CN109000524B - Boundary control blasting method for reducing over-excavation and under-excavation - Google Patents

Boundary control blasting method for reducing over-excavation and under-excavation Download PDF

Info

Publication number
CN109000524B
CN109000524B CN201810899895.5A CN201810899895A CN109000524B CN 109000524 B CN109000524 B CN 109000524B CN 201810899895 A CN201810899895 A CN 201810899895A CN 109000524 B CN109000524 B CN 109000524B
Authority
CN
China
Prior art keywords
blasting
hole
excavation
aerial vehicle
unmanned aerial
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810899895.5A
Other languages
Chinese (zh)
Other versions
CN109000524A (en
Inventor
南亚林
陈能远
牛利刚
许江波
田理嘉
甄平福
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Electronic Research Institute Of Engineering Investigations And Design
Changan University
Original Assignee
China Electronic Research Institute Of Engineering Investigations And Design
Changan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Electronic Research Institute Of Engineering Investigations And Design, Changan University filed Critical China Electronic Research Institute Of Engineering Investigations And Design
Priority to CN201810899895.5A priority Critical patent/CN109000524B/en
Publication of CN109000524A publication Critical patent/CN109000524A/en
Application granted granted Critical
Publication of CN109000524B publication Critical patent/CN109000524B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D1/00Blasting methods or apparatus, e.g. loading or tamping
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques
    • F42D3/04Particular applications of blasting techniques for rock blasting
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D5/00Safety arrangements

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

The invention relates to a boundary control blasting method for reducing over-excavation and under-excavation, which at least comprises the following steps: the method comprises the steps of unmanned aerial vehicle terrain surveying in the early stage, site cleaning and drawing lofting, blast hole arrangement, drilling machine operation and blast hole construction, longitudinal blasting operation, cleaning, grouting hole arrangement, drilling machine operation and grouting hole construction, grouting, charging of slope secondary blast hole excavation, secondary blast hole operation and monitoring, supporting and gradually completing high slope blasting excavation supporting. The invention has the following advantages: according to the boundary control blasting method for reducing the overexcavation and the underexcavation, provided by the invention, the blasting is arranged through the blasting holes, most rock masses outside the designed excavation line can be effectively removed, the blasting is arranged through the secondary blasting holes, a small part of rock masses outside the designed excavation line can be effectively removed, and the rock masses outside the designed excavation line can be successively removed through the batch blasting, so that the overexcavation and the underexcavation can be reduced, the construction cost is saved, and the boundary control blasting method has higher practical value and social value.

