind of Subgrade in Mountain Area and construction method
CN112681043A (en) * 2020-12-18 2021-04-20 湖北省路桥集团有限公司 Roadbed splicing and widening structure and construction method
CN113403904A (en) * 2021-07-21 2021-09-17 中信国安建工集团有限公司 Highway filling and digging boundary roadbed structure and construction operation method
CN117926653A (en) * 2023-12-19 2024-04-26 安徽省公路桥梁工程有限公司 Method for half-filling and half-digging roadbed at poor geological interface of soft rock

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0384117A (en) * 1989-08-25 1991-04-09 Railway Technical Res Inst Steep sloping method of banking slope
AU632967B2 (en) * 1992-02-19 1993-01-14 Charles St'Clair Matheson Easy gutter cleaner
US5930923A (en) * 1996-12-26 1999-08-03 Yugenkaisha Unit Shoji Limited Method for operation to excavate underdrain in the field ground and a device for operation to excavate underdrain
US20050047866A1 (en) * 2003-09-02 2005-03-03 Chen Jui Wen Construction of environmental and water-permeable paving
JP2005097858A (en) * 2003-09-22 2005-04-14 Ito Yogyo Co Ltd Drainage block and pavement structure using it
BRPI0902835A2 (en) * 2009-08-21 2012-06-12 Engegraut Servicos Tecnicos Ltda deep radial consolidation process or cpr for soft or peat clay soils using finite element method in process programming and control
CN203741666U (en) * 2014-01-27 2014-07-30 安徽省公路桥梁工程有限公司 Roadbed structure for preventing cut-fill section of highway in cold region from frost boiling
CN104264557A (en) * 2014-08-28 2015-01-07 杭州江润科技有限公司 Semi-filling and semi-excavating ecological subgrade structure and construction method
CN104594329A (en) * 2014-12-17 2015-05-06 河海大学 Device for treating differential settlement of road and bridge transition sections through load reducing and method of device
CN204356888U (en) * 2014-12-23 2015-05-27 中山市博见金属制品有限公司 A new type of drainage ditch
CN106759792A (en) * 2016-12-02 2017-05-31 安徽省公路桥梁工程有限公司 A kind of inspection shaft construction technique
CN208455387U (en) * 2018-04-30 2019-02-01 安徽省公路桥梁工程有限公司 Subgrade structure at the junction of filling and excavation of mountain roads

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0384117A (en) * 1989-08-25 1991-04-09 Railway Technical Res Inst Steep sloping method of banking slope
AU632967B2 (en) * 1992-02-19 1993-01-14 Charles St'Clair Matheson Easy gutter cleaner
US5930923A (en) * 1996-12-26 1999-08-03 Yugenkaisha Unit Shoji Limited Method for operation to excavate underdrain in the field ground and a device for operation to excavate underdrain
US20050047866A1 (en) * 2003-09-02 2005-03-03 Chen Jui Wen Construction of environmental and water-permeable paving
JP2005097858A (en) * 2003-09-22 2005-04-14 Ito Yogyo Co Ltd Drainage block and pavement structure using it
BRPI0902835A2 (en) * 2009-08-21 2012-06-12 Engegraut Servicos Tecnicos Ltda deep radial consolidation process or cpr for soft or peat clay soils using finite element method in process programming and control
CN203741666U (en) * 2014-01-27 2014-07-30 安徽省公路桥梁工程有限公司 Roadbed structure for preventing cut-fill section of highway in cold region from frost boiling
CN104264557A (en) * 2014-08-28 2015-01-07 杭州江润科技有限公司 Semi-filling and semi-excavating ecological subgrade structure and construction method
CN104594329A (en) * 2014-12-17 2015-05-06 河海大学 Device for treating differential settlement of road and bridge transition sections through load reducing and method of device
CN204356888U (en) * 2014-12-23 2015-05-27 中山市博见金属制品有限公司 A new type of drainage ditch
CN106759792A (en) * 2016-12-02 2017-05-31 安徽省公路桥梁工程有限公司 A kind of inspection shaft construction technique
CN208455387U (en) * 2018-04-30 2019-02-01 安徽省公路桥梁工程有限公司 Subgrade structure at the junction of filling and excavation of mountain roads

