CN107354950A CN201710568276.3A CN201710568276A CN107354950A CN 107354950 A CN107354950 A CN 107354950A CN 201710568276 A CN201710568276 A CN 201710568276A CN 107354950 A CN107354950 A CN 107354950A
Authority
CN
China
Prior art keywords
catch pit
drainpipe
construction
ditch
ponding well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710568276.3A
Other languages
Chinese (zh)
Inventor
张伟
王浩
柳东阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN201710568276.3A priority Critical patent/CN107354950A/en
Publication of CN107354950A publication Critical patent/CN107354950A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/08Restraining of underground water by employing open ditches arranged below the level of the water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0006Plastics
    • E02D2300/0007PVC

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

It is the technical problem such as surrounding enviroment differential settlement, the increase of cost and extension of duration caused by precipitation depth to solve catch pit elevator bottom depth in the prior art the invention discloses a kind of economic quickly catch pit local dewatering method.The technical scheme is that:A kind of economic quickly catch pit local dewatering method, comprises the following steps:S1 excavates catch pit in foundation ditch;S2 excavates bright ditch in the bottom surrounding of catch pit;S3:In the corner of catch pit, ponding well is set;S4 sets drainpipe, and S5 sets self priming pump in ponding well;S6 puts to fill out in draining tube wall surrounding and ponding well location puts appropriate microlith;S7 starts self priming pump and drawn water;S8 carries out concrete cushion construction, construction of leveling blanket and waterproof coiled material construction successively after catch pit cheats bottom and catch pit crater wall is dried, to catch pit crater wall and hole bottom;S9 raft plates pour.Present invention ensures that construction quality and construction safety, reduce construction cost, ensure the construction period.

Description

A kind of economic quickly catch pit local dewatering method
Technical field
The present invention relates to technical field of building construction, and in particular to a kind of economic quickly catch pit local dewatering method.
Background technology
Skyscraper arranges elevator pit and catchmented to make full use of the underground space to be provided with basement more in basement Hole, generally low than the foundation ditch bottom absolute altitude 1~3m of its absolute altitude.Because embedded depth of foundation is deeper, it usually needs take base pit dewatering to protect Working face needed for the stabilization of card excavation slope and construction.Existing Foundation Pit Support Design code regulation, design of foundation pit precipitation water level should Less than foundation ditch bottom surface 0.5m, if using elevator, catch pit elevation of bottom as designing precipitation water level, it is necessary to discharge water increase, Surrounding building and the differential settlement constructed are had a great influence, while the depth down of dewatering well, increasing number, arrangement are tight Gather, persistently draw water and not only increase cost, and extend the duration;If water level can not reduce in catch pit elevator, can cause A large amount of infiltrations of bottom and crater wall are cheated, dry working face can not be obtained, influence construction speed and construction quality, therefore, catch pit Local dewatering is urgently to be resolved hurrily.
The content of the invention
For the deficiency of above-mentioned background technology, the invention provides a kind of economic quickly catch pit local dewatering method, It is surrounding enviroment differential settlement, cost caused by precipitation depth to solve catch pit elevator bottom depth in the prior art Increase and the extension of duration, and bed course, screed-coat and waterproof roll caused by catch pit water level is higher the technology such as can not construct Problem.
The technical scheme is that:A kind of economic quickly catch pit local dewatering method, comprises the following steps:S1: Catch pit is excavated in foundation ditch;
S2:The bottom surrounding of catch pit in step sl excavates bright ditch;
S3:The corner of catch pit in step sl is provided with ponding well;
S4:Drainpipe is placed in bright ditch in step s 2, drainpipe is seamlessly connected and placed around catch pit, the pipe of drainpipe Water seepage hole is uniformly provided with wall;
S5:Self priming pump is set in ponding well in step s3, and self priming pump is connected with the drainpipe in step S4;
S6:Put to fill out in draining tube wall surrounding and ponding well location and put appropriate microlith, avoid mud from blocking the water seepage hole on tube wall;
S7:Start self priming pump to be drawn water, must not have a power failure during drawing water, observe catch pit crater wall and cheat the infiltration situation at bottom;
S8:After catch pit cheats bottom and catch pit crater wall is dried, are carried out by concrete cushion successively and is applied for catch pit crater wall and hole bottom Work, construction of leveling blanket and waterproof coiled material construction;
S9:Raft plate takes out the self priming pump in ponding well before pouring, and raft board concrete is cast in catch pit, and drainpipe is retained in In raft foundation.
A width of 270 ~ the 330mm of ditch of bright ditch in the step S2, ditch depth are 270 ~ 330mm.
A length of 290 ~ 320mm of ponding well in the step S3, a width of 290 ~ 320mm, depth are 480 ~ 510mm, self priming pump In ponding well and guaranteed water level covers pump head.
Drainpipe in the step S4 is PVC plastic pipe, a diameter of 70 ~ 80mm of water seepage hole, is set on the outside of water seepage hole There are 10 mesh steel wires.
Invention not only avoids the appearance caused by the intensification of local foundation ditch bottom the problems such as catch pit infiltration drift sand, and disappear Except the differential settlement of the surrounding building of precipitation radius caused by a large amount of precipitation, while it ensure that next procedure is constructed Acting surface basic unit it is solid, smooth, clean, dry, allow construction it is smooth, save construction cost.In addition, constructed Drainpipe in journey does not have to take out, and improves operating efficiency, and prevent water level from rising again, it is ensured that smoothly safety is carried out for construction.
Brief description of the drawings
Fig. 1 is the set location schematic diagram of ponding well in the embodiment of the present invention 1.
Fig. 2 is the set location schematic diagram of ponding well in the embodiment of the present invention 2.
Fig. 3 is the set location schematic diagram of ponding well in the embodiment of the present invention 3.
Embodiment
Embodiment 1:As shown in figure 1, a kind of economic quickly catch pit local dewatering method, comprises the following steps:S1: Catch pit is excavated in foundation ditch, cheat bottom using catch pit carries out catch pit dewatering design as design water level;
S2:The bottom surrounding of catch pit in step sl excavates bright ditch 1, the ditch a width of 300mm, ditch depth 300mm of bright ditch 1.
S3:The corner of catch pit in step sl sets ponding well 2 according to water size, and the water of catch pit is more When, 4 ponding wells 2 are set respectively in the corner of catch pit, a length of 300mm of ponding well, a width of 300mm, depth 500mm, from Sucking pump is located in ponding well and guaranteed water level covering pump head.
S4:Drainpipe is placed in bright ditch in step s 2, drainpipe is seamlessly connected and placed around catch pit, drainpipe Tube wall top half on be uniformly provided with water seepage hole, drainpipe is PVC plastic pipe, a diameter of 75mm of water seepage hole, water seepage hole Outside is provided with 10 mesh steel wires, and the setting of steel wire prevents soil from entering drainpipe, blocks pipeline.
S5:Self priming pump is set in ponding well in step s3, and self priming pump is connected with the drainpipe in step S4, self-priming Pump suctions out the water penetrated into drainpipe.
S6:Put to fill out in draining tube wall surrounding and ponding well location and put appropriate microlith, avoid mud from blocking oozing on tube wall Water hole.
S7:Start self priming pump to be drawn water, must not have a power failure during drawing water, observe catch pit crater wall and cheat the infiltration feelings at bottom Condition.
S8:After catch pit cheats bottom and catch pit crater wall is dried, concrete cushion is carried out to catch pit crater wall and hole bottom and applied Work, construction of leveling blanket then is being carried out, is finally carrying out waterproof coiled material construction.
S9:Half an hour takes out the self priming pump in ponding well before raft plate pours, and drainpipe does not take out, and raft board concrete pours Build in catch pit, drainpipe indwelling is in raft foundation.
Embodiment 2:As shown in Fig. 2 a kind of economic quickly catch pit local dewatering method, in S2 in step sl The bottom surrounding of catch pit excavates bright ditch 1, the ditch a width of 270mm, ditch depth 270mm of bright ditch 1.
S3:The corner of catch pit in step sl sets ponding well 2 according to water size, and the water of catch pit is general When, 2 ponding wells 2 of diagonal setting at the corner of catch pit, a length of 290mm of ponding well 2, a width of 290mm, depth 480mm, Self priming pump is located in ponding well and guaranteed water level covering pump head.
S4:Drainpipe is placed in bright ditch in step s 2, drainpipe is seamlessly connected and placed around catch pit, drainpipe Tube wall top half on be uniformly provided with water seepage hole, drainpipe is PVC plastic pipe, a diameter of 70mm of water seepage hole, water seepage hole Outside is provided with 10 mesh steel wires, and the setting of steel wire prevents soil from entering drainpipe, blocks pipeline.
Embodiment 3:As shown in figure 3, a kind of economic quickly catch pit local dewatering method, in S2 in step sl The bottom surrounding of catch pit excavates bright ditch 1, the ditch a width of 330mm, ditch depth 330mm of bright ditch 1.
S3:The corner of catch pit in step sl sets ponding well 2 according to water size, and the water of catch pit is less When, any one angle sets 1 ponding well 2, a length of 320mm of ponding well, a width of 320mm at the corner of catch pit, and depth is 510mm, self priming pump is located in ponding well and guaranteed water level covering pump head.
S4:Drainpipe is placed in bright ditch in step s 2, drainpipe is seamlessly connected and placed around catch pit, drainpipe Tube wall top half on be uniformly provided with water seepage hole, drainpipe is PVC plastic pipe, a diameter of 80mm of water seepage hole, water seepage hole Outside is provided with 10 mesh steel wires, and the setting of steel wire prevents soil from entering drainpipe, blocks pipeline.
The foregoing is only a preferred embodiment of the present invention, but protection scope of the present invention be not limited thereto, Any one skilled in the art the invention discloses technical scope in, the change or replacement that can readily occur in, It should all be included within the scope of the present invention.

Claims (4)

  1. A kind of 1. economic quickly catch pit local dewatering method, it is characterised in that comprise the following steps:S1:Opened in foundation ditch Dig catch pit;
    S2:The bottom surrounding of catch pit in step sl excavates bright ditch;
    S3:The corner of catch pit in step sl is provided with ponding well;
    S4:Drainpipe is placed in bright ditch in step s 2, drainpipe is seamlessly connected and placed around catch pit, the pipe of drainpipe Water seepage hole is uniformly provided with wall;
    S5:Self priming pump is set in ponding well in step s3, and self priming pump is connected with the drainpipe in step S4;
    S6:Put to fill out in draining tube wall surrounding and ponding well location and put appropriate microlith, avoid mud from blocking the water seepage hole on tube wall;
    S7:Start self priming pump to be drawn water, must not have a power failure during drawing water, observe catch pit crater wall and cheat the infiltration situation at bottom;
    S8:After catch pit cheats bottom and catch pit crater wall is dried, are carried out by concrete cushion successively and is applied for catch pit crater wall and hole bottom Work, construction of leveling blanket and waterproof coiled material construction;
    S9:Raft plate takes out the self priming pump in ponding well before pouring, and raft board concrete is cast in catch pit, and drainpipe is retained in In raft foundation.
  2. 2. economic quickly catch pit local dewatering method according to claim 1, it is characterised in that:In the step S2 A width of 270 ~ the 330mm of ditch of bright ditch, ditch depth are 270 ~ 330mm.
  3. 3. economic quickly catch pit local dewatering method according to claim 1, it is characterised in that:In the step S3 A length of 290 ~ 320mm of ponding well, a width of 290 ~ 320mm, depth are 480 ~ 510mm, and self priming pump is located in ponding well and ensures water Position covering pump head.
  4. 4. economic quickly catch pit local dewatering method according to claim 1, it is characterised in that:In the step S4 Drainpipe be PVC plastic pipe, a diameter of 70 ~ 80mm of water seepage hole, the outside of water seepage hole is provided with 10 mesh steel wires.
CN201710568276.3A 2017-07-13 2017-07-13 A kind of economic quickly catch pit local dewatering method Pending CN107354950A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710568276.3A CN107354950A (en) 2017-07-13 2017-07-13 A kind of economic quickly catch pit local dewatering method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710568276.3A CN107354950A (en) 2017-07-13 2017-07-13 A kind of economic quickly catch pit local dewatering method

Publications (1)

Publication Number Publication Date
CN107354950A true CN107354950A (en) 2017-11-17

Family

ID=60293016

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710568276.3A Pending CN107354950A (en) 2017-07-13 2017-07-13 A kind of economic quickly catch pit local dewatering method

Country Status (1)

Country Link
CN (1) CN107354950A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108625382A (en) * 2018-05-16 2018-10-09 安徽建筑大学 Water accumulation preventing system for branch pipe type in-building pit building
CN109440775A (en) * 2018-12-27 2019-03-08 云南省建设投资控股集团有限公司 A kind of sunk type foundation pit Yield rainfall relation system, construction method and application method
CN109736337A (en) * 2019-02-22 2019-05-10 宁蔚蔚 A kind of substrate elevator catch pit drift sand processing guarantees the dewatering device and method of bed course integrality
CN113136884A (en) * 2021-04-26 2021-07-20 中国二十二冶集团有限公司 Construction method of strongly weathered rock foundation pit well rich in low-pressure-bearing fracture water

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009179945A (en) * 2008-01-29 2009-08-13 Yoshitaka Igawa Well conduit for road and its construction method
CN101705691A (en) * 2009-10-30 2010-05-12 南通建工集团股份有限公司 Construction method of dewatering well under foundation slab in foundation pit
CN102162253A (en) * 2011-05-07 2011-08-24 山东新城建工股份有限公司 Precipitation construction method employing pipe embedding in deep foundation pits
CN106223351A (en) * 2016-07-26 2016-12-14 中国二十二冶集团有限公司 Self priming pump reduces local groundwater level construction method
CN106703057A (en) * 2016-12-02 2017-05-24 温州中海建设有限公司 Basement ground construction maintenance drainage structure of large building and method for constructing basement concrete layer

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009179945A (en) * 2008-01-29 2009-08-13 Yoshitaka Igawa Well conduit for road and its construction method
CN101705691A (en) * 2009-10-30 2010-05-12 南通建工集团股份有限公司 Construction method of dewatering well under foundation slab in foundation pit
CN102162253A (en) * 2011-05-07 2011-08-24 山东新城建工股份有限公司 Precipitation construction method employing pipe embedding in deep foundation pits
CN106223351A (en) * 2016-07-26 2016-12-14 中国二十二冶集团有限公司 Self priming pump reduces local groundwater level construction method
CN106703057A (en) * 2016-12-02 2017-05-24 温州中海建设有限公司 Basement ground construction maintenance drainage structure of large building and method for constructing basement concrete layer

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108625382A (en) * 2018-05-16 2018-10-09 安徽建筑大学 Water accumulation preventing system for branch pipe type in-building pit building
CN109440775A (en) * 2018-12-27 2019-03-08 云南省建设投资控股集团有限公司 A kind of sunk type foundation pit Yield rainfall relation system, construction method and application method
CN109440775B (en) * 2018-12-27 2020-11-24 云南省建设投资控股集团有限公司 Sinking type foundation pit dewatering and drainage system, construction method and use method
CN109736337A (en) * 2019-02-22 2019-05-10 宁蔚蔚 A kind of substrate elevator catch pit drift sand processing guarantees the dewatering device and method of bed course integrality
CN113136884A (en) * 2021-04-26 2021-07-20 中国二十二冶集团有限公司 Construction method of strongly weathered rock foundation pit well rich in low-pressure-bearing fracture water

Similar Documents

Publication Publication Date Title
CN107354950A (en) A kind of economic quickly catch pit local dewatering method
CN101250879B (en) Method for processing bottom solum trickleing water of deep building pit
CN104711994A (en) Foundation pit deep well rainfall and plugging construction method
CN104196034A (en) Foundation pit construction method employing steel sheet piles as support cofferdam
CN103046565B (en) Draining method for ultra-deep batholith deep foundation pit
CN105002913A (en) Strongly-permeable stratum deep foundation pit bottom sealing water stopping structure and construction method thereof
CN203569578U (en) Recharge well capable of preventing well casing blocking and water bursting
CN108331000A (en) Caisson sinking construction method
CN110847199A (en) Construction method for drainage of underground water of deep foundation pit
CN104775439B (en) A kind of pattern foundation pit supporting structure sealing integral structure and its construction method
CN107217683A (en) A kind of drainage pipeline basis filling anti-collapse structure of antiseepage and its construction method
CN207538059U (en) A kind of water drainage of deep foundation pit structure
CN108571020A (en) The prominent concrete floor casting method for gushing decompression control water of deep basal pit artesian water
CN110629777A (en) Well point dewatering device and system and construction method thereof
CN107059904A (en) A kind of underground pipe gallery ponding well excavation method
CN111411639B (en) Shallow foundation pit dewatering construction method for water-rich pebble layer
CN209308079U (en) Water draw-off for Underground Building for Anti-floating
CN104846837B (en) The construction method of ultra-deep well in a kind of bright draining foundation ditch
CN110670613A (en) Anti-seepage structure of foundation pit elevator shaft and construction method thereof
CN216615927U (en) Emergency structure system applied to single-row enclosure of foundation pit
CN216475128U (en) Building bottom plate drainage structure with temporary water tank in water collecting well
CN110185051A (en) Deep narrow excavation water discharge method
CN206359989U (en) Substrate local dewatering drainage arrangement
CN210946854U (en) Anti-seepage structure of foundation pit elevator shaft
CN212175794U (en) Deep basal pit falls and arranges two unification sump pit structures

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171117

RJ01 Rejection of invention patent application after publication