Description

Boundary control blasting method for reducing over-excavation and under-excavation
Technical Field
The invention relates to the technical field of slope excavation controlled blasting of geotechnical engineering, in particular to a boundary controlled blasting method for reducing over-excavation and under-excavation.
Background
China is a mountainous country. In recent years, with the increasing of the investment of the country on the infrastructure projects, more and more highway and railway construction projects are provided. In the construction of highway and railway engineering in mountain areas, roads often pass between rivers, valleys and mountains, and the construction of the engineering often involves the excavation of high slopes.
In the construction of highway, railway and other projects in mountain areas, a drilling and blasting method is often adopted for operation. However, in the drilling and blasting construction, the overbreak and the underbreak are relatively uncontrollable, and the excessive overbreak causes not only an increase in cost but also, more importantly, an increase in the cost of the overfilled concrete. In actual construction, although the overbreak and the underexcavation are reduced as much as possible, the technical method is not appropriate, so that the engineering cost is increased in the construction process, and the construction period is prolonged.
At present, the high slope blasting technology has been widely applied in the building engineering industry, but is an innovative and perfect subject for the high slope blasting construction under special conditions. China is currently building and developing along coastal and developed cities to radiate towards second-line, third-line and remote mountainous areas, and very high requirements are put forward for high slope blasting under complex conditions of complex geology, vertical high slopes and pedestrian and vehicle traffic in lower national roads, and the blasting is more and more common in later engineering construction.
We therefore propose a boundary-controlled blasting method that reduces overbreak and underbreak.
Disclosure of Invention
The invention aims to provide a boundary control blasting method for reducing over-excavation and under-excavation.
The invention is realized by the following technical scheme:
a boundary control blasting method for reducing overbreak and underbreak at least comprises the following steps:
s001, surveying the terrain of the unmanned aerial vehicle in the early stage;
setting the ground resolution of a high slope in a mountain area according to the requirement of an aerial photography project;
planning a flight route of the unmanned aerial vehicle;
at takeoff, through the following calculation formula:
Figure GDA0002403694920000021
calculating the theoretical relative height H between the unmanned aerial vehicle and the ground, andadjusting the initial flying height of the unmanned aerial vehicle according to the theoretical relative height H;
wherein f is a lens focal length of aerial equipment carried on the unmanned aerial vehicle, a is a pixel size of the aerial equipment carried on the unmanned aerial vehicle, and GSD is a theoretical ground resolution;
after taking off and reaching a preset aerial photographing area, starting aerial photographing operation;
in the flying process of the unmanned aerial vehicle, the flying height of the unmanned aerial vehicle is adjusted according to the fluctuation degree of the ground; before setting unmanned aerial vehicle to become high, unmanned aerial vehicle's flying height is H0, and the altitude variation of current topography is H, then unmanned aerial vehicle flying height control module is as follows to flying height's accommodate value lambda H:
λH=h;
h is a negative value if the ground height decreases; if the ground height is increased, H is a positive value, and the flight height adjusting value lambda H of the unmanned aerial vehicle is obtained at the moment;
when the lambda H is a negative value, the unmanned aerial vehicle flight height module controls the flight height of the unmanned aerial vehicle to be decreased by the lambda H, and when the lambda H is a positive value, the unmanned aerial vehicle aircraft height control module controls the flight height of the unmanned aerial vehicle to be increased by the lambda H;
s002: cleaning on site and lofting drawings;
cleaning and flattening the terrain map of the high slope in the mountain ridge area shot by the S001;
according to a design drawing of a high slope in a mountain area, lofting an excavation line of the high slope;
s003: arranging blast holes; finding a designed excavation line of a high slope on the upper side of the high slope in the mountain area, arranging a plurality of blasting holes at the position 1.0m outside the excavation ground line of the first-stage slope surface along the excavation direction and at the position 1.0m in the transverse interval, and arranging the direction of the blasting holes downwards along the excavation surface; the inclination angle of the blast hole is the same as the design inclination angle of the side slope;
s004: drilling machine operation and blast hole construction; drilling by a drilling machine according to the corresponding positions of the blast holes to form the blast holes; the diameter of the blast hole is 30mm, the depth of the blast hole is 3m, and the depth is up to the step surface of the second-stage side slope surface;
s005: performing longitudinal blasting operation; blasting by putting explosives into the blasting holes; the single-hole loading quantity is 1800g according to a calculation formula Q ═ aLBq;
wherein the transverse interval a of the blast holes is 1.0m, the drilling depth L is 3.0m, the blasting thickness B is 0.5m, and the unit consumption q of the explosive is 1200g/m3
Carrying out blasting vibration monitoring during longitudinal blasting operation, wherein the monitoring comprises monitoring point arrangement and inspection tour inspection modes; the monitoring point arrangement specifically comprises monitoring at the upper side, the middle part and the lower side of the high slope so as to prevent excessive blasting and adjust the blasting strategy in time; the patrol inspection mode adopts a project safety responsible person to patrol inspection within the blasting time, so that irrelevant persons are prevented from entering a blasting hazard area, and major potential safety hazards are prevented;
after the explosive is placed in the blasting hole, the top of the blasting hole is blocked by a water bag containing water, when the explosive explodes, the water bag and the water in the water bag can be exploded to form an atomized water vapor layer, and the atomized water vapor layer is combined with dust particles during explosion to form slurry so as to reduce the dust during blasting;
s006: cleaning; cleaning sandy soil and rock sundries on the step surface of the second-stage side slope surface after blasting, and leveling the step surfaces of the first-stage side slope surface and the second-stage side slope surface;
s007: arranging grouting holes; arranging a plurality of grouting holes at the position 1.0m away from the excavation ground line of the first-stage side slope surface towards the inner side of the excavation direction and at the position with the transverse interval of 0.5m, wherein the direction of the grouting holes is downwards arranged along the excavation surface; the inclination angle of the grouting hole is the same as the design inclination angle of the side slope.
S008: drilling machine operation and grouting hole construction; drilling by a drilling machine according to the corresponding position of the grouting hole to form the grouting hole; the diameter of the grouting hole is 80mm, the depth of the grouting hole is 3m, and the depth is up to the step surface of the second-stage side slope surface;
s009: grouting; cement mortar with a water cement ratio of 1:1 is injected into the grouting hole, so that the cement mortar is diffused to each position in the grouting hole, and a reinforcing column with set thickness is formed in the grouting hole;
s010: excavating a secondary blasting hole on the side slope and charging; a plurality of secondary blasting holes are formed in the outer side of the designed excavation line of the first-stage side slope surface along the inclined plane of the first-stage side slope surface, explosives are arranged in the secondary blasting holes, and the arrangement direction of the secondary blasting holes is perpendicular to the direction of the grouting holes;
s011: performing secondary blast hole operation and monitoring; blasting by putting explosives into the secondary blasting holes; the single-hole explosive loading is 72g according to a calculation formula Q ═ aLBq;
wherein the transverse interval a of the blast holes is 1.0m, the drilling depth L is 0.3m, the blasting thickness B is 0.2m, and the unit consumption q of the explosive is 1200g/m3
Carrying out blasting vibration monitoring during secondary blasting hole blasting operation, wherein the monitoring comprises monitoring point arrangement and inspection tour inspection modes; the monitoring point arrangement specifically comprises monitoring at the upper side, the middle part and the lower side of the high slope so as to prevent excessive blasting and adjust the blasting strategy in time; the patrol inspection mode adopts a project safety responsible person to patrol inspection within the blasting time, so that irrelevant persons are prevented from entering a blasting hazard area, and major potential safety hazards are prevented;
s012: supporting; after the secondary blast hole operation is finished, carrying out sand blasting support on the first-stage slope surface; meanwhile, an anchor rod hole is formed in the first-stage slope surface corresponding to the reinforcing column body, and an anchor rod is fixedly connected with the reinforcing column body through the anchor rod hole;
s013: the high slope blasting excavation supporting is completed step by step; and after the blasting excavation support of the first grade of slope surface is finished, performing blasting excavation support of the second grade of slope surface, and repeating the steps S004-S012 until all the high slope blasting excavation supports are finished.
Preferably, after the explosive is put into the secondary blasting hole, the top of the secondary blasting hole is blocked by a water bag containing water; when the explosive explodes, the water bag and the water in the water bag can be exploded for four shots to form an atomized water vapor layer, and the atomized water vapor layer is combined with dust particles during explosion to form slurry, so that dust during explosion is reduced.
Preferably, the water bag is a plastic sealing water bag.
The technical scheme is preferably that high water-jetting guns are arranged around the explosion holes and the secondary explosion holes, and dust fall is carried out on the explosion area before, during and after explosion through the high water-jetting guns.
The technical scheme is preferably that the explosive is emulsion explosive or ammonium nitrate explosive.
The technical scheme is preferably that the secondary blasting holes are arranged in a plum blossom shape.
The technical scheme is preferably that the drilling machine adopts a hydraulic drill, a down-the-hole drill or a hand pneumatic drill.
The technical scheme is preferably that the inclination angle of the blast hole is the same as the design inclination angle of the side slope.
The technical scheme is preferably that the inclination angle of the grouting hole is the same as the design inclination angle of the side slope.
Preferably, the second-stage slope surface is arranged on the lower side of the first-stage slope surface.
Compared with the prior art, the invention has the following advantages: according to the boundary control blasting method for reducing the overexcavation and the underexcavation, provided by the invention, the blasting is arranged through the blasting holes, most rock masses outside the designed excavation line can be effectively removed, the blasting is arranged through the secondary blasting holes, a small part of rock masses outside the designed excavation line can be effectively removed, and the rock masses outside the designed excavation line can be successively removed through the batch blasting, so that the overexcavation and the underexcavation can be reduced, the construction cost is saved, and the boundary control blasting method has higher practical value and social value.
In the invention, unmanned aerial vehicle surveying is adopted, so that the terrain condition of the area to be constructed can be accurately mastered in the early stage; blasting vibration monitoring is carried out during blasting operation, so that irrelevant personnel are prevented from entering a blasting hazard area, and major potential safety hazards are prevented.
The dust fall is carried out on the explosion area before, during and after explosion by arranging the water bag and the high-speed water jet gun, the dust mass is covered in a three-dimensional manner, multiple reduction is carried out, the harmful gas and the raise dust of large-area open blasting are effectively reduced, and the device is clean and environment-friendly.
Drawings
FIG. 1 is a schematic diagram of the construction steps of a boundary controlled blasting method for reducing overbreak and underbreak according to the present invention.
Detailed Description
The following describes embodiments of the present invention in further detail with reference to the accompanying drawings.
Fig. 1 is a schematic diagram showing the construction steps of the boundary control blasting method for reducing overbreak and underbreak according to the present invention.
The invention relates to a boundary control blasting method for reducing over-excavation and under-excavation, which comprises the following steps of:
s001, surveying the terrain of the unmanned aerial vehicle in the early stage;
setting the ground resolution of a high slope in a mountain area according to the requirement of an aerial photography project;
planning a flight route of the unmanned aerial vehicle;
at takeoff, through the following calculation formula:
Figure GDA0002403694920000061
calculating a theoretical relative height H of the unmanned aerial vehicle and the ground, and adjusting the initial flying height of the unmanned aerial vehicle according to the theoretical relative height H;
the aerial photographing device comprises an unmanned aerial vehicle, a GSD and a high-altitude camera, wherein f is a lens focal length of the aerial photographing device carried on the unmanned aerial vehicle, a is a pixel size of the aerial photographing device carried on the unmanned aerial vehicle, and the GSD is a theoretical ground resolution, wherein the aerial photographing device is in the prior art and can be a high-altitude camera.
After taking off and reaching a preset aerial photographing area, starting aerial photographing operation;
in the flying process of the unmanned aerial vehicle, the flying height of the unmanned aerial vehicle is adjusted according to the fluctuation degree of the ground; before setting unmanned aerial vehicle to become high, unmanned aerial vehicle's flying height is H0, and the altitude variation of current topography is H, then unmanned aerial vehicle flying height control module is as follows to flying height's accommodate value lambda H:
λH=h;
h is a negative value if the ground height decreases; if the ground height is increased, H is a positive value, and the flight height adjusting value lambda H of the unmanned aerial vehicle is obtained at the moment;
when lambda H is a negative value, the unmanned aerial vehicle flying height module controls the flying height of the unmanned aerial vehicle to decrease lambda H, and when lambda H is a positive value, the unmanned aerial vehicle airplane height control module controls the flying height of the unmanned aerial vehicle to increase lambda H. It should be noted that the unmanned aerial vehicle aircraft altitude control module is prior art for control unmanned aerial vehicle's flying height.
S002: cleaning on site and lofting drawings;
cleaning and flattening the terrain map of the high slope in the mountain ridge area shot by the S001;
according to a design drawing of a high slope in a mountain area, lofting an excavation line of the high slope;
s003: arranging blast holes; finding a designed excavation line of a high slope on the upper side of the high slope in the mountain area, arranging a plurality of blasting holes at the position 1.0m outside the excavation ground line of the first-stage slope surface along the excavation direction and at the position 1.0m in the transverse interval, and arranging the direction of the blasting holes downwards along the excavation surface;
s004: drilling machine operation and blast hole construction; drilling by a drilling machine according to the corresponding positions of the blast holes to form the blast holes; the diameter of the blast hole is 30mm, the depth of the blast hole is 3m, and the depth is up to the step surface of the second-stage side slope surface; the drilling machine is the existing equipment, can adopt hydraulic drill, down-the-hole drill or hand pneumatic drill, and specific model can be configured according to actual conditions.
S005: performing longitudinal blasting operation; blasting by putting explosives into the blasting holes; the single-hole loading quantity is 1800g according to a calculation formula Q ═ aLBq; the explosive adopts emulsion explosive;
wherein the transverse interval a of the blast holes is 1.0m, the drilling depth L is 3.0m, the blasting thickness B is 0.5m, and the unit consumption q of the explosive is 1200g/m3. Of course, the explosive may be a detonator.
Carrying out blasting vibration monitoring during longitudinal blasting operation, wherein the monitoring comprises monitoring point arrangement and inspection tour inspection modes; the monitoring point arrangement specifically comprises monitoring at the upper side, the middle part and the lower side of the high slope so as to prevent excessive blasting and adjust the blasting strategy in time; the inspection tour mode adopts the responsible personnel of project safety to inspect the inspection tour in the blasting time, avoids irrelevant personnel to get into the blasting harm region, prevents great potential safety hazard.
After the explosive is placed in the blasting hole, the top of the blasting hole is blocked by a water bag containing water, when the explosive explodes, the water bag and the water in the water bag can be exploded to form an atomized water vapor layer, and the atomized water vapor layer is combined with dust particles during explosion to form slurry so as to reduce the dust during blasting; the water bag is a plastic sealing water bag;