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610435A (en) * 2019-01-29 2019-04-12 中国机械设备工程股份有限公司 A kind of loess high roadbed cheuch ground discharge structure and its laying method
CN109610435B (en) * 2019-01-29 2023-09-12 中国机械设备工程股份有限公司 Loess high fill valley foundation drainage structure and laying method thereof
CN110055831A (en) * 2019-04-28 2019-07-26 中铁二院工程集团有限责任公司 A kind of abrupt slope high-speed railway concrete rigid short circuit based structures and construction method
CN110172884A (en) * 2019-06-04 2019-08-27 中信国安建工集团有限公司 A kind of Subgrade in Mountain Area and construction method
CN110172884B (en) * 2019-06-04 2024-02-13 中信国安建工集团有限公司 A mountain road subgrade and construction method
CN112681043A (en) * 2020-12-18 2021-04-20 湖北省路桥集团有限公司 Roadbed splicing and widening structure and construction method
CN113403904A (en) * 2021-07-21 2021-09-17 中信国安建工集团有限公司 Highway filling and digging boundary roadbed structure and construction operation method
CN117926653A (en) * 2023-12-19 2024-04-26 安徽省公路桥梁工程有限公司 Method for half-filling and half-digging roadbed at poor geological interface of soft rock

Also Published As

Publication number Publication date
CN108486976B (en) 2023-06-27

Similar Documents

Publication Publication Date Title
CN108486976B (en) Roadbed structure at mountain highway filling and digging junction and construction method thereof
CN107503257B (en) One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method
CN106759473B (en) The constructing structure and its construction method of underground pipe gallery and road
CN113445396B (en) High-fill road foundation filling construction method for high liquid limit soil road section
CN110306616A (en) A kind of construction method of sewage conduct
CN106013191A (en) Environmental-friendly grass concrete highway slope protection structure and construction method thereof
CN110219359A (en) A kind of Submersed type inspection well and its construction method
CN111322087A (en) Construction method for soft soil highway tunnel entrance semi-open semi-hidden tunnel in mountainous area
CN116696386B (en) A construction method suitable for tunnels in eroded hilly terrain
CN104499479A (en) Dig-hole pile construction method based on penetration of sand gravel backfilling layer
CN109914161B (en) Construction method of high-speed railway filling roadbed in soft soil area
CN111101540B (en) A construction method for an open-cut tunnel passing through an existing power tunnel
CN116377780A (en) Construction Method of High Fill Subgrade in Mountainous Highway
CN207109475U (en) It is close to mountain high-filled subgrade stabilization and Deformation control structure
CN112983461B (en) Construction method of bias-pressure tunnel opening in sloped mass
CN103074882A (en) Construction method for reinforcing island-type perennial frozen-soil foundation by adopting gravel piles
CN107288120A (en) A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash
CN102966072A (en) Construction method for treating widened and heightened engineering joint surfaces of dikes on soft clay foundation
CN108978385A (en) A kind of roadbed construction method on the road Tong Cun
CN106049196A (en) Construction method of ballastless track subgrade with combined flexible piles and pile rafts at same fracture surfaces
CN116876280B (en) Construction method of high embankment
CN108571000A (en) The construction method of underground water cutting when wearing existing railway under a kind of road of location along the river
CN108824412B (en) Soft foundation treatment method based on gabion wall reinforced soil and dynamic compaction
CN208455387U (en) Subgrade structure at the junction of filling and excavation of mountain roads
CN207032212U (en) A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 230031 no.445 Huangshan Road, Shushan District, Hefei City, Anhui Province

Patentee after: Anhui Construction Engineering Highway and Bridge Construction Group Co.,Ltd.

Country or region after: China

Address before: 230031 no.445 Huangshan Road, Shushan District, Hefei City, Anhui Province

Patentee before: ANHUI ROAD & BRIDGE ENGINEERING Co.,Ltd.

Country or region before: China

CP03 Change of name, title or address