CN108952769A - Maintenance method for tunnel secondary lining formwork trolley - Google Patents

Maintenance method for tunnel secondary lining formwork trolley Download PDF

Info

Publication number
CN108952769A
CN108952769A CN201811007453.1A CN201811007453A CN108952769A CN 108952769 A CN108952769 A CN 108952769A CN 201811007453 A CN201811007453 A CN 201811007453A CN 108952769 A CN108952769 A CN 108952769A
Authority
CN
China
Prior art keywords
door frame
template
tunnel
modular unit
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811007453.1A
Other languages
Chinese (zh)
Other versions
CN108952769B (en
Inventor
夏孝军
张滔
李兴权
秦晓波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 19th Metallurgical Group Co ltd
Original Assignee
China 19th Metallurgical Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 19th Metallurgical Group Co ltd filed Critical China 19th Metallurgical Group Co ltd
Priority to CN201811007453.1A priority Critical patent/CN108952769B/en
Publication of CN108952769A publication Critical patent/CN108952769A/en
Application granted granted Critical
Publication of CN108952769B publication Critical patent/CN108952769B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a maintenance method of a tunnel secondary lining form trolley, belongs to the field of maintenance of construction equipment, and aims to shorten the maintenance time of the secondary lining form trolley and improve the maintenance efficiency of the secondary lining form trolley. The method comprises the following steps: step one, supporting the bottom of the angle template on an inverted arch for backfilling; temporarily fixing the hinged positions of the template units at two ends of the tunnel secondary lining trolley; step two, the connection between the template unit and the portal is released; step three, moving the portal out of the template unit along the longitudinal direction of the tunnel; fourthly, maintaining the portal; moving the maintained portal frame to the original position; step six, connecting the portal frame with the template unit; and step seven, releasing the temporary fixation. According to the invention, the template unit is separated from the portal frame, and the portal frame is moved out independently for portal frame repair, so that the traction is more convenient and labor-saving; inside alright carry out the portal and restore in the tunnel, finally shortened maintenance duration, improved maintenance efficiency.

Description

Tunnel Second Lining formwork jumbo method for maintaining
Technical field
The invention belongs to construction equipments to repair field, particularly Tunnel Second Lining formwork jumbo method for maintaining.
Background technique
Secondary lining formwork jumbo is widely used in Tunnel Second Lining Construction, is usually made of following sections: Arc formwork unit door frame and connects the multiple hydraulic cylinders of door frame and support shuttering unit on the inside of the modular unit.Template Unit generally includes the top template, the side template positioned at two sides and the angle mould positioned at two side bottoms that are located at dome portions along its circumferential direction Plate;Described side template one end and corresponding top template one end are hinged, and the other end and corresponding Angle formwork one end are hinged;The door frame includes The crossbeam at top and the supporting leg of two sides of the bottom;The supporting leg top is connected with crossbeam.
In secondary lining pours, secondary lining formwork jumbo is insecure because door frame supporting leg bottom supports, and causes door frame branch Leg bottom is moved inwardly, to cause door frame crossbeam torsional deformation, causes trolley that can not continue to use.Therefore, it is necessary to Repair and replacement are carried out to trolley door frame crossbeam, supporting leg is corrected.Currently, the mode of operation generallyd use are as follows: by secondary lining Formwork jumbo is built with overall pulling down outside machine travel to hole is loaded, crossbeam is cut by professional to on-the-spot guidance and is corrected, then The crossbeam repair welding steel plate maintenance that correction is finished, finally completes rear haulage to original position for secondary lining formwork jumbo assembly.It should Although the problem of beam deformation that method for maintaining solves, maintenance time is long, is unfavorable for the fast of secondary lining formwork jumbo Speed is repaired.
Summary of the invention
The object of the present invention is to provide a kind of Tunnel Second Lining formwork jumbo method for maintaining, to shorten secondary lining template The maintenance time of trolley improves the maintenance efficiency of secondary lining formwork jumbo.
The technical solution adopted by the present invention is that: Tunnel Second Lining formwork jumbo method for maintaining, the secondary lining trolley The door frame of modular unit is used to support including arc formwork unit and on the inside of modular unit;The modular unit is along its circumferential direction Top template, the side template positioned at two sides and the Angle formwork positioned at two side bottoms including being located at dome portions;Described side template one end Hinged with corresponding top template one end, the other end and corresponding Angle formwork one end are hinged;The door frame includes crossbeam and the bottom at top The supporting leg of two sides;The supporting leg top is connected with crossbeam;The following steps carried out including sequence:
Step 1: filling in cushion block between Angle formwork bottom and inverted arch fill concrete top surface, support Angle formwork bottom In inverted arch fill concrete top surface;At the both ends of Tunnel Second Lining trolley, by Angle formwork and side template, side template and top template Hinged place be fixed temporarily;
Step 2: releasing the connection between modular unit and door frame;
Step 3: door frame is removed modular unit along tunnel longitudinal direction, it is kept completely separate door frame with modular unit;
Step 4: carrying out door frame maintenance;
Step 5: moving to original position for the door frame finished has been repaired;
Step 6: door frame is connected with modular unit;
Step 7: releasing being fixed temporarily between Angle formwork and side template, side template and the hinged place of top template.
Further, in step 1, junction steel plate, the template of the junction steel plate and stitching portion two sides are set in hinged place Welded connecting is fixed temporarily with realizing.
Further, after step 3, and before step 4, diagonal brace is set, described diagonal brace one end is supported in inverted arch and returns Top of concrete is filled out, the other end is supported on the inside of modular unit.
Further, the diagonal brace is supported in side template.
Further, it in step 4, is removed in place to door frame, before repairing, corrects the supporting leg of door frame.
Further, using the supporting leg of chain block correction door frame.
The beneficial effects of the present invention are: it is of the invention, by separating modular unit with door frame, individually removes door frame and carry out door Un-wheeling repair is multiple, compared with moving integrally secondary lining formwork jumbo, is more convenient laborsaving firstly, drawing, has saved manpower and traction is set It is standby;Secondly, the height and width in door frame occupancy tunnel are smaller, after individually removing door frame, it is easier to look for foot in tunnel internal Enough spaces are used for door frame repair, conducive to the investment for shortening manpower and pulling equipment, while also shortening maintenance cycle;Most Afterwards, when removing door frame, modular unit indwelling provides accurate position in original position, for the door frame after repairing, and it is multiple to shorten door frame The adjustment time of position, improves maintenance efficiency.
Detailed description of the invention
Fig. 1 is Tunnel Second Lining formwork jumbo structural schematic diagram;
Fig. 2 is that Fig. 1 removes door frame rear pattern plate cellular construction schematic diagram.
In figure, modular unit 1, top template 11, side template 12, Angle formwork 13, door frame 2, crossbeam 21, supporting leg 22, connection steel Plate 3, diagonal brace 4.
Specific embodiment
It is as follows that the present invention is described further with reference to the accompanying drawings and examples:
Tunnel Second Lining formwork jumbo method for maintaining, as shown in Figure 1, the secondary lining formwork jumbo includes arc mould Plate unit 1 and the door frame 2 that modular unit 1 is used to support on the inside of modular unit 1;The modular unit 1 includes along its circumferential direction Top template 11 positioned at dome portions, the side template 12 positioned at two sides and the Angle formwork 13 positioned at two side bottoms;The side template 12 One end and corresponding 11 one end of top template are hinged, and the other end and corresponding 13 one end of Angle formwork are hinged;The door frame 2 includes the cross at top Beam 21 and the supporting leg of two sides of the bottom 22;22 top of supporting leg is connected with crossbeam 21;The following steps carried out including sequence:
Step 1: filling in cushion block between 13 bottom of Angle formwork and inverted arch fill concrete top surface, make 13 bottom of Angle formwork It is supported in inverted arch fill concrete top surface;At the both ends of Tunnel Second Lining formwork jumbo, by Angle formwork 13 and side template 12, side Template 12 and the hinged place of top template 11 are fixed temporarily;
Step 2: releasing the connection between modular unit 1 and door frame 2;
Step 3: it is longitudinal by the removal modular unit 1 of door frame 2 along tunnel, it is kept completely separate door frame 2 with modular unit 1;
It is repaired Step 4: carrying out door frame 2;
Step 5: moving to original position for the door frame 2 finished has been repaired;
Step 6: door frame 2 is connected with modular unit 1;
Step 7: releasing interim solid between Angle formwork 13 and side template 12, side template 12 and the hinged place of top template 11 It is fixed.
The present invention individually removes door frame 2 and carries out the reparation of door frame 2, with whole shifting by separating modular unit 1 with door frame 2 Dynamic secondary lining formwork jumbo is compared, firstly, traction is more convenient laborsaving, has saved manpower and pulling equipment;Secondly, door frame 2 accounts for It is smaller with the height and width in tunnel, after individually removing door frame 2, it is easier to look for enough spaces for door in tunnel internal 2 repair of frame conducive to the investment for shortening manpower and pulling equipment, while also shortening maintenance cycle;Finally, when removing door frame 2, 1 indwelling of modular unit provides accurate position in original position, for the door frame 2 after repairing, when shortening the adjustment of the reset of door frame 2 Between.
In step 1, cushion block is filled between 13 bottom of Angle formwork and inverted arch fill concrete top surface, its object is to make For 13 self-supporting of Angle formwork in inverted arch fill concrete top surface, cushion block can be steel plate, or timber wedge, can also be steel plate with Timber wedge is applied in combination, and is determined according to the specific spacing etc. between Angle formwork 13 and inverted arch fill concrete top surface, to meet angle Template 13 is securely supported at inverted arch fill concrete top surface, does not generate subject to displacement between the two.
Due in secondary lining formwork jumbo in use, between side template 12 and top template 11, side template 12 and Angle formwork It is hinged between 13, in order to avoid causing modular unit 1 to collapse because of generation relative displacement at hinge joint, therefore, in step 1 In, Angle formwork 13 and side template 12, side template 12 and the hinged place of top template 11 are fixed temporarily so that hinge template 13 with It will not relatively rotate between side template 12, will not relatively rotate between side template 12 and top template 11.
Connection in step 2, between releasing Angle formwork 13, side template 12 and top template 11 and door frame 2.Modular unit 1 Each component part and door frame 2 between generally use hydraulic cylinder etc. and be attached, when specific operation, unclamp hydraulic cylinder and door frame Connection bolt between 2, is retained in hydraulic cylinder on modular unit 1.
Angle formwork 13 is fixed temporarily with side template 12, side template 12 and the hinged place of top template 11, is releasing angle mould It is carried out before connection between plate 13, side template 12 and top template 11 and door frame 2, so that door frame 2 remains unchanged when being fixed temporarily It plays a supporting role to modular unit 1, modular unit 1 collapses caused by capable of effectivelying prevent because of reasons such as vibrations, improves template list The stability that member 1 is reinforced.
In step 3, after door frame 1 removes modular unit 1, compare since it occupies tunnel space relative to entire trolley It is small, there are enough spaces to overhaul in tunnel for door frame 1, therefore, door frame 1, can be as needed in tunnel without removing tunnel Suitable position overhauled.
Hinged place realization can be set in using two pieces of collets to be fixed temporarily, but collet installation is inconvenient, it is preferred that as schemed Shown in 2, in step 2, junction steel plate 3 is set in hinged place, the junction steel plate 3 and the template of hinged place two sides are welded to connect It is fixed temporarily with realizing.
It is welded to connect realization by the template of junction steel plate 3 and hinged place two sides to be fixed temporarily, operation is simple.Work as position When the hinged place of Angle formwork 13 and side template 12, the template of hinged place two sides is respectively corresponding Angle formwork 13 and side template 12.When being located at the hinged place of side template 12 and top template 11, the template of hinged place two sides is respectively corresponding 12 He of side template Top template 11.
In order to modular unit 1 enhance protect, avoid because vibration etc. reasons cause modular unit 1 be fixed temporarily failure or Integrated deflection etc., it is preferred that after step 3, before step 4, as shown in Fig. 2, setting diagonal brace 4,4 one end branch of diagonal brace It supports in inverted arch fill concrete top surface, the other end is supported in 1 inside of modular unit.Refer to that modular unit 1 encloses on the inside of modular unit 1 At arch surround region in.
Diagonal brace 4 can be supported in Angle formwork 13, it is preferred that the diagonal brace 4 is supported in side template 12.For diagonal brace 4 itself Stability, diagonal brace 4 is advisable horizontal by 45 ° of installations.
It in step 4, is removed in place to door frame 2, before repairing, corrects the supporting leg 22 of door frame 2.
Preferably, using the supporting leg 22 of chain block correction door frame 2.
It is fixed on the lining cutting of tunnel two sides using chain block one end, the other end acts on supporting leg 22, by supporting leg 22 to two sides It pulls open, adjustment is more convenient laborsaving.

Claims (6)

1. Tunnel Second Lining formwork jumbo method for maintaining, the secondary lining trolley includes arc formwork unit (1) and is located at The door frame (2) of modular unit (1) is used to support on the inside of modular unit (1);The modular unit (1) includes being located at arch along its circumferential direction The top template (11) at top, the side template (12) positioned at two sides and the Angle formwork (13) positioned at two side bottoms;The side template (12) one end and corresponding top template (11) one end are hinged, and the other end and corresponding Angle formwork (13) one end are hinged;Door frame (2) packet Include the crossbeam (21) at top and the supporting leg (22) of two sides of the bottom;Supporting leg (22) top is connected with crossbeam (21);Its feature It is, the following steps carried out including sequence:
Step 1: filling in cushion block between Angle formwork (13) bottom and inverted arch fill concrete top surface, make Angle formwork (13) bottom It is supported in inverted arch fill concrete top surface;At the both ends of Tunnel Second Lining trolley, by Angle formwork (13) and side template (12), side Template (12) and the hinged place of top template (11) are fixed temporarily;
Step 2: releasing the connection between modular unit (1) and door frame (2);
Step 3: it is longitudinal by door frame (2) removal modular unit (1) along tunnel, it is kept completely separate door frame (2) with modular unit (1);
Step 4: carrying out door frame (2) maintenance;
Step 5: moving to original position for the door frame (2) finished has been repaired;
Step 6: door frame (2) is connected with modular unit (1);
Step 7: releasing facing between Angle formwork (13) and side template (12), side template (12) and the hinged place of top template (11) When fix.
2. Tunnel Second Lining formwork jumbo method for maintaining as described in claim 1, which is characterized in that in step 1, cutting with scissors It meets place and junction steel plate (3) is set, the template of the junction steel plate (3) and stitching portion two sides is welded to connect to be fixed temporarily with realizing.
3. Tunnel Second Lining formwork jumbo method for maintaining as described in claim 1, which is characterized in that after step 3, And before step 4, it is arranged diagonal brace (4), described diagonal brace (4) one end is supported in inverted arch fill concrete top surface, and the other end is supported in On the inside of modular unit.
4. Tunnel Second Lining formwork jumbo method for maintaining as claimed in claim 3, which is characterized in that diagonal brace (4) branch It supports in side template (12).
5. the Tunnel Second Lining formwork jumbo method for maintaining as described in claim 1-4 any one claim, feature It is, in step 4, is removed in place to door frame (2), before repairing, correct the supporting leg (22) of door frame (2).
6. Tunnel Second Lining formwork jumbo method for maintaining as claimed in claim 5, which is characterized in that rectified using chain block The supporting leg (22) of positive door frame (2).
CN201811007453.1A 2018-08-31 2018-08-31 Maintenance method for tunnel secondary lining formwork trolley Active CN108952769B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811007453.1A CN108952769B (en) 2018-08-31 2018-08-31 Maintenance method for tunnel secondary lining formwork trolley

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811007453.1A CN108952769B (en) 2018-08-31 2018-08-31 Maintenance method for tunnel secondary lining formwork trolley

Publications (2)

Publication Number Publication Date
CN108952769A true CN108952769A (en) 2018-12-07
CN108952769B CN108952769B (en) 2020-02-07

Family

ID=64475017

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811007453.1A Active CN108952769B (en) 2018-08-31 2018-08-31 Maintenance method for tunnel secondary lining formwork trolley

Country Status (1)

Country Link
CN (1) CN108952769B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110273695A (en) * 2019-07-13 2019-09-24 中国三冶集团有限公司 A kind of Tunnel Second Lining formwork jumbo and its stage molding pouring procedure

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002235495A (en) * 2001-02-07 2002-08-23 Gifu Kogyo Co Ltd Concrete placing method and device for tunnel widening work
JP2007092310A (en) * 2005-09-27 2007-04-12 Mk Engineering:Kk Inner form structure
CN101824994A (en) * 2010-04-27 2010-09-08 池州恒毅设备制造有限公司 Concrete lining steel formwork jumbo
KR20110131530A (en) * 2010-05-31 2011-12-07 선산철강공업(주) A travelling steel form
CN204419200U (en) * 2014-11-14 2015-06-24 中铁二十一局集团第三工程有限公司 One kind of multiple bore tunnel hydraulic lining trolleys
CN207177929U (en) * 2017-09-30 2018-04-03 中铁十二局集团有限公司 Arc adhesion type two serves as a contrast concrete and pours elephant trunk by window
CN108035737A (en) * 2017-12-07 2018-05-15 中国十九冶集团有限公司 Tunnel secondary lining template trolley sealing foot structure and mounting method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002235495A (en) * 2001-02-07 2002-08-23 Gifu Kogyo Co Ltd Concrete placing method and device for tunnel widening work
JP2007092310A (en) * 2005-09-27 2007-04-12 Mk Engineering:Kk Inner form structure
CN101824994A (en) * 2010-04-27 2010-09-08 池州恒毅设备制造有限公司 Concrete lining steel formwork jumbo
KR20110131530A (en) * 2010-05-31 2011-12-07 선산철강공업(주) A travelling steel form
CN204419200U (en) * 2014-11-14 2015-06-24 中铁二十一局集团第三工程有限公司 One kind of multiple bore tunnel hydraulic lining trolleys
CN207177929U (en) * 2017-09-30 2018-04-03 中铁十二局集团有限公司 Arc adhesion type two serves as a contrast concrete and pours elephant trunk by window
CN108035737A (en) * 2017-12-07 2018-05-15 中国十九冶集团有限公司 Tunnel secondary lining template trolley sealing foot structure and mounting method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110273695A (en) * 2019-07-13 2019-09-24 中国三冶集团有限公司 A kind of Tunnel Second Lining formwork jumbo and its stage molding pouring procedure

Also Published As

Publication number Publication date
CN108952769B (en) 2020-02-07

Similar Documents

Publication Publication Date Title
CN103898836B (en) Cable stayed bridge H type Sarasota height top rail steel battered leg prestress stent construction method
JP6902184B2 (en) Work equipment and overhang erection method
CN104109999A (en) Construction method for bridge tower transverse beams
CN105350454B (en) Steel arch rib outer wrapped concrete construction method for steel trussed arch bridge
CN209457425U (en) A kind of ancient architecture wall recovery support
JP2009144362A (en) Method of self-supporting arched concrete reinforcement for tunnel
JP6071581B2 (en) Pipe laying method
CN108952769A (en) Maintenance method for tunnel secondary lining formwork trolley
CN109722992A (en) A kind of device and method of dumbbell-shaped arch rib installation positioning
CN204386608U (en) A kind of tunnel invert construction tool
CN107100655A (en) Weak surrounding rock locally changes the simple temporary support system of arch and its applies method
CN106979023A (en) The adjustable concrete end mould of Tunnel Second Lining width and its adjusting method
CN101476330B (en) Thick and large-volume concrete elastic base and construction method thereof
CN107905818B (en) Tunnel concrete lining construction auxiliary equipment and construction process
KR200283076Y1 (en) Mobile tunel mold with a system for adjusting position of upper mold
JP2020153104A (en) Repair method of bridge pier
CN109372261A (en) A kind of masonry secretly buries the pre-buried fixed framing device of case
JP6534938B2 (en) Lining plate installation and rain curing jig and lining plate installation method using the jig
CN211314211U (en) Jacking and descending device of shield machine
CN102817322A (en) Shrinkable internal model without draw bar
CN207437103U (en) Weak surrounding rock locally changes the simple temporary support system of arch
CN103981893A (en) Embedded bolt suspending and reinforcing device and method for foundation of steam turbine
CN219910785U (en) Synchronous binding rack for open cut tunnel steel bars
CN110952448A (en) Construction method of steel shell concrete combined cable tower
CN104878734B (en) A kind of ship lift Nut column removes frock and method for dismounting thereof

Legal Events

Date Code Title Description