arranging a high water-jetting gun around the explosion hole, and performing dust fall on an explosion area before, during and after explosion by the high water-jetting gun; the high-speed water-jetting gun is an existing device, such as a fire-fighting high-speed water-jetting gun.
S006: cleaning; cleaning sandy soil and rock sundries on the step surface of the second-stage side slope surface after blasting, and leveling the step surfaces of the first-stage side slope surface and the second-stage side slope surface;
s007: arranging grouting holes; arranging a plurality of grouting holes at the position 1.0m away from the excavation ground line of the first-stage side slope surface towards the inner side of the excavation direction and at the position with the transverse interval of 0.5m, wherein the direction of the grouting holes is downwards arranged along the excavation surface;
s008: drilling machine operation and grouting hole construction; drilling by a drilling machine according to the corresponding position of the grouting hole to form the grouting hole; the diameter of the grouting hole is 80mm, the depth of the grouting hole is 3m, and the depth is up to the step surface of the second-stage side slope surface; the drilling machine adopts a hydraulic drill, a down-the-hole drill or a hand pneumatic drill.
S009: grouting; cement mortar with a water cement ratio of 1:1 is injected into the grouting hole, so that the cement mortar is diffused to each position in the grouting hole, and a reinforcing column with set thickness is formed in the grouting hole;
s010: excavating a secondary blasting hole on the side slope and charging; a plurality of secondary blasting holes are formed in the outer side of the designed excavation line of the first-stage side slope surface along the inclined plane of the first-stage side slope surface, explosives are arranged in the secondary blasting holes, and the arrangement direction of the secondary blasting holes is perpendicular to the direction of the grouting holes; the secondary blasting holes are arranged in a plum blossom shape.
S011: performing secondary blast hole operation and monitoring; blasting by putting explosives into the secondary blasting holes; the single-hole explosive loading is 72g according to a calculation formula Q ═ aLBq; the explosive adopts emulsion explosive;
wherein the transverse interval a of the blast holes is 1.0m, the drilling depth L is 0.3m, the blasting thickness B is 0.2m, and the unit consumption q of the explosive is 1200g/m3
After the explosive is put into the secondary blasting hole, the top of the secondary blasting hole is blocked by a water bag containing water; when the explosive explodes, the water bag and the water in the water bag can be exploded for four shots to form an atomized water vapor layer, and the atomized water vapor layer is combined with dust particles during explosion to form slurry so as to reduce the dust during explosion; the water bag is a plastic sealing water bag; arranging a high-jetting water gun around the secondary explosion hole, and performing dust fall on an explosion area before, during and after explosion by the high-jetting water gun;
carrying out blasting vibration monitoring during secondary blasting hole blasting operation, wherein the monitoring comprises monitoring point arrangement and inspection tour inspection modes; the monitoring point arrangement specifically comprises monitoring at the upper side, the middle part and the lower side of the high slope so as to prevent excessive blasting and adjust the blasting strategy in time; the patrol inspection mode adopts a project safety responsible person to patrol inspection within the blasting time, so that irrelevant persons are prevented from entering a blasting hazard area, and major potential safety hazards are prevented;
s012: supporting; after the secondary blast hole operation is finished, carrying out sand blasting support on the first-stage slope surface; meanwhile, an anchor rod hole is formed in the first-stage slope surface corresponding to the reinforcing column body, and an anchor rod is fixedly connected with the reinforcing column body through the anchor rod hole; after the anchor rod is connected with the reinforcing column body, the structure of the first-stage side slope surface is favorably reinforced, and the stability is improved;
s013: blasting, excavating and supporting all the high slopes step by step; and after the blasting excavation support of the first grade of slope surface is finished, performing blasting excavation support of the second grade of slope surface, and repeating the steps S004-S012 until all the high slope blasting excavation supports are finished.
In conclusion, the boundary control blasting method for reducing the overbreak and the underexcavation can set explosive blasting through the blasting holes, can effectively remove most rock masses outside the designed excavation line, can set explosive blasting through the secondary blasting holes, can effectively remove small rock masses outside the designed excavation line, and can gradually remove rock masses outside the designed excavation line through batch blasting. In addition, the unmanned aerial vehicle is adopted for surveying, so that the terrain condition of the area to be constructed can be accurately mastered in the early stage; blasting vibration monitoring is carried out during blasting operation, so that irrelevant personnel are prevented from entering a blasting damage area, and major potential safety hazards are prevented; the dust fall is carried out on the explosion area before, during and after explosion by arranging the water bag and the high-speed water jet gun, the dust mass is covered in a three-dimensional manner, multiple reduction is carried out, the harmful gas and the raise dust of large-area open blasting are effectively reduced, and the device is clean and environment-friendly.
The present invention is not limited to the above-described embodiments, and any variations, modifications, and alterations that may occur to one skilled in the art may be made without departing from the spirit of the invention.

Claims (1)

1. A boundary control blasting method for reducing overbreak and underbreak is characterized by at least comprising the following steps:
s001, surveying the terrain of the unmanned aerial vehicle in the early stage;
setting the ground resolution of a high slope in a mountain area according to the requirement of an aerial photography project;
planning a flight route of the unmanned aerial vehicle;
at takeoff, through the following calculation formula:
Figure FDA0003197848880000011
calculating a theoretical relative height H of the unmanned aerial vehicle and the ground, and adjusting the initial flying height of the unmanned aerial vehicle according to the theoretical relative height H;
the system comprises an unmanned aerial vehicle, a GSD and a camera, wherein f is a lens focal length of aerial equipment carried on the unmanned aerial vehicle, a is a pixel size of the aerial equipment carried on the unmanned aerial vehicle, and the GSD is a theoretical ground resolution, wherein the aerial equipment is a high-altitude camera; after taking off and reaching a preset aerial photographing area, starting aerial photographing operation;
in the flying process of the unmanned aerial vehicle, the flying height of the unmanned aerial vehicle is adjusted according to the fluctuation degree of the ground; before setting unmanned aerial vehicle to become high, unmanned aerial vehicle's flying height is H0, and the altitude variation of current topography is H, then unmanned aerial vehicle flying height control module is as follows to flying height's accommodate value lambda H:
λH=h;
h is a negative value if the ground height decreases; if the ground height is increased, H is a positive value, and the flight height adjusting value lambda H of the unmanned aerial vehicle is obtained at the moment;
when the lambda H is a negative value, the unmanned aerial vehicle flying height module controls the flying height of the unmanned aerial vehicle to decrease | lambda H |, and when the lambda H is a positive value, the unmanned aerial vehicle airplane height control module controls the flying height of the unmanned aerial vehicle to increase lambda H; the unmanned aerial vehicle airplane height control module is used for controlling the flight height of the unmanned aerial vehicle;
s002: cleaning on site and lofting drawings;
cleaning and flattening the terrain map of the high slope in the mountain ridge area shot by the S001;
according to a design drawing of a high slope in a mountain area, lofting an excavation line of the high slope;
s003: arranging blast holes; finding a designed excavation line of a high slope on the upper side of the high slope in the mountain area, arranging a plurality of blasting holes at the position 1.0m outside the excavation ground line of the first-stage slope surface along the excavation direction and at the position 1.0m in the transverse interval, and arranging the direction of the blasting holes downwards along the excavation surface;
s004: drilling machine operation and blast hole construction; drilling by a drilling machine according to the corresponding positions of the blast holes to form the blast holes; the diameter of the blast hole is 30mm, the depth of the blast hole is 3m, and the depth is up to the step surface of the second-stage side slope surface; the drilling machine adopts a hydraulic drill, a down-the-hole drill or a hand pneumatic drill;
s005: performing longitudinal blasting operation; blasting by putting explosives into the blasting holes; the single-hole loading quantity is 1800g according to a calculation formula Q ═ aLBq; the explosive adopts emulsion explosive;
wherein the transverse interval a of the blast holes is 1.0m, the drilling depth L is 3.0m, the blasting thickness B is 0.5m, and the unit consumption of explosive is 1200g/m 3;
carrying out blasting vibration monitoring during longitudinal blasting operation, wherein the monitoring comprises monitoring point arrangement and inspection tour inspection modes; the monitoring point arrangement specifically comprises monitoring at the upper side, the middle part and the lower side of the high slope so as to prevent excessive blasting and adjust the blasting strategy in time; the patrol inspection mode adopts a project safety responsible person to patrol and inspect in the blasting time, so that irrelevant persons are prevented from entering a blasting hazard area, and major potential safety hazards are prevented;
after the explosive is placed in the blasting hole, the top of the blasting hole is blocked by a water bag containing water, when the explosive explodes, the water bag and the water in the water bag can be exploded to form an atomized water vapor layer, and the atomized water vapor layer is combined with dust particles during explosion to form slurry so as to reduce the dust during blasting; the water bag is a plastic sealing water bag;
arranging a high water-jetting gun around the blasting hole, and performing dust fall on an explosion area before, during and after explosion by the high water-jetting gun;
s006: cleaning; cleaning sandy soil and rock sundries on the step surface of the second-stage side slope surface after blasting, and leveling the step surfaces of the first-stage side slope surface and the second-stage side slope surface;
s007: arranging grouting holes; arranging a plurality of grouting holes at the position 1.0m away from the excavation ground line of the first-stage side slope surface towards the inner side of the excavation direction and at the position with the transverse interval of 0.5m, wherein the direction of the grouting holes is downwards arranged along the excavation surface;
s008: drilling machine operation and grouting hole construction; drilling by a drilling machine according to the corresponding position of the grouting hole to form the grouting hole; the diameter of the grouting hole is 80mm, the depth of the grouting hole is 3m, and the depth is up to the step surface of the second-stage side slope surface; the drilling machine adopts a hydraulic drill, a down-the-hole drill or a hand pneumatic drill;
s009: grouting; cement mortar with a water cement ratio of 1:1 is injected into the grouting hole, so that the cement mortar is diffused to each position in the grouting hole, and a reinforcing column with set thickness is formed in the grouting hole;
s010: excavating a secondary blasting hole on the side slope and charging; a plurality of secondary blasting holes are formed in the outer side of the designed excavation line of the first-stage side slope surface along the inclined plane of the first-stage side slope surface, explosives are arranged in the secondary blasting holes, and the arrangement direction of the secondary blasting holes is perpendicular to the direction of the grouting holes; the secondary blasting holes are arranged in a plum blossom shape;
s011: performing secondary blast hole operation and monitoring; blasting by putting explosives into the secondary blasting holes; the single-hole explosive loading is 72g according to a calculation formula Q ═ aLBq; the explosive adopts emulsion explosive;
wherein the transverse interval a of the blast holes is 1.0m, the drilling depth L is 0.3m, the blasting thickness B is 0.2m, and the unit consumption of explosive is 1200g/m 3;
after the explosive is put into the secondary blasting hole, the top of the secondary blasting hole is blocked by a water bag containing water; when the explosive explodes, the water bag and the water in the water bag can be exploded for four shots to form an atomized water vapor layer, and the atomized water vapor layer is combined with dust particles during explosion to form slurry so as to reduce the dust during explosion; the water bag is a plastic sealing water bag; arranging a high water-jetting gun around the secondary blasting hole, and performing dust fall on an explosion area before, during and after explosion by the high water-jetting gun;
carrying out blasting vibration monitoring during secondary blasting hole blasting operation, wherein the monitoring comprises monitoring point arrangement and inspection tour inspection modes; the monitoring point arrangement specifically comprises monitoring at the upper side, the middle part and the lower side of the high slope so as to prevent excessive blasting and adjust the blasting strategy in time; the patrol inspection mode adopts a project safety responsible person to patrol and inspect in the blasting time, so that irrelevant persons are prevented from entering a blasting hazard area, and major potential safety hazards are prevented;
s012: supporting; after the secondary blast hole operation is finished, carrying out sand blasting support on the first-stage slope surface; meanwhile, an anchor rod hole is formed in the first-stage slope surface corresponding to the reinforcing column body, and an anchor rod is fixedly connected with the reinforcing column body through the anchor rod hole; after the anchor rod is connected with the reinforcing column body, the structure of the first-stage side slope surface is favorably reinforced;
s013: blasting, excavating and supporting all the high slopes step by step; and after the blasting excavation support of the first grade of slope surface is finished, performing blasting excavation support of the second grade of slope surface, and repeating the steps S004-S012 until all the high slope blasting excavation supports are finished.
CN201810899895.5A 2018-08-09 2018-08-09 Boundary control blasting method for reducing over-excavation and under-excavation Active CN109000524B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810899895.5A CN109000524B (en) 2018-08-09 2018-08-09 Boundary control blasting method for reducing over-excavation and under-excavation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810899895.5A CN109000524B (en) 2018-08-09 2018-08-09 Boundary control blasting method for reducing over-excavation and under-excavation

Publications (2)

Publication Number Publication Date
CN109000524A CN109000524A (en) 2018-12-14
CN109000524B true CN109000524B (en) 2021-11-05

Family

ID=64596464

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810899895.5A Active CN109000524B (en) 2018-08-09 2018-08-09 Boundary control blasting method for reducing over-excavation and under-excavation

Country Status (1)

Country Link
CN (1) CN109000524B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110158621B (en) * 2019-05-27 2021-04-13 福建省新华都工程有限责任公司 Method for improving pre-cracking and joint forming effect of side slope surrounding rock through pre-grouting reinforcement
CN112610220B (en) * 2020-12-11 2022-11-29 中交二公局第六工程有限公司 Tunnel overburdened and undermined total cost control method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103412568A (en) * 2013-08-27 2013-11-27 重庆市勘测院 Method for obtaining remote-sensing images by same-sortie variable-flight-height unmanned aerial vehicle
CN104005417A (en) * 2014-06-09 2014-08-27 中交一公局第一工程有限公司 Construction method for high side slope of loosen and calaclastic rock
CN104089551A (en) * 2014-04-11 2014-10-08 中国水利水电第十一工程局有限公司 Old sluice directional incline, collapse, demolition and blasting construction method
CN104107609A (en) * 2014-07-02 2014-10-22 中国长江三峡集团公司 Combined dust settling method for large-area excavation and explosion in water conservancy and hydropower project
CN105737699A (en) * 2016-02-25 2016-07-06 中铁十八局集团有限公司 Secondary blasting rapid excavation method for deep holes of steps on IV-V-grade surrounding rock of double-track tunnel

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100795849B1 (en) * 2006-11-15 2008-01-21 주식회사 오륙개발 Nature stone engineering method use self drilling nail
CN102021911B (en) * 2010-11-26 2012-07-25 中国水电顾问集团成都勘测设计研究院 Side slope reinforcing method and structure
CN104747194A (en) * 2015-03-10 2015-07-01 中铁九局集团有限公司 Three-wire parallel small spacing large section tunnel group construction method
CN105571415B (en) * 2015-12-29 2017-03-22 重庆大学 Precise control method for smooth surface blasting of fractured rock mass of highway tunnel
CN107254878B (en) * 2017-07-06 2019-03-08 四川大学 A kind of excavation method of hydroelectric project dam abutment high gradient slope control dust

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103412568A (en) * 2013-08-27 2013-11-27 重庆市勘测院 Method for obtaining remote-sensing images by same-sortie variable-flight-height unmanned aerial vehicle
CN104089551A (en) * 2014-04-11 2014-10-08 中国水利水电第十一工程局有限公司 Old sluice directional incline, collapse, demolition and blasting construction method
CN104005417A (en) * 2014-06-09 2014-08-27 中交一公局第一工程有限公司 Construction method for high side slope of loosen and calaclastic rock
CN104107609A (en) * 2014-07-02 2014-10-22 中国长江三峡集团公司 Combined dust settling method for large-area excavation and explosion in water conservancy and hydropower project
CN105737699A (en) * 2016-02-25 2016-07-06 中铁十八局集团有限公司 Secondary blasting rapid excavation method for deep holes of steps on IV-V-grade surrounding rock of double-track tunnel

Also Published As

Publication number Publication date
CN109000524A (en) 2018-12-14

Similar Documents

Publication Publication Date Title
CN110487138B (en) Full-section smooth blasting construction method for high-altitude small-section long steep slope tunnel
CN109339797B (en) Extremely-small-clear-distance tunnel exit shock absorption construction method
CN109000524B (en) Boundary control blasting method for reducing over-excavation and under-excavation
CN113279622B (en) Method for dismantling thin-wall reinforced concrete chimney through high-notch blasting
CN105333778A (en) Medium-deep hole large-section composite cut blasting structure and method
CN107063014A (en) Cutting shallow hole step controlled blasting slope cutting method in complex environment
CN109855496B (en) Comprehensive melon breaking type deep hole cutting blasting method for hard rock in tunnel
CN103557758B (en) Expanded excavation area hole inside and outside combined delay subarea differential initiation network in tunnel blasting
CN104654941B (en) A kind of dam foundation Rapid Excavation explosive forming method based on explosives mix-load truck
CN112832781A (en) Tunnel construction process
CN107478113A (en) A kind of UHV transmission line stake well one-shot forming blasting method
CN105466290A (en) Cutting excavation blasting method
CN109594989B (en) Quick construction method for simultaneously detonating three steps of weak surrounding rock tunnel and double trestles
CN110631439A (en) Small-clear-distance blasting control method for subway station
CN111121572B (en) Tunnel blasting excavation method with multifunctional holes
CN111594179B (en) One-step forming construction method for excavation of large-section arch cover of underground excavated station of subway
CN108915694A (en) It the step tunneling boring unprotect layer tight-face blasting of tunnel lower layer and repairs the roads and protects logical construction method
CN103557756B (en) Advanced pilot tunnel hole-by-hole delay detonation network in tunnel blasting
CN112228079B (en) Construction method for newly-built tunnel by crossing existing line at small angle
CN202247902U (en) Millisecond controlled blasting demolishing structure for foundation pit inner support beam
CN105588479A (en) Three-times elementary error vibration reduction major blasting method using rock flour spaced loading in blasting holes
CN116733477A (en) Extremely high ground stress dry and hard surrounding rock tunnel smooth surface and rock burst prevention and control drilling and burst excavation method
CN112097578B (en) Method for controlling root bottom of open-pit limestone mine after blasting
CN114935289A (en) Blasting structure for sub-smooth surface tunneling
CN209706671U (en) The drilling of the towering cuboid reinforced concrete structure of directional blasting demolishment is arranged

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 710061 middle section of south 2nd Ring Road, Yanta District, Xi'an City, Shaanxi Province

Applicant after: CHANG'AN University

Applicant after: CHINA ELECTRONIC Research Institute OF ENGINEERING INVESTIGATIONS AND DESIGN

Address before: No.70 Youyi East Road, Xi'an, Shaanxi 710054

Applicant before: CHINA ELECTRONIC Research Institute OF ENGINEERING INVESTIGATIONS AND DESIGN

Applicant before: CHANG'AN University

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant