CN108999206A - A kind of construction method of bridge bearing platform - Google Patents

A kind of construction method of bridge bearing platform Download PDF

Info

Publication number
CN108999206A
CN108999206A CN201810708401.0A CN201810708401A CN108999206A CN 108999206 A CN108999206 A CN 108999206A CN 201810708401 A CN201810708401 A CN 201810708401A CN 108999206 A CN108999206 A CN 108999206A
Authority
CN
China
Prior art keywords
binder
section
pour
cushion cap
bearing platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810708401.0A
Other languages
Chinese (zh)
Other versions
CN108999206B (en
Inventor
徐恭义
张金涛
刘俊锋
张燕飞
徐力
胡辉跃
别业山
熊锴
孙建飞
龚俊
胡文军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Reconnaissance and Design Institute Co Ltd
Original Assignee
China Railway Major Bridge Reconnaissance and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Reconnaissance and Design Institute Co Ltd filed Critical China Railway Major Bridge Reconnaissance and Design Institute Co Ltd
Priority to CN201810708401.0A priority Critical patent/CN108999206B/en
Publication of CN108999206A publication Critical patent/CN108999206A/en
Application granted granted Critical
Publication of CN108999206B publication Critical patent/CN108999206B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Abstract

The invention discloses a kind of construction method of bridge bearing platform, include the following steps: pile foundation of constructing at the design position of two cushion caps respectively;Cofferdam is transferred to the design position of cushion cap, and is located at pile foundation in cofferdam;Bottom concrete is poured in cofferdam, pumps the water in cofferdam later;Cushion cap is poured respectively in two pile foundations, a section binder is poured before two cushion cap sides pour respectively, and cushion cap pours placement a period of time after the completion with a section binder is before poured;Wherein, it pours a section binder bottom before two to be connected with bottom concrete, section binder one end is poured before two, and corresponding cushion cap is connected and pours the other end of section binder before two and is oppositely arranged respectively, pours between one end that section binder is oppositely arranged that there are preset clearances before two;A section binder is poured after pouring at preset clearance, and it is integral that section binder connection is poured before making two.The present invention can reduce influence of the concrete shrinkage and creep to structure, improve the stress performance of structure.

Description

A kind of construction method of bridge bearing platform
Technical field
The present invention relates to deepwater foundation construction fields in science of bridge building, and in particular to a kind of construction method of bridge bearing platform.
Background technique
Bridge bearing platform is the reinforced concrete platform for being used to be coupled each stake top being arranged at the top of bridge pile foundation, and bridge is held The effect of platform is subject to and transmits the load transmitted by pier shaft.The conventional method of bridge bearing platform construction are as follows: cofferdam is transferred and is positioned Afterwards, underwater bottom concrete construction is carried out, is drawn water after the intensity of bottom concrete reaches requirement to cofferdam inside, finally The construction bearing platform basis under water-less environment.
In recent years with the fast development of China's capital construction facility, the demand to volume of transport is significantly increased, a collection of super large Come into being across, ultra-wide bridge, these bridges consider many factors bridge piers such as landscape, removals and king-tower be mostly separate it is basic, Basis mostly uses solid binder connection composite entity suspended deck structure stress, however, such traditional cap design of pile method is not only mixed It is big to coagulate influence of the shrinkage and creep effect of soil to structure, so that basic scale increases;In addition concrete masonry's amount of cushion cap binder It greatly increases, causes the huge waste of material.
Summary of the invention
In view of the deficiencies in the prior art, the purpose of the present invention is to provide a kind of construction method of bridge bearing platform, Influence of the concrete shrinkage and creep to structure can be reduced.
To achieve the above objectives, the technical solution adopted by the present invention is that: a kind of construction method of bridge bearing platform, including as follows Step:
The construction pile foundation at the design position of two cushion caps respectively;
Cofferdam is transferred to the design position of the cushion cap, and is located at pile foundation in the cofferdam;
Bottom concrete is poured in the cofferdam, pumps the water in the cofferdam later;
The cushion cap is poured respectively in two pile foundations, pours a section binder, institute before the two cushion cap sides pour respectively State cushion cap and it is described before pour a section binder pour after the completion of place a period of time;Wherein, two it is described before pour section binder bottom and institute Bottom concrete is stated to be connected, two it is described before pour section binder one end respectively the corresponding cushion cap be connected and two it is described before pour section The other end of binder is oppositely arranged, two it is described before pour between one end that section binder is oppositely arranged that there are preset clearances;
A section binder is poured after pouring at the preset clearance, make two it is described before to pour the connection of section binder integral.
Further, the cushion cap and it is described before pour section binder standing time be 80~100 days.
Further, the cushion cap and it is described before pour section binder standing time be 90 days.
Further, before the cofferdam is drawn water, further include by the bottom concrete place a period of time so that The step of bottom concrete reaches design strength.
Further, the bottom concrete standing time is 28~30 days.
Further, two it is described before pour one end that section binder is oppositely arranged open up it is fluted.
Further, two it is described before pour the groove of section binder and interconnect and form entirety.
Further, poured before described it is horizontally spaced on section binder offer multiple grooves, two it is described before pour Groove on section binder is arranged in a one-to-one correspondence, two it is described before pour the corresponding groove on section binder and interconnect.
Further, the cushion cap lower surface is flushed with the bottom concrete upper surface.
Compared with the prior art, the advantages of the present invention are as follows:
(1) using the present invention, pouring due to cushion cap and before placed one end time after the completion of a section binder pours, concrete is completed Significant percentage of shrinkage and creep effect value greatly reduces contraction Xu for generating frame in addition two cushion caps are separation Change effect improves the stress performance of structure to reduce influence of the shrinkage and creep effect to main structure stress;
(2) using the present invention, due to preceding pour opened up on section binder it is fluted so that bridge bearing platform connection by original entity Structure becomes hollow structure, alleviates dead load, so that main body cushion cap binder structure materials save, saves concrete masonry and uses Amount, and it is easy for construction, easy to operate, there is significant economic benefit.
Detailed description of the invention
Fig. 1 is bridge bearing platform schematic view of facade structure provided in an embodiment of the present invention;
Fig. 2 be in Fig. 1 before pour the A-A of section binder to sectional view;
Fig. 3 is bridge bearing platform planar structure schematic diagram provided in an embodiment of the present invention.
In figure: 1, cushion cap;2, pile foundation;3, cofferdam;4, bottom concrete;5, preceding to pour a section binder;50, groove;6, section is poured after Binder;7, king-tower king-post.
Specific embodiment
Invention is further described in detail with reference to the accompanying drawings and embodiments.
The embodiment of the present invention provides a kind of construction method of bridge bearing platform, includes the following steps:
S1: pile foundation 2 of constructing at the design position of two cushion caps 1 respectively, it is shown in Figure 1;
Cofferdam 3: being transferred to the design position of cushion cap 1 by S2, and bury certain depth in cofferdam 3, and is enclosing two pile foundations 2 all It is shown in Figure 1 in weir 3;
S3: pouring bottom concrete 4 in cofferdam 3, pumps the water in cofferdam 3 later;In order to guarantee that bottom concrete 4 reaches To the intensity of design, before cofferdam 3 is drawn water, bottom concrete 4 is placed a period of time, when bottom concrete 4 is placed Between can according to Specific construction require select, usually 28~30 days.
S4: pouring cushion cap 1 respectively in two pile foundations 2, and 1 lower surface of cushion cap flushes with 4 upper surface of bottom concrete, holds two Section binder 5 is poured in 1 side of platform before pouring respectively, cushion cap 1 pours placement a period of time after the completion with section binder 5 is before poured, due to cushion cap 1 It placed one end time with section binder 5 is preceding poured, complete significant percentage of shrinkage and creep effect value, while two cushion caps 1 are point From, greatly reduce the shrinkage and creep effect for generating frame;This step effectively reduces the shrinkage and creep of concrete to main body The influence of structure stress improves the stress performance of structure, and cushion cap 1 and the standing time for before pouring section binder 5 are 80~100 days, It is preferred that 90 days;It is shown in Figure 1, section binder 5 is poured before two between two cushion caps 1, and be in "-" type cloth along two cushion caps, 1 line It sets, wherein pour section binder 5 before two and be cast on bottom concrete 4,5 one end of section binder is poured before two and distinguishes corresponding cushion cap 1 Be connected and pour the other end of section binder 5 before two and be oppositely arranged, poured before two between one end that section binder 5 is oppositely arranged exist it is reserved between Gap;
S5: pouring section binder 6 after pouring at preset clearance, poured before making two section binder 5 connect it is integral, referring to Fig. 1 and Fig. 3 It is shown.
S6: on cushion cap 1 again row construction king-tower king-post 7, referring to shown in Fig. 1 and Fig. 3.
It is shown in Figure 1, one end that section binder 5 is oppositely arranged is poured before two and opens up fluted 50, due to preceding pouring section binder 5 On open up fluted 50 so that bridge bearing platform connection from original entity structure becomes hollow structure, alleviate dead load, save Materials have been saved, concrete masonry's dosage is saved.It is interconnected simultaneously referring to the groove 50 for pouring section binder 5 shown in Fig. 1 and Fig. 3, before two It is formed whole.
It is shown in Figure 2, it is horizontally spaced on preceding pouring section binder 5 to offer multiple grooves 50, section system is poured before two Groove 50 on beam 5 is arranged in a one-to-one correspondence, and corresponding groove 50 on section binder 5 is poured before two and is interconnected.
Using the present invention, on the one hand, pouring due to cushion cap 1 and before placed one end time, coagulation after the completion of section binder 5 pours Soil completes significant percentage of shrinkage and creep effect value, in addition two cushion caps 1 are separation, greatly reduce and generates frame Shrinkage and creep effect improves the stress performance of structure to reduce influence of the shrinkage and creep effect to main structure stress; On the other hand, fluted 50 are opened up on section binder 5 due to preceding pouring, so that the connection of bridge bearing platform 1 is become from original entity structure Hollow structure alleviates dead load, so that main body cushion cap binder structure materials save, saves concrete masonry's dosage, Er Qieshi Work is convenient, easy to operate, has significant economic benefit.
The present invention is not limited to the above-described embodiments, for those skilled in the art, is not departing from Under the premise of the principle of the invention, several improvements and modifications can also be made, these improvements and modifications are also considered as protection of the invention Within the scope of.The content being not described in detail in this specification belongs to the prior art well known to professional and technical personnel in the field.

Claims (9)

1. a kind of construction method of bridge bearing platform, which comprises the steps of:
Pile foundation (2) are constructed at the design position of two cushion caps (1) respectively;
Cofferdam (3) are transferred into the design position of the cushion cap (1), and are located at pile foundation (2) in the cofferdam (3);
Bottom concrete (4) are poured in the cofferdam (3), pump the water in the cofferdam (3) later;
The cushion cap (1) is poured respectively on two pile foundations (2), pours section system before two cushion cap (1) sides pour respectively Beam (5), the cushion cap (1) and it is described before pour a section binder (5) pour after the completion of place a period of time;Wherein, two it is described before pour section Binder (5) bottom is connected with the bottom concrete (4), two it is described before pour a section binder (5) one end and distinguish corresponding institute State cushion cap (1) be connected and two it is described before pour the other end of a section binder (5) and be oppositely arranged, two it is described before pour that a section binder (5) are opposite to be set There are preset clearances between the one end set;
A section binder (6) are poured after pouring at the preset clearance, make two it is described before pour a section binder (5) connection it is integral.
2. the construction method of bridge bearing platform as described in claim 1, it is characterised in that: the cushion cap (1) and it is described before pour section The standing time of binder (5) is 80~100 days.
3. the construction method of bridge bearing platform as claimed in claim 2, it is characterised in that: the cushion cap (1) and it is described before pour section The standing time of binder (5) is 90 days.
4. the construction method of bridge bearing platform as described in claim 1, it is characterised in that: before the cofferdam (3) is drawn water, Further include the steps that placing the bottom concrete (4) a period of time so that the bottom concrete (4) reaches design strength.
5. the construction method of bridge bearing platform as claimed in claim 4, it is characterised in that: when the bottom concrete (4) is placed Between be 28~30 days.
6. the construction method of bridge bearing platform as described in claim 1, it is characterised in that: two it is described before to pour a section binder (5) opposite One end of setting opens up fluted (50).
7. the construction method of bridge bearing platform as claimed in claim 6, it is characterised in that: two it is described before pour the recessed of a section binder (5) Slot (50) interconnects and forms entirety.
8. the construction method of bridge bearing platform as claimed in claim 6, it is characterised in that: pour a section binder (5) Shang Yanshui before described Square be equipped with multiple grooves (50) to being spaced apart, two it is described before the groove (50) that pours on a section binder (5) be arranged in a one-to-one correspondence, Two it is described before pour the corresponding groove (50) on a section binder (5) and interconnect.
9. the construction method of bridge bearing platform as described in claim 1, it is characterised in that: cushion cap (1) lower surface with it is described Bottom concrete (4) upper surface flushes.
CN201810708401.0A 2018-07-02 2018-07-02 Construction method of bridge bearing platform Active CN108999206B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810708401.0A CN108999206B (en) 2018-07-02 2018-07-02 Construction method of bridge bearing platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810708401.0A CN108999206B (en) 2018-07-02 2018-07-02 Construction method of bridge bearing platform

Publications (2)

Publication Number Publication Date
CN108999206A true CN108999206A (en) 2018-12-14
CN108999206B CN108999206B (en) 2020-07-21

Family

ID=64598021

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810708401.0A Active CN108999206B (en) 2018-07-02 2018-07-02 Construction method of bridge bearing platform

Country Status (1)

Country Link
CN (1) CN108999206B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101038723B1 (en) * 2010-10-28 2011-06-02 이용오 Reinforcement structure of footing body and reinforcement method using this building cutoff collar, scouring protection and supporting
CN102733306A (en) * 2012-02-14 2012-10-17 四川川交路桥有限责任公司 Construction method for prefabricating and installing straining beam of water pier of bridge in reservoir area
CN203160113U (en) * 2013-01-30 2013-08-28 中铁二院工程集团有限责任公司 Dumbbell type bearing platform
CN105544382A (en) * 2015-12-10 2016-05-04 中铁大桥局集团有限公司 Construction method of dumbbell-shaped bearing platform
CN106869032A (en) * 2017-02-27 2017-06-20 中铁十九局集团有限公司 A kind of bridge bearing platform constructing tie beam method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101038723B1 (en) * 2010-10-28 2011-06-02 이용오 Reinforcement structure of footing body and reinforcement method using this building cutoff collar, scouring protection and supporting
CN102733306A (en) * 2012-02-14 2012-10-17 四川川交路桥有限责任公司 Construction method for prefabricating and installing straining beam of water pier of bridge in reservoir area
CN203160113U (en) * 2013-01-30 2013-08-28 中铁二院工程集团有限责任公司 Dumbbell type bearing platform
CN105544382A (en) * 2015-12-10 2016-05-04 中铁大桥局集团有限公司 Construction method of dumbbell-shaped bearing platform
CN106869032A (en) * 2017-02-27 2017-06-20 中铁十九局集团有限公司 A kind of bridge bearing platform constructing tie beam method

Also Published As

Publication number Publication date
CN108999206B (en) 2020-07-21

Similar Documents

Publication Publication Date Title
CN106869321A (en) The prefabricated regeneration concrete bean column node and its construction method of a kind of reinforcement
CN205894281U (en) Integral basement of coincide assembly of arch without beam system
CN103835413B (en) Covered with Angles silk screen Mortar Plates in-line frame foamed concrete bearing wall and the practice
CN108360678B (en) A kind of assembled beam-column node tenon connection structure
CN103898831A (en) Ultrahigh-performance-concrete prefabricated assembled-type arch rib and manufacturing and mounting method thereof
CN205894313U (en) Prefabricated assembled steel pipe retrains frame node entirely
CN108442239A (en) A kind of full assembled light abutment and its construction method
CN108560544A (en) A kind of sleeve connection assembled pile foundation and its construction method
CN107090908B (en) A kind of vertical prefabricated components joint connecting method
CN206737118U (en) A kind of prefabricated regeneration concrete bean column node of reinforcement
CN107044175A (en) The vertical linked system of fabricated shear wall with concealed beam sleeper and its installation method
CN106836262A (en) A kind of construction method of packaged type bridges substructure
CN208486404U (en) A kind of concrete shear force wall of steel bar template integrative installation technology
CN106088318A (en) The overlapping assembled integral basement that flat slab system is combined with post and lintel system
CN208328665U (en) A kind of full assembled light abutment
CN104612142B (en) Integral abutment bridge structure based on composite flexible piles and construction method thereof
CN207846457U (en) The ductility connecting structure of assembled vertical member and basis
CN206956949U (en) Overlap wall and intermediate layer laminated floor slab connecting node
CN106088317A (en) The overlapping assembled integral basement that post and lintel system is combined with flat slab system
CN205501843U (en) Consolidate rigid framed arch bridge
CN205024719U (en) Pile foundation and integrated reverse construction vertical braces system of underground continuous wall
CN208685794U (en) Vertically concrete frame structure body and book moulding body are overlapped with horizontal entirety
CN208347063U (en) The prefabricated double board wall units of one kind, shear-wall element and assembly concrete shear wall
CN108999206A (en) A kind of construction method of bridge bearing platform
CN206233359U (en) A kind of assembled architecture reinforced concrete member

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant