CN108978691A - Precipitation system in foundation pit - Google Patents

Precipitation system in foundation pit Download PDF

Info

Publication number
CN108978691A
CN108978691A CN201810938916.XA CN201810938916A CN108978691A CN 108978691 A CN108978691 A CN 108978691A CN 201810938916 A CN201810938916 A CN 201810938916A CN 108978691 A CN108978691 A CN 108978691A
Authority
CN
China
Prior art keywords
steel pipe
hole
pit
foundation pit
artificial
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810938916.XA
Other languages
Chinese (zh)
Inventor
孔利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201810938916.XA priority Critical patent/CN108978691A/en
Publication of CN108978691A publication Critical patent/CN108978691A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water

Abstract

The present invention relates to precipitation systems in technical field of building construction more particularly to a kind of foundation pit.Precipitation system includes: artificial pit-hole in the foundation pit;Head plate is set to the bottom of the artificial pit-hole;Steel pipe is vertically installed in artificial pit-hole, and the length of the steel pipe is higher than the depth of artificial pit-hole, and one end is fixedly connected with the head plate;Immersible pump is set in the steel pipe;Drainpipe, one end are located in the steel pipe, and the other end is located at ground;Mung bean sand bed;Wherein, the steel pipe is divided into upper and lower part, and the lower part is provided with several holes, and the lower part of the steel pipe is provided around filter screen.Precipitation system is not take up the duration in foundation pit disclosed by the invention, influences on Planning of construction periods smaller;Easy construction, it is easy to operate, construction personnel is required low;And large scale equipment is not generated, and material needs are few, and cost of construction materials is low, and it is small on foundation pit influence, it will not be raw to ground local products compared with large disturbances, the reduction of energy continuous and effective and the water being discharged in foundation pit.

Description

Precipitation system in foundation pit
Technical field
The present invention relates to precipitation systems in technical field of building construction more particularly to a kind of foundation pit.
Background technique
At present in foundation construction, since working-day claims or geological condition are reconnoitred the factors such as unknown and restricted, cause in foundation pit After the completion of excavation, situations such as bottom of foundation ditch flows into foundation pit there are underground water or surface water, bottom of foundation ditch water level is excessively high subsequent Waterproof and reinforcing bar binding can not construct in construction.According to normal condition, foundation pit internal water accumulation is removed by the way of the bright row that catchments.But Foundation pit is smaller in a practical situation or there are in Groundwater infiltration foundation pit, can not accomplish to excavate gutter, Huo Zhekai in foundation pit Water flow flows into always the phenomenon that gutter in drainage trenching foundation pit, can have an impact to subsequent construction.
Summary of the invention
Technical problem solved by the invention is to provide precipitation system in a kind of foundation pit, to reduce and be discharged in foundation pit Water, solve the problems, such as the excessively high waterproof in subsequent construction of bottom of foundation ditch water level and reinforcing bar binding can not construct.
Technical problem solved by the invention is realized using following technical scheme:
One aspect of the present invention discloses precipitation system in a kind of foundation pit, comprising:
Artificial pit-hole;
Head plate is set to the bottom of the artificial pit-hole;
Steel pipe is vertically installed in artificial pit-hole, and the length of the steel pipe is higher than the depth of artificial pit-hole, and one end with The head plate is fixedly connected;
Immersible pump is set in the steel pipe;
Drainpipe, one end are located in the steel pipe, and the other end is located at ground;
Mung bean sand bed;
Wherein, the steel pipe is divided into upper and lower part, and the lower part is provided with several holes, the lower part of the steel pipe It is provided around filter screen.
Preferably, described hole is evenly arranged.
Preferably, the lower part of the steel pipe is provided around two layers of filter screen.
The second aspect of the present invention discloses a kind of method for carrying out precipitation processing using precipitation system in above-mentioned foundation pit, The following steps are included:
S1: an artificial pit-hole is dug inside the foundation pit excavated;
S2: preparing steel pipe, sets hole in the lower part of the steel pipe, and filter screen is arranged in the hole periphery winding of steel pipe, under Weld head plate in portion;
S3: steel pipe is embedded in the pit-hole dug, and surrounding fills and presents green bean paste;
S4: immersible pump is placed in the steel duct;
S5: opening immersible pump, which is persistently drawn water, guarantees level of ground water height.
Preferably, in S5, height of water level 400-500mm below foundation pit work surface is kept.
Preferably, in S2, the length of the steel pipe is 1400-1600mm.
Preferably, in S2, the diameter of described hole is 12mm.
Preferably, the immersible pump is the vertical immersible pump that diameter is 100mm.
Preferably, in S2, the position below steel pipe 1m sets hole.
Third aspect of the present invention discloses above-mentioned method in the application of construction technical field.
Foregoing invention is with the following advantages or beneficial effects:
Precipitation system is not take up the duration in foundation pit disclosed by the invention, influences on Planning of construction periods smaller;Easy construction, operation Simply, construction personnel is required low;And large scale equipment is not generated, material needs less, and cost of construction materials is low, influences on foundation pit It is small, it will not be raw to ground local products compared with large disturbances, the reduction of energy continuous and effective and the water being discharged in foundation pit.Utilize precipitation in the foundation pit The method and step that system carries out precipitation processing is few, simple to operation.
Detailed description of the invention
The present invention will be further described with reference to the accompanying drawings, but the embodiment in attached drawing is not constituted to any limit of the invention System.
Fig. 1 is foundation pit schematic diagram;
Fig. 2 is steel pipe schematic diagram;
Fig. 3 is strainer schematic diagram;
Fig. 4 is immersible pump schematic diagram;
Fig. 5 is artificial pit-hole schematic diagram;
Fig. 6 is penstock installation schematic diagram;
Fig. 7 is the schematic diagram that draws water;
Fig. 8 is subsequent construction schematic diagram;
Fig. 9 is tube sealing schematic diagram;
Figure 10 is concreting schematic diagram;
In figure:
The artificial pit-hole of 1-, 2- steel pipe, 3- immersible pump, 4- mung bean sand bed, 5- drainpipe, 6- protective layer, 7- waterproof roll;
Specific embodiment
Present invention will be further explained below with reference to specific examples.It should be understood that these embodiments be only used for the present invention without For limiting the scope of the invention.
Embodiment 1
As shown in figs 1 to 6, present embodiment discloses precipitation systems in a kind of foundation pit, specifically, precipitation system in the foundation pit System includes:
Artificial pit-hole 1;
Head plate is set to the bottom of the artificial pit-hole;
Steel pipe 2 is vertically installed in artificial pit-hole 1, and the length of the steel pipe 2 is higher than the depth of artificial pit-hole 1, and one End is fixedly connected with the head plate;
Immersible pump 3 is set in the steel pipe 2;
Drainpipe 5, one end are located in the steel pipe 2, and the other end is located at ground;
Mung bean sand bed 4;
Wherein, the steel pipe 2 divides for upper and lower part, and the lower part is provided with several holes, the lower part of the steel pipe 2 Around being provided with filter screen.
Described hole is evenly arranged.
The lower part of the steel pipe 2 is provided around two layers of filter screen.
Wherein, mung bean sand bed can be crossed in drainage impurity and a fixed effect is played to soil.
Fig. 7 is that the base pit dewatering system is drawn water schematic diagram.
Precipitation system is not take up the duration in foundation pit disclosed in the present embodiment, influences on Planning of construction periods smaller;Easy construction, behaviour Make simply, to require construction personnel low;And large scale equipment is not generated, material needs less, and cost of construction materials is low, influences on foundation pit It is small, it will not be raw to ground local products compared with large disturbances, the reduction of energy continuous and effective and the water being discharged in foundation pit.
Embodiment 2
It is including following present embodiment discloses a kind of method for carrying out precipitation processing using precipitation system in above-mentioned foundation pit Step:
S1: an artificial pit-hole is dug inside the foundation pit excavated;
S2: preparing steel pipe, sets hole in the lower part of the steel pipe, and filter screen is arranged in the hole periphery winding of steel pipe, under Weld head plate in portion;
S3: steel pipe is embedded in the pit-hole dug, and surrounding fills and presents green bean paste;
S4: immersible pump is placed in the steel duct;
S5: opening immersible pump, which is persistently drawn water, guarantees level of ground water height.
Specifically, keeping height of water level 400-500mm below foundation pit work surface in S5.In S2, the steel pipe Length is 1400-1600mm.In S2, the diameter of described hole is 12mm.The immersible pump is that diameter is the vertical latent of 100mm Water pump.In S2, the position below steel pipe 1m sets hole.
After the completion of precipitation work, as Figure 8-Figure 10, subsequent construction process is as follows:
One, it is laid with underground waterproof coiled material, the steel pipe for exposing foundation pit face uses roofing board and tube coil of wire material way, by steel pipe packet Firmly, and persistently it draws water and guarantees level of ground water height.After the completion of normal construction process and program construction, preparation pours coagulation Soil.
Two, it before pouring, is poured into steel pipe same concrete (or dedicated grouting material), concrete is cut off after pouring into be exposed Steel pipe, waterproof roll lap seal, the subsequent constructions such as protective layer.
Three, subsequent construction is normally carried out, casting concrete.
Specific embodiments of the present invention are described in detail above, but it is merely an example, the present invention is simultaneously unlimited It is formed on particular embodiments described above.To those skilled in the art, any couple of present invention carries out equivalent modifications and Substitution is also all among scope of the invention.Therefore, without departing from the spirit and scope of the invention made by equal transformation and Modification, all should be contained within the scope of the invention.

Claims (10)

1. precipitation system in a kind of foundation pit characterized by comprising
Artificial pit-hole;
Head plate is set to the bottom of the artificial pit-hole;
Steel pipe is vertically installed in artificial pit-hole, and the length of the steel pipe is higher than the depth of artificial pit-hole, and one end with it is described Head plate is fixedly connected;
Immersible pump is set in the steel pipe;
Drainpipe, one end are located in the steel pipe, and the other end is located at ground;
Mung bean sand bed;
Wherein, the steel pipe is divided into upper and lower part, and the lower part is provided with several holes, the lower part winding of the steel pipe It is equipped with filter screen.
2. precipitation system in foundation pit according to claim 1, which is characterized in that described hole is evenly arranged.
3. precipitation system in foundation pit according to claim 1, which is characterized in that the lower part of the steel pipe is provided around two Layer filter screen.
4. a kind of method for carrying out precipitation processing using precipitation system in foundation pit described in claim 1-3 any one, special Sign is, comprising the following steps:
S1: an artificial pit-hole is dug inside the foundation pit excavated;
S2: preparing steel pipe, sets hole, the hole periphery winding setting filter screen of steel pipe, lower part weldering in the lower part of the steel pipe Connect head plate;
S3: steel pipe is embedded in the pit-hole dug, and surrounding fills and presents green bean paste;
S4: immersible pump is placed in the steel duct;
S5: opening immersible pump, which is persistently drawn water, guarantees level of ground water height.
5. according to the method described in claim 4, it is characterized in that, keeping height of water level below foundation pit work surface in S5 400-500mm。
6. according to the method described in claim 4, it is characterized in that, the length of the steel pipe is 1400-1600mm in S2.
7. according to the method described in claim 4, it is characterized in that, the diameter of described hole is 12mm in S2.
8. according to the method described in claim 4, it is characterized in that, the immersible pump is the vertical immersible pump that diameter is 100mm.
9. according to the method described in claim 4, it is characterized in that, the position below steel pipe 1m sets hole in S2.
10. the method according to any one of claim 4-9 is in the application of construction technical field.
CN201810938916.XA 2018-08-17 2018-08-17 Precipitation system in foundation pit Pending CN108978691A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810938916.XA CN108978691A (en) 2018-08-17 2018-08-17 Precipitation system in foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810938916.XA CN108978691A (en) 2018-08-17 2018-08-17 Precipitation system in foundation pit

Publications (1)

Publication Number Publication Date
CN108978691A true CN108978691A (en) 2018-12-11

Family

ID=64554183

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810938916.XA Pending CN108978691A (en) 2018-08-17 2018-08-17 Precipitation system in foundation pit

Country Status (1)

Country Link
CN (1) CN108978691A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202577326U (en) * 2012-02-14 2012-12-05 江苏江中集团有限公司 Water lowering device for mine pit
CN204000909U (en) * 2014-05-27 2014-12-10 江苏南通三建集团有限公司 A kind of immersed tube Precipitation Structure
CN104452786A (en) * 2014-11-14 2015-03-25 武汉一冶建筑安装工程有限责任公司 Deep foundation pit elevator shaft sump dewatering construction method
CN106223351A (en) * 2016-07-26 2016-12-14 中国二十二冶集团有限公司 Self priming pump reduces local groundwater level construction method
CN205839777U (en) * 2016-05-31 2016-12-28 中国一冶集团有限公司 Well-points dewatering well filter structure
CN206581279U (en) * 2017-03-13 2017-10-24 青岛建设集团有限公司 A kind of foundation ditch pressure release type dewatering well and its plugging structure
CN206784412U (en) * 2017-03-29 2017-12-22 南京南大岩土工程技术有限公司 A kind of precipitation well construction

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202577326U (en) * 2012-02-14 2012-12-05 江苏江中集团有限公司 Water lowering device for mine pit
CN204000909U (en) * 2014-05-27 2014-12-10 江苏南通三建集团有限公司 A kind of immersed tube Precipitation Structure
CN104452786A (en) * 2014-11-14 2015-03-25 武汉一冶建筑安装工程有限责任公司 Deep foundation pit elevator shaft sump dewatering construction method
CN205839777U (en) * 2016-05-31 2016-12-28 中国一冶集团有限公司 Well-points dewatering well filter structure
CN106223351A (en) * 2016-07-26 2016-12-14 中国二十二冶集团有限公司 Self priming pump reduces local groundwater level construction method
CN206581279U (en) * 2017-03-13 2017-10-24 青岛建设集团有限公司 A kind of foundation ditch pressure release type dewatering well and its plugging structure
CN206784412U (en) * 2017-03-29 2017-12-22 南京南大岩土工程技术有限公司 A kind of precipitation well construction

Similar Documents

Publication Publication Date Title
CN105201002B (en) A kind of underground structure oozes drainage system and its construction method
CN107938692B (en) Drainage and recharging construction method and structure
CN104032760A (en) Foundation pit construction tube well dewatering method
CN107059903A (en) Bottom plate plugging dewatering well construction method is worn in foundation ditch
CN102418347B (en) Drainage construction method for blind drain and sump wells in deep foundation pit
CN102433886A (en) Construction method for adding water lowering well in water collecting well
LU500273B1 (en) New comprehensive dewatering and drainage method and drainage device for mudstone subway station
CN110847199A (en) Construction method for drainage of underground water of deep foundation pit
CN112921173A (en) South ionic rare earth in-situ leaching system and method
CN110004935A (en) A kind of locally deep pit drain measure trench system and construction method
CN108677982A (en) Complex geological condition foundation pit substrate excavates Tunnel gushing treatment method
CN105569094A (en) Water discharge and drainage system and construction method adopting basement bottom plate water buoyant force releasing method
CN104775439B (en) A kind of pattern foundation pit supporting structure sealing integral structure and its construction method
CN109372016A (en) Basement bottom plate rear pouring tape structure and construction method under high artesian
CN105484277A (en) Component for tubular well precipitation construction in elevator foundation pit or sump and construction method
CN110397050B (en) Beam-anchor type light drainage retaining wall and construction method thereof
CN111456056A (en) Construction method of dewatering well in deep foundation pit
CN107354950A (en) A kind of economic quickly catch pit local dewatering method
CN215163017U (en) South ion type rare earth in-situ leaching system and liquid collecting pipe with dredger thereof
CN210288405U (en) Local deep pit water conservancy diversion escape canal system
CN205205844U (en) Member is used in construction of tubular well precipitation in elevator foundation ditch or sump pit
CN205077527U (en) Drainage system is dredged to basement bottom plate release water buoyancy method
CN218148458U (en) Deep water deep foundation pit drainage system of fissure development rock stratum
CN208578054U (en) A kind of embed-type shallow-layer combined water drain pipe
CN207828994U (en) It is a kind of draining and recharge constructing structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181211